ESTIMATE ( MAN & EQUIPMENT ) HOURS FOR CIVIL ACTIVITIES

Hour Rate
MH/Unit
ACTIVITY DESCRIPTION UNIT DAILY OUTPUT CREW SRUCTURE

SITE WORK

UTILITY WORK
Trench Excavation (Width 60 cm , not to exceed 1
m deep) , 10 Km hauling
LM 100.0 1-Backhoe 0.57 m3 , 2-Dump Truck ,3-Labourer 0.24
Trench Excavation (Width 60 cm , not to exceed 2
m deep) , 10 Km hauling
LM 70.0 1-Backhoe 0.57 m3 , 2-Dump Truck ,3-Labourer 0.34
Trench Excavation (Width 100 cm , not to exceed 5
m deep) , 10 Km hauling
LM 35.0 1-Backhoe 1.15 m3 , 4-Dump Truck , 4-Labourer 1.37
1-Mini Loader , Vibrating Plate , Water Tanker , 4-
Backfill & Compact Trench M3 36.0
Labourer
0.89
Excavating Utility Trench 0.2 m Wide , 0.9 m Deep LM 75.0 1-Trencher-Chain 12 HP , 2 Labourer 0.21
BUILDING WORK
Excavation for Raft Foundation , 10 Km hauling M3 150.0 1-Backhoe Optr., 2-Dump Truck Driver,3-Labourer 0.16
Excavation for Isolated Footings , 10 Km hauling M3 100.0 1-Backhoe Optr., 2-Dump Truck Driver,3-Labourer 0.24
1-Mini Loader Optr., 1-compactor, Water Tanker , 3-
Backfill around Footings M3 60.0
Labourer
0.400
Excavating Only & Haul in Pile By Dozer 75 HP , 15
m Haul , Common Earth
M3 350.0 2- Labor , 1- Dozer 75 HP 0.046
Excavation for Elevator Pits and Building Foundation
, Common Earth
M3 163.0 1- Hydralulic Excavator 1.15 m3 , 2-Labor 0.098
Backfill From Existing Stockpile , No Compaction ,
15 m Haul , Common Earth
M3 373.0 2- Labor , 1- Dozer 75 HP 0.043

EARTHWORK EQUIPMENT PRODUCTION

DOZING
Dozing, Ripping & Stock Piling in Soil M2 1000 1 Operator + 2 Laborer 0.02
Dozing, Ripping & Stock Piling in Rock M2 400 1 Operator + 2 Laborer 0.04
LOADING
Loading in Soil , From Stockpile M3 600 1 Operator + 1 Laborer 0.01
Loading in Rock , From Stockpile M3 450 1 Operator + 1 Laborer 0.02
Loading Excavated Material on Trucks & Hauling to
32 Km Round Trip
M3 512 2- Labor , 1-Shovel 2 m3 Bucket , 8- Dump Truck 15 Ton 0.031
Loading Excavated Material on Trucks & Hauling to
80 Km Round Trip
M3 216 2- Labor , 1-Shovel 2 m3 Bucket , 8- Dump Truck 15 Ton 0.074
HAULING
Hauling 20km/in Soil M3 48 1 Dump Truck
Hauling 20km/in Soil M3 72 1 Dump Truck
Hauling 20km/in Rock M3 48 1 Dump Truck
Hauling 20km/in Rock M3 72 1 Dump Truck
Hauling 7km/in Soil M3 144 1 Dump Truck
Hauling 7km/in Soil M3 176 1 Dump Truck
Hauling 7km/in Rock M3 144 1 Dump Truck
Hauling 7km/in Rock M3 176 1 Dump Truck
Hauling Excavated or Borrow Material , 15 m3 Dump
Truck , Round Trip 10 Km
M3 1192 2- Labor , 4- Dump Truck , 1- Shovel Bucket 2.92 m3 0.013
Hauling Excavated or Borrow Material , 15 m3 Dump
Truck , Round Trip 32 Km
M3 448 2- Labor , 4- Dump Truck , 1- Shovel Bucket 2.92 m3 0.036

DRILLING FOR BLASTING


Drilling for Blasting at spacing of 1.5 M C C In Solid
Rock
M3 184 1 Operator + 1 Laborer 0.04
Blasting m3 300 2 Blasting Technician + 10 Laborer 0.32
Cover During Blasting M3 70 M2 / 30000 M3

BRI-STAR TECHNIQUE
Drilling with Drilling Wagon For 1m Deep LM 120 1 Operator + 1 Laborer 0.07
Filling Bri-Star Materials For 1.0m Deep Holes 2kgs
m3 1 Filling Technician + 4 Laborer
of B.S. (0.18 M3 are used)
120LM/day = 1
Production of 1 Drilling Wagon 20'0 18/2 = 11M 3
day

CONCRETE ACTIVITIES AS A BULK

Blinding Concrete M2 60.0 2-Rghcarp., 2-Mason, 3-Labourer 0.93


Foundation (Forms & Rebar fixing included and
Concrete Placing , )
Isolated footing under 0.75 M3 M3 10.0 1 Gang Leader , 6-Rghcarp., 2-Stlfxr., 1-Mason, 4-Labourer 11.20
Isolated footing over 4.0 M3 M3 14.0 1 Gang Leader , 6-Rghcarp., 2-Stlfxr., 1-Mason,4-Labourer 8.00
Strip footing M3 18.0 1 Gang Leader , 6-Rghcarp., 2-Stlfxr., 1-Mason,4-Labourer 6.22
Mat foundation under 7.5 M3 M3 21.0 1 Gang Leader , 6-Rghcarp., 2-Stlfxr., 1-Mason, 4-Labourer 5.33
Mat foundation over 15.0 M3 ( Rebar Rate Not
Exceed 100 Kg/m3 )
M3 26.0 1 Gang Leader , 6-Rghcarp., 2-Stlfxr., 1-Mason,4-Labourer 4.31
Retaining Wall (gravity) ( Forms & Rebar Fixing
and Concrete Placing )
1200 mm. high M3 9.0 1 Gang Leader , 18-Rghcarp., 2-Stlfxr., 1-Mason,2-Labourer 21.33
3000 mm. high M3 12.5 1 Gang Leader , 18-Rghcarp., 2-Stlfxr., 1-Mason,2-Labourer 14.08
Ground beams ( Forms & Rebar Fixing and
Concrete Placing )
M3 15.0 1-Foreman, 16-Rghcarp., 4-Stlfxr., 1-Mason,2-Labourer 12.80
Slab on Grade (Forms & Rebar Fixing and
Concrete Placing )
100 mm. thk. M2 220.0 1 Gang Leader , 6-Mason, 2-Laborer 0.33
150 mm. thk. M2 215.0 1 Gang Leader , 6-Mason, 2-Laborer 0.33
200 mm. thk. M2 200.0 1 Gang Leader , 6-Mason, 2-Laborer 0.36
300 mm. thk. M2 170.0 1 Gang Leader , 6-Mason, 2-Laborer 0.42
Slab on Grade ( Forms & Rebar Fixing and
Concrete Placing )
100 mm. thk. M3 34.0 1 Gang Leader , 2-Rghcarp., 4-Stlfxr.,3-Labour, 1-Mason 2.59
150 mm. thk. M3 55.0 -do- 1.60
Columns ( Forms & Rebar Fixing and Concrete
Placing )
300 mm. x 300 mm. M3 4.5 1 Gang Leader , 6-Rghcarp., 2-Stlfxr.,4-Labour, 1-Mason 24.89
400 mm. x 400 mm. M3 5.3 -do- 21.13
600 mm. x 600 mm. M3 5.4 -do- 20.74
900 mm. x 900 mm. M3 7.3 -do- 15.34
R.C. Wall ( Forms & Rebar Fixing and Concrete
Placing )

200 mm. thk. X 2400 mm. high M3 12.5 1 Gang Leader , 14-Rghcarp., 6-Stlfxr.,2-Labour, 1-Mason 15.36
200 mm. thk. X 4275 mm. high M3 10.5 -do- 18.29
300 mm. thk. X 2400 mm. high M3 14.0 -do- 13.71
Suspended Beams ( Forms & Rebar Fixing and
Concrete Placing )
3.05 meter span M3 10.0 1 Gang Leader , 12-Rghcarp., 4-Stlfxr.,2-Labour, 1-Mason 16.00
7.60 meter span M3 11.0 -do- 14.55
Suspended Solid Slab ( Forms & Rebar Fixing
and Concrete Placing )
1-way beam & slab M3 12.0 1 Gang Leader , 16-Rghcarp., 4-Stlfxr.,2-Labour, 2-Mason 16.67
2-way beam & slab M3 15.0 -do- 13.33
Waffle Slab ( Forms & Rebar Fixing and Concrete
Placing )
762 mm. dome M3 10.0 -do- 20.00

CONCRETE ACTIVITIES
ESTIMATE ( MAN & EQUIPMENT ) HOURS FOR CIVIL ACTIVITIES
Hour Rate
MH/Unit
ACTIVITY DESCRIPTION UNIT DAILY OUTPUT CREW SRUCTURE

FORM WORK - CONCRETE BREAK DOWN


ACTIVITIES

TIMBER FORMWORK FABRICATION


Raft Foundation/Strip Footing M2 15 2 Carpenter + 1 Laborer 1.60
Single Foundation M2 12 2 Carpenter + 1 Laborer 2.00
Column M2 15 2 Carpenter + 1 Laborer 1.60
Column Bracket M2 10 2 Carpenter + 1 Laborer 2.40
Wall M2 20 2 Carpenter + 1 Laborer 1.20
Wall Bracket LM 15 1 Carpenter + 1 Laborer 1.07
Tie Beam M2 10 2 Carpenter + 1 Laborer 2.40
Beam M2 10 1 Carpenter + 1 Laborer 1.60
suspended Slab M2 10 1 Carpenter + 1 Laborer 1.60
stair M2 10 2 Carpenter + 1 Laborer 2.40
PRE -
STRIPPING , CLEANING & HOISTING
FABRICATED
FORMWORK TO NEXT PLACE
ELEMENTS
Pre-Fabricated Raft Foundation/Strip Footing M2 70 1 Carpenter + 1 Laborer 0.23
Pre-Fabricated Single Foundation M2 50 1 Carpenter + 1 Laborer 0.32
Pre-Fabricated Column M2 45 1 Carpenter + 1 Laborer 0.36
Pre-Fabricated Column with Bracket M2 40 1 Carpenter + 1 Laborer 0.40
Pre-Fabricated Wall without Bracket M2 45 1 Carpenter + 2 Laborer 0.53
Pre-Fabricated Wall with Bracket M2 50 1 Carpenter + 2 Laborer 0.48
Pre-Fabricated Tie Beam M2 35 1 Carpenter + 1 Laborer 0.46
Pre-Fabricated beams Including Drop Beam M2 30 1 Carpenter + 1 Laborer 0.53
Pre-Fabricated Steel Column PCS 8 1 Carpenter + 1 Laborer 2.00
In-Situ Slab/Including Beam, Drop Beam & Steel
Props
M2 85 1 Carpenter + 3 Laborer 0.38
Fixing Waffle over Ready Made Shuttering M2 30 1 Carpenter + 3 Laborer 1.07
In-Site Columns Neck-Timber Board M2 30 1 Carpenter + 1 Laborer 0.53
In-Situ Stair & Platform-Timber Board F/W M2 24 1 Carpenter + 1 Laborer 0.67
In-Situ Blinding Concrete F/W Timber Board M2 40 1 Carpenter + 1 Laborer 0.40

STEEL WORK - CONCRETE BREAK DOWN


ACTIVITIES

STEEL RE-BAR REINFORCEMENT FABRICATION


& ERECTION
Raft / Strip Footing KG 1200 2 Steel Fixer + 2 Laborer 0.027
Single Footing KG 1000 2 Steel Fixer + 2 Laborer 0.032
Rectangular Column without Bracket KG 700 2 Steel Fixer + 1 Laborer 0.034
Rectangular Column with Bracket KG 600 2 Steel Fixer + 1 Laborer 0.040
Wall without Bracket KG 800 2 Steel Fixer + 1 Laborer 0.030
Wall with Bracket KG 700 2 Steel Fixer + 1 Laborer 0.034
Tie Beam KG 700 2 Steel Fixer + 1 Laborer 0.034
Beams Including Drop Beam KG 600 2 Steel Fixer + 1 Laborer 0.040
Rounded Column KG 600 2 Steel Fixer + 1 Laborer 0.040
Slab / Including Beam, Drop Beam KG 700 2 Steel Fixer + 1 Laborer 0.034
Waffle System Including Main Beams Secondary
Beams & Top Slab
KG 500 2 Steel Fixer + 1 Laborer 0.048
Columns Neck KG 450 2 Steel Fixer + 1 Laborer 0.053
Stair & Platform KG 600 2 Steel Fixer + 1 Laborer 0.040

CONCRETE WORK - CONCRETE BREAK DOWN


ACTIVITIES

Lean concrete m2 200 1 Gange Leader + 1 Carpenter + 2 Mason + 3 Laborer 0.28


1 Gang Leader , 2 Carpenter , 8 labor , 3 Cement Finisher ,
Raft / Strip Footing , Pumped M3 260
2 Vibrator , 1 Concrete Pump & Trans Mixer
0.43

Single Footing with Concrete , Pumped M3 120 1 Gang Leader + 1 Carpenter + 2 Mason + 8 Laborer 0.80

Column with Concrete , Pumped M3 30 1 Gang Leader + 1 Carpenter + 1 Mason + 6 Laborer 2.40
Wall with Concrete , Pumped M3 64 1 Gang Leader , 1 Carpenter + 1 Mason + 6 Laborer 1.13
Tie Beam with Concrete , Pumped M3 75 I Gang Leader , 1 Carpenter + 1 Mason + 6 Laborer 0.96
Beams & Drop Beams , Pumped M3 55 1 Gang Leader , 1 Carpenter + 1 Mason + 6 Laborer 1.31

Slab Including Beams , Pumped M3 92 1 Gang Leader , 2 Carpenter + 3 Mason + 8 Laborer 1.22

Waffle System Slab , Pumped M3 80 1 Gang Leader , 2 Carpenter + 3 Mason + 8 Laborer 1.40

Columns Neck , Pumped M3 20 1 Gang Leader , 1 Carpenter + 1 Mason + 6 Laborer 3.60

Stair & Platform , Pumped M3 65 1 Gang Leader , 1 Carpenter , 2 Mason + 7 Laborer 1.35

Concrete Curing M2 120 1 Labour 0.07

Concrete Surface Repair M2 16 1 Mason 0.50


Concrete Scraping M2 2 1 Labour 4.00

Microsillica kg 500 1 Labour 0.02

BLOCKWORK
100mm Block with All Accessories(horizontal ,
vertical reinforcement ,mortar)
M2 11.2 1 Mason + 1 Laborer 1.43
150mm Block with All Accessories(horizontal
,vertical reinforcement , mortar)
M2 9.6 1 Mason + 1 Laborer 1.67
200mm Block with All Accessories(horizontal,
vertical reinforcement, mortar)
M2 8 1 Mason + 1 Laborer 2.00
100mm Block without Accessories M2 15 1 Mason + 1 Laborer 1.07
150mm Block without Accessories M2 14 1 Mason + 1 Laborer 1.14
200mm Block without Accessories M2 12 1 Mason + 1 Laborer 1.33

METAL WORKS

hand rails for stairs / erection LM 10.0 3-Structural Steel Worker 2.40
Ladder (aluminum/steel bolted to conc.)/ erection LM 12.0 3-Structural Steel Worker 2.00
Metal Decking (76mm. deep galv.) M2 40.0 1-Metal Sheet Foreman, 3-Metal Sheet Worker 0.80

THERMAL & MOISTURE PROTECTION

Dampproofing

Brushed on below grade, 1-coat& surface cleaning M2 48.0 1-Labourer 0.17


Brushed on below grade, 2-coat M2 32.0 1-Labourer 0.25
Waterproofing on Slab/wet areas
1- Ply felt M2 4-Waterproofer, 2-Labourer
1- Ply glass fiber fabric M2 4-Waterproofer, 2-Labourer
2- Ply felt M2 4-Waterproofer, 2-Labourer
2- Ply glass fiber fabric M2 4-Waterproofer, 2-Labourer
3- Ply felt M2 102.0 4-Waterproofer, 2-Labourer 0.47
3- Ply glass fiber fabric M2 78.0 4-Waterproofer, 2-Labourer 0.62
Waterproofing to Roof Deck
a) Modified bitumen, 3mm. w/ torch welding M2 102.0 2-Waterproofer, 2-Labourer 0.31
b) Modified bitumen, 4mm. w/ torch welding M2 93.0 2-Waterproofer, 2-Labourer 0.34
Insulation to Roof Deck
Extruded polysterene, 25mm. thk. M2 75.0 1-Labourer 0.11
Extruded polysterene, 51mm. thk. M2 70.0 1-Labourer 0.11
Extruded polysterene, 76mm. thk. M2 65.0 1-Labourer 0.12
ESTIMATE ( MAN & EQUIPMENT ) HOURS FOR CIVIL ACTIVITIES
Hour Rate
MH/Unit
ACTIVITY DESCRIPTION UNIT DAILY OUTPUT CREW SRUCTURE

Extruded polysterene, 102mm. thk. M2 60.0 1-Labourer 0.13


Rigid Wall Insulation
Fiberglass; 25mm. thk M2 54.0 1-Rough Carpenter 0.15
Fiberglass; 38mm. thk M2 52.0 1-Rough Carpenter 0.15
Fiberglass; 50mm. thk M2 50.0 1-Rough Carpenter 0.16
Fiberglass; 75mm. thk M2 48.0 1-Rough Carpenter 0.17
Metal Cladding
Sandwich wall panel (factory made) M2 20.0 2-Metal Sheet Worker, 2-Helper 1.60
Corrugated, 0.61mm. thk. M2 35.0 2-Metal Sheet Worker, 2-Helper 0.91

DOORS & WINDOWS

Steel Frame PCS 3 1 J Carpenter + 1 Laborer 5.33


Wooden Frame PCS 2 1 J Carpenter + 1 Laborer 8.00
Timber Doors PCS 2 2 J Carpenter + 1 Laborer 12.00
Steel Doors PCS 2 2J Carpenter + 1 Laborer 12.00
Special Doors/ main entrance door / around 8 m2 PCS 1 3 J Carpenter + 2 Laborer 40.00
Cubical Doors PCS 4 3 J Carpenter + 1 Laborer 8.00
Wooden Mashrabia M2 4 2 J Carpenter + 1 Laborer 6.00
Aluminum Partitions M2 10 3 Alm. Workers + 2 Laborer 4.00
Aluminum Windows complete with frames and
accessories /size around 1.2*1.8= 2 m2
PCS 5 3 Alm. Workers + 2 Laborer 8.00
Aluminum Doors complete with frames and
accessories
PCS 2 3 Alm. Workers + 2 Laborer 20.00

FINISHES

PLASTERING
Plaster Accessories/ metal lath and corner bead M2 30 1 Mason 0.27
Brown Coat Plaster M2 180 2 Mason + 1 Laborer 0.13
Finishing Coat Plastering M2 16 1 Mason + 1 Laborer 1.00
Portland Cement plaster to soffit M2 24.0 2-Plasterer, 1-Laborer 1.00
Portland cement plaster to suspended metal M2 12.0 2-Plasterer, 1-Laborer 2.00
Gypsum plaster on suspended metal lathe M2 12.0 2-Plasterer, 1-Laborer 2.00
FLOORING
Cement Sand Screed M2 25 1 Mason + 1 Laborer 0.64
Cement Sand Screed & Floor Hardener M2 50 2 Mason + 4 Laborer 0.96
TILING
Ceramic Floor Tile (mortar) 200'200 M2 15 2 Tiler + 2 Laborer 2.13
Ceramic Wall Tile/ floor tile (adhesive) 200'200 M2 18 2 Tiler + 2 Laborer 1.78
Terrazo Tiling M2 30 2 Tiler + 2 Laborer 1.07
Marble/Granite Floor Tiling 400'400'20 M2 8 1 Tiler + 1 Laborer 2.00
Granite Wall Tiling (not mechanical/ mortar) M2 5 1 Tiler + 1 Laborer 3.20
Skirting (terrazo/marble /ceramic / wood) LM 20 1 Tiler + 1 Laborer 0.80
Concrete Tiles M2 25 2 Tiler + 2 Laborer 1.28
Vinyl tiles M2 10 1-Tile Setter, 1-Laborer 1.60
Carpet M2 10 1-Carpet Installer, 1-Helper 1.60
PAINTING
Emulsion Paint (surface preperation and putty) M2 80 4 Painter + 1 Laborer 0.50
Emulsion Paint 1st & 2nd Coats M2 160 4 Painter + 1 Laborer 0.25
Emulsion Paint Final Coat M2 240 4 Painter + 1 Laborer 0.17
Oil Paint//// Per Coat M2 50 4 Painter + 1 Laborer 0.80
FALSE CEILING
F/C Hangers & Frames Only M2 20 1 F/C Carpenter + 1 Laborer 0.80
F/C Alm. & Mineral Accoustical M2 20 1 F/C Carpenter + 1 Laborer 0.80
F/C Gipsum Board Complete M2 20 1 F/C Carpenter + 1 Laborer 0.80
F/C Accostical M2 30 1 F/C Carpenter + 1 Laborer 0.53

SPECIALTIES

Demountable partition M2 10.0 2-Finishing Carpenters 1.60


Plastic laminate toilet cubicle Nos. 3.0 2-Finishing Carpenters 5.33
Access flooring M2 5.0 2-Finishing Carpenters 3.20
Toilet paper dispenser (surface mounted) Nos. 10.0 1-Finishing Carpenter 0.80
Soap dispenser (surface mounted) Nos. 5.0 1-Finishing Carpenter 1.60
Towel bar holder - 457mm. long Nos. 10.0 1-Finishing Carpenter 0.80
Towel bar holder - 762mm. long Nos. 10.0 1-Finishing Carpenter 0.80