Claims of Culvrt-138A: The President Infrastructure & Construction and Siddique Engineering & Construction Joint Venture
Claims of Culvrt-138A: The President Infrastructure & Construction and Siddique Engineering & Construction Joint Venture
CLAIMS OF CULVRT-138A
SL TYPE OF
DATE CLAIMS IN DETAILS LOCATION QTY. HOURS
NO LOSS
Rebar Bending Machine is not working
almost 3 hours and there are two groups are Base Camp,
1 05/04/20 Manpower 9 3
working by sharing the only one Rebar Max
Cutting Machine.
Working for unloading MS Pipe, Gas Cylinder
2 12/06/20 Culvert-138A Manpower 3 1.5
etc
Rebar Bending Machine is not working at Base Camp,
3 11/06/20 Manpower 10 6
11:00 am Max
13/03/20 -
16 Interruption of work due to Rain Culvert-138A Manpower
30/06/20
THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION
AND SIDDIQUE ENGINEERING & CONSTRUCTION JOINT VENTURE
CLAIMS OF CULVRT-140
TYPE OF
SL NO DATE CLAIMS IN DETAILS LOCATION QTY. Hrs. TOTAL AMOUNT
LOSS
Manpower
Planning to start concrete casting but due to bad
with
13 17/07/20 condition of excess road, the concrete casting is Culvert-140 15 5
transport
postponed
fare
29/03/20-
14 Interruption of work due to Rain Culvert-140 Manpower
10/08/20
THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION
AND SIDDIQUE ENGINEERING & CONSTRUCTION JOINT VENTURE
CLAIMS OF CULVRT-145
SL DATE CLAIMS IN DETAILS LOCATION TYPE OF LOSS QTY. HOUR
09/11/20 -
2 Excavation by Manpower ,, Manpower 12 8
10/11/20
10/11/20 -
3 Backfilling by Manpower ,, Manpower 16 8
11/11/20
CLAIMS OF CULVRT-146
SL
DATE CLAIMS IN DETAILS LOCATION TYPE OF LOSS QTY. HOURS
NO
1 21/11/20 Levelling and dressing of Cut-off wall for the second time Culvert-146 Manpower 8 4
21/11/20 -
2 Removing of soil that fall on and side of cut-off wall ,, Manpower 40 4
30/11/20
22/11/20 - Power supply is not provided. Cut-off wall rebar cutttin and
3 ,, Manpower 6 8
23/11/20 bending from Culvert-145
24/11/20 -
4 Steel Shutter is not provided on time ,, Manpower 16 5
25/11/20
22/11/20 - Welding machine is unavailable and cut-off wall shuttering is
5 ,, Manpower 10 4
25/11/20 delayed
Generator break down due to mechanical problem[Fix
6 29/11/20 ,, Manpower 7 4
within 4 hors]
Generator break down due to electrical and mechanical
7 01/12/20 ,, Manpower 9 2
problem[Work stopped 02 hours]
CLAIMS OF CULVRT-158
SL DATE CLAIMS IN DETAILS LOCATION TYPE OF LOSS QTY. HOUR
Culvert -
1 24/01/21 Manual Backfilling. Quantity: 05 Tractors Manpower 12 8
158
25/01/21 -
5 Use of G.I Wire for straightening the Shutter ,, Manpower 14 kg
12/02/21