Professional Documents
Culture Documents
Manual Analysis and Design of Post Tensioned Pre-Stressed Concrete T-Beam Segment Bridge Using Proto-Type Model
Manual Analysis and Design of Post Tensioned Pre-Stressed Concrete T-Beam Segment Bridge Using Proto-Type Model
ABSTRACT
The report examines in detail the application of segmental precast T-Beam girder
construction in achieving long spans in bridge structures. Numerous examples from
throughout the world indicate that such construction can provide an effective means
of achieving long span in the range of 100 to 500 ft. Used segmental pre-cast bridge
structure member is manufactured in a number of short units which during erection
are joined together, end to end, and post-tensioned to form the completed
superstructure. Cantilever concrete T-Beam girder bridges composed of precast
reinforced and pre-stressed concrete beams with a T- cross section and a cast-in-
place top slab are frequently used for medium spans due to their competitiveness. The
service behaviour of such bridges is very much influenced by their segmental
construction, due to time-dependent materials behaviour that makes it difficult to
accurately predict the stresses, strains, and deflections. A 1:2 scale model of a two-
span cantilever bridge was tested in order to study its behaviour during the
construction process and under permanent loads. The analysis results were compared
with analytical predictions obtained by means of a prototype model developed for the
nonlinear and time-dependent analysis of segmentally erected, reinforced and pre-
stressed concrete structures. Generally good agreement was obtained, showing the
adequacy of the model to reproduce the structural design of the different elements in
the post-tensioned pre-stressed bridge structure.
Key words: PSC Bridge; Pre-stressed concrete segment; T-beam deck design; Post-
tensioned T-beam girder; Post-tensioned deck slab.
Cite this Article: Palden Humagai, Pavan Kumar Peddineni and C. Raja Mallu,
Manual Analysis and Design of Post Tensioned Pre-Stressed Concrete T-Beam
Segment Bridge Using Proto-Type Model. International Journal of Civil Engineering
and Technology, 8(4), 2017, pp. 1872–1887.
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=8&IType=4
1. INTRODUCTION
Precast segmental construction for pre-stressed concrete bridges has been widely used in the
world. This method has many advantages, such as quality guaranteed standard precast
segments, fast speed construction time and the least site work. Lots of pre-stressed concrete
bridges in the world were built by precast segmental construction method in recent 20 years.
In Highway Bridge construction there is an increasing trend toward the use of longer spans.
This trend is the result of a number of different requirements relating to safety, economy,
function, and aesthetics. In 1967 report of the special AASHO Traffic Safety Committee
implemented to adopt and use of two-span Bridge for overpasses crossing divided highways
in order to eliminate the bridge piers normally placed adjacent to the outside shoulders. The
objective of the report is to examine in detail one means of achieving long spans in bridge
structures, namely, segmental precast T-beam girder construction.
Figure 1
1.1. Objective
The main aspect of the research is post-tensioned substructures. Relatively few post-tensioned
substructures have been used in the past. There are many possible applications in bridge
substructures where post-tensioning can provide structural and economical benefits, and can
possibly improve durability. Post-tensioning is now being used in cantilever bridge
substructures, and it is reasonable to expect the use of post-tensioning to increase in the future
as pre-casting of substructure components becomes more prevalent and as foundation sizes
increase. This is expected, even though some problems have been encountered in post-
tensioned bridges throughout the world as mentioned previously. How to improve durability
using post-tensioning, and how to ensure that the post-tensioning system does not introduce
new durability problems.
Manual analysis and design of post-tensioned T-beam bridge girder.
A proto-type model developed to define the post-tensioning technique.
To examine the effectiveness use of post-tensioning in bridge substructures.
1.2. Scope
The project scope and necessary work plans are:
Extensive Literature Review.
3. METHODOLOGY
Segmental construction employs precast segments cast of highest quality concrete, in sizes
which can be transported and erected. The segments are usually reinforced with mild steel
and are designed to be connected by post-tensioning after erection.
3.2. Loads to be Considered for Analysis and Design of the Bridge Structure
While analysis and designing of road bridges and culverts, the following loads, forces and
stresses should be considered, where applicable.
Dead load
Live load
Snow load
Impact or dynamic effect due to vehicles
Impact due to floating bodies or vessels
Wind load
Longitudinal forces caused by the tractive effort of vehicles or by braking of vehicles
Longitudinal forces due to frictional resistance of expansion bridges
Centrifugal force due to curvature
Horizontal force due to water currents
Buoyancy
Earth pressure include live load surcharge
Temperature effects
Deformation effects
Secondary effects
Erection effects
Forces and effects due to earth quake
Grade effect (for design of bearings for bridges built in grade or cross fall)
Wave pressure
3.3. Manual Analysis and Design of Pre-Stressed Concrete T-Beam Bridge Deck
Using Proto-Type Model
Value of k or 1/k
Figure 3 Moment co-efficient for slabs completely loaded with uniformly distributed load, m1 and
m2 Correspond to k and 1/k respectively.
Effective depth of the slab =d= = 39.57 ∗ 106 /2.3 ∗ 1000000 = 131.16mm
Total dead load on the girder including self -weight = 22.37+10.2 = 32.6kN/m
The loading is sketched in figure.
It is observed that the stresses at bottom as well as top layers of the girders under the two
conditions considered are well within the limits.
4. CONCLUSION
The main focus was manual analysis and design of post-tensioned pre-stressed concrete t-
beam bridge deck, subjected to tracked vehicle load as per IRC code in order to examine the
stresses and deflections. As per the analysis it was observed that the stresses at the bottom as
well as top layer of the girder under the two condition consider are well within the
permissible limits (IRC 18-2000&IS 1343-2000). The required flexural strength of the T-
beam is within the limit thus the deck is safe.
REFERENCES
[1] Antonio R. Mari and Manuel Valdes (2000). “Long-Term Behavior of Continuous Precast
Concrete Girder Bridge Model.” J. Bridge Eng., 2000, 5(1): 22-30
[2] Marc J. Veletzo and P.E., M.ASCE;and José I(2000). “Modelling of Jointed Connections
in Segmental Bridges.” J. Bridge Eng., 2011, 16(1): 139-147
[4] Michelle Rambo-Roddenberry, Ph.D., P.E., M.ASCE1; Daniel Kuhn, P.E(2016). “Barrier
Effect on Transverse Load Distribution for Prestressed Concrete Segmental Box Girder
Bridges.” J. Bridge Eng., 2016, 21(6): -1—1
[5] Shuqing Wang and Chung C. Fu, F.ASCE(2015). “Simplification of Creep and Shrinkage
Analysis of Segmental Bridges.” J. Bridge Eng., 2015, 20(8): -1--1
[6] Campbell TI and KodurVKR (1990). “Deformation controlled nonlinear analysis of pre-
stressed concrete continuous beams.” PCI Journal. 35(5), pp. 42-55.
[7] Dunker, K. F., and Rabbat, B. G. (I992). "Performance of pre-stressed concrete highway
bridges in the United States-the first 40 years." PCIJ.,37(3), 48-64.
[8] Francis T.K. AU and Cliff C.Y. LEUNG / Procedia Engineering 14 (2011) 1425–1432
[9] Mast, R F. (1993). "Lateral stability of long pre-stressed concrete beams-part 2." PCI J.,
38(1),70-88.
[10] Mitchell D, Cook WD, Khan AA and Tham T (1993). “Influence of high strength
concrete on transfer and development length of pre-tensioning strand”. PCI Journal.
38(3), pp. 62-74.
[11] Priestley MJN and Park R (1972). “Moment redistribution in continuous pre-stressed
concrete beams”. Magazine of Concrete Research. 24(80), pp. 157-166.