Productivity Rate
Productivity Rate
Hour Rate
MH/Unit
ACTIVITY DESCRIPTION UNIT DAILY OUTPUT CREW SRUCTURE
SITE WORK
UTILITY WORK
Trench Excavation (Width 60 cm , not to exceed 1
m deep) , 10 Km hauling
LM 100.0 1-Backhoe 0.57 m3 , 2-Dump Truck ,3-Labourer 0.24
Trench Excavation (Width 60 cm , not to exceed 2
m deep) , 10 Km hauling
LM 70.0 1-Backhoe 0.57 m3 , 2-Dump Truck ,3-Labourer 0.34
Trench Excavation (Width 100 cm , not to exceed 5
m deep) , 10 Km hauling
LM 35.0 1-Backhoe 1.15 m3 , 4-Dump Truck , 4-Labourer 1.37
1-Mini Loader , Vibrating Plate , Water Tanker , 4-
Backfill & Compact Trench M3 36.0
Labourer
0.89
Excavating Utility Trench 0.2 m Wide , 0.9 m Deep LM 75.0 1-Trencher-Chain 12 HP , 2 Labourer 0.21
BUILDING WORK
Excavation for Raft Foundation , 10 Km hauling M3 150.0 1-Backhoe Optr., 2-Dump Truck Driver,3-Labourer 0.16
Excavation for Isolated Footings , 10 Km hauling M3 100.0 1-Backhoe Optr., 2-Dump Truck Driver,3-Labourer 0.24
1-Mini Loader Optr., 1-compactor, Water Tanker , 3-
Backfill around Footings M3 60.0
Labourer
0.400
Excavating Only & Haul in Pile By Dozer 75 HP , 15
m Haul , Common Earth
M3 350.0 2- Labor , 1- Dozer 75 HP 0.046
Excavation for Elevator Pits and Building Foundation
, Common Earth
M3 163.0 1- Hydralulic Excavator 1.15 m3 , 2-Labor 0.098
Backfill From Existing Stockpile , No Compaction ,
15 m Haul , Common Earth
M3 373.0 2- Labor , 1- Dozer 75 HP 0.043
DOZING
Dozing, Ripping & Stock Piling in Soil M2 1000 1 Operator + 2 Laborer 0.02
Dozing, Ripping & Stock Piling in Rock M2 400 1 Operator + 2 Laborer 0.04
LOADING
Loading in Soil , From Stockpile M3 600 1 Operator + 1 Laborer 0.01
Loading in Rock , From Stockpile M3 450 1 Operator + 1 Laborer 0.02
Loading Excavated Material on Trucks & Hauling to
32 Km Round Trip
M3 512 2- Labor , 1-Shovel 2 m3 Bucket , 8- Dump Truck 15 Ton 0.031
Loading Excavated Material on Trucks & Hauling to
80 Km Round Trip
M3 216 2- Labor , 1-Shovel 2 m3 Bucket , 8- Dump Truck 15 Ton 0.074
HAULING
Hauling 20km/in Soil M3 48 1 Dump Truck
Hauling 20km/in Soil M3 72 1 Dump Truck
Hauling 20km/in Rock M3 48 1 Dump Truck
Hauling 20km/in Rock M3 72 1 Dump Truck
Hauling 7km/in Soil M3 144 1 Dump Truck
Hauling 7km/in Soil M3 176 1 Dump Truck
Hauling 7km/in Rock M3 144 1 Dump Truck
Hauling 7km/in Rock M3 176 1 Dump Truck
Hauling Excavated or Borrow Material , 15 m3 Dump
Truck , Round Trip 10 Km
M3 1192 2- Labor , 4- Dump Truck , 1- Shovel Bucket 2.92 m3 0.013
Hauling Excavated or Borrow Material , 15 m3 Dump
Truck , Round Trip 32 Km
M3 448 2- Labor , 4- Dump Truck , 1- Shovel Bucket 2.92 m3 0.036
BRI-STAR TECHNIQUE
Drilling with Drilling Wagon For 1m Deep LM 120 1 Operator + 1 Laborer 0.07
Filling Bri-Star Materials For 1.0m Deep Holes 2kgs
m3 1 Filling Technician + 4 Laborer
of B.S. (0.18 M3 are used)
120LM/day = 1
Production of 1 Drilling Wagon 20'0 18/2 = 11M 3
day
200 mm. thk. X 2400 mm. high M3 12.5 1 Gang Leader , 14-Rghcarp., 6-Stlfxr.,2-Labour, 1-Mason 15.36
200 mm. thk. X 4275 mm. high M3 10.5 -do- 18.29
300 mm. thk. X 2400 mm. high M3 14.0 -do- 13.71
Suspended Beams ( Forms & Rebar Fixing and
Concrete Placing )
3.05 meter span M3 10.0 1 Gang Leader , 12-Rghcarp., 4-Stlfxr.,2-Labour, 1-Mason 16.00
7.60 meter span M3 11.0 -do- 14.55
Suspended Solid Slab ( Forms & Rebar Fixing
and Concrete Placing )
1-way beam & slab M3 12.0 1 Gang Leader , 16-Rghcarp., 4-Stlfxr.,2-Labour, 2-Mason 16.67
2-way beam & slab M3 15.0 -do- 13.33
Waffle Slab ( Forms & Rebar Fixing and Concrete
Placing )
762 mm. dome M3 10.0 -do- 20.00
CONCRETE ACTIVITIES
ESTIMATE ( MAN & EQUIPMENT ) HOURS FOR CIVIL ACTIVITIES
Hour Rate
MH/Unit
ACTIVITY DESCRIPTION UNIT DAILY OUTPUT CREW SRUCTURE
Single Footing with Concrete , Pumped M3 120 1 Gang Leader + 1 Carpenter + 2 Mason + 8 Laborer 0.80
Column with Concrete , Pumped M3 30 1 Gang Leader + 1 Carpenter + 1 Mason + 6 Laborer 2.40
Wall with Concrete , Pumped M3 64 1 Gang Leader , 1 Carpenter + 1 Mason + 6 Laborer 1.13
Tie Beam with Concrete , Pumped M3 75 I Gang Leader , 1 Carpenter + 1 Mason + 6 Laborer 0.96
Beams & Drop Beams , Pumped M3 55 1 Gang Leader , 1 Carpenter + 1 Mason + 6 Laborer 1.31
Slab Including Beams , Pumped M3 92 1 Gang Leader , 2 Carpenter + 3 Mason + 8 Laborer 1.22
Waffle System Slab , Pumped M3 80 1 Gang Leader , 2 Carpenter + 3 Mason + 8 Laborer 1.40
Stair & Platform , Pumped M3 65 1 Gang Leader , 1 Carpenter , 2 Mason + 7 Laborer 1.35
BLOCKWORK
100mm Block with All Accessories(horizontal ,
vertical reinforcement ,mortar)
M2 11.2 1 Mason + 1 Laborer 1.43
150mm Block with All Accessories(horizontal
,vertical reinforcement , mortar)
M2 9.6 1 Mason + 1 Laborer 1.67
200mm Block with All Accessories(horizontal,
vertical reinforcement, mortar)
M2 8 1 Mason + 1 Laborer 2.00
100mm Block without Accessories M2 15 1 Mason + 1 Laborer 1.07
150mm Block without Accessories M2 14 1 Mason + 1 Laborer 1.14
200mm Block without Accessories M2 12 1 Mason + 1 Laborer 1.33
METAL WORKS
hand rails for stairs / erection LM 10.0 3-Structural Steel Worker 2.40
Ladder (aluminum/steel bolted to conc.)/ erection LM 12.0 3-Structural Steel Worker 2.00
Metal Decking (76mm. deep galv.) M2 40.0 1-Metal Sheet Foreman, 3-Metal Sheet Worker 0.80
Dampproofing
FINISHES
PLASTERING
Plaster Accessories/ metal lath and corner bead M2 30 1 Mason 0.27
Brown Coat Plaster M2 180 2 Mason + 1 Laborer 0.13
Finishing Coat Plastering M2 16 1 Mason + 1 Laborer 1.00
Portland Cement plaster to soffit M2 24.0 2-Plasterer, 1-Laborer 1.00
Portland cement plaster to suspended metal M2 12.0 2-Plasterer, 1-Laborer 2.00
Gypsum plaster on suspended metal lathe M2 12.0 2-Plasterer, 1-Laborer 2.00
FLOORING
Cement Sand Screed M2 25 1 Mason + 1 Laborer 0.64
Cement Sand Screed & Floor Hardener M2 50 2 Mason + 4 Laborer 0.96
TILING
Ceramic Floor Tile (mortar) 200'200 M2 15 2 Tiler + 2 Laborer 2.13
Ceramic Wall Tile/ floor tile (adhesive) 200'200 M2 18 2 Tiler + 2 Laborer 1.78
Terrazo Tiling M2 30 2 Tiler + 2 Laborer 1.07
Marble/Granite Floor Tiling 400'400'20 M2 8 1 Tiler + 1 Laborer 2.00
Granite Wall Tiling (not mechanical/ mortar) M2 5 1 Tiler + 1 Laborer 3.20
Skirting (terrazo/marble /ceramic / wood) LM 20 1 Tiler + 1 Laborer 0.80
Concrete Tiles M2 25 2 Tiler + 2 Laborer 1.28
Vinyl tiles M2 10 1-Tile Setter, 1-Laborer 1.60
Carpet M2 10 1-Carpet Installer, 1-Helper 1.60
PAINTING
Emulsion Paint (surface preperation and putty) M2 80 4 Painter + 1 Laborer 0.50
Emulsion Paint 1st & 2nd Coats M2 160 4 Painter + 1 Laborer 0.25
Emulsion Paint Final Coat M2 240 4 Painter + 1 Laborer 0.17
Oil Paint//// Per Coat M2 50 4 Painter + 1 Laborer 0.80
FALSE CEILING
F/C Hangers & Frames Only M2 20 1 F/C Carpenter + 1 Laborer 0.80
F/C Alm. & Mineral Accoustical M2 20 1 F/C Carpenter + 1 Laborer 0.80
F/C Gipsum Board Complete M2 20 1 F/C Carpenter + 1 Laborer 0.80
F/C Accostical M2 30 1 F/C Carpenter + 1 Laborer 0.53
SPECIALTIES