Professional Documents
Culture Documents
WI01-QCD-03 Painting Inspection - 01jul20
WI01-QCD-03 Painting Inspection - 01jul20
Forms/Records
This document is held on the server. Hard copies may be printed. However, these are not updated. Therefore, if you
are working from a hard copy and unsure if it is current please refer to the master on the server.
Page 1 of 12
WI01/QCD-03
Revision History
This document is held on the server. Hard copies may be printed. However, these are not updated. Therefore, if you
are working from a hard copy and unsure if it is current please refer to the master on the server.
Page 2 of 12
WI01/QCD-03
I. PURPOSE
The purpose of this work instruction is requirements for the protection against corrosion of
the external surfaces of ferrous metal using protective coating systems construction.
II. SCOPE
The protective coating systems specified include surface preparation, paint application
method, inspection requirement and acceptable minimum dried film thicknesses.
Equipment items covered by this work instruction include above and underground piping,
equipment, furnace plating, storage tanks and other miscellaneous unprotected steel items.
This work instruction does not specify high temperature resistant systems for operating
temperatures above 5400C, nor temperature indicating paints for refractory line Equipment
items.
Vendor must be submitted method statement, inspection plan (ITP), certificate of
equipment, material to KESV for purpose of this work and notify to KESV inspection plan
according ITP.
III. REFERENCE
British Standards
BS 5493 – (previously C.P.2008) code of practice for protective coating of iron and steel
structures against corrosion.
International organization for standardization
ISO 8501(2007): Pictorial standards of surface preparation for painting of steel surface.
Visual assessment of surface cleanliness.
Steel structures painting council standards
SSPC - PA1 - Shop, Field and Maintenance Painting of Steel
SSPC - PA2 - Measurement of Dry Paint Thicknesses with Magnetic Gauges
SSPC Surface Preparation Standard (SP2, SP3, SP5, SP7, SP10, SP11, SP12, SP16)
American society for testing and materials
ASTM - Standard specification for pipe, steel, black and hot - dipped, zinc - coated,
welded and seamless.
Or standards/specification/requirements of customer for project and equipment
instruction manual from manufacture.
This document is held on the server. Hard copies may be printed. However, these are not updated. Therefore, if you
are working from a hard copy and unsure if it is current please refer to the master on the server.
Page 3 of 12
WI01/QCD-03
3. DFT: Dry Film Thickness.
4. SHOP: Shall be defined as preparing and painting of new, bare steel surfaces in a
Manufacturer's or Fabricator's shop or equipment works prior to transportation to the
site of construction or a controlled environment paint facility erected at the permanent
site of construction.
5. FIELD: Shall be defined as preparing and painting of new bare or shop primed steel
surfaces or even completely painted shop steel surfaces at the permanent site of Plant
construction.
6. PE: Project Engineer.
V. RESPONSIBILITIES
V.1. Board of Management
- The BOD is responsible for approving and allocating company resources to ensure this
work instruction is carried out throughout KESV.
V.2. KESV Staffs/Departments
- All related departments are responsible for applying this work instruction: …
- All KESV staffs must ensure specifications in this work instruction are applied
throughout the documentation process.
V.3. Quality control department
- Check the effectiveness of the implementation of this work instruction.
- Provide necessary training to the whole company and specifically to the project team on
the requirements of this work instruction.
- Conduct regular audit with integrated audit plan to ensure the effectiveness of this work
instruction.
This document is held on the server. Hard copies may be printed. However, these are not updated. Therefore, if you
are working from a hard copy and unsure if it is current please refer to the master on the server.
Page 5 of 12
WI01/QCD-03
F01/QCD-03
1Receive procedure
KESV
and related F02/QCD-03
documents
VENDOR, F01/QCD-03
2 Prepare surface
KESV
and painting condition F02/QCD-03
VENDOR, N F01/QCD-03
3 Check
KESV F02/QCD-03
F01/QCD-03
4 VENDOR
Application
F02/QCD-03
VENDOR,
Inspect and N F01/QCD-03
5
KESV
repair F02/QCD-03
Y
F01/QCD-03
6 VENDOR
Report
F02/QCD-03
Record
This document is held on the server. Hard copies may be printed. However, these are not updated. Therefore, if you
are working from a hard copy and unsure if it is current please refer to the master on the server.
Page 6 of 12
WI01/QCD-03
7 KESV
2) EXPLANATION
Stage 1: Receive procedure and related documents
After receiving procedure and related documents, if any ambiguities or contradictions
between these requirements and vendor standards or experience shall be notified to KESV
attention for resolution before vendor proceeds this work.
SHOP Preparation:
- All the provisions for shop surface preparation shall be applicable for field preparation. If
the specified requirements are impractical because of field conditions, this work
instruction becomes invalidated and revised coating systems shall be devised to suit the
imposed field preparation conditions.
- Shop prepared and primed surfaces shall be field repaired after erection of primed
equipment.
This document is held on the server. Hard copies may be printed. However, these are not updated. Therefore, if you
are working from a hard copy and unsure if it is current please refer to the master on the server.
Page 7 of 12
WI01/QCD-03
- Over areas considered to be inaccessible after erection shop applied primer repairs, field
applied primers.
- Prior to remove grease, oil and application of priming paint, the metal surface and
feathered area of shop coating shall be solvent cleaned and thoroughly washed.
- Surface preparation with power tool or hand tools paper abrasive shall be pursued to
achieve a level of specification St 3.
- Paint material shall be thoroughly mixed immediately prior to application. Mixing shall be
by means of mechanical stirrers.
- The type of thinner shall comply with the paint manufacturers written instructions.
- When thinners are permissible, they shall be added during the paint mixing process
Stage 3: Check
- Before the painting application, Vendor shall be checking the surface and environment
condition and filled in painting report and dust assessment, KESV will witness if require.
Stage 4: Application
- Paint materials shall only be applied by the paint manufacturers recommended method.
Care shall be taken to select paint materials to suit the intended application method.
This document is held on the server. Hard copies may be printed. However, these are not updated. Therefore, if you
are working from a hard copy and unsure if it is current please refer to the master on the server.
Page 8 of 12
WI01/QCD-03
- Material and air pressure on the spray guns shall be regulated to achieve optimum
atomization of the paint with the lowest possible pressures to avoid spray ricochet from
the surface being painted.
- Each coat of paint shall be in a proper state of cure or dryness before the application of the
succeeding coat.
- Shop primed surfaces contaminated during transport and site storage shall be thoroughly
washed down with fresh clean water and allowed to dry before the application of further
paint coatings.
- The maximum time between find surface preparation and prime coat application inside the
fabrication shop shall be 4 hours.
a) Application method
The following methods of application are covered by this specification: brush, roller, air
spray, airless may be used for places of difficult access when no other method is practical.
Whichever application method is used, the dry film thickness of each coat shall meet the
requirement of the specification or the manufacturer’s recommendation, whichever has
precedence, as agreed upon by KESV
Roller Application:
- Rolling shall be done so that a smooth coat as uniform in thickness as possible is achieved.
Their nap should be appropriate for the particular surface roughness.
- Roller application may be used on flat or slightly curved surfaces and shall be in
accordance with the recommendations of the coating manufacturer and roller
manufacturer. Roller application shall not be used on irregular surfaces such as rivets,
bolts, crevices, welds, corners, or edges, unless otherwise specified. When permitted,
however, the coating applied by roller on these irregular surfaces shall be subsequently
brushed out to form a continuous and unbroken film.
Airless Spray Application:
- Using fluid tips with proper orifice size and fan angle (5:19” or 5:20”), and the fluid
control gun of proper construction to achieved dried thickness film
- Wet film thickness (comb) gauges shall be used by painter operatives to ensure an even
and adequate DFT will be achieved.
- Material and air pressure on the spray guns shall be regulated to achieve optimum
atomization of the paint with the lowest possible pressures to avoid spray ricochet from
the surface being painted.
Stage 6: Report
Vendor must make the report each of item follow this work instruction and submit to
KESV.
Stage 7: Record
Vendor must make the report each of item follow this work instruction and submit to
KESV.
VIII. TRAINING
Training needs will be identified and conducted, if required, in accordance with procedure
“ADM-02 Training”.
IX. RECORDS
1. F01/QCD-03: Painting Inspection Report
2. F01/QCD-03: Dust Assessment
X. PROCESS CRITERIA
This document is held on the server. Hard copies may be printed. However, these are not updated. Therefore, if you
are working from a hard copy and unsure if it is current please refer to the master on the server.
Page 10 of 12
WI01/QCD-03
Not application
ITEM:
DRAWING No :
A) SURFACE PREPARATION
Surface Finish Specification Abrasive Manufacturer
Surface Profile : Type and Grade of Abrasive
Surface Roughness: Abrasive Size
Cleaning Method Controlled work operation
Coating System Number
B) PAINT PREPARATION
Paint name Paint Manufacturer
Paint Type & Code No. Paint Color
Type of Solvent Used Thinner
Batch and Curing Agent No.
Condition of Paint Container
Method of Application: Airless Spray / Roller / Brush
C) PAINT APPLICATION
st nd rd th
PAINT TYPE 1 COAT 2 COAT 3 COAT 4 COAT
Air Temp. (OC)
Surface Temp. (OC)
Relative Humidity (%)
Dew Point (OC)
Film Thickness Range
Min Max Min Max Min Max Min Max
(µm)
Wet Film Thickness (µm)
Date DFT Taken
Dry Film Thickness (µm)
This document is held on the server. Hard copies may be printed. However, these are not updated. Therefore, if you
are working from a hard copy and unsure if it is current please refer to the master on the server.
Page 11 of 12
WI01/QCD-03
This document is held on the server. Hard copies may be printed. However, these are not updated. Therefore, if you
are working from a hard copy and unsure if it is current please refer to the master on the server.
Page 12 of 12