THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION

AND SIDDIQUE ENGINEERING & CONSTRUCTION JOINT VENTURE

CLAIMS OF CULVRT-138A

SL DATE CLAIMS IN DETAILS LOCATION TYPE OF QTY. HOURS


NO LOSS

Rebar Bending Machine is not working


1 05/04/20 almost 3 hours and there are two groups are Base Camp, Manpower 9 3
working by sharing the only one Rebar Max
Cutting Machine.

Working for unloading MS Pipe, Gas Cylinder


2 12/06/20 etc Culvert-138A Manpower 3 1.5

Rebar Bending Machine is not working at Base Camp,


3 11/06/20 Manpower 10 6
11:00 am Max

Wrong dimension of #23 U Bar (180 Nos)


4 12/06/20 thats correct on site. Culvert-138A Manpower 4 9

Wrong dimension of #12 Bar (100 Nos) thats


5 11/06/20 Culvert-138A Manpower 4 8
correct on site.

Wrong dimension of #28 Bar (100 Nos) thats


6 11/06/20 Culvert-138A Manpower 4 4
correct on site.

Surveyors kill four (04) hours to set co-


7 07/06/20 ordinate Culvert-138A Manpower 18 4

8 31/05/20 Props are reached on site at 6:05 pm Culvert-138A Manpower 17 5

Mud Pump, grinding Machine(4 Nos) was


9 23/03/20 damaged due to no regulator/Voltmetre Culvert-138A Machinaries
with generator

Working in faeces water causing medical


10 14/03/20 treament for the workers Culvert-138A Manpower 8

11 14/03/20 Water Pump is not started until lunch Culvert-138A Manpower 3 4

Required Material (MS Pipe) is not reached


12 14/06/20 Culvert-138A Manpower 8
on site

13 13/06/20 Surveyors went back without finished the Culvert-138A Manpower 19 2.5
site work
Manpower
Rebar Bending Machine was broken at Base Camp, with
14 11/06/20 10:00am and couldnot solve the problem on 8 2
Max transport
this day fare

14-
15 18/03/20 Working days of Mud pump Culvert-138A Machinaries

13/03/20
16 -30/06/20 Interruption of work due to Rain Culvert-138A Manpower
THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION
AND SIDDIQUE ENGINEERING & CONSTRUCTION JOINT VENTURE

CLAIMS OF CULVRT-140

TYPE OF
SL NO DATE CLAIMS IN DETAILS LOCATION QTY. Hrs. TOTAL AMOUNT
LOSS

Due to communication gap between the CM & Manpower


PM and Security Incharge. Workers be waited with
1 29/03/20 Culvert-140 13 5
and come back from the Main Gate of Max transport
Office, Ramu fare

Permit and request to work before not Manpower


2 31/03/20 providing the required materials on site. [Note: Culvert-140 with 16 5
Necessary materials is stored in to yard due to transport
COVID-19] fare

3 05/04/20 Delay due to not starting the Generator. Culvert-140 Manpower 20 3


Generator started at 01:00pm.

Working for unloading Ply-wood, MS Pipe, Gas


4 12/06/20 Culvert-140 Manpower 4 1.5
Cylinder, U head, Dasha etc

Wrong dimension of #28 Bar (52 Nos) thats


5 11/06/20 correct on site. Culvert-140 Manpower 3 3

Surveyors ordered to shut down generator and


6 06/06/20 Culvert-140 Manpower 18 2
kill two and a half hours to set co-ordinate

Required Materials(U head, Props, Dasha) are


7 02/06/20 Culvert-140 Manpower 15 3
not reached on site

9 13/06/20 Required Material (MS Pipe) is not reached on Culvert-140 Manpower 15 4


site

10 06/06/20 Generator was damaged due to mechanical Culvert-140 Manpower 18 5


problem from lunch

11 01/06/20 Generator control box was broken at 8:30 am Culvert-140 Manpower 12 2


and fixed at 10:30 pm

09- Manpower has lost due to not dewatering by


12 Culvert-140 Manpower 27 4
10/08/20 pump while doing the shutter removing work

Manpower
Planning to start concrete casting but due to with
13 17/07/20 bad condition of excess road, the concrete Culvert-140 transport 15 5
casting is postponed fare

29/03/20-
14 10/08/20 Interruption of work due to Rain Culvert-140 Manpower
THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION
AND SIDDIQUE ENGINEERING & CONSTRUCTION JOINT VENTURE

CLAIMS OF CULVRT-145
SL DATE CLAIMS IN DETAILS LOCATION TYPE OF LOSS QTY. HOUR

1 21/10/20 Unable to handover the culvert by doing backfilling Culvert Manpower 22


-08/11/20 and compaction on time. [Workers Khoraki-12 days] -145

09/11/20
2
-10/11/20
Excavation by Manpower ,, Manpower 12 8

10/11/20
3
-11/11/20
Backfilling by Manpower ,, Manpower 16 8

Delay to concrete casting (CC) due to Consultant


4 10/11/20 Checks, transportatin of concrete mixer ,, Manpower 17 3

Bar No 9,10,6,7,23,25,33 are not correct. Corrected


5 12/11/20
by using manpower ,, Manpower 8 32

Missing of febricated rebar and Re-febricate.[ Bar


6 12/11/20
No:20,14,15] ,, Manpower 3 16

Accident occurs. One worker become senseless and


7 14/11/20 admitted in Cox's Bazar Medical, Sadar ,, Manpower

15/11/20 Everyday manpower loss due to tightness of the


8
-15/12/20 generator while starting. ,, Manpower 2 30

9 24/11/20 Delay to Survey Consultant Check ,, Manpower 16 5

10 19/12/20 Rebar Cleaning ,, Manpower 4 8


-21/12/20
Difference of slab level given by Surveyor between
11 5/12/20 consecutive two time. Props below slab was required ,, Manpower 5 4
to re-level.

12 6/12/20 Undulating Channel is straighten by manpower ,, Manpower 2 5

13 7/12/20 Fail to supply of Scaffolding Clamps, U head ,, Manpower 8 8

Worker injured while starting the generator. The skin


14 15/12/20 of hand is torn and six (06) stitches are being given by ,, Manpower
Ramu Upozila Hospital

After injury occurs, nobody was willingly start the


15 16/12/20
generator. ,, Manpower 12 2

Excavator is not available. East side site development


16 17/12/20
was undone. ,, Manpower 08 5

19/12/20
17
-21/12/20
Rebar Cleaning ,, Manpower 15 4

Change of concrete casting method. Concrete pump


18 31/12/20 is replaced by crane and bucket ,, Manpower 17 5

11/11/21
19 -31/12/20 Use of G.I Wire for straightening the Shutter ,, Manpower 35 kg

20 4/01/21 Delay on the casting of wearing coat ,, Manpower 10 5


THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION
AND SIDDIQUE ENGINEERING & CONSTRUCTION JOINT VENTURE

CLAIMS OF CULVRT-146
SL
DATE CLAIMS IN DETAILS LOCATION TYPE OF LOSS QTY. HOURS
NO

1 21/11/20 Levelling and dressing of Cut-off wall for the second time Culvert-146 Manpower 8 4

21/11/20
2
-30/11/20
Removing of soil that fall on and side of cut-off wall ,, Manpower 40 4

22/11/20 Power supply is not provided. Cut-off wall rebar cutttin and
3
-23/11/20 bending from Culvert-145 ,, Manpower 6 8

24/11/20
4
-25/11/20
Steel Shutter is not provided on time ,, Manpower 16 5

22/11/20 Welding machine is unavailable and cut-off wall shuttering


5 -25/11/20 is delayed ,, Manpower 10 4

Generator break down due to mechanical problem[Fix


6 29/11/20
within 4 hors] ,, Manpower 7 4

Generator break down due to electrical and mechanical


7 01/12/20 problem[Work stopped 02 hours] ,, Manpower 9 2

8 02/12/20 Excavator is unavailable ,, Manpower 12 8


Levelling and dressing of Box and Wing Apron portion for
9 03/12/20
the second time ,, Manpower 8 6

10 7/12/20 Fail to supply scaffolding clamps ,, Manpower 7 8

11 10/12/20 Correction of rebar [ Bar No: 6,7,10,23,25,33] ,, Manpower 3 24

Generator break down due to electrical and mechanical


12 12/12/20
problem[Work stopped 2.5 hours] ,, Manpower 8 2.5

13 14/12/20 Delay on Consultant check ,, Manpower 16 5

Generator break down due to mechanical problem[Work


14 14/12/20
stopped 2 hours] ,, Manpower 8 2

Welding machine break down due to electrical


15 14/12/20 problem[Work stopped 3 hours] ,, Manpower 2 3

16 13,14/12/20 Rebar Cleaning ,, Manpower 2 8

Failure of shutter due to unable to supply of clamps and U


17 15/12/20
head. Which we fix later by cutting with grending machine ,, Manpower 2 24

Generator break down due to mechanical and mechanical


18 28/12/20 problem[Work stopped 6 hours] ,, Manpower 8 6

19 30/12/20 Material mobilization from Culvert-145 to 146 ,, Manpower 6 4

20 03/01/21 Wooden shutter mobilization from culvert 145 to 146 ,, Manpower 8 16

Generator break down due to mechanical problem[Work


21 06/01/21
stopped 2 hours] ,, Manpower 8 2

19 22/11/21 Use of G.I Wire for straightening the Shutter ,, Manpower 32 kg


-16/01/20
Due to high slump of concrete, the finishing is become
22 16/01/21
lengthy. ,, Manpower 12 5
THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION
AND SIDDIQUE ENGINEERING & CONSTRUCTION JOINT VENTURE

CLAIMS OF CULVRT-158
SL DATE CLAIMS IN DETAILS LOCATION TYPE OF LOSS QTY. HOUR

1 24/01/21 Manual Backfilling. Quantity: 05 Tractors Culvert Manpower 12 8


-158

2 25/01/21 Material unloading ,, Manpower 4 2

Missing of febricated rebar and Re-febricate.[ Bar


3 08/11/20
No:13(2),13(3)] ,, Manpower 5 7

4 11/02/21 Client fails to start concreting of base slab ,, Manpower 22 11

25/01/21
5 -12/02/21 Use of G.I Wire for straightening the Shutter ,, Manpower 14 kg