COST, TIME AND RESOURCE SHEET Santos

Santos (Sampang) Pty Ltd

PROJECT: OYONG DEVELOPMENT PROJECT


CTR NO: EH05 CTR TITLE: SAFETY ENGINEERING
START DATE: END DATE: DURATION:
SCOPE OF SERVICE:
1. Develop facility safety philosophy, considering full plant life cycle, ie design/operation and abandonment.
2. Perform preliminary health and safety engineering reviews, in accordance with Santos Standards, including
noise and vibrations aspects. Perform safety review, Hazard Study 1 & 2 and HAZOP as per Santos
Standards, with Santos representatives in attendance as required. Safety and operability reviews shall pay
particular attention to manning levels, security of operation, loss control, fire and gas detection systems,
means of escape temporary accomodations and safe refuge requirements.
3. Perform flare and vent radiation and dispersion study, define stack heights and positions.
4. Incorporate requirements into design to meet Santos' tolerability level and regulatory requirements.

INPUT REQUIREMENTS:

DELIVERABLE LISTING:
1. Safety Philosophy.
2. HAZID & HAZOP Reports.
3. Dispersion/radiation calculations and technical note.

COST, TIME AND RESOURCE ESTIMATE:


Resource (Labour) Hours Rate Cost
Lead Engineer (National) 140.00
Engineer 220.00

Resource (Non-Labour) Units Rate Cost

TOTAL
REVISION DATE APPROVED CLIENT
COST, TIME AND RESOURCE SHEET Santos
Santos (Sampang) Pty Ltd

PROJECT: OYONG DEVELOPMENT PROJECT


CTR NO: EH10 CTR TITLE: FIRE PROTECTION DESIGN
START DATE: END DATE: DURATION:
SCOPE OF SERVICE:
1. Develop active and passive fire protection philosophy (including consideration of fire protection during
drilling operations).
2. Define the requirements for active and passive fire protection, including but not limited to the requirement
for fusible loops, location of fire monitors, fire water pump sizing and selection.

3. Define fire and gas detection systems.

INPUT REQUIREMENTS:

DELIVERABLE LISTING:
1. Fire Protection Philosophy.

COST, TIME AND RESOURCE ESTIMATE:


Resource (Labour) Hours Rate Cost
Lead Engineer (National) 60.00
Engineer 80.00

Resource (Non-Labour) Units Rate Cost

TOTAL
REVISION DATE APPROVED CLIENT
COST, TIME AND RESOURCE SHEET Santos
Santos (Sampang) Pty Ltd

PROJECT: OYONG DEVELOPMENT PROJECT


CTR NO: EH15 CTR TITLE: SAFETY LAYOUTS & ESCAPE ROUTES
START DATE: END DATE: DURATION:
SCOPE OF SERVICE:
1. Prepare Safety Equipment Layout and Escape Route philsopophy.
2. Prepare technical note for incorporating findings into facilites layout.

INPUT REQUIREMENTS:

DELIVERABLE LISTING:
1. Safety Equipment Layouts, Escape Route and Fire Demarcation drawings.
2. Technical note.

COST, TIME AND RESOURCE ESTIMATE:


Resource (Labour) Hours Rate Cost
Lead Engineer (National) 50.00
Engineer 100.00
Senior Draftsman (National) 40.00
Draftsman 80.00

Resource (Non-Labour) Units Rate Cost

TOTAL
REVISION DATE APPROVED CLIENT
COST, TIME AND RESOURCE SHEET Santos
Santos (Sampang) Pty Ltd

PROJECT: OYONG DEVELOPMENT PROJECT


CTR NO: EH20 CTR TITLE: QUALITATIVE SAFETY REVIEW
START DATE: END DATE: DURATION:
SCOPE OF SERVICE:
1. Perform a preliminary safety review of the design of the wellhead compression platform and onshore
processing facility. The qualitative assessment should consider the following:

- the type and nature of hazardous events that could occur, eg. Gas explosion, jet fires, ship collision,
personnel transfer.
- the source or originating causes of the event and give a ranking to its probability of occurrence.
- the possible consequences of the event and the severity.
- the means of escalation and the potential final outcome.
- the means of mitigation, with change recommendations to mitigate the risk..
- the overall assessment of risk and the hazard to personnel safety.

INPUT REQUIREMENTS:

DELIVERABLE LISTING:
1. Preliminary Qualitative Safety Review Report.

COST, TIME AND RESOURCE ESTIMATE:


Resource (Labour) Hours Rate Cost
Lead Engineer (National) 40.00
Engineer 60.00

Resource (Non-Labour) Units Rate Cost

TOTAL
REVISION DATE APPROVED CLIENT
COST, TIME AND RESOURCE SHEET Santos
Santos (Sampang) Pty Ltd

PROJECT: OYONG DEVELOPMENT PROJECT


CTR NO: EH25 CTR TITLE: Quantitative Risk Assessment (QRA)
START DATE: END DATE: DURATION:
SCOPE OF SERVICE:
1. Perform a preliminary Quantified Risk Assessment using appropriate specialist analysis software for the
design of the wellhead compression platform and the onshore processing facility, which shall establish that the
risk to personnel, facility and the environment fall within internationally accepted norms for this type of facility.
The analysis shall be of a level of detail such that the major contributors to the overall level of risk can be
clearly identified and that any mitagory measures can be propoerly evaluated and implemented.

INPUT REQUIREMENTS:

DELIVERABLE LISTING:
1. Quantitative Risk Assessment (QRA) Report

COST, TIME AND RESOURCE ESTIMATE:


Resource (Labour) Hours Rate Cost
Lead Engineer (National) 60.00
Engineer 80.00

Resource (Non-Labour) Units Rate Cost

TOTAL
REVISION DATE APPROVED CLIENT