Download as pdf or txt
Download as pdf or txt
You are on page 1of 133

Chapter 1 Introduction

Energy is considered the life-blood of the economy. It is essential in achieving economic

growth but very critical in sustaining a nation’s progress. For some reasons, the rapid

increase in population and other growing interrelated demand of power. Currently system

load of Mindanao island or Mindanao grid requires 1,242 MW capacity in which the

known generation capacity is only 1,045 MW. A study according to the Mindanao Power

Monitoring Committee. These statistics create insufficiency of power which is equivalent

to 197 MW.

In view of the early projection, our company “ MINDANAO ENERGY SYSTEMS, INC.” was

formed. Despite of the current situation, in the late 1980’s Cagayan de Oro City had been

experiencing a power problem which resulted to power shading in the area. And in the

early 1990’s our company was established by CAGAYAN ELECTRIC POWER AND LIGHT

COMPANY, ALL ASIA CAPITAL AND TRUST COMPANY, ARM FORCES OF THE PHILIPINES

SAVINGS AND LOAN ASSOCIATION, INC. (AFPSLAI), ASIA POWER DEVELOPMENT LIMITED

OF NEW ZEALAND and ANGELES ELECTRIC as stake holders. Minergy, Inc. is the acronym

of our company the first private independent power producer in Mindanao duly accredited

by the Department of Energy.

Minergy, Inc. was started operating with three(3 ) units Sulzer diesel engine having an

electrical output of 6.3 MW each engine. Because of our commitment to the customer, to

provide electricity that conforms to their requirement and is also a mandate of the

demand, Minergy, Inc. had put up an additional of two(2) units Wartsila diesel engine

with 13.7 MW electrical capacity each engine. The plant was fully commercialized in

operation last January 25, 2012. And we believe this additional power mean significant

answer in improving power industry in Mindanao.

1
The total cost of the project which include mobilization cost, auxiliary equipment,

installation cost and consultancy is seven hundred seventy million pesos (Php

770,000,000). The cost is very low comparing to the rate of $1,000 per Kw because the

company is buying second hand equipment.

Minergy, Inc. is operating in load following or peaking load mode meaning it will only

operate when there is shortage of power in the Mindanao grid specially during peak

load interval. Load forecast is scheduled by our sole customer Cagayan Electric Power

and Light Company a power distribution utility.

Minergy, Inc. power plant is located within the City proper of Cagayande Oro in

Baranggay Tablon. It is with in the industrialized zone and from the heart of Cagayan

de Oro it is about 15 kilometers away going to Butuan City.

2
Chapter 2 Importance and Limitation

II.I Objective of the Report

The objective of this report is to document concepts, strategies, formulas, standards,

method and references relating to the design, installation, operation and maintenance of

our new diesel power plant. To also include the expertise of some private practioners that

was involved in the project, the contructors, minergy project monitoring team and most

specially the consultant that was trained by Wartsila.

II.II Significance of the Report

The report demonstates the value of our commiment to up hold professional excellence.

Second, it may served as a vital reference for the new comers in diesel power. And it could

also be a relevant guide to the students.

II.III Scope and limitation of the report

Ideas pertaining to this report limits only in the design, installations, operation and

maintenance of two(2) 13.7MW Wartsila 16V46 including the treament auxiliaries which

are necessary in operating a diesel power plant. It could also be a useful guide beyond our

concern of interest the study of geoanalytical analysis of subsurface condition of soil.

Chapter 3 Proposed Design, Installation, Operation and Maintenance of 13.7MW

Wartsila 16V46 Diesel Power Plant to include all Mechanical Component

To Complete the System for Mindanao Energy Systems, Inc., Tablon,

Cagayan de Oro City.

3
III.I Design and Specification of 13.7 MW 16V46 Wartsila Engine;

The expansion project has a total output of 27.4 MW consist of two(2) units 13.7 MW

16V46 Wartsila engine. Engine main and operational data are as follow;

III.Ia Engine Technical Data;

Engine Speed, RPM : 514

Cylider Bore, mm : 460

Stroke, mm : 580

Firing Pressure(max.), bar : 180

Mean effective pressure, bar : 21.9

Charge air pressure, bar : 2.8

Mean piston speed, m/sec : 9.9

III.Ib Engine Operating data;

Fuel oil nominal pressure before injection pumps, bar : 7

Fuel oil alarm pressure before injection pumps, bar : 4

Fuel oil temperature before injection pumps(max), °C : 130

Fuel oil viscosity before injection pumps(max) cSt : 12

Lube oil nominal pressure before engine, bar : 4

Lube oil alarm pressure before engine, bar : 3

Lube oil pressure engine stop, bar : 2

Lube oil nominal temperature before engine, °C : 63

Lube oil alarm temperature before engine, °C : 80

H.T. cooling water nominal pressure before engine, bar : 3.2

H.T. cooling water alarm pressure before engine, bar : 2

H.T. cooling water maximum pressure before engine, bar : 4

H.T. cooling water temperature before engine, °C : 78

4
H.T. cooling water nominal temperatur after jacket , °C : 83

L.T. cooling water nominal pressure before engine, bar : 3.2

L.T. cooling water alarm pressure before engine, bar : 2

L.T. cooling water maximum pressure before engine, bar : 4

L.T. cooling water nominal temperature before engine, °C : 32

L.T. cooling water maximum temperature before engine, °C : 38

Starting air nominal pressure, bar : 30

Starting air alarm pressure, bar : 18

Starting air comsumption per start, mᶟ : 7.8

Tolerance:

At an ambient temperature of 25°C and 100 % load, temperature is + - 10°C

III.II Heat Balance and Computations of Wartsila Engine;

Computations refer from the specication of low temperature(L.T.) turbo air cooler, high

temperature(H.T.) jacket water cooler and lube oil(L.O.) cooler in the template: 31%

exhaust gases and 5% losses taken from Wartsila manual.

5
III.IIa Determine heat rejected in turbo air cooler, 𝑸𝒍𝒕 in W;

𝑄𝑙𝑡 = AU∆tm where : A = 65.50 m² plates total area

U = 899 W/m² - ⁰C heat transfer coefficient

from Alfa Laval Manual

∆tm = logarithmic mean temperature

Determine logarithmic mean temperature, ∆tm in ⁰C;

∆tm = (t₄ - t₂) – (t₃ - t₁) / ln ((t₄ - t₂)/ (t₃ - t₁)) ; taken from page 531

where : t₄ = 46.1 ⁰C inlet LT water temp. Thermodynamics by V.M. Faires

t₂ = 38.7 ⁰C outlet raw water temp. and C. M. Simmang

t₃ = 38.0 ⁰C outlet LT water temp.

t₁ = 32.0 ⁰C inlet raw water temp.

∆tm = (46.1 – 38.7) – (38.0 – 32.0) / ln ((46.1 – 38.7)/(38.0 – 32.0))

∆tm = 7.4 – 6.0 / ln (7.4/6.0)

∆tm = 1.4 / ln 1.23

∆tm = 6.763 ⁰C

therefore:

𝑄𝑙𝑡 = 65.5 × 899 × 6.763 m² (W/m² - ⁰C ) ⁰C

𝑄𝑙𝑡 = 398,236 W or 398.236 KW

Percentage heat rejected;

% = Q/engine output × 100% where: engine output = 13,700 KW

% = 398.236/13700

% = 2.9

III.IIb Determine heat rejected in the engine jacket water, 𝑸𝒉𝒕 in KW;

𝑄ℎ𝑡 = AU∆tm where : A = 24.5 m² plates total area

6
U = 899 W/m² - ⁰C heat transfer coefficient

∆tm = logarithmic mean temperature

Determine logarithmic mean temperature, ∆tm in ⁰C;

∆tm = (t₄ - t₂) – (t₃ - t₁) / ln ((t₄ - t₂)/ (t₃ - t₁))

where : t₄ = 91.0 ⁰C inlet HT water temp.

t₂= 51.7 ⁰C outlet raw water temp.

t₃ = 75.4 ⁰C outlet HT water temp.

t₁ = 38.7 ⁰C inlet raw water temp.

∆tm = (91.0 – 51.7) – (75.4 – 38.7) / ln ((91.0 – 51.7)/(75.4 – 38.7))

∆tm = 39.3 – 36.7 / ln (39.3/36.7)

∆tm = 2.6 / ln 1.07

∆tm = 38.43 ⁰C

therefore:

𝑄ℎ𝑡 = 24.5 × 899 × 38.43 m² (W/m² - ⁰C ) ⁰C

𝑄ℎ𝑡 = 846,400 W or 846.40 KW

Percentage heat rejected;

% = Q/engine output × 100%

% = 846.40/13700

% = 6.18

III.IIc Determine heat rejected in lubrication oil due friction, 𝑸𝒍𝒐 in KW;

𝑄𝑙𝑜 = AU∆tm where : A = 97.34 m² plates total area

U = 899 W/m² - ⁰C heat transfer coefficient

∆tm = logarithmic mean temperature

Determine logarithmic mean temperature, ∆tm in ⁰C;

∆tm = (t₄- t₂) – (t₃ - t₁) / ln ((t₄ - t₂)/ (t₃ - t₁ ))

where : t₄ = 73.7 ⁰C inlet lube oil temp.

7
t₂ = 49.9 ⁰C outlet LT water temp.

t₃ = 63.0 ⁰C outlet lube oil temp.

t₁ = 46.0 ⁰C inlet LT water temp.

∆tm = (73.7 – 49.9) – (63.0 – 46.0) / ln ((73.7 – 49.9)/(63.0 – 46.0))

∆tm = 23.8 – 17.0 / ln (23.8/17.0)

∆tm = 6.8 / ln 1.4

∆tm = 20.21 ⁰C

therefore:

𝑄𝑙𝑜 = 97.34 × 899 × 20.21 m² (W/m² - ⁰C ) ⁰C

𝑄𝑙𝑜 = 1,768,550 W or 1,768.550 KW

Percentage heat rejected;

% = 𝑄/engine output × 100%

% = 1,768.550/13700

% = 12.9

III.IId Solving engine thermal efficiency using actual fuel rate = 0.219 liters/𝑲𝑾𝒉 ;

thermal eff = 𝐾𝑊ℎ/𝑄𝑓 where: 𝑄𝑓 = 𝑤𝑓 × 𝐻𝑉

heat rate = 𝑄𝑓/𝐾𝑊ℎ 𝐻𝑉 = heating value of fuel from Shell

fuel rate = 𝑤𝑓/𝐾𝑊ℎ 𝐻𝑉 = 37,620.72 BTU/liter

Simplefy the equation; 𝑤𝑓 = mass flow, liters/sec

𝐾𝑊ℎ = 𝑤𝑓/fuel rate ; use this equation to heat rate

therefore;

heat rate = 𝑄𝑓/(𝑤𝑓/fuel rate)

heat rate = 𝑤𝑓 × 𝐻𝑉/(𝑤𝑓/fuel rate)

heat rate = 𝐻𝑉 × fuel rate

heat rate = 37,620.72 × 0.219 (BTU/liter) (liter/𝐾𝑊ℎ)

heat rate = 8,238.94 BTU/𝐾𝑊ℎ

8
Solving for thermal eff: a reciprocal of heat rate

thermal eff = 1/heat rate ; where: KWh = 3,412.2 BTU

thermal eff = 1/8,238.94

thermal eff = 0.000121375 𝐾𝑊ℎ/BTU × 3,412.2 BTU/𝐾𝑊ℎ

thermal eff = 0.4141 × 100%

thermal eff = 41.41 % almost the same in the figure above on the energy balance.

III.III Project Site Preparation and Soil Investigation;

A project implementation is usually prepared and started by plant lay outing to make sure

space is properly assigned. Follows the clearing of vegetation, construction of road

to have accessibility for the mobilization of the equipment in the site and lastly, the

removal of the soil surface which is usually treated as contaminated materials. Since

construction is site specific, it is very important to investigate the subsurface conditions

which often influenced the design of the project as well as its foundation. The uncertainty

in the design is particularly a big problem in geotechnical engineering. To determine it,

makes foundation design suitable to the area of interest. Physical exploration and

investigation of the ground by means of bore holes gives appropriate data needed for

the specific determined soil mitigation.

Geotechnical engineering is the study of ground soil analysis. In the project of 27.4 MW

Wartsila Diesel Power Plant this study is applied and conducted soil penetration test which

derived soil jet grouting in order to place the load to the depth where the soil description

is stable in terms of bearing capacity . Refer from the Field Log of Bore holes attached,

explains the making of the decision which was conducted by Peter Ground Improvement,

Inc. a foundation engineering and specialty contractors. The average total depth of the

boreholes in which there are traces of sandy and gravel description of soil is twenty one

(21) meters. Since it very deep the mitigation is jet grouting of concrete material with

9
reinforce bar of twenty three(23) mm diameter. Second purpose is to make sure that the

adjacent plant nearby will not be affected during construction. Most specially if the

adjacent plant is a power generating unit, their alignment between the generator and the

engine where taken into consideration. And also other delicate equipment alignment such

as high speed turbo charger. Finally, to ensure guaranteed safety in the establishments

nearby avoid huge intensity of vibration during construction such as hammering of pile

grout.

III.IV Field Log of Borehole and Soil Penetration Test Specific;

In soil penetration test the hammer weight should be 63.5 kgs. and the spoon length is

0.46m to 0.76m long. The dropping height of the hammer should be 0.75m. The number of

blows between thirty(30) to fifty(50) per foot characterized a compact dense soil. More

than that number of blows per foot consider hard compact soil. Pls. refer chart on the

following page.

10
11
12
13
14
15
There are six(6) bore holes that was evaluated but illustrate only the first and the last hole.

16
We see the number of N- blows column and their equivalent depth and characteristics of

the soil.

III.V Design and Installation of Foundation;

The ground under the foundation block shall be made of compacted sand and gravel,

having good carrying capacity, thus preventing any portion of the foundation block

from tilting, slipping or sinking. Before the construction of foundation block, concreted

load distribution pad shall be made about 153mm thick to ensure load balance distribution

to the concentrated area of interest or to obtain the bearing area. The total equipment

and foundation weight is harmoniously set in this pad, other known as wall footing.

And this footing is reinforced under by twelve(12) structures of jet grouting pile so

arrange in two(2) column equally distanced. Jet grouting pile depth is about twenty

one(21) meters long as discussed in the site preparation and soil investigation chapter.

The reinforce bar of the jet grouting pile of twenty three(23)mm diameter is extended

above the distribution pad long enough to hold or connect to the reinforce bars of the

foundation structure.

III.VI Foundation Design and Load Computations;

Total weight of the equipment, 𝑊𝑒 𝑖𝑛 kgs

𝑊𝑒 = 355,000 kgs

Determine the dynamic weight of the foundation, 𝑊𝑑 𝑖𝑛 kgs

𝑊𝑑 = 𝑒 × 𝑊𝑒 × √𝑁 ; the empirical formula from PSME CODE section 2.4.2.C.3.D

𝑊𝑑 = 0.11 × 355,000 × √500 kgs. where: 𝑒 = 0.11 from table 2.2 same section

𝑊𝑑 = 873,184 kgs 𝑁 = 500 rpm

Determine the foundation total weight, 𝑊𝑓 𝑖𝑛 kgs ;

𝑊𝑓 = 𝑊𝑑 + 𝑊𝑒

17
𝑊𝑓 = 873,184 + 355,000 kgs;

𝑊𝑓 = 1,228,184 kgs

Determine if the foundation weight is safe, X𝑓

Wf = X𝑓 𝑊𝑒 where: X𝑓 = multiplier variable, the value is

X𝑓 = Wf ÷ We from three (3) to five (5) taken

X𝑓 = 1,228,184 ÷ 355,000 from PSME CODE section 2.4.1.B

X𝑓 = 3.5 safe

Determine the total load acting against the jet pile, 𝑊𝑡 𝑖𝑛 kgs ;

𝑊𝑡 = 𝑊𝑒 + 𝑊𝑓

𝑊𝑡 = 355,000 + 1,228,184 kgs

𝑊𝑡 = 1,583,184 kgs

Determine the total area of the foundation, 𝐴𝑓 𝑖𝑛 m²

𝐴𝑓 = 𝑙 × 𝑤 where: 𝑙 = 17.325 m, length of the foundation

𝐴𝑓 = 17.325 × 4.8 𝑤 = 4.80 m, width of the foundation

𝐴𝑓 = 83.16 m²

Determine foundation normal stress to the area, 𝑃𝑛 𝑖𝑛 kgs/m²

𝑃𝑛 = 𝑊𝑡/𝐴𝑓

𝑃𝑛 = 1,583,184 / 83.16

𝑃𝑛 = 19,037.8 kgs/m²

Factor of safety from soil bearing pressure over the foundation normal stress, 𝐹𝑆 ;

𝐹𝑆 = 𝑃𝑠𝑏/𝑃𝑛 where: 𝑃𝑠𝑏 = Soil bearing pressure 𝑖𝑛 kgs/m²

𝐹𝑆 = 98,000/19,037.8 = 98,000 kgs/m² taken from page 105 table

𝐹𝑆 = 5.1 4-5 of Power Plant Engineering by F.T. Morse

bore hole shows sand and gravel.

III.VII Foundation Surface Preparation, Installation and Gen-Set Coupling Alignment;

Pre-surface preparation of the foundation and anchor bolt pockets cleaning, mechanical

18
chipping or similar methods should be made. A rough surface will aid adhesion. This is

done before loading the equipment to the foundation. A minimum of ten(10) days

before the equipment should be mounted to the foundation as standard from section

2.4.2.C.3.A of the PSME CODE. Observed foundation elevation for any sinking

movement that is occurring over period of time after the generating unit was placed,

maybe three(3) weeks without movement will proceed. Final surface preparation in

the equipment’s foundation requires a standard from the manufacturer’s point of view.

The surface in contact with the engine fixing rail bed and the generator must be

well leveled. The tolerance of the top surface should be plus or minus 0.50 mm

smoothness. The difficulty of achieving the result requires more time using traditional

set up which uses concrete grouting material to the anchor bolts in the pocket and

engine fixing rail bed seat. Quick dry grouting epoxy is applied in the 27.4 MW

Wartsila project for it is more advantageous than the concrete. It has flowage

characteristic meaning gradual self-leveling deformation, ability to withstand higher

shock load, can be used in much thinner cross section, exhibits negligible shrinkage and

extremely high compressive tensile strength in a short period of time. The epoxy

grouting materials typically consists of base resins and a hardener that are mixed at the

job site immediately before placement. Foundation surface preparation and anchor

bolt pocket to which epoxy grout is applied will be carefully cleaned, leaving

surface free from all foreign materials, oil, grease and etc. If unsound concrete is

encountered, it will be necessary to chip back to sound concrete. When foundation

surfaces and anchor bolt pockets are ready as per checklist standard, level the

engine fixing rail bed through jack bolts leaving the grout clearance thickness

which is 50.8 mm and anchor bolts should be properly in place in the pocket. After

grouting activities wait until 28 hrs. and inspection will be conducted for any

unfavorable observations. If none then proceed to anchor bolts tightening in three

phases, first is 170 Nm, second is 350Nm and last is the final torque of 700 Nm

per Wartsila manual specifications. But before doing the tightening be sure all the

19
jack bolts where loosen. The reason of phasing the tightening is to avoid thermal

shock on the bolt caused by friction when tighten. Attached are the specific of fixing rail

bed leveling and anchor bolts grouting activities as seen in the following pages.

III.VIII Engine Fixing Rail Bed Leveling Before Grouting Specific

20
III.IX Anchor Bolt Specific;

21
III.X Foundation Anchor Bolt Pocket Specific;

Front View

Side View

22
23
III.XI Scheduling Form Before Grouting Anchor Bolt;

III.XII Anchor Bolt Grouting Specific;

24
III.XIII Anchor Bolts Second Tightening Torque Schedule and Tightening Sequence;

Note: Torque is equal to 350 Nm.

25
III.XIV Anchor Bolts Final Tightening Torque Schedule and Tightening Sequence;

Note: Torque is equal to 700 Nm.

When the engine is properly set and the grout is already cured, it is the time to adjust

the 304 pieces of 24mm bolt head engine rubber plate to a final torque of 170 Nm per

26
manual specification. Each side has 152 pieces and is adjusted gradually half turn each run

per bolt synchronized to its opposite pair in the other side of the engine. Attached is the

procedural checklist as shown in the next page. These rubber plates absorbs the vibration

of the engine during operation. When finished it means the engine is well balanced and

ready for coupling alignment activity. Engine total weight sets in these rubber plates.

III.XV Engine Rubber Plate Specific;

27
III.XVI Coupling Axial, Angular and Lateral Alignment;

Coupling alignment between the engine and the generator must be done patiently with

accuracy, referring to the manual alignment should be within the tolerable range. The

tools needed in aligning the coupling is the dial indicator and hydraulic jack enough to

move a very heavy equipment. Since the engine side is properly fixed this our reference

point deriving parallelism and axial alignment. Manual serves us a guide in determining

bit offset parallel alignment. Facing the engine at flywheel coupling end with clockwise

rotation of the engine, generator coupling center is offset to the right of up to 0.25mm

from the center of the engine coupling as shown in the drawing below. And the

generator coupling center must be lower than the engine coupling center at a range of

1~1.5 mm.

III.XVII Coupling Alignment Specific;

28
Figure above is the final coupling alignment of Wartsila engine # 2 and the generator.

There is main reason why alignment is offset to the right, the generator and lower a little

bit from the engine. First the generator is slightly offset to the right, it is because the

engine is the driver and it rotates clockwise. In this manner the coupling bolts that

holds the driven equipment when the engine started to run, the bolt face and bolt hole

face in the driven side is already seated tightly without clearance in order to avoid

tearing the bolt hole in the driven side cause by tremendous load impact during starting.

And the driven is a little bit lower than the driver because this engine sets on the

rubber plate as stated above. This rubber plate has compressibility than metal plate,

giving allowance to engine side for compressibility of the plate. When elastical

flywheel coupling finally aligned, electrical personnel took exciter and rotor air gap

clearance to ensure generator is well balance and side play or thrust clearance free of

movement equal to 0.57mm. Generator bearing clearance is 0.22mm. Upon inspection if

the results are recommendable. Then take crankshaft deflection measurement and

29
prepare again epoxy grouting material to fixed the generator side. From the experiences,

we learned that the best time to schedule grouting activity would be during night time,

to slowly cure the grouting material. If the grouting fiber settles gradually it makes the

structure more stronger.

III.XVIII Exciter and Rotor Air Gap Clearance Specific;

Figure above is taken from ABB generator # 2.

30
III.XIX Crankshaft Deflection Measurement Specific;

The difference between two(2) diametrically opposed reading must not exceed 0.30 mm

and the difference between corresponding adjacent cranks reading must not exceed

0.15mm as per manufacturer’s standard. Figure taken from Wartsila engine # 2.

31
III.XX Design and Installation of Exhaust Gas Pipe, Charge Air Pipe and Bellows;

Generating unit should be installed in its final position before any external pipes are

connected. In the installation of exhaust gas bellows after the turbo charger make sure

to put protection cover on the upper flange of the bellows in order to keep debris and

welding sparks from falling into the turbine side of the turbo charger. Set first straightly the

flexible bellows and adjust it to its correct length, L using threaded stud bolt support long

enough connecting both flange end of the bellows with an adjusting nut after the flanges.

Please refer to the table 1-0. And finally install it to counter flange of the turbo charger.

III.XXI Flange Maximum Straightness Tolerances;

Check straightness of the flanges, not acceptable if over 2mm

III.XXII Exhaust Gas Bellows Axial, Angular and Lateral Tolerances;

32
Right way and allowed tolerances for exhaust gas bellows

Right way and allowed tolerances for exhaust gas bellows

33
III.XXIII Exhaust Gas Double Bellows Table;

N = Number of bolt holes Working pressure : 0.5 bars above atmospheric

Fa = Axial rate Test pressure : 1.5 bars above atmospheric

FL = Lateral rate Working temp. : max. 450 ̊C

K = Bolt hole diamemter Material : bellows & sleeves, AISI 321

III.XXIV Charge Air Bellows Axial, Angular and Lateral Tolerances;

Charge air rectangular bellows installation is exactly the same procedures in exhaust gas

bellows mounting. It only defers on the allowed clearances recommended. See illustration

drawing;

Check straightness of the flanges, not accepted if over 2mm.

34
L2 – L1 ≤ 5 L2 – L1 ≤ 2

Right way and allowed tolerances for charge air bellows

35
III.XXV Design, Installation and Operation of Fuel Oil System;

III.XXV.I Designed and Installation Instructions;

When working with the fuel oil system, always observed the utmost cleanliness. Pipes,

tanks and fuel treatment equipment such as pumps, filters, heaters and viscometers

should be carefully cleaned before put into use. Fuel piping system before final

installation to the complete fuel oil system will undergo chemical acid pickling process for

four(4) to five(5 ) hours using ten(10) percent hydrochloric acid and ten(10) percent

formalin inhibitor. Inhibitor is alkaline base solution, to control or retard the strength of

acid reaction to the pipe. The very purpose of this process is to clean out all welding sludge

inside the pipe during fabrication stage in which metal sludge is dangerous to piston

and cylinder mating contact and other mating parts inside the engine. After pickling

the pipeline should be rinse with neutralizing solution of ten(10) percent caustic soda

and fifty(50) grams of trisodiophospate per liter of water at 40 ⁰C to 50 ⁰C temperature

for twenty(20) minutes making sure acid reaction during pickling is stop. And then rinse it

with hot water in few minutes. When all the fuel treatment auxiliaries and pipes are in

placed or installed ready for operation before the final connection to the generating

engine oil flushing should be conducted using recommended flushing oil. If possible

pressure of the circulating flushing oil should be at least 1.5 times the working pressure to

ensure proper final cleaning along the system. The higher the pressure to cause turbulent

flow of the flushing medium the better. Before the flushing oil goes into the flushing tank,

it should be provided with filter easy to inspect for monitoring purposes. When starting

the oil flushing bigger mesh of the filter is used until it will become smaller if observed

foreign dirt is already fine. When the oil flushing is observed clean the final filter 30

microns mesh is installed for final circulation for couples of hour depending on the

appearance of the flushing oil filter. In the system where fuel final filter casing is

already installed during flushing, the 20 microns mesh filter will be inserted when flushing

filter before the flushing tank is observed clean as stated above for final oil flushing

36
circulation and it is also clean periodically same thing on the filter at end of the circulation

before the flushing tank. When the flushing oil is observed clean it is the time to connect

the fuel auxiliary system to the engine. The auxiliary boiler should be in function for heat

source of the flushing oil temperature as required per manual recommendation. Flushing

medium temperature equal to the operating temperature of the system is enough.

III.XXV.Ia Fuel Oil Purifier Unit;

Heavy Fuel Oil Purifier will purify fuel by centrifugal process meaning the denser the object

moves outward from the center of the bowl to separate from the fuel of lesser density.

The heavier object is thrown to the sealing water inside the bowl located in the

perimeter circumference of the bowl’s inside diameter. And lighter fuel oil remain in the

center of the bowl passing through a set of disks so design for filtering and collected by a

paring disc out from separator to the service tank ready for use.

37
Make : HFO Separator FOPX 613 Working Temperature : 85⁰C to 90 ⁰C

Capacity : 6,700 liters/hour Working Pressure : 2.0 bars

III.XXV.Ib Heavy Fuel Oil Separator Single Line Diagram;

38
III.XXV.Ic Heavy Fuel Oil and Light fuel Oil Feeder Pump Unit;

Heavy Fuel Oil Feeder Unit - 2 units Light Fuel Oil feeder Unit - 1 unit

Make : IMO ACG 045K5/ITBP Make : IMO ACG 045K5/IVBP

Capacity : 13,100 liters/hour Capacity : 12,400 liters/hour

Working Viscosity : 75 cSt Working Viscosity : 7 cSt

39
Working Pressure : 4.0 bars Working Pressure : 4.0 bars

III.XXV.Id Heavy Fuel Oil and Light fuel Oil Feeder Pump Single Line Diagram;

40
III.XXV.Ie Fuel Oil Conditioning Booster Unit;

Pump - 2-units Booster Unit

Make : IMO ACE 038N2/NTPB Make : AMB-C 15000 SS

Capacity : 9,310 liters/hour

41
Working Viscosity : 16 cSt

Working Pressure : 4.0 bars to 8.0 bars

III.XXV.If Fuel Conditioning Booster Single Line Diagram;

42
III.XXV.Ig Fuel Oil Duplex Final Filter Unit;

Make : Duplex Filter TYP 2.06.5.4.265.500

Capacity : 2 × 32 liters

Filter Fineness Nominal : 20 microns

Filter Fineness Maximum : 35 microns

Working Temperature : 150 ⁰C

Working Pressure Filter : 10 bars

Heating Temperature : 200 ⁰C

Heating Pressure : 14 bars

43
III.XXV.Ih Flexible Fuel Hose Installation Specific;

44
First to fastened is the engine side with high temperature resistance gasket in between

flanges. Tighten the fixed bolts in crosswise sequence until hand tight. And then connect

the free end of the isolating hose to external piping of the engine. The hose shall be bend

to 500 mm length as shown in the diagram. Anchor the pipe near the flange rigidly to

prevent bursting of hose cause by engine vibration. Most common cause of bursting is

poor clamping. Purpose of the hose is to isolate engine vibration to external pipe.

III.XXV.Ii Main Injection Valves and Pilot Injection Valves Unit;

45
The pressure gauge 1 on the instrument panel and a pressure sensor 2 connected to

the fuel oil supply line indicate the fuel oil pressure before the engine. The pressure

sensor 2 is fitted for remote indication and alarms. Leaking fuel oil from injection

system is collected in a leak fuel manifold 3 into the hot box and pump back to the

settling tank. Turning the pressure regulating valve 5 clockwise to achieve higher pressure

and counter-clockwise to lower. Pre-adjustment, raise the pressure in the fuel oil system

by closing the pressure regulating valve clockwise until booster pump pressure reaches 12

bar. Then finally adjust pressure regulating valve by opening counter-clockwise to level

of the operating pressure of fuel oil, 7.0 bar to 9.0 bar per WARTSILA MANUAL

recommendation in section 1.2.

III.XXV.Ij Retur Fuel Unit of Heavy Fuel Oil;

46
Return Pump

Make : IMO ACE 025 N2 NTBP

Capacity : 2,800 liters/hour

Type : Screw

Tank

Capacity : 250 liters

III.XXV.Ik Return Fuel Unit of Heavy Fuel Oil Single Line Diagram;

47
III.XXV.II Operation Instructions;

The engine is designed for continuous heavy fuel service. It can be started and stopped on

heavy fuel oil provided that the fuel is heated to the correct temperature and viscosity. For

medium speed engine as per recommendation taken from viscosity, temperature and type

of heavy fuel oil standard, the viscosity value will range from 10cSt to 12 cSt and the

temperature ranges from 110 ̊C to 130 ̊C. See attached table. This treatment occurred in

the fuel conditioning booster and includes pressure requirement with a range from

7 bars to 9 bars before the fuel injection valves. Fuel oil system starts from tank

farm and is conveyed by pumping into the settling tank where the first filtering is

occurred through settling process. It is heated 10 ̊C lesser than the flash point

temperature of Bunker C fuel to avoid ignition. The heavier density objects separate

from the fuel oil settling down to the bottom of the tank. From settling tank heavy fuel

oil is pump to the fuel oil purifier for purification by centrifugal process and goes through

the service tank where fuel is considered clean and ready for service. From the service

tank the fuel is pump to the fuel conditioning booster for treatment per former

discussions. The pressure of fuel is regulated here by installing a pressure regulating valve

at the end of the pipe fuel manifold of the fuel conditioning booster and before the

return fuel line going through the settling tank, it ranges from 3.0 bars to 4.0 bars. The

pressure can be adjusted by installing a by-pass line on the fuel manifold before the

pressure regulating valve with a valve connecting to the return line after the said regulating

valve. Passing to the fuel conditioning booster the fuel is then pump to the final filter and

up through the distribution pipe manifold of the fuel injection valve before per cylinders.

The fuel in the manifold is regulated again by putting a non-return regulating valve at the

end of the return line manifold after the fuel injection valves before going back to

the fuel conditioning unit as discussed in item number V.I.I. Excess fuel from the

injection valve will return to fuel conditioning unit’s de-aerator tank for the purpose of

aerating gaseous matter.

48
When the generating unit is scheduled for long stand-by be sure to stop the engine after

operation with a diesoline fuel to prevent fuel line from clogging. Bunker C fuel when cold

is very viscos and can cause hard starting of the engine. And from long stand-by make sure

to start up the engine with diesoline again allowing to build up working temperature of the

mating parts to avoid thermal shock. Gradual loading of the engine should be arranged

giving all moving parts to expand properly due to temperature increase. Pre-start up guide

lines, make sure tanks level are checked. Before running the fuel conditioning booster, air

run the engine with the indicator or test cock open for the purpose of relieving impurities

inside the combustion chamber. At least heavy fuel oil is heated 85 °C per experienced

in Sulzer standard. This could be applied because the engines are using the same bunker

C, on that temperature it satisfy the viscosity. Make sure engine control mechanism such

as pump rack lever is free moving. The best way to do this is fill up the pre-start up

checklist before running the engine.

III.XXV.IIa Viscosity-Temperature Diagram;

Viscosity and temperature diagram is used in determining appropriate viscosity and

temperature of a certain fuel oil to feed to the fuel injection pump of the generating unit.

Viscosity is a measurement of flowage of a certain fluid, derives from how long the fluid

will pass through the standard orifice area at a certain degree of temperature, in mm²/sec

or centistoke. Looking in the viscosity - temperature diagram the ordinate is the

measurement of viscosity and the abscissa is the measurement of degree temperature in

degree centigrade. In the fuel oil system viscometer is installed in the fuel conditioning

after the heater. The heating element is programmed at a temperature range

recommended for medium speed engine. And the viscometer operation is constantly

vibrating inside the pipeline in which the intensity of vibration is controlled by the fuel oil

having identified viscosity from heating passing through it. When the fuel oil is viscos it will

slow down the intensity of vibration and this vibration measurement is converted

49
electronically into centistoke unit. The diagonal line inside the abscissa and the ordinate

specify the type of fuel the generating unit is used. The following page is the Viscosity –

Temperature diagram used in determining fuel oil treatment before the main fuel injection

valve. For guidance sample below the chart is provided.

50
III.XXVI Design, Installation and Operation of Lubrication Oil System;

III.XXVI.I Design and Installation Instructions;

Utmost cleanliness should be observed when treating the lubricating oil system. Dirt, metal

particles and similar that may cause serious damage in the bearing should be eliminated.

When installing pipes or other details from the lubricating system extra procedural care

should be followed. The same thing should be done as discussed in the installation of

fuel oil system like chemical de-scaling and acid pickling. During installation all openings

should be cover with blank gasket or tapes. When all pipes and auxiliaries are installed

the same thing is done, oil flushing will be conducted before final connection to the

generating system. What makes the difference are the final filter mesh used and the

temperature requirement during flushing. Lubrication oil system needs 60 microns mesh

and 70 ⁰C temperature. The following pages illustrate the lubrication oil treatment

auxiliaries installation. In the installation process there are several critical issues to be

discussed per manufacturer’s manual criteria. Like, before any external connection of

piping system the engine and the generator must be aligned to its final position. All these

standards have their own specific purposes.

III.XXVI.Ia Lube Oil Pump Unit;

51
Make : IMO ACE 038 N2 IVBP

Capacity : 10,000 liters/hour

Type : Screw

Working Pressure : 16 bars

52
III.XXVI.Ib Lube Oil Pump Unit Single Line Diagram;

53
III.XXVI.Ic Built-in Pump;

Lubricating oil pump is a gear pump double helical rotors and it is driven by the gear

mechanism at the free end of the generating unit. It is equipped with a pressure regulating

valve to keep the oil pressure constant in the lubrication oil feed pipe under variable

conditions; pressure changes after feed pump, pressure increase changes in the coolers

and filters etc. during operation due dirt accumulation. Pump circulation capacity is

280,000 liters/hour and working pressure = 8.0 bar. David Brown brand.

54
III.XXVI.Id Pre-Lubrication Pump Unit;

*Pre-lube pump provides lubrication oil during start up since built in pump is not running.

Make : LEISTRIZ L2N G 106

Capacity : 88,000 liters/hour

55
Type : Screw

Working Pressure : 4.0 bars

III.XXVI.Ie Lube Oil Thermostatic Valve Mixing Application;

56
Make : 6BOCB-145/63-01-00-AA

Valve Opening Set Point Temperature : 63 °C

Nominal diameter for pipe connection : 200 mm

Mixing application is used to lubrication oil treatment system where mixing an oil

fluid of different temperature in the thermostatic valve, temperature from the valve is

being controlled. Oil fluid will start to mixed when the temperature reaches to 63 ⁰C. The

57
wax element which is very sensitive to temperature difference will expand at high

temperature and pushes the valve to open. When the temperature is lower than 63⁰C port

"C" is close and oil from port "B" will by-pass to port "A” until the temperature increases and

the valve will open.

III.XXVI.If Lube Oil Thermostatic Valve Verification Result;

58
59
Figure above is the actual calibration’s result of the wax element which was conducted by

Minergy, Inc. personnel. Taken from engine # 4 and # 5 respectively.

60
III.XXVI.Ig Lubrication Oil Cooler Unit;

Make : M15-FFM8 Alfa Laval

Design pressure : 6.0 bars

Plate material : AISI 316

Plate thickness : 0.50 mm

61
Heating surface : 97.34 m²

Lube oil inlet temperature : 73.7 ⁰C

Lube oil outlet temperature : 63.0 ⁰C

Water inlet temperature : 46.0 ⁰C

Water outlet temperature : 49.9 ⁰C

III.XXVI.Ih Lube Oil Cooler Design and Heat Rejection Computations;

Determine heat rejected in lubrication oil due friction, 𝑄 𝑖𝑛 KW;

𝑄 = 𝐴𝑈∆𝑡𝑚 where : A = 97.34 m² plates total area

𝑈 = 899 W/m² - ⁰C heat transfer coefficient

from Alfa Laval Manual

∆𝑡𝑚 = logarithmic mean temperature

Determine logarithmic mean temperature, ∆t𝑚 𝑖𝑛 ⁰C;

∆𝑡𝑚 = (𝑡₄ - 𝑡₂) – (𝑡₃ – 𝑡₁) / ln ((t₄ - t₂)/ (t₃ - t₁)) ; taken from page 531 Thermodynamics

where : 𝑡ₐᵢ ₄ = 73.7 ⁰C inlet lube oil temp. by V.M. Faires and C. M. Simmang

𝑡ₐₒ ₂ = 49.9 ⁰C outlet LT water temp.

𝑡ᵥₒ ₃ = 63.0 ⁰C outlet lube oil temp.

𝑡ᵥᵢ ₁= 46.0 ⁰C inlet LT water temp.

∆𝑡𝑚 = (73.7 – 49.9) – (63.0 – 46.0) / ln ((73.7 – 49.9)/(63.0 – 46.0))

∆𝑡𝑚 = 23.8 – 17.0 / ln (23.8/17.0)

∆𝑡𝑚 = 6.8 / ln 1.4

∆𝑡𝑚 = 20.21 ⁰C

therefore:

𝑄 = 97.34 × 899 × 20.21 m² (W/m² - ⁰C ) ⁰C

𝑄 = 1,768,550 W

62
III.XXVI.Ii Lubrication Oil Automatic Filter;

Working pressure : 8.0 bar Automatic filter nominal fineness : 20 microns

Working temperature : 60°C Automatic filter maximuml fineness: 35 microns

63
III.XXVI.Ij Lubrication Oil Indicating Duplex Final Filter;

Make : Duplex Filter TYP 2.05.5.420.750 Capacity : 2 × 126 mᶟ

64
Working pressure filter : 8.0 bar Working temperature : 60 ⁰C

Filter nominal fineness : 50 microns Heating temperature : 200 ⁰C

Filter maximum fineness : 60 microns Heating pressure : 14 bars

III.XXVI.Ik Lubrication Oil Centrifugal Filter;

The engine is provided with a centrifugal by-pass filter as complement to the main filter.

The very purpose of this is to indicate the quality of lubrication oil. The filter comprises a

housing containing a hardened steel spindle on which a dynamically balanced rotor is free

to rotate. The oil flows through the housing, up to the central spindle 2 into the rotor. The

65
rotor has two compartment, the cleaning and the driving chamber. The oil flows from the

central tube 13 into the upper part of the rotor subject to high centrifugal force and dirt is

thrown to the walls of the rotor. And the flow of clean oil through the nozzles provides a

driving torque to the rotor.

III.XXVI.I𝒍 Lubrication Oil Purifier;

Make : LFO separator LOPX 710 Working temperature : 80⁰C to 90 ⁰C

Capacity : 4,200 liters/hour Working pressure : 2.0 bars

66
III.XXVI.Im Lubrication Oil Purifier Single Line Diagram;

67
III.XXVI.II Operation Instructions;

The engine is lubricated by wet sump oil system where the oil is mainly treated outside the

engine by continuous purification and filtering. The main function for the oil lubrication

are preventing metal to metal contact at the bearing surface, heat transfer cause by

friction and cleaning. Various auxiliary devices guarantee that oil lubrication is first rate in

all circumstances. The built-in oil pump takes suction from the wet sump and discharge it

under pressure through a pressure regulating valve to the LO cooler, regulated oil pressure

range is 4~8 bars. On the discharge side of the cooler there is a mixing type thermostatic

valve which control the oil flow to the cooler. The oil will by-pass the oil cooler if the

temperature drops below the set point of the thermostatic valve which is equivalent to

63 ̊C. After the cooler the oil will pass through the automatic fine filter and indicating filter

or final filter to the distributing pipe of the engine. After coming to the distributing pipe

at the bottom of the oil sump the oil circuit will up through the hydraulic jacks going to the

main bearings of the engine, through the crank shaft and to the connecting rod

bearings. After the connecting rod bearings oil circuit continue to flow up through the

connecting rod going to the gudgeon pin bearings. And is led to the piston through a

bored passages in the gudgeon pin and the skirt through the special nozzles to the

cylinder liner forming an oil film between the piston and the cylinder liner surfaces.

From the cylinder liner oil gets back to the oil sump.

When starting up the engine make sure pre-lubrication pump is running. Check the

pressure if conform s to 4.0 bar and also other parameters standard. Start the engine and

wait until lube oil temperature reaches to 40°C for loading instruction of the engine.

III.XXVII Design, Installation and Operation of Jacket Water Cooling System;

III.XXVII.I Design and Installation instructions;

68
The engine is cooled in two(2) systems namely the high temperature circuit (H.T.) and the

low temperature(L.T.) circuit. In the installation of piping system after the fabrication

activity the cleaning of inside pipe through acid picking is not a requirement. Before

connection to the engine make sure the whole system will be flushed with water.

Observed the pipe discharge line if the flow is already clean. The H.T. and L.T tanks

should be located above the engine height with the specific requirement of 0.7 ~1.5 bar

static pressure for H.T. and L.T. intake line below before H.T. and L.T. pumps. The

same with other treatment auxiliaries the system is connected to the engine using

expansion bellows to isolate piping system from engine vibration.

Computation of height for Static Pressure = 0.8 bar within 0.7~1.5 bar

𝑃=ῤɡℎ where: ῤ = density of water

𝑃= 1,000 × 9.81× ℎ ῤ = 1,000 mᶟ/kg

ℎ = 𝑃/1,000× 9.81 N/ (mᶟ/kg)(m²/sec) 𝑔 = 9.81 m²/sec

ℎ= 100,000/9,810

ℎ = 8.2 m

In the installation of thermostatic valve it should be properly aligned to the pipe. The

connection is different from the L.O. thermostatic valve, the intake is only one(1) port at A

and two(2) discharge ports at B and C. It is exactly opposite to L.O. line. This will be explain

later in item III.XXVII.Ib. To check the alignment make sure before tightening, all fixed bolts

are free to move. Avoid forced alignment using chain block because thermostatic valve is

easily broken. It is made of cast iron.

III.XXVII.Ia L.T. and H.T. Expansion Tank;

69
H.T. and L.T. capacity : 1,000 liter

Medium filled : soft wate

70
III.XXVII.Ib L.T. and H.T. Thermostatic Valve Unit;

Diverting application is used in H.T. and L.T. cooling water system where the temperature

of the cooling medium coming from the engine goes into the thermostatic valve and

it is being controlled. The wax element which is very sensitive to temperature will expand

71
and pushes the valve to open. It will start opening at 78 ̊C for HT cooler and 27 ̊C

for LT cooler as per actual instrumentation evaluation, pls. see attached copy. For HT

system when the temperature of the cooling water is lower than 78 ̊ C the fluid will by-

pass to port “B” back to the engine until valve opens at high temperature and the water

temperature needs for treatment to the HT cooler. The same thing will happen to L.T.

cooling system.

III.XXVII.Ic L.T. and H.T. Thermostatic Valve Verification Result;

72
73
III.XXVII.Id L.T. Turbo Air Cooler Unit;

74
III.XXVII.Ie L.T. Cooler Design and Heat Rejection Computations;

Determine heat rejected in , 𝑄𝑙𝑡 𝑖𝑛 W;

𝑄𝑙𝑡 = 𝐴𝑈∆𝑡𝑚 where : A = 65.50 m² plates total area

U = 899 W/m² - ⁰C heat transfer coefficient

from Alfa Laval Manual

∆𝑡𝑚 = logarithmic mean temperature

Determine logarithmic mean temperature, ∆tm in ⁰C;

∆tm = (t₄ - t₂) – (t₃ - t₁) / ln ((t₄ - t₂)/ (t₃ - t₁)) ; taken from page 531 Thermodynamics

where : t₄ = 46.1 ⁰C inlet LT water temp. by V.M. Faires and C. M. Simmang

t₂ = 38.7 ⁰C outlet raw water temp.

t₃ = 38.0 ⁰C outlet LT water temp.

t₁ = 32.0 ⁰C inlet raw water temp.

∆𝑡𝑚 = (46.1 – 38.7) – (38.0 – 32.0) / ln ((46.1 – 38.7)/(38.0 – 32.0))

∆𝑡𝑚 = 7.4 – 6.0 / ln (7.4/6.0)

∆𝑡𝑚 = 1.4 / ln 1.23

∆𝑡𝑚 = 6.763 ⁰C

therefore:

𝑄𝑙𝑡 = 65.5 × 899 × 6.763 m² (W/m² - ⁰C ) ⁰C

𝑄𝑙𝑡 = 398,236 W

Make : AK20-FM Alfa Laval

Design pressure : 6.0 bars

Plate material : AISI 316

Plate thickness : 0.40 mm

Heating surface : 65.5 m²

Soft water Inlet temperature : 46.1 ⁰C

Soft water outlet temperature : 38.0 ⁰C

Raw water Inlet temperature : 32.0 ⁰C

75
Raw water outlet temperature : 38.7 ⁰C

Maximum temperature : 95.0 °C

III.XXVII.If H.T. Jacket Water Cooler Unit;

76
III.XXVII.Ig H.T. Cooler Design and Heat Rejection Computations;

Determine heat rejected in the engine jacket water, 𝑄 𝑖𝑛 KW;

𝑄ℎ𝑡 = 𝐴𝑈𝑡𝑚 where : A = 24.5 m² plates total area

𝑈 = 899 W/m² - ⁰C heat transfer coefficient

from Alfa Laval Manual

∆𝑡𝑚 = logarithmic mean temperature

Determine logarithmic mean temperature, ∆tm in ⁰C;

∆tm = (t₄ - t₂) – (t₃ - t₁) / ln ((t₄ - t₂)/ (t₃ - t₁)) ;

where : t₄ = 91.0 ⁰C inlet HT water temp.

t₂ = 51.7 ⁰C outlet raw water temp.

t₃ = 75.4 ⁰C outlet HT water temp.

t₁ = 38.7 ⁰C inlet raw water temp.

∆𝑡𝑚 = (91.0 – 51.7) – (75.4 – 38.7) / ln ((91.0 – 51.7)/(75.4 – 38.7))

∆𝑡𝑚 = 39.3 – 36.7 / ln (39.3/36.7)

∆𝑡𝑚 = 2.6 / ln 1.07

∆𝑡𝑚 = 38.43 ⁰C

therefore:

𝑄ℎ𝑡 = 24.5 × 899 × 38.43 m² (W/m² - ⁰C ) ⁰C

𝑄ℎ𝑡 = 846,400 W

Make : AK20-FM Alfa Laval

Design pressure : 6.0 bars

Plate material : AISI 316

Plate thickness : 0.40 mm

Heating surface : 24.5 m²

Soft water inlet temperature : 91.0 ⁰C

Soft water outlet temperature : 75.4 ⁰C

Raw water inlet temperature : 38.7 ⁰C

77
Raw water outlet temperature : 51.7 ⁰C

Maximum temperature : 95.0 °C

III.XXVII.Ih Jacket Cooling Water Preheating Unit;

Working pressure maximum : 6.0 bar

78
Working temperature maximum : 95 °C

Heating capacity : 81 KW

Capacity : 66.0 liters

III.XXVII.II Operation Instructions;

The engine is cooled by close circuit fresh water system, divided into high temperature

circuit (HT) and the low temperature circuit (LT). Fresh water indicates treated soft water.

The HT-circuit cools the cylinders, cylinder heads, charge air and turbo chargers. From the

built in pump water flows under pressure to the distributing duct which is cast in the

engine block. From the distributing ducts, the water flows through the cooling water bores

in the cylinder liners and continues to cylinder heads. In the cylinder head water is force by

the intermediate deck to flow along the flame plate, around the valves to the exhaust valve

seats and up along the fuel injector sleeve. From the cylinder head assembly waters flows

out through a connection piece pipe to the collecting pipe. Parallel to the flow of water to

the cylinders, part of the water flows through the turbocharger. Both cooling water coming

out from the cylinder heads and turbo charger will goes to the air vent compartment. Part

of water coming in the air vent compartment flows to the HT expansion tank for venting

purposes, to avoid pressure build-up in the HT cooling system cause by expansion of water

due to heat absorption. And large fraction of this cooling water circulates to charge air

cooler then to system outside the engine for treatment. Discharge water from the engine

pass through the diverting type thermostatic valve. If the temperature of the cooling

water is low it will be diverted without temperature treatment to the cooler, thermostatic

valve port to the cooler is set to 80 ̊C. On the discharge side of the HT cooler the circuit

returns back to the built-in pump. And the fraction of water up through the expansion

tank is connected to the treatment circuit before the built-in pump. During start up of

engine wait until jacket water reaches to 70 °C, the engine can be loaded.

The low temperature circuit(LT) cools the charge air and the lube oil. Fresh water from the

79
built-in pump flows under pressure through the second stage of the charge air cooler then

to the outside circuit of the engine which is the lube oil cooler. It continues to the diverting

type thermostatic valve which by-pass if the cooling water temperature is low without

temperature treatment to the cooler. Discharge side of the LT cooler returns back to the

built-in pump. The same with the HT system, a fraction of the LT cooling water after the

charge air cooler will pass through a vent compartment and goes up to the LT expansion

tank for the purpose same as stated in the HT circuit.

III.XXVIII Design, Installation, and Operation of Starting Air System;

III.XXVIII.I Design and Installation Instructions;

Like any other treatment auxiliaries piping installation of air system should be clean

thoroughly which needs acid pickling process. Because this medium will get inside the

combustion chamber like fuel and lube oil engaged on mating parts that are moving.

The air compressor equipment and the compressor tank should be installed and aligned

first before piping installation. Take note, a non return check valve should be properly

inspected if functioning good. Air tank should have a relief valve as per PSME Code

standard on pressure vessel which is 3% to 5% above the maximum working pressure.

Piping line is connected to the engine using flexible hose to isolate from vibration.

Design and computations on factor of safety:

𝑃 = (TS × t × E)/R × FS where: TS = ultimate tensile stress, N/mm²

FS = (TS × t × E)/RP TS = 482,500 kPa for mild steel.

FS = (482.5 × 15 × .7)/(560 × 3) From Design of Machine Members

FS = 3.1 by Doughtie and Vallance page 94

a factor of 2 to 3 for heavy shock load.

From PSME Code section 7.5.a.1 %

for double butt weld is 70%.

80
III.XXVIII.Ia Air Compressor Vessel;

81
III.XXVIII.Ib Starting air Compressor Flexible Hose;

82
III.XX.VIII.II Operations Instructions;

The engine is started with compressed air having a maximum pressure of thirty(30) bars

and minimum pressure required is fifteen(15) bars. A pressure gauge mounted on the

instrument panel indicates the pressure before the main starting valve. The inlet air pipe

from the starting air tank is provided with a non-return valve and the blow off valve

installed before the main starting valve or right after the non-return valve. The main

starting valve and slow turning valve are operated pneumatically via solenoid control

valves and by pushing the start button on the local instrument panel or by activating

solenoids from remote control. The slow turning valve is automatically activated for

two(2) revolutions if engine has been stopped for more than thirty(30) minutes. In slow

turning air will go to the slow turning valve through the pressure control valve, a non-

return valve in the slow turning line prevents from leaking out during the main start.

The shut-off valve prevents air from leaking out during slow turning. When the main

starting valve opens the air can go partly through the flame arrestors to the starting valve

on the cylinder head. Part of the air goes through the starting air distributor to open the

starting valve s on the cylinder head. The starting air distributor controls the opening time

and sequence of the starting valves. Blocking valve on turning gear are precautions to

prevent the engine from starting when turning gear is engaged.

III.XXIX Raw Water Line and Cooling Towers;

Raw water line is the external cooling water that cools the L.T. cooler and the H.T. cooler.

From the cooling tower basin cooled raw water flows to the strainer before it is pump to

The coolers. It passes through the L.T. cooler and then to the H.T. and going back to the

cooling tower distribution pipe wherein cooling process is occurred. Total heat absorb by

the raw water is equal to heat from L.T. and H.T. coming from the internal of the engine as

computed above in section III.XXVII.Ie and IIIXXVII.If, 𝑄𝑐𝑡 = 1,244,636 W.

83
Cooling Tower Specification by Wartsila

Engineering Item: Stand By Generator of Wartsila Vasa 2x16V46 Gen set

Project: Circularity FRP Cooling Tower.

Quantity: 2 Sets

Item Description Specification Remark

1. Type Revise flow of high temperature proof

2. Flow Rate 500 mᵌ /hr

3 Water inlet Temperature 55°C

4. Water out Temperature 32°C

5. Wet Bulb Temperature 29°C

6. Water Splash Rate 0.02 %

7. Noise 85 db (A) 1 M distance

8. Load of Wind 60 m / Sec

9. Power 400 V x 3 x 60 Hz

III.XXIX.Ia Cooling Tower Basic Mass Balance;

Make up rate = Evaporation rate + Windage rate + Blow down rate

84
M = make up rate, kg/sec

E = evaporation rate, kg/sec

W = windage rate, kg/sec

B = blow down rate, kg/sec

E = mcpΔt/HV where: m = 107 kg/sec

E = (107 × 4.184 × 19.7)/2260 cp = 4.184 KJ/kg-°C

E = 3.9 kg/sec Δt = 51.7 – 32 °C

HV = latent heat vaporization, KJ/kg

W=%W×m HV = 2260 KJ/kg

W = 0.002 × 107 % W = 0.2% ave

W = 0.214 kg/sec . C = cycle of concentration

C = 4 cycles actual from the plant.

C = M/(B + W)

M = C(B + W)

M = (4 × B) + (4 × 0.214)

M = 4B + 0.86

From eqn above;

M = E + W + B, substitute the value of M

4B + 0.86 = E + W + B

4B - B = 3.9 + 0.214 -0.86

3B = 3.254

B = 3.254/3

B = 1.085 kg/sec

Therefore;

M =E+W+B

M = 3.9 + 0.214 + 1.085

M = 5.198 kg/sec

85
III.XXX Design, Installation and Operation of Waste Heat Recovery Boiler;

III.XXX Design and Installation Instructions Waste Heat Recovery Boiler;

Waste heat recovery boiler is installed for the purpose of heating the bunker fuel and the

lubrication oil in the purification process. Looking through the steam heating system single

line diagram steam flows to the booster unit and in parallel connection to lubrication oil

purifier, HFO safety filter, HFO oil purifier, HFO buffer or service tank and settling tank.

As discussed above in fuel oil and lubrication oil system, heat treatment is necessary to

attain correct purification temperature and in the booster unit it conditions the required

viscosity of the fuel to the injection valve. After the heating element valves, strainer and

steam trap set up should be installed for maintenance and operation purposes as shown in

the diagram below. The same installation set up in the by pass line. Steam trap is used

to save steam and to make sure condensate should be taken out in the heat exchanger.

The presence of condensate in the steam line is dangerous, it will cause water hammer.

III.XXX.Ia Pipe Trapping Valves Specific;

86
III.XXX.Ib Waste Heat Recovery Boiler Specific;

87
88
Computations of boiler heat energy in KW:

Rated working pressure, P = 8.0 bar

Rated steam temperature, T = 175 °C

Rated steam capacity, m = 1,500 kg/hr

Water temperature, T = 20°C

From steam tables; @ 8.0 bar saturated steam temperature is equal to 170.43 °C;

Since boiler design has no super heater tubes, assumed saturated steam.

therefore:

ℎ𝑔 = 2769.1 KJ/kg @20°C ℎ𝑓 = 83.96 KJ/kg

solving for 𝑄 𝑖𝑛 KW:

𝑄 = m (ℎ𝑔 - ℎ𝑓) where: m = (1,500 kg/hr) × (hr/3600 sec)

𝑄 = 0.416(2769.1-83.96) m = 0.416 kg/sec

𝑄 = 1,117 KW

Percentage heat utilized from smokestack;

% = 1,117/13700

% = 8.1

III.XXX.II Operation Instructions;

The most important parameters to inspect before starting up the boiler are the water

drum level, by pass damper to be normally open to avoid abrupt heating of boiler tubes

and the main damper valve is normally closed. The same in the engine it should be

gradually heated until working temperature and working pressure are attained. Make sure

test cock is tested. Before loading all the heating element conduct condensate blowing

along steam line and blow down water drum to check for any sludge deposit. When

everything is normal finally adjust the main dumper to its operating position.

89
III.XXXI Periodic Maintenance of Engines and Auxiliaries;

Mindanao Energy Systems, Inc. has formulated its own documented periodic maintenance

schedule in accordance with the Manufacturer’s standard. So arrange in order to be user’s

friendly. Maintenance activities are also very critical job in the power plant industry. We

could just relate how huge the energy output the machine handles. That is why checklist is

very important and a requisites in every details of the work that the mechanic do during

periodic maintenance. And in so doing it promotes safety not only on the machine but as

will as the workers. Checklist is also design for traceability, one way of accounting the

technical knowledge of the worker. Below are details of the periodic maintenance

checklist. They are compose of four(4) main checklists which are to specify; the 3,000 PMS,

6,000 PMS, 9,000 PMS and the 12,000 PMS. Each of these checklists are also supported

with the very detailed checklists as provided below. Electrical activities are included in the

main checklist but the detail checklists are not included.

III.XXXI.I 3,000 Running Hours Preventive Maintenance Activity;

MINDANAO ENERGY SYSTEM, INC.

Tablon, Cagayan de Oro City FM-MMD-53 RO

3,000 PMS CHECKLIST FOR WARTSILA ENGINE NO. __ AND ITS AUXILIARIES

Engine Number:____________ WorK Order No:____________

Running Hours:_____________ Date: ____________________

ITEM ACTIVITIES

A. MECHANICAL

I CRANKSHAFT

1.1 * Measure crankshaft deflection at hot and cold conditions. Pls. refer to FM-

90
MMD-55 RO checklist.

II MAIN BEARINGS

2.1 * Visual inspection of main bearing nos. 1-9 for any sign of abnormality.

2.2 * Check main bearing studs & lateral studs/nuts by visual counting of threads and

compare with others or try to check loosening direction using tommy.

III CONNECTING ROD

3.1 * Visual inspection of connecting rod bearings for any sign of abnormality.

3.2 * Check studs & nuts by visual counting of threads and compare with others or try

to check loosening direction using tommy.

3.3 * Visual inspection of connecting rod shim between upper and lower part of

connecting rod for unbalance metal to metal contact.

IV PISTON & CYLINDER LINERS

4.1 * Visual inspection of skirts and liner running surfaces from the crankcase for any

sign of abnormality.

4.2 * Inspection for cooling water leak from cylinder heads.

V CYLINDER HEADS

5.1 * Visual inspection of valve gear bushes, pins, springs, lock-rings and rocker arms.

5.2 * Check tightness of studs/nuts for exhaust valve, starting valve, safety valve,

injector and valve gear body. Pls. refer to FM-MMD-56 RO and FM-MMD-59 RO

checklist.

5.3 * Check intake and exhaust valve tappet clearances. Pls. refer to FM-MMD-57 RO

checklist.

5.4 * Clean and check valve spring cage for any sign of abnormality.

VI CAMSHAFT

6.1 * Visual inspection of cams and cam case for any sign of abnormality such as metal

chips.

6.2 * Visual inspection of contact faces and tappet rollers.

6.3 * Visual inspection of camshaft bearing for any sign of abnormality.

VII TURBOCHARGER

7.1 * Inspect and clean turbocharger filter.

91
VIII FUEL INJECTION PUMPS AND FUEL INJECTOR VALVES

8.1 * Pull-out main injection valves and replace with reconditioned spares. Pls. refer to

FM-MMD-73 RO checklist.

8.2 * Clean and check freedom of movement of fuel injection pump regulating linkage.

8.3 * Check for fuel leak from the injection pumps and nozzles.

IX FLYWHEEL COUPLING ELASTICAL MOUNTING

9.1 * Visual inspection on thrust rubber element for any sign of critical crack and wear.

9.2 * Check alignment and tightness of the thrust rubber element, engine side bolts'

torque equal to 1,600Nm and generator side bolts' torque is 1,040Nm.

9.3 * Check dimensions for any significant changes. It measures 460mm from the face

of the coupling engine side and the engine block end. Pls. refer to fixing rail

installation plan.

X CONTROL MECHANISM

10.1 * Check for free movement of control mechanism, clean and lubricate.

XI EXHAUST PIPING

11.1 * Visual inspection of expansion bellows guide element, renew antiseize compound.

11.2 * Re-tightening of bolts.

11.3 * Inspect insulation box vibration damper element. Replace if necessary.

XII AUXILIARIES

12.1 * Clean cooling tower basin and check for any crack or leak.

12.2 * Check water distribution alignment and fixed bolts tightness.

12.3 * Inspection of fans alignment and check fixed bolts tightness.

12.4 * Clean centrifugal filter. Remember to open the valve before the filter when finish

cleaning.

12.5 * Inspection and cleaning of intake air filters.

XIII WASTE HEAT RECOVERY BOILER

13.1 * Conduct heat recovery boiler external and internal inspection. Pls. refer FM-

MMD-75 RO.

13.2 * Visual inspection of feed water tank and feed pump system for any leak.

92
B. OPERATIONS

XIV TURBOCHARGER

14.1 * Take oil sample from turbine and compressor for evaluation. Check for any sign

of abnormality (wear and tear).

14.2 * Change oil if necessary.

XV GOVERNOR

15.1 * Check oil level, add appropriate amount if necessary.

15.2 * Check for leak.

C. ELECTRICAL

XVI ALTERNATOR

16.1 * Visual inspection of alternator for any abnormalities or any signs of crack.

16.2 * Clean the alternator with dry rags and use vacuum cleaner for final cleaning.

16.3 * Clean, check and retighten mounting bolts on exciter diodes.

XVII MAGNETIC PICK-UP

17.1 * Clean and check magnetic pick-up clearance at turbo charger, 2.5mm.

17.2 * Clean and check magnetic pick-up clearance at engine flywheel, 2.5mm.

XVIII MOTORS

18.1 * Inspect, clean and test all motor controls.

18.2 * Inspect / clean all motor driving pumps.

XIX OIL MIST DETECTOR

19.1 * Servicing of oil mist detector.

19.2 * Inspect / clean oil mist detector piping and support.

XX WARNING AND TRIPPING SENSORS

20.1 * Simulation test of warning and tripping sensors. Pls. refer to FM-EMD-24 to FM-EMD-30.

D. OPERATIONS SHIFT ENGINEERS UNSCHEDULED REPAIR LOG

XXI ABNORMALITIES

21.0 * Rectify all abnormalities observed & recorded by Shift Engineers & Operators.

See separate list.

93
Checked by: ____________________ Confirmed by : ____________________

MMD / EMD Leadman / Jr. PMS Engr. MMD & EMD Sup. / PMS Engr.

Date:_____________________ Date:_____________________

Noted by:______________________

AVP- Diesel Power Division Head

Date:______________________

Remarks:

94
MINDANAO ENERGY SYSTEMS INC.

Tablon,Cagayan de Oro City FM-MMD-55 RO

WARTSILA CRANKSHAFT DEFLECTION CHECKLIST

Engine Number:____________ Work Order No:____________

Running Hours:_____________ Date: ____________________

Temperature @ cooled/hot condition:____________

95
Following limits of misalignment are stated for an engine at ambient temperature:

a.) On the same crank,the difference between two diametrically opposed readings must not exceed

0.30mm.Realignment is necessary if this limit is exceeded by more than 0.02mm.

b.) On two adjacent cranks, the difference between two corresponding readings must not

exceed 0.15mm realignment is necessary if this limit exceeded.

NOTE: In a hot engine the corresponding values must be based on experiences from the

particular installation.

Time started:____________________ DONE BY:____________________

Time finished:___________________ ____________________

Checked by:_____________________ Confirmed by:____________________

MMD Leadman MMD Supervisor

Date:_________________ Date:________________

Noted by:________________________

AVP- Diesel Power Division Head

Date:______________________

Remarks:

96
MINDANAO ENERGY SYSTEMS, INC.

Tablon, Cagayan de Oro City FM-MMD-56 RO

WARTSILA TIGHTENING CHECKLIST FOR CYLINDER HEAD STUD BOLT / NUT

Engine Number:____________ Work Order No: ________________

Running Hours:_____________ Date:_________________________

Pre-Tightening Final-Tightening Elongation

Measure "X" Pre-tensioning Measure "X1" Final "X1" - "X"

100 bar 430 bar

Cyl.
1 2 3 4 1 2 3 4 1 2 3 4
Head
L1

L2

L3

L4

L5

L6

L7

L8

R1

R2

R3

R4

R5

R6

R7

R8

97
Checked By:___________________ Confirmed By:__________________

MMD leadman MMD SUPERVISOR

Date:__________________ Date:________________

Noted by: _____________________

AVP-Diesel Power Division Head

Date:_____________________

Remarks:

98
MINDANAO ENERGY SYSTEMS, INC.

Tablon, Cagayan de Oro City FM-MMD-57 RO

WARTSILA TAPPET CLEARANCE CHECKLIST

Engine Number:____________________ Work Order No:____________________

Running Hours:_____________________ Date:_____________________________

CLEARANCE BEFORE ADJUSTMENT FINAL ADJUSTED CLEARANCE

Cyl.
no. INTAKE EXHAUST INTAKE EXHAUST DONE BY

R1

R2

R3

R4

R5

R6

R7

R8

L1

L2

L3

L4

L5

L6

L7

L8

NOTE: Nominal Valve Clearance at Cold Condition are, 1.00 mm for inlet and 1.5 mm for

nimonic exhaust valves.

99
Checked by:____________________ Confirmed by:___________________

MMD Leadman MMD Supervisor

Date:_________________ Date:__________________

Noted by:______________________

AVP- Diesel Power Division Head

Date:_______________________

Remarks:

100
101
102
MINDANAO ENERGY SYSTEMS, INC.

Tablon, Cagayan de Oro City FM-MMD-73 RO

MAIN FUEL INJECTION VALVE REMOVAL AND INSTALLATION GUIDE CHECKLIST

Engine Number:_____ Work Order No:____________

Running Hours:__________ Date:____________________

ACTIVITIES Started Finished Done by

I Removing of main injection valve

1.1 Remove the rocker arm casing and the hot-box cover. _______ _______ _______

1.2 Remove the injection pipe by openning the nuts( 6) and _______ _______ _______

( 7) and the leak fuel connection( 8).

1.3 Loosen the sealing flange of the connection piece by _______ _______ _______

loosening the nuts(9) and unscrew the connection piece.

Protect the fuel holes.

1.4 Remove the fastening nuts( 26) of the injection valve. _______ _______ _______

1.5 Lift out the injection valve by using the eyebolt M12 _______ _______ _______

( 805001). If necessary, use extractor ( 837038). If too

much force has to be used, there is a risk of the stainless

sleeve of the cylinder head coming loose which, in such

a case, must be checked.

1.6 Protect the fuel inlet hole of the injection valve and the _______ _______ _______

bore in the cylinder head.

II Installation of main fuel injection valve

2.1 Check that the bottom of the stainless sleeve in the _______ _______ _______

cylinder head is clean. If necessary clean or lap the

surface.

2.2 Put new o-rings on the injection valve. Lubricate the _______ _______ _______

injection valve.

103
2.3 Fit the injection valve into the cylinder head bore. _______ _______ _______

2.4 Tighten the fastening nuts( 26) of the injection valve to _______ _______ _______

correct torque in step of 10…20 Nm.

2.5 Put new o-rings in the sealing flange on the connection _______ _______ _______

piece. Place the flange on the connection piece and

tighten the connection piece to 150 Nm. +/- 5 Nm.

2.6 Tighten the sealing flange fastening screws ( 9). _______ _______ _______

2.7 Mount the injection pipe and tighten the cap nuts to _______ _______ _______

600 Nm. +/- 15 Nm.

2.8 Mount the hot-box covers the rocker arm casing. _______ _______ _______

Pls. refer to Wartsila injection system manual.

Checked by:____________________ Confirmed by:____________________

MMD Leadman MMD Super visor

Date :_____________________ Date :___________________

Note by :______________________

AVP-Diesel Power Division Head

Date :____________________

Remarks:

104
MINDANAO ENERGY SYSTEMS, INC.

Tablon, Cagayan de Oro City FM-MMD-75 RO

WHR BOILER INSPECTION CHECKLIST

Engine Number:___________________ Work Order No:____________________

Running Hours:____________________ Date:____________________________

ACTIVITIES Started Finished Done by

1.0 Cool down boiler before inspection.

2.0 Check exhaust duct inlet and by-pass damper to close position ______ ______ _______

for safe inspection activities.

3.0 Good light maybe used during inspection to obtain best view ______ ______ _______

for any defective surfaces.

4.0 Open manholes and holes cover in a combustion furnace. ______ ______ _______

5.0 Clean outside boiler tube surface, fins, boiler casing wall and ______ ______ _______

ducting.

6.0 Visual inspection of any defective or corroded outside boiler ______ ______ _______

tubes surface, fins, boiler casing wall and ducting. Conduct

repair if necessary.

7.0 Check main damper blades for any defect or corrosion. ______ ______ _______

test for opening and closing of the blades.

8.0 Clean the peep sight glass. ______ ______ _______

9.0 Check the piping on the low water cut-off for corrosion and ______ ______ _______

scale build-up.

10.0 Check all valves for proper operation. ______ ______ _______

11.0 Before closing the manholes and hand holes thoroughly ______ ______ _______

check for tools, rags and other paraphernalia.

FM-MMD-75 RO

105
12.0 Open and drain out water from the boiler drum a certain ______ ______ _______

percentage enough to see upper end portion of the inside

tubes surface for any scale formation, corrosion and oil

presence. clean if necessary.

13.0 Conduct hydro testing of boiler 1.5 times the working ______ ______ _______

pressure, applicable when welding works is done on

the tubes.

14.0 Conduct safety relief valve testing during first start-up. ______ ______ _______

15.0 Check piping pressure of the feed water pump for ______ ______ _______

any irregularity.

Checked by:____________________ Confirmed by:____________________

MMD Leadman MMD Supervisor

Date :__________________ Date :__________________

Note by :_______________________

AVP- Diesel Power Division Head

Date :_____________________

Remarks:

106
III.XXXI.II 6,000 Running Hours Preventive Maintenance Activities;

MINDANAO ENERGY SYSTEM, INC.

Tablon, Cagayan de Oro City FM-MMD-54 RO

6,000 PMS CHECKLIST FOR WARTSILA ENGINE NO. __ AND ITS AUXILIARIES

Engine Number:____________ Work Order No:____________

Running Hours:_____________ Date: ____________________

ITEM ACTIVITIES

A. MECHANICAL

I CRANKSHAFT

1.1 * Measure crankshaft deflection at hot conditions. Pls. refer to FM-MMD-55 RO

checklist.

II MAIN BEARINGS

2.1 * Visual inspection of main bearing nos. 1-9 for any sign of abnormality.

2.2 * Remove main bearing no. "___ " (pull down lower bearing shell) and inspect its condition.

Pls. refer to FM-MMD-58 RO.

2.3 * Check main bearing studs & lateral studs/nuts by visual counting of threads and compare

with others or try to check loosening direction using tommy.

III CONNECTING ROD

3.1 * Visual inspection of connecting rod bearings for any sign of abnormality.

3.2 * Check studs & nuts by visual counting of threads and compare with others or try to check

loosening direction using tommy.

3.3 * Visual inspection of connecting rod shim between upper and lower part of connecting rod

for unbalance metal to metal contact.

IV PISTON & CYLINDER LINERS

4.1 * Visual inspection of skirts and liner running surfaces from the crankcase for any sign of

abnormality.

107
4.2 * Inspection for cooling water leak from cylinder heads.

4.3 * Visual inspection of anti polishing ring for any broken pieces.

V CYLINDER HEADS

5.1 * Visual inspection of valve gear bushes, pins, springs, lock-rings and rocker arms.

5.2 * Check tightness of studs/nuts for exhaust valve, starting valve, safety valve, injector and

valve gear body. Pls. refer to FM-MMD-56 RO and FM-MMD-59 RO checklist.

5.3 * Check intake and exhaust valve tappet clearances. Pls. refer to FM-MMD-57 RO checklist.

5.4 * Clean and check valve spring cage for any sign of abnormality.

5.5 * Inspect inlet and outlet valves for pitting and corrosion. If machine grinding is necessary,

promptly replace with ready, reconditioned spare cylinder head. Pls. refer to

FM-MMD-62 RO, FM-MMD-65 RO and FM-MMD-72 RO.

VI CAMSHAFT

6.1 * Visual inspection of cams and cam case for any sign of abnormality such as metal chips.

6.2 * Visual inspection of contact faces and tappet rollers.

6.3 * Visual inspection of camshaft bearing for any sign of abnormality.

VII TURBOCHARGER

7.1 * Inspect and clean turbocharger filter.

VIII FUEL INJECTION PUMPS AND FUEL INJECTOR VALVES

8.1 * Pull-out main injection valves and replace with reconditioned spares. Pls. refer to FM-

MMD-73 RO checklist.

8.2 * Clean and check freedom of movement of fuel injection pump regulating linkage.

8.3 * Check for fuel leak from the injection pumps and nozzles.

IX FLYWHEEL COUPLING ELASTICAL MOUNTING

9.1 * Visual inspection on thrust rubber element for any sign of critical crack and wear.

9.2 * Check alignment and tightness of the thrust rubber element, engine side bolts' torque

equal to 1,600Nm and generator side bolts' torque is 1,040Nm.

9.3 * Check dimensions for any significant changes. It measures 460mm from the face of the

coupling engine side and the engine block end. Pls. refer to fixing rail installation plan.

X CONTROL MECHANISM

10.1 * Check for free movement of control mechanism, clean and lubricate.

108
10.2 * Check for wear in all connecting links between the governor and all injection pumps.

10.3 * Check the adjustment and function of the starting fuel limiter. Pls. refer to chapter 22 of

the Wartsila Manual.

XI EXHAUST PIPING

11.1 * Visual inspection of expansion bellows guide element, renew antiseize compound.

11.2 * Re-tightening of bolts.

11.3 * Inspect insulation box vibration damper element. Replace if necessary.

XII AUXILIARIES

12.1 * Clean cooling tower basin and check for any crack or leak.

12.2 * Check water distribution alignment and fixed bolts tightness.

12.3 * Inspection of fans alignment and check fixed bolts tightness.

12.4 * Clean centrifugal filter. Remember to open the valve before the filter when finish

cleaning.

12.5 * Inspection and cleaning of intake air filters.

XIII WASTE HEAT RECOVERY BOILER

13.1 * Conduct heat recovery boiler external and internal inspection. Pls. refer FM-MMD-75 RO.

13.2 * Visual inspection of feed water tank and feed pump system for any leak.

B. OPERATIONS

XIV TURBOCHARGER

14.1 * Check turbo oil at turbine & compressor sides. Change oil if necessary.

14.2 * Inspect drained oil for any sign of abnormality (wear & tear).

XV GENERATOR BEARING

15.1 * Drain oil sample for evaluation and analysis. Change oil if necessary.

XVI L.O. AUTOBACKWASH FILTER

16.1 * Cleaning of sludge basket filter.

C. ELECTRICAL

XVII ALTERNATOR

17.1 * Conduct insulation resistance test before and after cleaning. Pls. refer to FM-EMD-09.

17.2 * Visual inspection of alternator for any abnormalities or any signs of crack.

109
17.3 * Clean and check stator winding, rotating resistor, rotor winding, exciter's stator,exciter's

rotor for any sign of insulation brittleness and damage. Also check generator casing for

any chips recovered. Use vacumm cleaner, new paint brush and dry rags in cleaning.

17.4 * Check exciter's stator winding(field) supply wire and retighten loosen bolts and nuts.

17.5 * Clean and check terminal box, including CT's, PT's and booster. Use high dielectric

strength solvent in cleaning. Retighten loosen terminals, bolts and nuts.

17.6 * Prior to cover check for any tools, rugs and etc. left.

XVIII GENERATOR 'S SURGE PROTECTION EQUIPMENT

18.1 * Conduct insulation resistance test before and after cleaning. Pls. refer to FM-EMD-09.

18.2 * Clean and check surge, lighting arrester and enclosure box with rugs. Retighten loosen

terminals, bolts and nuts. Prior to cover check for any tools, rugs and etc. left.

XIX MAGNETIC PICK-UP

19.1 * Clean and check magnetic pick-up clearance at turbo charger, 2.5mm.

19.2 * Clean and check magnetic pick-up clearance at engine flywheel, 2.5mm.

XX MOTORS

20.1 * Conduct insulation resistance test before and after cleaning. Pls. refer to FM-EMD-09.

20.2 * Clean and check driving motors for any damage. Retighten loosen terminals, bolts and

nuts. Pls. refer to FM-EMD-03.

20.3 * Inspect, clean motor control magnetic contactors and retighten loosen terminals, bolts

and nuts in the MCC.

XXI OIL MIST DETECTOR

21.1 * Servicing of oil mist detector.

21.2 * Inspect / clean oil mist detector piping and support.

XXII WARNING AND TRIPPING SENSORS

22.1 * Simulation test of warning and tripping sensors. Pls. refer to FM-EMD-24 to FM-EMD-30.

XVIII SOLENOID VALVES

23.1 * Inspect / clean FOP's, LOP's and air system solenoid valves.

D. OPERATIONS SHIFT ENGINEERS UNSCHEDULED REPAIR LOG

XIV ABNORMALITIES

110
24.1 * Rectify all abnormalities observed & recorded by Shift Engineers & Operators. See

separate list.

Checked by: ____________________ Confirmed by : ____________________

MMD / EMD Leadman / Jr. PMS Engr. MMD & EMD Sup. / PMS Engr.

Date:_________________________ Date:____________________

Noted by:______________________

AVP- Diesel Power Division Head

Date:______________________

Remarks:

111
112
113
114
115
III.XXXI.III 9,000 Running Hours Preventive Maintenance Activities;

MINDANAO ENERGY SYSTEM, INC.

Tablon, Cagayan de Oro City FM-MMD-61 RO

9,000 PMS CHECKLIST FOR WARTSILA ENGINE NO. __ AND ITS AUXILIARIES

Engine Number:____________ WorK Order No:____________

Running Hours:_____________ Date: ____________________

ITEM ACTIVITIES

A. MECHANICAL

I CRANKSHAFT

1.1 * Measure crankshaft deflection at hot and cold conditions. Pls. refer to FM-

MMD-55 RO checklist.

II MAIN BEARINGS

2.1 * Visual inspection of main bearing nos. 1-9 for any sign of abnormality.

2.2 * Check main bearing studs & lateral studs/nuts by visual counting of threads and

compare with others or try to check loosening direction using tommy.

III CONNECTING ROD

3.1 * Visual inspection of connecting rod bearings for any sign of abnormality.

3.2 * Check studs & nuts by visual counting of threads and compare with others or try

to check loosening direction using tommy.

3.3 * Visual inspection of connecting rod shim between upper and lower part of

connecting rod for unbalance metal to metal contact.

IV PISTON & CYLINDER LINERS

4.1 * Visual inspection of skirts and liner running surfaces from the crankcase for any

sign of abnormality.

4.2 * Inspection for cooling water leak from cylinder heads.

V CYLINDER HEADS

116
5.1 * Visual inspection of valve gear bushes, pins, springs, lock-rings and rocker arms.

5.2 * Check tightness of studs/nuts for exhaust valve, starting valve, safety valve,

injector and valve gear body. Pls. refer to FM-MMD-56 RO and FM-MMD-59 RO

checklist.

5.3 * Check intake and exhaust valve tappet clearances. Pls. refer to FM-MMD-57 RO

checklist.

5.4 * Clean and check valve spring cage for any sign of abnormality.

VI CAMSHAFT

6.1 * Visual inspection of cams and cam case for any sign of abnormality such as metal

chips.

6.2 * Visual inspection of contact faces and tappet rollers.

6.3 * Visual inspection of camshaft bearing for any sign of abnormality.

VII TURBOCHARGER

7.1 * Inspect drained oil for any sign of abnormality (wear & tear).

7.2 * Dismantle completely turbocharger and thorough clean cooling water duct for any scale

deposit.

7.3 * Check bearings, replace if necessary. Assemble turbo charger as per FM-MMD-70 RO

checklist.

7.4 * Inspect and clean turbocharger filter.

VIII FUEL INJECTION PUMPS AND FUEL INJECTOR VALVES

8.1 * Pull-out main injection valves and replace with reconditioned spares. Pls. refer to

FM-MMD-73 RO checklist.

8.2 * Clean and check freedom of movement of fuel injection pump regulating linkage.

8.3 * Check for fuel leak from the injection pumps and nozzles.

IX FLYWHEEL COUPLING ELASTICAL MOUNTING

9.1 * Visual inspection on thrust rubber element for any sign of critical crack and wear.

9.2 * Check alignment and tightness of the thrust rubber element, engine side bolts'

torque equal to 1,600Nm and generator side bolts' torque is 1,040Nm.

9.3 * Check dimensions for any significant changes. It measures 460mm from the face

of the coupling engine side and the engine block end. Pls. refer to fixing rail

117
installation plan.

X CONTROL MECHANISM

10.1 * Check for free movement of control mechanism, clean and lubricate.

XI EXHAUST PIPING

11.1 * Visual inspection of expansion bellows guide element, renew antiseize compound.

11.2 * Re-tightening of bolts.

11.3 * Inspect insulation box vibration damper element. Replace if necessary.

XII AUXILIARIES

12.1 * Clean cooling tower basin and check for any crack or leak.

12.2 * Check water distribution alignment and fixed bolts tightness.

12.3 * Inspection of fans alignment and check fixed bolts tightness.

12.4 * Clean centrifugal filter. Remember to open the valve before the filter when finish

cleaning.

12.5 * Inspection and cleaning of intake air filters.

XIII WASTE HEAT RECOVERY BOILER

13.1 * Conduct heat recovery boiler external and internal inspection. Pls. refer FM-

MMD-75 RO.

13.2 * Visual inspection of feed water tank and feed pump system for any leak.

B. OPERATIONS

XIV TURBOCHARGER

14.1 * Take oil sample from turbine and compressor for evaluation. Check for any sign

of abnormality (wear and tear).

XV GOVERNOR

15.1 * Check oil level, add appropriate amount if necessary.

15.2 * Check for leak.

C. ELECTRICAL

XVI ALTERNATOR

16.1 * Visual inspection of alternator for any abnormalities or any signs of crack.

16.2 * Clean the alternator with dry rags and use vacuum cleaner for final cleaning.

16.3 * Clean, check and retighten mounting bolts on exciter diodes.

118
XVII MAGNETIC PICK-UP

17.1 * Clean and check magnetic pick-up clearance at turbo charger, 2.5mm.

17.2 * Clean and check magnetic pick-up clearance at engine flywheel, 2.5mm.

XVIII MOTORS

18.1 * Inspect, clean and test all motor controls.

18.2 * Inspect / clean all motor driving pumps.

XIX OIL MIST DETECTOR

19.1 * Servicing of oil mist detector.

19.2 * Inspect / clean oil mist detector piping and support.

XX WARNING AND TRIPPING SENSORS

20.1 * Simulation test of warning and tripping sensors. Pls. refer to FM-EMD-24 to FM-EMD-30.

D. OPERATIONS SHIFT ENGINEERS UNSCHEDULED REPAIR LOG

XXI ABNORMALITIES

21.1 * Rectify all abnormalities observed & recorded by Shift Engineers & Operators.

See separate list.

Checked by: ____________________ Confirmed by : ____________________

MMD / EMD Leadman / Jr. PMS Engr. MMD & EMD Sup. / PMS Engr.

Date:_____________________ Date:_____________________

Noted by:______________________

AVP- Diesel Power Division Head

Date:______________________

Remarks:

119
120
III.XXXI.IV 12,000 Running Hours Preventive Maintenance Activities;

MINDANAO ENERGY SYSTEM, INC.

Tablon, Cagayan de Oro City FM-MMD-76 RO

12,000 PMS CHECKLIST FOR WARTSILA ENGINE NO. __ AND ITS AUXILIARIES

Engine Number:____________ Work Order No:____________

Running Hours:_____________ Date: ____________________

ITEM ACTIVITIES

A. MECHANICAL

I CRANKSHAFT

1.1 * Measure crankshaft deflection at hot conditions. Pls. refer to FM-MMD-55 RO

checklist.

1.2 * Measure deflection after checking of engine holding down bolts (anchor/foundation

bolts) or after PMS.

1.3 * Visual inspection of counterweights locking plate.

II MAIN BEARINGS

2.1 * Visual inspection of bearing nos. 1-9 for any sign of abnormality.

2.2 * Pull down lower bearing shell nos. 1 - 9. Inspect condition of bearing shells.

2.3 * Installation of main bearing nos. 1 - 9 (refer to tightening checklist)

2.4 *Inspect bearing studs & lateral studs/nuts by visual counting of threads and compare with

other or try to check loosening direction using tommy.

III CRANKSHAFT LOCATING BEARING

3.1 *Inspect condition of bearing shells and bearing ring halves (remove bearing shell).

3.2 * Check axial clearance. Pls. refer to checklist clearance .

3.3 * Installation of bearing shells. Pls. refer to manual.

IV CRANKCASE

4.1 * Check tightness of all bolted connections and locking devices.

121
4.2 * Check tightness of engine holding down bolts.

4.3 * Cleaning of crankcase. Observed for any metal

V BOTTOM END BEARING

5.1 * Visual inspection of bearing nos. 1-16 for any sign of abnormality.

5.2 * Check studs & nuts by visual counting of threads and compare with others or try to check

loosening direction using tommy.

5.3 * Pull down bearing shells nos. L1 - L8. Inspect bearing condition.

5.4 * Installation of bearing shell nos. L1 - L8. Pls. refer to FM-MMD- 66 RO.

VI CYLINDER LINERS

6.1 * Remove all cylinder liner 1-16.

6.2 * Reconditioning of cylinder liners. Pls. refer to FM-MMD-63 RO and FM-MMD-64 RO.

6.3 * Installation of cylinder liners.

VII CYLINDER HEADS

7.1 * Remove all accessories attaching to the cylinder heads. Fuel valve cooling fittings, starting
air line, exhaust and inlet flange, fuel pipes, valve gear cover and rocker arm assembly

7.2 * Pull out cylinder heads 1 - 16.

7.3 * Reconditioning of cylinder heads. Pls. refer to FM-MMD-62 and FM-MMD-65.

7.4 * Reconditioning of relief valves. Pls. refer to reconditioning checklist.

7.5 * Reconditioning of starting valves. Pls. refer to reconditioning checklist.

7.6 * Installation of cylinder heads.

VIII ROCKER ARMS

8.1 * Inspect bearing bushes and shafts and determine clearance. Pls. refer to FM-MMD-65.

checklist

8.2 * Installation of rocker arms.

IX HEAVY FUEL PIPES AND FUEL DELIVERY VALVES

9.1 * Overhaul of delivery valves. Pls. refer to checklist.

X INLET VALVES AND OUTLET VALVES

10.1 * Overhaul and machine grind where necessary. Renew if necessary.

XI CAMSHAFTS

11.1 * Inspect condition of cams.

122
11.2 * Remove some camshaft bearing at random for inspection. Two at left bank and two at

right bank.

11.3 * Visual inspection of camshaft bearing for any sign of abnormality.

11.4 * Check axial clearance.

XII TURNING GEAR

12.1 * Change oil.

XIII WORKING PISTON

13.1 * Remove all piston and overhaul.

13.2 * Overhauling of piston. Pls.r efer to checklist.

13.3 * Installation of piston. Pls. refer to tightening checklist.

XIV ENGINE BLOCK

14.1 * Checking for cracks.

14.2 * Cleaning of air space and cooling space.

14.3 * Retightening of bolts. Pls. mark paint on tightened bolts.

14.4 * Check studs for cylinder cover bottom sealant. Add silicon sealant if necessary.

XV CAMSHAFT DRIVE

15.1 * Inspect condition of gear teeth and check tooth backlash clearance. Pls. refer to

clearance checklist.

XVI AIR COOLER

16.1 * Pull out left bank and right bank air cooler.

16.2 * Installation left bank and right bank air cooler.

XVII MECHANICAL OVERSPEED

17.1 *Check function of over speed test.

XVIII FUEL INJECTION PUMPS

18.1 * Adjust pumps regulating rack nos. 1-16 on engine.

18.2 * Overhaul leaking control rack nos. R1 to R8 and L1 to L8.

XIX LUBRICATING OIL BUILT-IN PUMP.

19.1 * Inspect the drive gear wheel gear tooth profile.

19.2 * Overhauling of pumps. Pls. refer to checklist

XX CYLINDER COOLING WATER PUMPS

123
20.1 *Inspect the drive gear wheel gear tooth profile.

20.2 * Overhauling of pumps . Pls. refer to checklist

XXI EXHAUST PIPING

21.1 * Servicing of expansion bellows guide element, renew anti seize compound.

21.2 * Re-tightening of bolts. Mark bolt with paint immediately after retightened.

21.3 * Checked insulation box vibration damper limiting screw.

XXII AUXILIARIES

22.1 * Clean and inspect lube oil cooler.

22.2 * Clean and inspect L.T. and H.T. jacket water cooler.

22.3 * Check or overhauling of starting air compressor.

22.4 * Pop test starting air reservoir safety valve.

22.5 * Pop test starting compressor air line safety valve, 1st and 2nd stage.

22.6 *Overhauling of L.O. purifier.

XXIII WASTE HEAT RECOVERY BOILER

23.1 * Conduct waste heat recovery boiler for external and internal inspection, observed any

sign leakages. Pls. refer FM-MMD-75 RO.

23.2 * Visual inspection of feed water tank and feed pump system for any leak.

23.3 * Conduct hydro test using feed pump and thorough inspect for any rags and tools left

before closing the furnace maintenance manhole.

B. OPERATIONS

XXIV TURBOCHARGER

24.1 * Check turbo oil at turbine & compressor sides. Change oil if necessary.

24.2 * Inspect drained oil for any sign of abnormality (wear & tear).

XXV GENERATOR BEARING

25.1 * Drain oil sample for evaluation and analysis. Change oil if necessary.

XXVI LUBE OIL AUTO BACKWASH FILTER AND FINAL FITERS

26.1 * Clean and inspect filters for any metal wear sludge. Metal wear recovered for

identification.

26.2 * Clean and check also filter mesh for any damage. Replace if necessary.

XXVII GOVERNOR ACTUATOR

124
27.1 * Inspect gear wheels.

27.2 * Conduct change oil.

XXVIII GENERATOR BEARING

28.1 *Check and clean generator bearing for any sign of damage.

C. ELECTRICAL

XXIX ALTERNATOR

29.1 * Conduct insulation resistance test before and after cleaning. Pls. refer to FM-EMD-09.

29.2 * Visual inspection of alternator for any abnormalities or any signs of crack.

29.3 * Clean and check stator winding, rotating resistor, rotor winding, exciter's stator, exciter's

rotor for any sign of insulation brittleness and damage. Also check generator casing for

any chips recovered. Use vacuum cleaner, new paint brush and dry rags in cleaning.

29.4 * Check exciter's stator winding(field) supply wire and retighten loosen bolts and nuts.

29.5 * Clean and check terminal box, including CT's, PT's and booster. Use high dielectric

strength solvent in cleaning. Retighten loosen terminals, bolts and nuts.

29.6 * Prior to cover check for any tools, rugs and etc. left.

XXX GENERATOR 'S SURGE PROTECTION EQUIPMENT

30.1 * Conduct insulation resistance test before and after cleaning. Pls. refer to FM-EMD-09.

30.2 * Clean and check surge, lighting arrester and enclosure box with rugs. Retighten loosen

terminals, bolts and nuts. Prior to cover check for any tools, rugs and etc. left.

XXXI MAGNETIC PICK-UP

31.1 * Clean and check magnetic pick-up clearance at turbo charger, 2.5mm.

31.2 * Clean and check magnetic pick-up clearance at engine flywheel, 2.5mm.

XXXII MOTORS

32.1 * Conduct insulation resistance test before and after overhaul. Pls. refer to FM-EMD-09.

32.2 * Check and replace driving motors bearings. Retighten loosen terminals, bolts and nuts.

Pls. refer to FM-EMD-03.

32.3 * Inspect, clean motor control magnetic contactors and retighten loosen terminals, bolts

and nuts in the MCC.

XXXIII OIL MIST DETECTOR

33.1 * Servicing of oil mist detector.

125
33.2 * Inspect / clean oil mist detector piping and support.

XXXIV WARNING AND TRIPPING SENSORS

34.1 * Simulation test of warning and tripping sensors. Pls. refer to FM-EMD-24 to FM-EMD-30.

XXXV SOLENOID VALVES

35.1 * Inspect / clean FOP's, LOP's and air system solenoid valves.

D. OPERATIONS SHIFT ENGINEERS UNSCHEDULED REPAIR LOG

XXXVI ABNORMALITIES

36.1 * Rectify all abnormalities observed & recorded by Shift Engineers & Operators. See

separate list.

Checked by: ____________________ Confirmed by : ____________________

MMD / EMD Leadman / Jr. PMS Engr. MMD & EMD Sup. / PMS Engr.

Date:_________________________ Date:____________________

Noted by:______________________

AVP- Diesel Power Division Head

Date:______________________

Remarks:

126
127
128
129
130
131
IV Comments and recommendations;

Our station energy used in Sulzer operation without waste heat recovery boiler, equates to

five(5) percent of the gross generated power. For the two(2) Warstsila engines running

with waste heat recovery boiler the station energy used is only three(3) percent of the

gross generation. For reference, two(2) 13.0 MW Wartsila engines operating at 12.0

hours per day. Total energy generated is equal to 312,000 KWh per day. Three(3) percent

of that is 9,360 KWh. Assuming no heat recovery boiler is applied. So, five (5) percent of

the total energy generation per day is 15,600 KWh.

Savings for installing waste heat recovery boiler in KWh;

Savings in a day = 15,600 – 9,360 = 6,240 KWh per day

Savings in a year = 6,240 X 365 days

Savings in a year = 2,277,600 KWh if per KWh amounts to Php 8.35

Savings in a year = 2,277,600 X 8.35 Php

therefore:

Savings in a year = 19,017,960 Php per year

From the computations above I would highly recommend to steam trace

132
133

You might also like