A.

Work Description:
1. Provision of 2 new urinals in Players changing room.
2. Relocation of 1no. Wall mounted hand dryer.
3. Provision of 1no. Boot sink.
4. Removal and re-fixing of existing sanitary wares.

B. Cost Estimation:
METHOD OF
ESTIMATED ESTIMATED
STATEMENT ITEM DESCRIPTION UNIT RATE REMARKS
QUANTITY COST
CODE

Material Cost
1 Urinal with partition Set 2 0.00 Waterless
2 4" PVC pipe length 2 0.00
3 2" x 4" PVC reducer length 1 0.00
4 2" PVC pipe length 4 0.00
5 2" PVC wye Nos 1 0.00
6 2" x 90° PVC elbow Nos 1 0.00
7 2" x 45° PVC elbow Nos 1 0.00
8 4" x 90° PVC elbow Nos 1 0.00
Boot wash sink including Cold & Hot water
9 Mixer with cold and hot water PPR piping, Nos 1 0.00 Janitor type
insulation etc.
Miscellenious items (pvc fittings,PPR
10 fittings, Valves,teflon, glue, sealant, lot 1 0.00
screws, etc.)
11 Linear Shower drain channel type Nos 8 0.00
12 4" Floor Drain Nos 9 0.00
13 Hand Spray with angle valve Nos 4 0.00
Material Cost 0.00
10% Plus 0.00
Total Material Cost QR 0.00
Labor Cost QTY Required Total
Engineer 1.00 5 0.00
Supervisor 1.00 12 0.00
1 - Skilled 1.00 96 0.00
2 - Semiskilled 2.00 96 0.00
Total Labor Cost QR 0.00
Total cost 0.00

C. Planned Work Schedule:

Commencement Date : Completion Date :

D. ASPIRE ZONE'S APPROVAL

Representative's Name : Signature / Approval :

E. Remarks

1. The above Mechanical cost estimate is for budgeting purposes only. Actual price may increase or decrease depending on the actual
site requirements. All quantities and prices are tentative only.

2. Civil and electrical cost is not included on this estimate.