THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION

AND SIDDIQUE ENGINEERING & CONSTRUCTION JOINT VENTURE

CLAIMS OF CULVRT-138A

SL TYPE OF
DATE CLAIMS IN DETAILS LOCATION QTY. HOURS
NO LOSS
Rebar Bending Machine is not working
almost 3 hours and there are two groups are Base Camp,
1 05/04/20 Manpower 9 3
working by sharing the only one Rebar Max
Cutting Machine.
Working for unloading MS Pipe, Gas Cylinder
2 12/06/20 Culvert-138A Manpower 3 1.5
etc
Rebar Bending Machine is not working at Base Camp,
3 11/06/20 Manpower 10 6
11:00 am Max

Wrong dimension of #23 U Bar (180 Nos)


4 12/06/20 Culvert-138A Manpower 4 9
thats correct on site.

Wrong dimension of #12 Bar (100 Nos) thats


5 11/06/20 Culvert-138A Manpower 4 8
correct on site.

Wrong dimension of #28 Bar (100 Nos) thats


6 11/06/20 Culvert-138A Manpower 4 4
correct on site.

Surveyors kill four (04) hours to set co-


7 07/06/20 Culvert-138A Manpower 18 4
ordinate

8 31/05/20 Props are reached on site at 6:05 pm Culvert-138A Manpower 17 5

Mud Pump, grinding Machine(4 Nos) was


9 23/03/20 damaged due to no regulator/Voltmetre Culvert-138A Machinaries
with generator
Working in faeces water causing medical
10 14/03/20 Culvert-138A Manpower 8
treament for the workers

11 14/03/20 Water Pump is not started until lunch Culvert-138A Manpower 3 4


Required Material (MS Pipe) is not reached
12 14/06/20 Culvert-138A Manpower 8
on site
Surveyors went back without finished the
13 13/06/20 Culvert-138A Manpower 19 2.5
site work
Rebar Bending Machine was broken at Manpower
Base Camp, with
14 11/06/20 10:00am and couldnot solve the problem on 8 2
Max transport
this day
fare
14-
15 Working days of Mud pump Culvert-138A Machinaries
18/03/20

13/03/20 -
16 Interruption of work due to Rain Culvert-138A Manpower
30/06/20
THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION
AND SIDDIQUE ENGINEERING & CONSTRUCTION JOINT VENTURE

CLAIMS OF CULVRT-140

TYPE OF
SL NO DATE CLAIMS IN DETAILS LOCATION QTY. Hrs. TOTAL AMOUNT
LOSS

Due to communication gap between the CM & Manpower


PM and Security Incharge. Workers be waited with
1 29/03/20 Culvert-140 13 5
and come back from the Main Gate of Max transport
Office, Ramu fare
Manpower
Permit and request to work before not providing
with
2 31/03/20 the required materials on site. [Note: Necessary Culvert-140 16 5
transport
materials is stored in to yard due to COVID-19]
fare
Delay due to not starting the Generator.
3 05/04/20 Culvert-140 Manpower 20 3
Generator started at 01:00pm.

Working for unloading Ply-wood, MS Pipe, Gas


4 12/06/20 Culvert-140 Manpower 4 1.5
Cylinder, U head, Dasha etc
Wrong dimension of #28 Bar (52 Nos) thats
5 11/06/20 Culvert-140 Manpower 3 3
correct on site.

Surveyors ordered to shut down generator and


6 06/06/20 Culvert-140 Manpower 18 2
kill two and a half hours to set co-ordinate

Required Materials(U head, Props, Dasha) are


7 02/06/20 Culvert-140 Manpower 15 3
not reached on site
Required Material (MS Pipe) is not reached on
9 13/06/20 Culvert-140 Manpower 15 4
site
Generator was damaged due to mechanical
10 06/06/20 Culvert-140 Manpower 18 5
problem from lunch

Generator control box was broken at 8:30 am


11 01/06/20 Culvert-140 Manpower 12 2
and fixed at 10:30 pm

09- Manpower has lost due to not dewatering by


12 Culvert-140 Manpower 27 4
10/08/20 pump while doing the shutter removing work

Manpower
Planning to start concrete casting but due to bad
with
13 17/07/20 condition of excess road, the concrete casting is Culvert-140 15 5
transport
postponed
fare
29/03/20-
14 Interruption of work due to Rain Culvert-140 Manpower
10/08/20
THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION
AND SIDDIQUE ENGINEERING & CONSTRUCTION JOINT VENTURE

CLAIMS OF CULVRT-145
SL DATE CLAIMS IN DETAILS LOCATION TYPE OF LOSS QTY. HOUR

21/10/20 - Unable to handover the culvert by doing backfilling Culvert -


1 Manpower 22
08/11/20 and compaction on time. [Workers Khoraki-12 days] 145

09/11/20 -
2 Excavation by Manpower ,, Manpower 12 8
10/11/20
10/11/20 -
3 Backfilling by Manpower ,, Manpower 16 8
11/11/20

Delay to concrete casting (CC) due to Consultant


4 10/11/20 ,, Manpower 17 3
Checks, transportatin of concrete mixer

Bar No 9,10,6,7,23,25,33 are not correct. Corrected


5 12/11/20 ,, Manpower 8 32
by using manpower
Missing of febricated rebar and Re-febricate.[ Bar
6 12/11/20 ,, Manpower 3 16
No:20,14,15]

Accident occurs. One worker become senseless and


7 14/11/20 ,, Manpower
admitted in Cox's Bazar Medical, Sadar

15/11/20 - Everyday manpower loss due to tightness of the


8 ,, Manpower 2 30
15/12/20 generator while starting.

9 24/11/20 Delay to Survey Consultant Check ,, Manpower 16 5


19/12/20 -
10 Rebar Cleaning ,, Manpower 4 8
21/12/20
Difference of slab level given by Surveyor between
11 5/12/20 consecutive two time. Props below slab was required ,, Manpower 5 4
to re-level.

12 6/12/20 Undulating Channel is straighten by manpower ,, Manpower 2 5

13 7/12/20 Fail to supply of Scaffolding Clamps, U head ,, Manpower 8 8


Worker injured while starting the generator. The skin
14 15/12/20 of hand is torn and six (06) stitches are being given by ,, Manpower
Ramu Upozila Hospital
After injury occurs, nobody was willingly start the
15 16/12/20 ,, Manpower 12 2
generator.
Excavator is not available. East side site development
16 17/12/20 ,, Manpower 08 5
was undone.
19/12/20 -
17 Rebar Cleaning ,, Manpower 15 4
21/12/20
Change of concrete casting method. Concrete pump
18 31/12/20 ,, Manpower 17 5
is replaced by crane and bucket
11/11/21 -
19 Use of G.I Wire for straightening the Shutter ,, Manpower 35 kg
31/12/20
20 4/01/21 Delay on the casting of wearing coat ,, Manpower 10 5
THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION
AND SIDDIQUE ENGINEERING & CONSTRUCTION JOINT VENTURE

CLAIMS OF CULVRT-146
SL
DATE CLAIMS IN DETAILS LOCATION TYPE OF LOSS QTY. HOURS
NO

1 21/11/20 Levelling and dressing of Cut-off wall for the second time Culvert-146 Manpower 8 4

21/11/20 -
2 Removing of soil that fall on and side of cut-off wall ,, Manpower 40 4
30/11/20
22/11/20 - Power supply is not provided. Cut-off wall rebar cutttin and
3 ,, Manpower 6 8
23/11/20 bending from Culvert-145
24/11/20 -
4 Steel Shutter is not provided on time ,, Manpower 16 5
25/11/20
22/11/20 - Welding machine is unavailable and cut-off wall shuttering is
5 ,, Manpower 10 4
25/11/20 delayed
Generator break down due to mechanical problem[Fix
6 29/11/20 ,, Manpower 7 4
within 4 hors]
Generator break down due to electrical and mechanical
7 01/12/20 ,, Manpower 9 2
problem[Work stopped 02 hours]

8 02/12/20 Excavator is unavailable ,, Manpower 12 8


Levelling and dressing of Box and Wing Apron portion for
9 03/12/20 ,, Manpower 8 6
the second time
10 7/12/20 Fail to supply scaffolding clamps ,, Manpower 7 8
11 10/12/20 Correction of rebar [ Bar No: 6,7,10,23,25,33] ,, Manpower 3 24

Generator break down due to electrical and mechanical


12 12/12/20 ,, Manpower 8 2.5
problem[Work stopped 2.5 hours]

13 14/12/20 Delay on Consultant check ,, Manpower 16 5


Generator break down due to mechanical problem[Work
14 14/12/20 ,, Manpower 8 2
stopped 2 hours]
Welding machine break down due to electrical
15 14/12/20 ,, Manpower 2 3
problem[Work stopped 3 hours]
16 13,14/12/20 Rebar Cleaning ,, Manpower 2 8

Failure of shutter due to unable to supply of clamps and U


17 15/12/20 ,, Manpower 2 24
head. Which we fix later by cutting with grending machine

Generator break down due to mechanical and mechanical


18 28/12/20 ,, Manpower 8 6
problem[Work stopped 6 hours]

19 30/12/20 Material mobilization from Culvert-145 to 146 ,, Manpower 6 4

20 03/01/21 Wooden shutter mobilization from culvert 145 to 146 ,, Manpower 8 16

Generator break down due to mechanical problem[Work


21 06/01/21 ,, Manpower 8 2
stopped 2 hours]
22/11/21 -
19 Use of G.I Wire for straightening the Shutter ,, Manpower 32 kg
16/01/20
Due to high slump of concrete, the finishing is become
22 16/01/21 ,, Manpower 12 5
lengthy.
THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION
AND SIDDIQUE ENGINEERING & CONSTRUCTION JOINT VENTURE

CLAIMS OF CULVRT-158
SL DATE CLAIMS IN DETAILS LOCATION TYPE OF LOSS QTY. HOUR

Culvert -
1 24/01/21 Manual Backfilling. Quantity: 05 Tractors Manpower 12 8
158

2 25/01/21 Material unloading ,, Manpower 4 2

Missing of febricated rebar and Re-febricate.[ Bar


3 08/11/20 ,, Manpower 5 7
No:13(2),13(3)]

4 11/02/21 Client fails to start concreting of base slab ,, Manpower 22 11

25/01/21 -
5 Use of G.I Wire for straightening the Shutter ,, Manpower 14 kg
12/02/21