S CURVE MINGGUAN

RENOVASI VENUE UTAMA DAN LAPANGAN LATIHAN PIALA DUNIA U-20 DI PROVINSI BALI
PT. PP (PERSERO), TBK
Jangka Waktu Pelaksanaan : 180 Hari Kalender
Mulai : 20 November 2020
Selesai : 18 Mei 2021

2020 2021
BOBOT NOVEMBER DESEMBER JANUARI FEBRUARI MARET APRIL MEI
NO URAIAN NILAI KONTRAK (Rp)
(%) 20 - 26 27 - 3 4 - 10 11 - 17 18 - 24 25 - 31 1-7 8 - 14 15 - 21 22 - 28 29 - 4 5 - 11 12 - 18 19 - 25 26 - 4 5 - 11 12 - 18 19 - 25 26 - 1 2-8 9 - 15 16 - 22 23 - 29 30 - 6 7 - 13 14 - 18
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

I. STADION I WAYAN DIPTA, BALI


A. PEKERJAAN PERSIAPAN 1,733,949,710 1.246 0.0100 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0476 0.0938
B. PEKERJAAN STRUKTUR
1 BANGUNAN TRIBUN BARAT
a. Pekerjaan Struktur Core Lift 207,207,471 0.149 0.0100 0.0100 0.0496 0.0496 0.0298
b. Pekerjaan Struktur Scoring Board 341,055,701 0.245 0.0490 0.0490 0.0490 0.0490 0.0490
2 PEKERJAAN TRIBUN EXISTING
a. Tribun Barat 1,635,559,933 1.176 0.0150 0.0539 0.0539 0.0539 0.0539 0.0539 0.0539 0.2103 0.2103 0.2103 0.2064
b. Tribun Timur 1,145,033,749 0.823 0.0450 0.0450 0.0450 0.0450 0.1286 0.1286 0.1286 0.1286 0.1286
c. Tribun Utara 484,508,098 0.348 0.0435 0.0435 0.0435 0.0435 0.0435 0.0435 0.0435 0.0435
d. Tribun Selatan 481,498,127 0.346 0.0433 0.0433 0.0433 0.0433 0.0433 0.0433 0.0433 0.0433
C PEKERJAAN ARSITEKTUR
a. Bangunan Tribun Barat 9,909,188,869 7.123 0.1000 0.1000 0.1000 0.3000 0.3000 0.3000 0.7497 0.7497 0.7497 0.7497 0.7497 0.7497 0.4748 0.4748 0.4748
b. Bangunan Tribun Timur 1,736,258,101 1.248 0.1040 0.1040 0.1040 0.1040 0.1040 0.1040 0.1040 0.1040 0.1040 0.1040 0.1040 0.1040
c. Bangunan Tribun Utara 773,165,438 0.556 0.0556 0.0556 0.0556 0.0556 0.0556 0.0556 0.0556 0.0556 0.0556 0.0556
d. Bangunan Tribun Selatan 732,296,966 0.526 0.0526 0.0526 0.0526 0.0526 0.0526 0.0526 0.0526 0.0526 0.0526 0.0526
D PEKERJAAN MEKANIKAL ,ELEKTRIKAL DAN PLUMBING
1 Pekerjaan Electrical 4,512,949,508 3.244 0.0250 0.0250 0.0250 0.0250 0.1801 0.1801 0.1801 0.1801 0.1801 0.1801 0.1801 0.1801 0.1801 0.1801 0.1801 0.1801 0.1801 0.1801 0.1801 0.1801 0.2622
2 Pekerjaan Electronic
a. Pekerjaan Telepon 552,521,400 0.397 0.0284 0.0284 0.0284 0.0284 0.0284 0.0284 0.0284 0.0284 0.0284 0.0284 0.0284 0.0284 0.0567
b. Pekerjaan Pendeteksian Dini (Fire Alarm) 580,662,200 0.417 0.0261 0.0261 0.0261 0.0261 0.0261 0.0261 0.0261 0.0261 0.0261 0.0261 0.0261 0.0261 0.0261 0.0261 0.0522
c. Pekerjaan Tata Suara (Sound System) 5,467,790,100 3.930 0.2807 0.2807 0.2807 0.2807 0.2807 0.2807 0.2807 0.2807 0.2807 0.2807 0.2807 0.2807 0.5614
d. Pekerjaan Instalasi Closed Circuit Televison (CCTV) 2,098,339,600 1.508 0.1005 0.1005 0.1005 0.1005 0.1005 0.1005 0.1005 0.1005 0.1005 0.1005 0.1005 0.1005 0.1005 0.2011
e. Pekerjaan Scoreboard dan Perlengkapannya 11,387,148,600 8.185 0.5116 0.5116 0.5116 0.5116 0.5116 0.5116 0.5116 0.5116 0.5116 0.5116 0.5116 0.5116 0.5116 0.5116 1.0231
f. Pekerjaan Building Automation System (BAS/BMS) 1,715,894,600 1.233 0.0881 0.0881 0.0881 0.0881 0.0881 0.0881 0.0881 0.0881 0.0881 0.0881 0.0881 0.0881 0.1762
3 Pekerjaan Mechanical 9,078,843,580 6.526 0.3435 0.3435 0.3435 0.3435 0.3435 0.3435 0.3435 0.3435 0.3435 0.3435 0.3435 0.3435 0.3435 0.3435 0.3435 0.3435 0.3435 0.6869
E PEKERJAAN LAPANGAN (FOP)
1 Pekerjaan Lintasan Lari 1,780,498,774 1.280 0.0711 0.0711 0.0711 0.0711 0.0711 0.0711 0.0711 0.0711 0.0711 0.0711 0.0711 0.0711 0.0711 0.0711 0.0711 0.0711 0.0711 0.0711
2 Pekerjaan Penggantian Rumput & Drainase 4,434,940,659 3.188 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.1226 0.2452
3 Pekerjaan Sistem Penyiraman Lapangan 653,589,367 0.470 0.0247 0.0247 0.0247 0.0247 0.0247 0.0247 0.0247 0.0247 0.0247 0.0247 0.0247 0.0247 0.0247 0.0247 0.0247 0.0247 0.0247 0.0495
4 Pekerjaan Tiang Gawang, Perlangkapan dan Garis Permainan 1,731,167,438 1.244 0.2074 0.2074 0.2074 0.2074 0.4148
F PEKERJAAN LAMPU LAPANGAN (LAMPU FOP) 2400 Lux
a. Pengadaan dan Pemasangan Lampu FOP 19,122,524,835 13.745 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545 0.6545
G PENGADAAN DAN PEMASANGAN KURSI
a. Pengadaan dan Pemasangan Kursi 5,929,071,520 4.262 0.2841 0.2841 0.2841 0.2841 0.2841 0.2841 0.2841 0.2841 0.2841 0.2841 0.2841 0.2841 0.2841 0.2841 0.2841
H PEKERJAAN KAWASAN
1 Pekerjaan Pagar 3,318,705,655 2.385 0.1403 0.1403 0.1403 0.1403 0.1403 0.1403 0.1403 0.1403 0.1403 0.1403 0.1403 0.1403 0.1403 0.1403 0.1403 0.2806
2 Pekerjaan Jalan dan Area Parkir 873,698,309 0.628 0.0419 0.0419 0.0419 0.0419 0.0419 0.0419 0.0419 0.0419 0.0419 0.0419 0.0419 0.0419 0.0419 0.0419 0.0419
3 Pekerjaan Normalisasi Saluran Kawasan 737,756,479 0.530 0.0379 0.0379 0.0379 0.0379 0.0379 0.0379 0.0379 0.0379 0.0379 0.0379 0.0379 0.0379 0.0379 0.0379
4 Pekerjaan Plaza 1,373,739,770 0.987 0.0705 0.0705 0.0705 0.0705 0.0705 0.0705 0.0705 0.0705 0.0705 0.0705 0.0705 0.0705 0.0705 0.0705
5 Pekerjaan Landsekap 330,279,125 0.237 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0198 0.0396
I PENAMBAHAN DAYA STADION IWD 112,700,000 0.081 0.0116 0.0116 0.0116 0.0116 0.0116 0.0231

II. STADION I GUSTI NGURAH RAI, BALI


A. PEKERJAAN PERSIAPAN 88,765,540 0.064 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025 0.0025
B. PEKERJAAN LAPANGAN (FOP)
1 PEKERJAAN PENGGANTIAN RUMPUT & DRAINASE 3,052,557,023 2.194 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.1755
2 PEKERJAAN SISTEM PENYIRAMAN LAPANGAN 748,989,479 0.538 0.0283 0.0283 0.0283 0.0283 0.0283 0.0283 0.0283 0.0283 0.0283 0.0283 0.0283 0.0283 0.0283 0.0283 0.0283 0.0283 0.0283 0.0567
3 PEKERJAAN TIANG GAWANG DAN GARIS PERMAINAN 74,988,168 0.054 0.0090 0.0090 0.0090 0.0090 0.0180
C. PEKERJAAN LAMPU LAPANGAN 800 Lux
1 PENGADAAN DAN PEMASANGAN LAMPU FOP 6,541,908,121 4.702 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239 0.2239
D. PEKERJAAN AREA CA (COMPETITION AREA )
1 PEKERJAAN RENOVASI BANGUNAN PENGELOLA 1,239,031,059 0.891 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445 0.0445
E. PENAMBAHAN DAYA STADION I.G NGURAH RAI 175,950,000 0.126 0.0158 0.0158 0.0158 0.0158 0.0158 0.0158 0.0316

III. STADION KOMPYANG SUJANA, BALI


A. PEKERJAAN PERSIAPAN 87,596,260 0.063 0.0012 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0024 0.0036
B. PEKERJAAN LAPANGAN (FOP)
1 PEKERJAAN PENGGANTIAN RUMPUT & DRAINASE 3,052,557,023 2.194 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.1755
2 PEKERJAAN SISTEM PENYIRAMAN LAPANGAN 856,989,371 0.616 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0648
3 PEKERJAAN TIANG GAWANG DAN GARIS PERMAINAN 74,988,168 0.054 0.0090 0.0090 0.0090 0.0090 0.0180
C. PEKERJAAN LAMPU LAPANGAN 800 Lux
1 PENGADAAN DAN PEMASANGAN LAMPU FOP 5,839,105,321 4.197 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999 0.1999
D. PEKERJAAN AREA CA (COMPETITION AREA )
1 PEKERJAAN, R.GANTI & KM, R.POMPA DAN PENGELOLA 881,471,672 0.634 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317 0.0317
E. PENAMBAHAN DAYA STADION KOMPYANG SUDJANA 147,200,000 0.106 0.0132 0.0132 0.0132 0.0132 0.0132 0.0132 0.0265

IV. LAPANGAN LATIHAN TRISAKTI, BALI


A. PEKERJAAN PERSIAPAN 82,248,352 0.059 0.0011 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0034
B. PEKERJAAN LAPANGAN (FOP)
1 PEKERJAAN PENGGANTIAN RUMPUT & DRAINASE 3,052,557,023 2.194 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.1755
2 PEKERJAAN SISTEM PENYIRAMAN LAPANGAN 856,989,371 0.616 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0648
3 PEKERJAAN TIANG GAWANG DAN GARIS PERMAINAN 74,988,168 0.054 0.0090 0.0090 0.0090 0.0090 0.0180
C. PEKERJAAN LAMPU LAPANGAN 800 Lux
1 PENGADAAN DAN PEMASANGAN LAMPU FOP 5,621,428,921 4.041 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.3848
D. PEKERJAAN AREA CA (COMPETITION AREA )
1 PEKERJAAN, R.GANTI & KM, R.POMPA DAN PENGELOLA 835,868,422 0.601 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300 0.0300
E. PENAMBAHAN DAYA LAPANGAN TRISAKTI 118,450,000 0.085 0.0106 0.0106 0.0106 0.0106 0.0106 0.0106 0.0213

V. LAPANGAN LATIHAN GELORA SAMUDRA KUTA, BALI


A. PEKERJAAN PERSIAPAN 82,248,352 0.059 0.0011 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0023 0.0034
B. PEKERJAAN LAPANGAN (FOP)
1 PEKERJAAN PENGGANTIAN RUMPUT & DRAINASE 3,052,557,023 2.194 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.0878 0.1755
2 PEKERJAAN SISTEM PENYIRAMAN LAPANGAN 856,989,371 0.616 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0324 0.0648
3 PEKERJAAN TIANG GAWANG DAN GARIS PERMAINAN 74,988,168 0.054 0.0090 0.0090 0.0090 0.0090 0.0180
C. PEKERJAAN LAMPU LAPANGAN 800 Lux
1 PENGADAAN DAN PEMASANGAN LAMPU FOP 5,621,428,921 4.041 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.1924 0.3848
D. PEKERJAAN AREA CA (COMPETITION AREA )
1 PEKERJAAN, R.GANTI & KM, R.POMPA DAN PENGELOLA 840,911,201 0.604 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302 0.0302
E. PENAMBAHAN DAYA LAPANGAN GELORA SAMODRA 118,450,000 0.085 0.0106 0.0106 0.0106 0.0106 0.0106 0.0106 0.0213

PROGRES MINGGUAN (%) 139,124,744,175 100.000 0.0309 0.2335 0.6714 0.7164 0.8528 2.0561 2.4510 2.7992 3.7566 3.9117 3.9416 5.0187 5.0990 5.4472 5.4472 5.4670 5.4670 5.0839 5.0839 5.1343 4.5670 4.8103 4.8103 4.8103 4.6739 7.6586
RENCANA
PROGRES MINGGUAN KUMULATIF (%) 0.0309 0.2645 0.9358 1.6522 2.5051 4.5612 7.0121 9.8113 13.5680 17.4797 21.4213 26.4400 31.5391 36.9863 42.4335 47.9005 53.3674 58.4514 63.5353 68.6696 73.2366 78.0469 82.8572 87.6676 92.3414 100.0000

Diketahui Oleh Diperiksa dan Disetujui Oleh


Bali, .............................2020
Kementerian Pekerjaan Umum dan Perumahan Rakyat Management Konstruksi Dibuat Oleh
Satuan Kerja Pelaksanaan Prasarana Permukiman Provinsi Bali PT. Kanta Karya Utama KSO PT. Disiplant Consult PT PP (PERSERO) Tbk

Ni Nengah Satriyani, ST Ir. Aleks Olli Msc, SH, MH


PPK PSP-POP Team Leader Dwi Aji Wicaksono
Project Manager
S CURVE BULANAN
RENOVASI VENUE UTAMA DAN LAPANGAN LATIHAN PIALA DUNIA U-20 DI PROVINSI BALI
PT. PP (PERSERO), TBK
Jangka Waktu Pelaksanaan : 180 Hari Kalender
Mulai : 20 November 2020
Selesai : 18 Mei 2021

2020 2021
NO URAIAN NILAI KONTRAK (Rp) BOBOT (%) NOVEMBER DESEMBER JANUARI FEBRUARI MARET APRIL MEI
1 2 3 4 5 6 7

I. STADION I WAYAN DIPTA, BALI


A. PEKERJAAN PERSIAPAN 1,733,949,710 1.246 0 0 0 0 0 0 0
B. PEKERJAAN STRUKTUR 4,294,863,079 3.087 0 1 2 0 - - -
C PEKERJAAN ARSITEKTUR 13,150,909,374 9.453 - 0 2 4 3 1 -
D PEKERJAAN MEKANIKAL ,ELEKTRIKAL DAN PLUMBING 35,394,149,589 25.441 - 0 1 5 6 6 6
E PEKERJAAN LAPANGAN (FOP) 8,600,196,238 6.182 0 0 1 1 1 1 2
F PEKERJAAN LAMPU LAPANGAN (LAMPU FOP) 2400 Lux 19,122,524,835 13.745 - 1 3 3 3 3 2
G PENGADAAN DAN PEMASANGAN KURSI 5,929,071,520 4.262 - - - 1 1 1 1
H PEKERJAAN KAWASAN 6,634,179,338 4.769 - - 0 1 1 1 1
A. PENAMBAHAN DAYA STADION IWD 112,700,000 0.081 0 0

II. STADION I GUSTI NGURAH RAI, BALI


A. PEKERJAAN PERSIAPAN 88,765,540 0.064 0 0 0 0 0 0 0
B. PEKERJAAN LAPANGAN (FOP) 3,876,534,669 2.786 - 0 1 0 0 0 1
C. PEKERJAAN LAMPU LAPANGAN 800 Lux 6,541,908,121 4.702 - 0 1 1 1 1 1
D. PEKERJAAN AREA CA (COMPETITION AREA ) 1,239,031,059 0.891 - 0 0 0 0 0 0
B. PENAMBAHAN DAYA STADION I.G NGURAH RAI 175,950,000 0.126 - - - - 0 0

III. STADION KOMPYANG SUJANA, BALI


A. PEKERJAAN PERSIAPAN 87,596,260 0.063 0 0 0 0 0 0 0
B. PEKERJAAN LAPANGAN (FOP) 3,984,534,561 2.864 - 0 1 0 0 0 1
C. PEKERJAAN LAMPU LAPANGAN 800 Lux 5,839,105,321 4.197 - 0 1 1 1 1 1
D. PEKERJAAN AREA CA (COMPETITION AREA ) 881,471,672 0.634 - 0 0 0 0 0 0
C. PENAMBAHAN DAYA STADION KOMPYANG SUDJANA 147,200,000 0.106 - - - - - 0 0

IV. LAPANGAN LATIHAN TRISAKTI, BALI


A. PEKERJAAN PERSIAPAN 82,248,352 0.059 0 0 0 0 0 0 0
B. PEKERJAAN LAPANGAN (FOP) 3,984,534,561 2.864 - 0 1 0 0 0 1
C. PEKERJAAN LAMPU LAPANGAN 800 Lux 5,621,428,921 4.041 - - 1 1 1 1 1
D. PEKERJAAN AREA CA (COMPETITION AREA ) 835,868,422 0.601 - 0 0 0 0 0 0
D. PENAMBAHAN DAYA LAPANGAN TRISAKTI 118,450,000 0.085 - - - - - 0 0

V. LAPANGAN LATIHAN GELORA SAMUDRA KUTA, BALI


A. PEKERJAAN PERSIAPAN 82,248,352 0.059 0 0 0 0 0 0 0
B. PEKERJAAN LAPANGAN (FOP) 3,984,534,561 2.864 - 0 1 0 0 0 1
C. PEKERJAAN LAMPU LAPANGAN 800 Lux 5,621,428,921 4.041 - - 1 1 1 1 1
D. PEKERJAAN AREA CA (COMPETITION AREA ) 840,911,201 0.604 - 0 0 0 0 0 0
F. PENAMBAHAN DAYA LAPANGAN GELORA SAMODRA 118,450,000 0.085 - - - - - 0 0

PROGRES MINGGUAN (%) 139,124,744,175 100.000 0.2645 4.2967 16.8601 21.0122 21.1019 19.3219 17.1428
RENCANA
PROGRES MINGGUAN KUMULATIF (%) 0 0.2645 4.5612 21.4213 42.4335 63.5353 82.8572 100.0000

Bali, ........................................... 2020


Diketahui Oleh Diperiksa dan Disetujui Oleh Dibuat Oleh
Kementerian Pekerjaan Umum dan Perumahan Rakyat Management Konstruksi PT PP (PERSERO) Tbk
Satuan Kerja Pelaksanaan Prasarana Permukiman Provinsi Bali PT. Kanta Karya Utama KSO PT. Disiplant Consult

Ni Nengah Satriyani, ST Ir. Aleks Olli Msc, SH, MH Dwi Aji Wicaksono
PPK PSP-POP Team Leader Project Manager
RESUME RENCANA PROGESS BULANAN
RENOVASI VENUE UTAMA DAN LAPANGAN LATIHAN PIALA DUNIA U-20 DI PROVINSI BALI

Progress (%) Progress (Rp)


No Bulan
Rencana Kumulatif Rencana Kumulatif
1 November 2020 0.264 0.264 367,933,223.933 367,933,223.933
2 Desember 2020 4.297 4.561 5,977,820,815.184 6,345,754,039.118
3 Januari 2021 16.860 21.421 23,456,590,475.994 29,802,344,515.112
4 Februari 2021 21.012 42.433 29,233,101,625.374 59,035,446,140.486
5 Maret 2021 21.102 63.535 29,357,914,625.473 88,393,360,765.959
6 April 2021 19.322 82.857 26,881,558,675.946 115,274,919,441.905
7 Mei 2021 17.143 100.000 23,849,824,733.253 139,124,744,175.158
S CURVE MINGGUAN
RENOVASI VENUE UTAMA DAN LAPANGAN LATIHAN PIALA DUNIA U-20 DI PROVINSI BALI
PT. PP (PERSERO), TBK
Jangka Waktu Pelaksanaan : 180 Hari Kalender
Mulai : 6 NOVEMBER 2020
Selesai : 7 MEI 2021

TAHUN 2020 TAHUN 2021


WAKTU PELAKSANAAN
BOBOT NOVEMBER DESEMBER JANUARI FEBRUARI MARET APRIL MEI
NO URAIAN NILAI KONTRAK (Rp) (%) DURASI DURASI 6-8 9 - 15 16 - 22 23 - 29 30 - 6 7 - 13 14 - 20 21 - 27 28 - 3 4 - 10 11 - 17 18 - 24 25 - 31 1-7 8 - 14 15 - 21 22 - 28 1-7 8 - 14 15 - 21 22 - 28 29 - 4 5 - 11 12 - 18 19 - 25 26 - 2 3-7
MULAI SELESAI (Hari) (Minggu) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

I. STADION I WAYAN DIPTA, BALI


A. PEKERJAAN PERSIAPAN 1,733,949,710 1.246 11/6/2020 5/7/2021 183 27 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462 0.0462
B. PEKERJAAN STRUKTUR
1 BANGUNAN TRIBUN BARAT
a. Pekerjaan Struktur Core Lift 207,207,471 0.149 11/23/2020 12/20/2020 28 4 0.0372 0.0372 0.0372 0.0372
b. Pekerjaan Struktur Scoring Board 341,055,701 0.245 12/7/2020 1/3/2021 28 4 0.0613 0.0613 0.0613 0.0613
2 PEKERJAAN TRIBUN EXISTING
a. Tribun Barat 1,635,559,933 1.176 11/9/2020 1/10/2021 63 9 0.1306 0.1306 0.1306 0.1306 0.1306 0.1306 0.1306 0.1306 0.1306
b. Tribun Timur 1,145,033,749 0.823 11/23/2020 1/10/2021 49 7 0.1176 0.1176 0.1176 0.1176 0.1176 0.1176 0.1176
c. Tribun Utara 484,508,098 0.348 11/16/2020 1/3/2021 49 7 0.0498 0.0498 0.0498 0.0498 0.0498 0.0498 0.0498
d. Tribun Selatan 481,498,127 0.346 11/16/2020 1/3/2021 49 7 0.0494 0.0494 0.0494 0.0494 0.0494 0.0494 0.0494
C PEKERJAAN ARSITEKTUR
a. Bangunan Tribun Barat 9,909,188,869 7.123 12/21/2020 3/7/2021 77 11 0.6475 0.6475 0.6475 0.6475 0.6475 0.6475 0.6475 0.6475 0.6475 0.6475 0.6475
b. Bangunan Tribun Timur 1,736,258,101 1.248 12/28/2020 2/21/2021 56 8 0.1560 0.1560 0.1560 0.1560 0.1560 0.1560 0.1560 0.1560
c. Bangunan Tribun Utara 773,165,438 0.556 1/4/2021 2/28/2021 56 8 0.0695 0.0695 0.0695 0.0695 0.0695 0.0695 0.0695 0.0695
d. Bangunan Tribun Selatan 732,296,966 0.526 1/11/2021 3/7/2021 56 8 0.0658 0.0658 0.0658 0.0658 0.0658 0.0658 0.0658 0.0658
D PEKERJAAN MEKANIKAL ,ELEKTRIKAL DAN PLUMBING
1 Pekerjaan Electrical 4,512,949,508 3.244 12/21/2020 3/7/2021 77 11 0.2949 0.2949 0.2949 0.2949 0.2949 0.2949 0.2949 0.2949 0.2949 0.2949 0.2949
2 Pekerjaan Electronic
a. Pekerjaan Telepon 552,521,400 0.397 1/11/2021 3/21/2021 70 10 0.0397 0.0397 0.0397 0.0397 0.0397 0.0397 0.0397 0.0397 0.0397 0.0397
b. Pekerjaan Pendeteksian Dini (Fire Alarm) 580,662,200 0.417 1/25/2021 4/4/2021 70 10 0.0417 0.0417 0.0417 0.0417 0.0417 0.0417 0.0417 0.0417 0.0417 0.0417
c. Pekerjaan Tata Suara (Sound System) 5,467,790,100 3.930 1/25/2021 4/4/2021 70 10 0.3930 0.3930 0.3930 0.3930 0.3930 0.3930 0.3930 0.3930 0.3930 0.3930
d. Pekerjaan Instalasi Closed Circuit Televison (CCTV) 2,098,339,600 1.508 1/11/2021 3/21/2021 70 10 0.1508 0.1508 0.1508 0.1508 0.1508 0.1508 0.1508 0.1508 0.1508 0.1508
e. Pekerjaan Scoreboard dan Perlengkapannya 11,387,148,600 8.185 1/4/2021 5/2/2021 119 17 0.4815 0.4815 0.4815 0.4815 0.4815 0.4815 0.4815 0.4815 0.4815 0.4815 0.4815 0.4815 0.4815 0.4815 0.4815 0.4815 0.4815
f. Pekerjaan Building Automation System (BAS/BMS) 1,715,894,600 1.233 1/11/2021 5/2/2021 112 16 0.0771 0.0771 0.0771 0.0771 0.0771 0.0771 0.0771 0.0771 0.0771 0.0771 0.0771 0.0771 0.0771 0.0771 0.0771 0.0771
3 Pekerjaan Mechanical 9,078,843,580 6.526 1/4/2021 5/2/2021 119 17 0.3839 0.3839 0.3839 0.3839 0.3839 0.3839 0.3839 0.3839 0.3839 0.3839 0.3839 0.3839 0.3839 0.3839 0.3839 0.3839 0.3839
E PEKERJAAN LAPANGAN (FOP)
1 Pekerjaan Lintasan Lari 1,780,498,774 1.280 1/11/2021 4/11/2021 91 13 0.0984 0.0984 0.0984 0.0984 0.0984 0.0984 0.0984 0.0984 0.0984 0.0984 0.0984 0.0984 0.0984
2 Pekerjaan Penggantian Rumput & Drainase 4,434,940,659 3.188 12/13/2020 5/2/2021 141 21 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518 0.1518
3 Pekerjaan Sistem Penyiraman Lapangan 653,589,367 0.470 2/22/2021 5/2/2021 70 10 0.0470 0.0470 0.0470 0.0470 0.0470 0.0470 0.0470 0.0470 0.0470 0.0470
4 Pekerjaan Tiang Gawang, Perlangkapan dan Garis Permainan 1,731,167,438 1.244 4/5/2021 5/7/2021 33 5 0.2489 0.2489 0.2489 0.2489 0.2489
F PEKERJAAN LAMPU LAPANGAN (LAMPU FOP) 2400 Lux
a. Pengadaan dan Pemasangan Lampu FOP 19,122,524,835 13.745 12/21/2020 5/2/2021 133 19 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234 0.7234
G PENGADAAN DAN PEMASANGAN KURSI
a. Pengadaan dan Pemasangan Kursi 5,929,071,520 4.262 12/28/2020 5/7/2021 131 19 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243 0.2243
H PEKERJAAN KAWASAN
1 Pekerjaan Pagar 3,318,705,655 2.385 1/18/2021 5/7/2021 110 16 0.1491 0.1491 0.1491 0.1491 0.1491 0.1491 0.1491 0.1491 0.1491 0.1491 0.1491 0.1491 0.1491 0.1491 0.1491 0.1491
2 Pekerjaan Jalan dan Area Parkir 873,698,309 0.628 2/1/2021 5/2/2021 91 13 0.0483 0.0483 0.0483 0.0483 0.0483 0.0483 0.0483 0.0483 0.0483 0.0483 0.0483 0.0483 0.0483
3 Pekerjaan Normalisasi Saluran Kawasan 737,756,479 0.530 2/8/2021 5/2/2021 84 12 0.0442 0.0442 0.0442 0.0442 0.0442 0.0442 0.0442 0.0442 0.0442 0.0442 0.0442 0.0442
4 Pekerjaan Plaza 1,373,739,770 0.987 2/8/2021 5/2/2021 84 12 0.0823 0.0823 0.0823 0.0823 0.0823 0.0823 0.0823 0.0823 0.0823 0.0823 0.0823 0.0823
5 Pekerjaan Landsekap 330,279,125 0.237 2/22/2021 5/7/2021 75 11 0.0216 0.0216 0.0216 0.0216 0.0216 0.0216 0.0216 0.0216 0.0216 0.0216 0.0216

II. STADION I GUSTI NGURAH RAI, BALI


A. PEKERJAAN PERSIAPAN 88,765,540 0.064 11/16/2020 4/18/2021 154 22 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029
B. PEKERJAAN LAPANGAN (FOP)
1 PEKERJAAN PENGGANTIAN RUMPUT & DRAINASE 3,052,557,023 2.194 11/16/2020 3/14/2021 119 17 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291
2 PEKERJAAN SISTEM PENYIRAMAN LAPANGAN 748,989,479 0.538 12/21/2020 3/14/2021 84 12 0.0449 0.0449 0.0449 0.0449 0.0449 0.0449 0.0449 0.0449 0.0449 0.0449 0.0449 0.0449
3 PEKERJAAN TIANG GAWANG DAN GARIS PERMAINAN 74,988,168 0.054 2/8/2021 3/14/2021 35 5 0.0108 0.0108 0.0108 0.0108 0.0108
C. PEKERJAAN LAMPU LAPANGAN 800 Lux
1 PENGADAAN DAN PEMASANGAN LAMPU FOP 6,541,908,121 4.702 12/14/2020 4/18/2021 126 18 0.2612 0.2612 0.2612 0.2612 0.2612 0.2612 0.2612 0.2612 0.2612 0.2612 0.2612 0.2612 0.2612 0.2612 0.2612 0.2612 0.2612 0.2612
D. PEKERJAAN AREA CA (COMPETITION AREA )
1 PEKERJAAN RENOVASI BANGUNAN PENGELOLA 1,239,031,059 0.891 12/14/2020 3/7/2021 84 12 0.0742 0.0742 0.0742 0.0742 0.0742 0.0742 0.0742 0.0742 0.0742 0.0742 0.0742 0.0742

III. STADION KOMPYANG SUJANA, BALI


A. PEKERJAAN PERSIAPAN 87,596,260 0.063 11/16/2020 4/18/2021 154 22 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029 0.0029
B. PEKERJAAN LAPANGAN (FOP)
1 PEKERJAAN PENGGANTIAN RUMPUT & DRAINASE 3,052,557,023 2.194 11/16/2020 3/14/2021 119 17 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291
2 PEKERJAAN SISTEM PENYIRAMAN LAPANGAN 856,989,371 0.616 12/21/2020 3/14/2021 84 12 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513
3 PEKERJAAN TIANG GAWANG DAN GARIS PERMAINAN 74,988,168 0.054 2/8/2021 3/14/2021 35 5 0.0108 0.0108 0.0108 0.0108 0.0108
C. PEKERJAAN LAMPU LAPANGAN 800 Lux
1 PENGADAAN DAN PEMASANGAN LAMPU FOP 5,839,105,321 4.197 12/14/2020 4/18/2021 126 18 0.2332 0.2332 0.2332 0.2332 0.2332 0.2332 0.2332 0.2332 0.2332 0.2332 0.2332 0.2332 0.2332 0.2332 0.2332 0.2332 0.2332 0.2332
D. PEKERJAAN AREA CA (COMPETITION AREA )
1 PEKERJAAN, R.GANTI & KM, R.POMPA DAN PENGELOLA 881,471,672 0.634 12/14/2020 3/7/2021 84 12 0.0528 0.0528 0.0528 0.0528 0.0528 0.0528 0.0528 0.0528 0.0528 0.0528 0.0528 0.0528

IV. LAPANGAN LATIHAN TRISAKTI, BALI


A. PEKERJAAN PERSIAPAN 82,248,352 0.059 11/16/2020 4/18/2021 154 22 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027
B. PEKERJAAN LAPANGAN (FOP)
1 PEKERJAAN PENGGANTIAN RUMPUT & DRAINASE 3,052,557,023 2.194 11/16/2020 3/14/2021 119 17 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291
2 PEKERJAAN SISTEM PENYIRAMAN LAPANGAN 856,989,371 0.616 12/21/2020 3/14/2021 84 12 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513
3 PEKERJAAN TIANG GAWANG DAN GARIS PERMAINAN 74,988,168 0.054 2/8/2021 3/14/2021 35 5 0.0108 0.0108 0.0108 0.0108 0.0108
C. PEKERJAAN LAMPU LAPANGAN 800 Lux
1 PENGADAAN DAN PEMASANGAN LAMPU FOP 5,621,428,921 4.041 12/14/2020 4/18/2021 126 18 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245
D. PEKERJAAN AREA CA (COMPETITION AREA )
1 PEKERJAAN, R.GANTI & KM, R.POMPA DAN PENGELOLA 835,868,422 0.601 12/14/2020 3/7/2021 84 12 0.0501 0.0501 0.0501 0.0501 0.0501 0.0501 0.0501 0.0501 0.0501 0.0501 0.0501 0.0501

V. LAPANGAN LATIHAN GELORA SAMUDRA KUTA, BALI


A. PEKERJAAN PERSIAPAN 82,248,352 0.059 11/16/2020 4/18/2021 154 22 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027 0.0027
B. PEKERJAAN LAPANGAN (FOP)
1 PEKERJAAN PENGGANTIAN RUMPUT & DRAINASE 3,052,557,023 2.194 11/16/2020 3/14/2021 119 17 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291 0.1291
2 PEKERJAAN SISTEM PENYIRAMAN LAPANGAN 856,989,371 0.616 12/21/2020 3/14/2021 84 12 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513 0.0513
3 PEKERJAAN TIANG GAWANG DAN GARIS PERMAINAN 74,988,168 0.054 2/8/2021 3/14/2021 35 5 0.0108 0.0108 0.0108 0.0108 0.0108
C. PEKERJAAN LAMPU LAPANGAN 800 Lux
1 PENGADAAN DAN PEMASANGAN LAMPU FOP 5,621,428,921 4.041 12/14/2020 4/18/2021 126 18 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245 0.2245
D. PEKERJAAN AREA CA (COMPETITION AREA )
1 PEKERJAAN, R.GANTI & KM, R.POMPA DAN PENGELOLA 840,911,201 0.604 12/14/2020 3/7/2021 84 12 0.0504 0.0504 0.0504 0.0504 0.0504 0.0504 0.0504 0.0504 0.0504 0.0504 0.0504 0.0504

VI. PENAMBAHAN DAYA


A. PENAMBAHAN DAYA STADION IWD 112,700,000 0.081 3/29/2021 5/7/2021 40 6 0.0135 0.0135 0.0135 0.0135 0.0135 0.0135
B. PENAMBAHAN DAYA STADION I.G NGURAH RAI 175,950,000 0.126 3/8/2021 4/18/2021 42 6 0.0211 0.0211 0.0211 0.0211 0.0211 0.0211
C. PENAMBAHAN DAYA STADION KOMPYANG SUDJANA 147,200,000 0.106 3/8/2021 4/18/2021 42 6 0.0176 0.0176 0.0176 0.0176 0.0176 0.0176
D. PENAMBAHAN DAYA LAPANGAN TRISAKTI 118,450,000 0.085 3/8/2021 4/18/2021 42 6 0.0142 0.0142 0.0142 0.0142 0.0142 0.0142
F. PENAMBAHAN DAYA LAPANGAN GELORA SAMODRA 118,450,000 0.085 3/8/2021 4/18/2021 42 6 0.0142 0.0142 0.0142 0.0142 0.0142 0.0142

PROGRES MINGGUAN (%) 139,124,744,175 100.000 0.0462 0.0462 0.7042 0.8406 0.9582 1.1713 2.3421 4.1695 4.5498 5.4233 5.7560 5.6569 6.0916 6.1399 6.3095 6.3095 6.2221 6.1526 4.9841 4.2258 4.0353 4.0488 3.8629 3.7645 2.7429 2.7429 0.7035
RENCANA
PROGRES MINGGUAN KUMULATIF (%) 0.0462 0.0923 0.7965 1.6371 2.5953 3.7666 6.1086 10.2781 14.8279 20.2512 26.0072 31.6641 37.7557 43.8956 50.2052 56.5147 62.7368 68.8894 73.8735 78.0993 82.1346 86.1834 90.0463 93.8107 96.5536 99.2965 100.0000