Professional Documents
Culture Documents
Construction Methodology
Construction Methodology
CONSTRUCTION
METHODOLOGY
PROJECT
CONSTRUCTION
METHODOLOGY
Page 2 of 10
PROJECT
CONSTRUCTION
METHODOLOGY
CONTENTS
Page 3 of 10
PROJECT
CONSTRUCTION
METHODOLOGY
The structural shell of the community centers and Guard room's is projected to complete by
3 months. Internal Finishing works will be overlapped with structural works and is projected
to be completed by 8 to 9 months.
Project Information
Project : C-----------------------
Location : -------------------------
Client/Owner : ------------------------
Project Consultant : M/s. ------------------------------
No. of Floors : Ground +Roof
Scope of Work : Construction and Maintenance of the project
Page 4 of 10
PROJECT
CONSTRUCTION
METHODOLOGY
Structural Works
Preparation Works
Works, Site layout drawings and other related items handed over by the
Infrastructure Subcontractor, will be taken over by ---------
Survey Setting-Out
All survey works will be carried out using fixed control points located at site.
Using GPS survey setting out is another option in order to minimize the
errors.
All horizontal & vertical members will be provided with coordinate points and
level on concrete slabs & columns/walls, respectively.
Page 5 of 10
PROJECT
CONSTRUCTION
METHODOLOGY
Casting of Concrete
Based on the approved design mixes for particular members, pouring shall be
done properly to achieve acceptable concrete surface.
Page 6 of 10
PROJECT
CONSTRUCTION
METHODOLOGY
Finished surfaces varies accordingly with the required next trade of work.
Mobile Pumpcretes:
As the Building height is less than 10m, mobile pumpcretes will be used.
Architectural Works
Finishing Works :
Block Works:
Block works will commence accordingly. Lay out, bedding, jointing and other
required accessories/reinforcement will be carried out as per the approved
shop drawings and project specification and methodology.
Blocks will be tested as required to monitor and to verify compliance with the
project specification and standards.
Box out for MEP requirements will be provided as per the approved shop
drawing. Final closure around service openings will be carried out after
completion of MEP works.
Plastering Works
Plastering works will be started accordingly after appropriate setting of blocks.
Plastering will be carried out in stages such as base and finish coats, as
required for the next trade.
MEP Works
MEP works and all related materials will be supplied and installed based on
the approved MEP Drawings and Specification. MEP subcontractor approval
shall be taken from the Engineer.
All substructure works will be carried out accordingly and shall be done in the
manner that will not affect the other trades in their work areas prior to
casting of concrete for the foundation.
MEP embedment shall be carried out carefully to ensure proper location and
points for MEP fixtures and accessories.
Page 7 of 10
PROJECT
CONSTRUCTION
METHODOLOGY
Toilets/Rest Area
Temporary toilets and rest area will be provided for workers
Loading Platforms
Safety Nets
Safety nets will be provided just below the concrete structural works in order
to avoid any accident which may occur due to falling materials from work
areas above.
Page 8 of 10
PROJECT
CONSTRUCTION
METHODOLOGY
Alcohol, Drugs, Explosives, Weapons and any illegal substances are not ALLOWED
in any ARP project; deviations will result delivering to local authorities.
Personal Protective Equipment (PPE) shall be used in accordance with Material or
Chemical Safety Data Sheets. However, the minimum PPE shall be worn at all
times by all site staff in accordance to Dubai Municipality Health & Safety
Construction Codes of Practice.
All power tools have to be inspected and tagged with the colour code of the
month.
Operatives using Jack Hammers would only be allowed to use it if they are
trained by a competent trainer and at the required intervals due to Hand Arm
Vibration Syndrome (HAVS).
Adequate wetting and or cleaning of the area will be carried out regularly in
order to suppress dust from site activity and suitable dusk mask shall be used.
Area has to be clear of water prior to use any power tools.
Waste or left over concrete shall be placed into a skip for waste management.
All activities involving moving plant shall be controlled by a nominated banks
man.
All plant & equipment should be checked for an up to date certification. In
addition, a visual inspection will be done by a competent person before use.
Certification for the plant will be confirmed and filed.
Quarantine procedures are to be followed to ensure that defective or suspect
equipment, which has been withdrawn from service, does not get back into
service without the prior inspection and approval from a competent person.
The Site Engineer / Foreman, who will instruct all operatives on safety
measures to be taken before the commencement of the job every day.
The Safety Officer, who will inform all site personnel involved in the
operations about the potential risks / hazards and control measures to be
taken.
Page 9 of 10
PROJECT
CONSTRUCTION
METHODOLOGY
Helmet
Goggles, visor
Dust mask
Hand Gloves
Overall
Ear Protectors
Safety foot wear
High Visibility Jacket
5.5 Handrails/Edge Protection;
Handrails will be provided wherever required in order to proceed with
works safely.
Slab edge will be protected by using handrails and toe boards.
Note :- For more details please see project health and safety plan.
Page 10 of 10