Professional Documents
Culture Documents
3.4.instrument Location Plan
3.4.instrument Location Plan
Junction Box
• An electrical junction box is a container for electrical connections.
• A small metal or plastic junction box may form part of an electrical conduit (A pipe or
channel for conveying fluids, such as water/ a tube or duct for enclosing electric wires
or cable.)
• Wiring system in a building, or may be buried in the plaster of a wall, concealed behind
an access panel or cast into concrete with only the lid showing.
• It sometimes includes terminals for joining wires.
• A similar container used for joining wires to electrical switches or sockets is called a
pattress.
• Junction boxes form an integral part of a circuit protection system where circuit
integrity has to be provided, as for emergency lighting or emergency power lines, or
the wiring between a nuclear reactor and a control room.
• In such an installation, the fireproofing around the incoming or outgoing cables must
also be extended to cover the junction box to prevent short circuits inside the box during
an accidental fire.
• Junction box is an enclosure used for cables interconnection between field devices and
control room.
• It encloses terminal strips for cable termination.
• Junction box shall be designed to suit environmental condition where the box will be
installed and shall have certification of Ingress Protection code and hazardous area
protection which conform to the classified area.
Junction Box consists of the following parts:
• Terminal block which comprises terminal strips for cable connections
• Gland plate (for non metallic junction box) for cable gland earthing
• An insulated earth bus bar for overall cable screen termination (optional, drain wire
could be connected to terminal strip)
• Mounting Rail complete with end bracket
It shows our TK-10 product tank, a typical vessel with a level control system, fixed-
speed discharge pump PP-10, and a recirculation system.
The pump has a HOA switch and a contact closure to provide pump status to the
computer.
Instrument station boxes represent the instruments.
The instrument station concept lets one box represent several instruments provided the
instruments are physically grouped.
• Location plan symbols and level of detail can differ from one customer to the next.
• But, they generally consist of a graphic representation of some portion of the process
floor, a component schedule, and possibly some detail sketches for clarification.
• These drawings are usually fairly large (22 by 34inches, for example).
• In general, the graphic presentation should cover approximately 50% of the drawing
area (usually the left side of the drawing).
• The scale of the graphical portion can vary widely since the only limitation is the
instrument density and level of detail.
Major pieces of equipment such as tanks and pumps should be shown for orientation
purposes.
These should be in a light line weight and appear as background.
They should be identified in some low-key manner such as, perhaps, the vessel tag
number or equipment name.
Instruments should be depicted near their expected final location either with bubbles or
numbered boxes.
Instrument elevation and instrument installation detail assignments should be noted
either on the body of the plan or in the component schedule.
Field junction boxes should be properly depicted and labeled.
Conduit should be represented in some fashion. Conduit size should be shown,
especially at reduction points, and conduit runs (cable routings) should be tagged.
A component schedule must provide the detail that the simplified graphic presentation
lacks.
The most efficient way to generate the component schedule is from the instrument
database as a report, but it can be maintained in Microsoft® Excel or any other medium.
If a database solution is sought, the instrument plan report (see the instrument database
section) can be easily modified as the drawing develops and then be pulled onto the
drawing just before it is finalized.
3. Design Considerations
During production of the plan drawing, the designer would be wise to consider the
following issues:
• Hazardous area classifications. Designers must understand the ramifications of the
area classification in effect for each process area. They must be sensitive to these
requirements when mounting remote transmitters and field junction boxes.
• Ergonomic considerations. Plant personnel must be able to transit the area, either on
foot or driving fork trucks or golf carts. Junction boxes and instrument stands should
be situated away from high-traffic areas to protect them from damage from fork trucks
or other vehicles.
• Maintenance accessibility. Be aware of any maintenance issues that might require
extraordinary requirements for accessibility in the process area. For example, a vessel
might need to be removed periodically for cleaning or refurbishing. Avoid mounting
equipment around temporary installations, and certainly avoid using any such item for
support.
Fig .2 Instrument location plan design. Step two: locate major equipment items
Fig 3. Instrument location plan design. Step three: locate instrument items
Fig 4. Instrument location plan design. Step four: add instrument stations
When an ideal location has been determined based on instrument station groupings and
the anticipated size of the box is known, the junction box can be tentatively spotted on
the instrument plan.
e.Route Conduit
• If you picture a conduit run in three dimensions, it typically exits a junction box,
rises to the overhead, travels along the overhead supported by structural beams
or some other support structure, and then begins to branch (see Fig.5).
• As the branches approach instrument stations or instrument station clusters, the
conduit drops along some vertical support to the instrument station.
• When viewed from above, such conduit runs appear similar to the branches of
a tree.
• Therefore the term trunk is used to describe the part of the conduit run that is
common to all the branches.
• Branches are common to groups of instrument stations, and drops refer to the
vertical sections of conduit that feed the instrument stations themselves.
Figure 10 shows a typical floor arrangement with conduit routing numbers added.
i. Generate a Component Schedule
The instrument location plan component schedule is a table that provides detail
about each instrument station.
This table usually appears in the upper right corner of the drawing.
A row of information is provided for each element represented by the instrument
station boxes.
As previously noted, a single instrument station box can represent multiple
instruments.
Therefore, instrument station numbers might be repeated several times in the
table.
Each instrument will have its own record in the table.
Beyond crossing the instrument station numbers to their associated instruments,
the component schedule crosses each instrument to its cable code.
Schedule
• Managing information about cabling from cabinet to cabinet or from device to cabinet
is very important to the constructor.
• It is also important to maintain this information as a permanent record in case of fire
for the purpose of disaster recovery.
• Since this type of information presents well in a tabular format, a series of tables, called
schedules.
• The schedules are most meaningful when accompanied by another tool called a location
plan drawing.
Cable Schedule
• Cable Schedule is a document containing list of instrument cable.
• Point-to-point wiring information is provided in a chart called a cable schedule.
• This document shows cable as well as gland required by each instrument or connection.
The information of the cable schedule shall consists:
• Cable Number
• Cable Type / Specification
• Cable Size
• Cable Length
• Source and destination termination description
• Cable gland type and size for each incoming cable
• Routing information is also provided in which each conduit and/or cable tray used is
listed.
Figure 11 depicts a cable (Cable W1) that is routed between a control panel (CP1) and a
junction box (JB2). The cable passes through conduit to a cable tray system. It then transits
back to conduit, and on to JB2.
Figure 11. Defining the cable route (wire W1, Route C1/T1/T2/C2/C2a)
Purpose of Cable Schedule
• Cable schedule is a reference in preparing Material Take-Off of cable for
procurement.
• Cable length shown on this document are approximate only.
• Therefore, there should be contingency for material procurement to allow spare for
cable cutting, unexpected barrier in the field, riser, etc.
• Cable schedule will be referred also during construction phase, however it is not
recommended to cut the cable based on the length information stated on the cable
schedule.
• For actual cutting during installation, the common practice is to pull the cable from
its drum and cut in the field.
Figure 12 shows a record in the cable schedule for cable W1 shown in Figure 11.
Drawing numbers are omitted here, but should be provided on both the source and
destination.
Note that the routing code (C1/T1/T2/C2/C2a) includes the entire path of the cable
through each conduit and tray leg.
Air Header
• An air header for an industrial air filter, said air header including a generally flat surface
which comprises means for mounting a first row of valves and a second row of valves
extending longitudinally along a length of said surface, said first row of valves being
offset laterally and longitudinally staggered from said second row of valves.