Method Statement Cleaning and Flushing of Pipework
Method Statement Cleaning and Flushing of Pipework
Abdali - Boulevard
TITLE OF METHOD STATEMENT : Cleaning, Flushing and Chemical Treatment Ref: MS - C10 No 8 Rev 0
of Hydronic Systems Pipe work
01 Scope of Work
02 Responsibility
03 Description of Works
05 Supervision Arrangements
08 Attachments
Abdali - Boulevard
TITLE OF METHOD STATEMENT : Cleaning, Flushing and Chemical Treatment Ref: MS - C10 No 8 Rev 0
of Hydronic Systems Pipe work
2.0 RESPONSIBILITY
2.1 The Construction manager is responsible over all for the implementation of the method statement, to
ensure that the team of engineers and foremen and operatives are aware of this method statement and,
to ensure that all resources (labour, material and equipment) are available to carry out the work as
planned.
2.2 The Senior Representatives of the service providers (Third Party Commissioning Organization and
Water Treatment Specialist) are responsible for carrying out the work as per the approved method
statement. They are also responsible for ensuring that adequate equipment for mobilization works is in
place prior to the starting of work.
2.3 The QA/QC Engineer is responsible for ensuring that the operations have been performed as per the
specification, for ensuring that the inspections are done as per Quality Control Procedure and that the
Inspections, and the works are offered for approval to the Employer's Commissioning Authority
Representative (CxA) and the Engineer as specified.
2.4 The Safety Engineer is responsible for ensuring that all safety precautions are in place, and that all
personnel onsite are using the prescribed Personal Protective Equipment (helmet, gloves, safety shoes,
coveralls, eye protection etc.). The Safety Engineer must also ensure that all relevant permissions are
available for the works.
2.5 With reference to specification sections 01815-1.7.E and 01815-3.3.G the CxA shall review and
comment on the plan for carrying out the works covered by this method statement including the testing
witnessing and final reports. Recommendations for the testing and witnessing are included in attachment
g). CxA shall certify that pipe cleaning, flushing, hydrostatic tests and chemical treatment have been
completed.
Abdali - Boulevard
TITLE OF METHOD STATEMENT : Cleaning, Flushing and Chemical Treatment Ref: MS - C10 No 8 Rev 0
of Hydronic Systems Pipe work
3.1 Objectives
3.1.1 To flush and clean the hydronic systems prior to operation.
3.1.2 To minimize the corrosion in the system metals.
3.1.3 To inhibit the formation of scale and sludge.
3.1.4 To inhibit the growth of microbiological organisms.
3.1.5 To maintain the engineering design and efficiency of the systems.
3.1.6 The objective should be to plan the flushing and chemical cleaning as one continuous process with no
delays between the flushing and chemical cleaning
3.2 Preliminary Works
3.2.1 Ensure that all safety requirements are in place, in accordance with the project safety plan.
3.2.2 Ensure that all Technicians and helpers are aware of the correct materials handling and application
procedures to ensure the best quality of workmanship. Toolbox talks shall be conducted by the works
supervisor, at maximum intervals of every fortnight, to highlight training and special needs for the
subject works
3.2.3 All materials shall be ordered after approval of the relevant drawings and material submittals.
3.3.4 Ensure that the latest revisions of the shop drawings are used for assessment of the water volume
and corresponding chemical quantity to be used.
3.3.5 It is envisaged that the major handling and application of chemicals will take place in and adjacent to
the ETS room at P1 Level. Care shall be taken to protect adjacent works from accidental chemical
spillage by covering by polythene/plastic sheets
3.3.6 On receipt of the material at site store, the same shall be inspected by the Store Keeper / Site
Engineer / QA/QC Engineer, to ensure the materials are delivered, in a good condition and without
damage, and are as per the approved material submittal.
3.3.7 Inspection request (MIR) shall be raised for Engineer’s approval, before transferring the materials to
site for application.
Abdali - Boulevard
TITLE OF METHOD STATEMENT : Cleaning, Flushing and Chemical Treatment Ref: MS - C10 No 8 Rev 0
of Hydronic Systems Pipe work
3.3.8 The Site Engineer shall ensure that all necessary access panels have been provided to enable re-
circulating points, valves and strainers to be reached during the progress of the works. This
requirement applies for example, to the access panel adjacent to each apartment fan coil unit, and the
re-circulating points at the ends of heating and chilled water mains in apartment corridors.
3.3.9 The Site Engineer shall ensure that there are no obstructions to the performance of the cleaning and
flushing operations in the work area.
3.3.10 The Site Engineer shall ensure that all tools and equipment are available as per the scheduled tasks,
and that they are suitable for their intended purpose, and comply with relevant contract requirements.
Abdali - Boulevard
TITLE OF METHOD STATEMENT : Cleaning, Flushing and Chemical Treatment Ref: MS - C10 No 8 Rev 0
of Hydronic Systems Pipe work
3.4.11Check that all drain cocks are set in their operational position.
3.4.12Ensure that access is maintained to all manual valve wheels and to the actuators of automatically
controlled valves.
3.4.13Ensure that there are adequate provisions for introducing chemicals into the systems (dosing pots), and
for drainage of water from the systems during flushing.
3.4.14Ensure that there is an adequate and permanent supply of electrical power for operation of associated
pumps.
Abdali - Boulevard
TITLE OF METHOD STATEMENT : Cleaning, Flushing and Chemical Treatment Ref: MS - C10 No 8 Rev 0
of Hydronic Systems Pipe work
reference 1.
3.2.6 Commence dynamic flushing with the primary ring main at P1 level, after first confirming that the
risers in each building are isolated.
3.2.7 With the primary ring main fully primed, turn on the temporary flushing pump. Gradually open the
drain valve until the drain rate balances the mains water flow into the temporary flushing tank. See
attachment f)
3.2.8 Turn on the primary pump and adjust the drain valve until the drain rate balances the mains flow
into the flushing tank. Monitor the pump motor current to ensure that full load current is not
exceeded.
3.2.9 Circulate water around the primary ring for a minimum of 1 hour.
3.2.10 Measure the flow rate in the primary ring to ensure that the required flushing velocity is being
achieved.
3.2.11 Run the pumps until the drain water runs clear.
3.2.12 Stop the pumps and close the drain valve, isolate and clean strainers.
3.2.13 Replace the strainer baskets and repeat the process until the strainer baskets no longer collect
significant amounts of sediment.
3.2.14 Repeat the process gradually introducing the risers and horizontal mains of the upper floors to the
process, in a pre-determined sequence.
3.2.15 If individual circuits or sections of pipe are left isolated for a period of time after flushing, the
soluble iron level of the water will increase, and to bring all parts of the system back within required
limits, the entire system should be flushed again simultaneously.
3.2.16 Sections 3.2.5 to 3.2.15 should be performed separately for the chilled water and heating systems.
3.2.17 Proceed to the Chemical Cleaning phase, within 24 hours of completion of the flushing process.
3.2.18 Fresh cleaning agent (NCE-1as per the attached data sheet) will be introduced to the systems
under the direction of the water treatment supervisor, and circulated for 12 to 16 hours. This stage
of the procedure is intended to remove oil, grease, rust and suspended material from the service
Abdali - Boulevard
TITLE OF METHOD STATEMENT : Cleaning, Flushing and Chemical Treatment Ref: MS - C10 No 8 Rev 0
of Hydronic Systems Pipe work
equipment.
3.2.19 Flush the system with fresh water to remove any residue of the cleaning agent NCE-1, and
dissolved materials.
3.2.20 Introduce the cleaning and passivating product (NCE-6 as per the attached data sheet), to
neutralize the system and to passivate the internal surfaces of the pipes. This stage will take
between 4 and 6 hours.
3.2.21 On completion of the passivation stage the system will be flushed once more with clean water to
remove all remaining traces of chemical cleaning agents, and then completely refilled using fresh
softened water.
3.2.22 The final stage in the process is the adding of corrosion inhibitors and biocides, and at this point
the temporary flushing loops should be removed or isolated so that the FCU's, AHUs heat
exchangers and system pumps are included in the system.
3.2.23 Following the complete filling of the heating and cooling systems with softened water, the final
stage of the process will be commenced, and which entails dosing with Biocides and Corrosion
Inhibitor. In the case of the chilled water system dosing will be with Bionetro 1020 and Biocide 190,
and for the heating system Oxyscan 5020 will be used. For the volumes required, and the target
water parameters refer to the information on the attached data sheets.
3.2.24 RSS or an equivalent approved organization as directed by the CxA, will be engaged to carry out
the sample testing outlined in attachments g) and h).
3.2.25 Note: When systems for future retail areas and offices are added, it is important that these
systems are subjected to the same comprehensive cleaning and flushing described above, before
physically connecting to the main distribution networks, to avoid contamination.
Abdali - Boulevard
TITLE OF METHOD STATEMENT : Cleaning, Flushing and Chemical Treatment Ref: MS - C10 No 8 Rev 0
of Hydronic Systems Pipe work
3) Water meter
4) Temporary flushing tank.
5) Temporary flushing pump.
5. SUPERVISION ARRANGEMENTS
The supervision of these works will be under the direct control of the Construction Manager, assisted
by the Sector Engineer, Site Engineers and Foremen with the back – up from the Technical Department.
All Subcontractor works will be coordinated and controlled by the Construction Manager. A full time
competent Subcontractor Project Supervisor shall be deployed to the site.
Abdali - Boulevard
TITLE OF METHOD STATEMENT : Cleaning, Flushing and Chemical Treatment Ref: MS - C10 No 8 Rev 0
of Hydronic Systems Pipe work
08. ATTACHMENTS
Abdali - Boulevard
TITLE OF METHOD STATEMENT : Cleaning, Flushing and Chemical Treatment Ref: MS - C10 No 8 Rev 0
of Hydronic Systems Pipe work