Culvert Construction (Boq)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION AND SIDDIQUE

ENGINEERING & CONSTRUCTION JOINT VENTURE

NAME OF THE WORK : CULVERT CONSTRUCTION


BILL OF QUANTITIES (BOQ) FOR LABOR WORK
Item No Description of Items Unit Rate (Tk.)
Earthwork in Excavation: Minor manual excavation in foundation trenches and cut-
1 cft 6
off wall zone.
Leveling and Dressing the Sand Surface: Cleaning the unsuitable materials, dressing
2 sft 3
and leveling the sand surface.
Blinding Concrete Casting Work: including leveling, vibrating, finishing the
3 sft 5
concrete.
Reinforced Cement Concrete Work: including casting in forms,leveling,
4 cft 12
compacting by vibrator machine, finishing the concrete.

5 Loading of Reinforcement, Formwork, MS Pipe etc. from store/truck/site kg 0.350

6 Unloading of Reinforcement, Formwork, MS Pipe etc. from store/truck/site kg 0.250


Reinforcement Fabrication: including straightening, cutting and cleaning rust, if
7 any, bending and binding in position with of G.I. wires and fixing to detail of kg 5.5
reinforcement as per design.
Making of 50 mm Concrete Clear Cover Block: including placement in proper place
8 pc 3
etc.
Making of 75 mm Concrete Clear Cover Block: including placement in proper place
9 pc 4
etc.
Fitting and Fixing of Weep Hole: including cut the PVC pipe, binding with G. I. wire
10 pc 25
and placement at the proper place.
Cleaning and Oiling of Shutter: including scraping with sand paper, cleaning of rust,
11 sft 3
concrete and oiling the shutter.
Placement of Shutter: including moving one place to another, centering, fitting,
12 sft 30
necessary supports by U head.
Installation of Tie Rod: including cleaning with oil, make hole to shutter, cutting &
13 pc 60
placing PVC pipe, placement and fixing the tie rod by butterfly clamps and nuts.
Placement of 30 mm Spacer Pipe: including cutting of PVC pipe, binding with G. I
14 pc 10
wire at proper place.
Horizontal and Vertical Bracing to Shutter: including cutting, placing the MS pipe,
15 rft 7
fixing and tied up with tie rod etc.
Making of Wooden Shutter: including cutting of plywood and wooden dasha
16 sft 26
(50mm*100mm) as desired dimensions, nailed with wooden dasha.
Temporary Platform, Staging, Scaffolding Work(Upto 3m): including placing and
17 sft 23
driving the MS pipe, fixing with clamps and welding if required.
Temporary Platform, Staging, Scaffolding Work(Above 3m): including placing and
18 sft 28
driving the MS pipe, fixing with clamps and welding if required.
Fare Face Finishing Work: including leveling, smoothing the concrete surface,
19 sft 3
coating with white cement etc.
Concrete Casting Work of Wearing Coat: including leveling, vibrating, finishing the
20 sft 20
concrete, maintain the concrete surface slope.
THE PRESIDENT INFRASTRUCTURE & CONSTRUCTION
JOINT VENTURE
& SIDDIQUE ENGINEERING & CONSTRUCTION

NAME OF THE WORK : CULVERT CONSTRUCTION


Culvert-42 (1×3m) Culvert-41 (2×5m) Culvert-46 (3×5m)
BILL OF QUANTITIES (BOQ) FOR LABOR WORK
Item Rate
Description of Items Unit Quantity Amount Quantity Amount Quantity Amount
No (Tk.)

Earthwork in Excavation: Minor manual excavation in foundation


1 cft 6 695.317 4171.9 1,038.12 6228.7 1,391.459 8348.8
trenches and cut-off wall zone.

Leveling and Dressing the Sand Surface: Cleaning the unsuitable


2 sft 3 3,895.176 11685.5 6,958.51 20875.5 11,276.50 33829.5
materials, dressing and leveling the sand surface.

Blinding Concrete Casting Work: including leveling, vibrating,


3 sft 5 3,895.176 19475.9 6,958.51 34792.6 11,276.50 56382.5
finishing the concrete.
Reinforced Cement Concrete Work: including casting in
4 forms,leveling, compacting by vibrator machine, finishing the cft 12 9,530.815 114369.8 19,457.73 233492.8 31,170.41 374044.9
concrete.
Loading of Reinforcement, Formwork, MS Pipe etc. from
5 kg 0.350 35470 12414.5 48116 16840.6 74960 26236.0
store/truck/site

Unloading of Reinforcement, Formwork, MS Pipe etc. from


6 kg 0.250 35470 8867.5 48116 12029.0 74960 18740.0
store/truck/site

Reinforcement Fabrication: including straightening, cutting and


7 cleaning rust, if any, bending and binding in position with of G.I. kg 5.5 35470 195085.0 48116 264638.0 74960 412280.0
wires and fixing to detail of reinforcement as per design.

Making of 50 mm Concrete Clear Cover Block: including


8 pc 3 1000 3000.0 2000 6000.0 3000 9000.0
placement in proper place etc.

Making of 75 mm Concrete Clear Cover Block: including


9 pc 4 1000 4000.0 2000 8000.0 3000 12000.0
placement in proper place etc.

Fitting and Fixing of Weep Hole: including cut the PVC pipe,
10 pc 25 12 300.0 26 650.0 40 1000.0
binding with G. I. wire and placement at the proper place.
Item Rate
Description of Items Unit Quantity Amount Quantity Amount Quantity Amount
No (Tk.)

Cleaning and Oiling of Shutter: including scraping with sand


11 sft 3 2,794.858 8384.6 3,532.252 10596.8 4,165.637 12496.9
paper, cleaning of rust, concrete and oiling the shutter.

Placement of Shutter: including moving one place to another,


12 sft 30 6,735.673 202070.2 8,431.76 252952.7 11,744.68 352340.3
centering, fitting, necessary supports by U head.
Installation of Tie Rod: including cleaning with oil, make hole to
13 shutter, cutting & placing PVC pipe, placement and fixing the tie pc 60 2234 134040.0 3266 195960.0 3864 231840.0
rod by butterfly clamps and nuts.
Placement of 30 mm Spacer Pipe: including cutting of PVC pipe,
14 pc 10 1117 11170.0 1633 16330.0 1932 19320.0
binding with G. I wire at proper place.

Horizontal and Vertical Bracing to Shutter: including cutting,


15 rft 7 13,192.86 92350.0 19,279.93 134959.5 22,813.94 159697.6
placing the MS pipe, fixing and tied up with tie rod etc.
Making of Wooden Shutter: including cutting of plywood and
16 wooden dasha (50mm*100mm) as desired dimensions, nailed with sft 26 3,940.81 102461.2 4,899.50 127387.1 7,579.04 197055.0
wooden dasha.
Temporary Platform, Staging, Scaffolding Work(Above 3m):
17 including placing and driving the MS pipe, fixing with clamps and sft 28 1515.277 42427.8 1,951.28 54635.9 2,453.49 68697.6
welding if required.
Fare Face Finishing Work: including leveling, smoothing the
18 sft 3 6,735.673 20207.0 8,431.76 25295.3 11,744.68 35234.0
concrete surface, coating with white cement etc.
Concrete Casting Work of Wearing Coat: including leveling,
19 vibrating, finishing the concrete, maintain the concrete surface sft 20 253.844 5076.9 758.28431 15165.7 1,148.81 22976.3
slope.

Total Amount 991558 1436830 2051519

Tk./cft 104 74 66