Professional Documents
Culture Documents
Summary Sheet #5
Summary Sheet #5
C19:
Costs associated with Goods for Sale: Purchasing costs, Ordering costs, Carrying costs, Stockout
costs, Costs of quality, Shrinkage costs
Economic order quantity (EOQ): calculates the optimal quantity of inventory to order under a given
set of assumptions
Safety stock: extra inventory held at all times above the quantity of inventory ordered
determined by the EOQ model
Just-in-time (JIT) Procurement (demand-pull manufacturing system): Price and quality terms are
defined by long-term purchase agreements; Electronic links are used to place POs at a fraction of the
cost of a traditional method (reduce the cost of placing PO – smaller EOQ)
Benefits of JIT:
1) Lower overhead costs - reduced need for materials handling, warehousing and inspection leads
2) Lower inventory levels - lower carrying costs of inventory
3) Focus on Quality - eliminating the specific causes of rework, scrap, and waste
4) Shorter manufacturing lead times
Materials Requirements Planning (MRP): a push-through system that manufactures finished goods
for inventory on the basis of demand forecasts
1) MRP sources: Demand forecasts of final products, A bill of materials (detailing); The quantities of
materials, components, and product inventories
2) Takes into account lead time; Sets a master production schedule; output of each department is
pushed through the production line whether it is needed or not (may result in an accumulation of
inventory)
Enterprise Resource Planning (ERP): Integrated set of software modules including accounting,
distribution, manufacturing, purchasing and human resources; a single database in real time
highlighting interdependencies and bottlenecks in business processes
C20:
Payback: Measures the time it will take to recoup the net initial investment in a project; doesn’t
recognize the time value of money and doesn’t consider the cash flow past the payback
point
Accrual Accounting Rate of Return Method (AARR or ARR): Fails to recognize the time value of
money and it does not track cash flows
Time Value of Money; Discounted cash flow methods (NPV) use the required rate of return (RRR)
Required rate of return (RRR) is also called discount rate, hurdle rate, cost of capital, opportunity
cost of capital
If NPV = 0, the return on investment = the RRR; If NPV is greater than 0, the return on investment is
greater than the RRR; A negative NPV means that the project will not yield the RRR
Internal Rate of Return (IRR): Calculates the discount rate at which the NPV = 0; Trial and error
approach; acceptable only if IRR >= RRR
NPV is preferred compared to IRR; NPV is in dollars
Major Types of Cash Flows: Initial invest; disposal; operating CFs that differ between alternatives;
Income tax impact
Sensitivity Analysis when calculating NPV: what if assumptions and estimates change
2
PV of tax shield on CCA:
r= discount rate
3
4