PREPARATION OF COMMUNITY ACTION PLAN Docs

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

PREPARATION OF COMMUNITY ACTION PLAN

ACTION PLAN
 Ensures that an organization’s vision is made concrete.
 It depicts how the members of the community utilize strategies to achieve their
objectives.
 List of action steps that will be implemented in the community are prepared to the
attainment of a project’s vision.

Purposes for Preparing an Action Plan:


 To demonstrate that a community is organized and committed to accomplish the tasks
planned.
 To ensure that details are carefully examined.
 To make people realize what is feasible and not in the community.
 To save time, energy, and resources due to efficient planning.
 To develop responsibility among members.
Preparing an Action Plan
 Select an appropriate and attainable goal.
 Clearly define your objectives.


Brainstorming with team members also can help create a stronger plan of action.  Some
members of the community who can be invited for brainstorming are the following:
 Influential people such as church, school or political leaders
 People who are directly involved in the problem (such as victims of abuse and their
parents)
 Potential volunteers
 Members of ethnic and cultural groups in the community
 People who display interest about the problem or issue.


Once the invited members of the team are already present, the following points can be
discussed:
 Vision
 Objectives
 Mission
 Strategies
 Targets and agents of change (e.g., youth, parents and guardians, clergy)
 Proposed changes for each sector of the community (e.g., schools, community,
service organizations, health organizations, government)


Examine the agreed action step by the group, and identify if the following points are
considered:
 What actions will be implemented?
 Who will implement these actions?
 When and how long will the actions take place?
 What resources (i.e., money, staff) are necessary to implement the action steps?
 Who should be informed about the actions that will be carried out?


Determine who is responsible for each action step and identify people who will assist in the
process.


Prepare a clear schedule to accomplish the action steps.  List the resources that are needed
to complete the action steps.


Review the action plan prepared and note for possible updates or modifications.  Identify if the
action plan prepared is:
 Complete: All action steps that are necessary are included in the list.
 Clear:  The people who are responsible for executing the actions steps are well
indicated, and other important details are included.
 Current:  it is in accordance with the present situation of the community. 


Communicate with the key people involved in the planning the progress of the action plan and
the effects of its implementation.


Celebrate one’s accomplishments.  This will motivate the people involved in the planning to
become more excited and interested in effectively and efficiently doing the steps in the action
plan.

1. Determine the importance of developing an action plan.

Developing an action plan can help change makers turn their visions into reality, and increase efficiency
and accountability within an organization. An action plan describes the way your organization will meet
its objectives through detailed action steps that describe how and when these steps will be taken.

2. Explain the steps in creating an action plan.

First we should know what is our goal, the resources needed, and what is our desired outcome,
then we should list down the steps or procedures of our plan, and then we should ask help to
others that can help you achieve your goal, then we should have a target date so that we will
work hard on our specific goals in creating an action plan
Sample Action Plan Template

Action Step Part/Dept. Date to Date


GOAL 1 Descriptions Responsible Begin Due

First we need to hire


some people that will
help clean the drainages. Brgy,Chairman November November
26,2020 26,2020

Second we need to
Cleaning the Drainage borrow some equipments November November
of from the barangay Brgy.Chairman
26,2020 26,2020
the Community in Brgy.
Pinagbuhatan Pasig
City
Third is we need to know
where are the areas in the
Kagawads/
barangay that suffer November November
Sangguniang
floods during typhoons 27,2020 27,2020
Kabataan

Fourth is to start cleaning


the drainage November November
Workers
 Man Power 28,2020 28,2020
 Cart
 Shovel
 Rake
 Sacks
 Rope
Fifth is to remove all the November November
 Dump truck Workers
things that blocked the 28,2020 28,2020
way of the water which
causes flood

Sixth is to remove all the Workers November November


garbages in the drainage 28,2020 28,2020
using the shovel and rake
and put it in a sack
Seventh we need to use
ropes so that the pipes November November
will also be cleaned Workers
28,2020 28,2020

Eight all the garbages


The desired outcome will place in a sack and
on this project is that will put on a cart and will
all the drainage will be deliver to the dump truck November November
clean so that when a Workers
waiting in the edge of the 29,2020 29,2020
typhoon comes the
street
probability of having
flood will be lessen.

Action Step Part/ Dept. Date to Date


GOAL 2 Descriptions Responsible  Begin  Due

Choose a design for the Brgy.Captain January January 7,


building 5,2021 2021

Building a Big Multi Find a high land so that it Kagawads/ January 8, January
Purpose Building will unable to reach by Sangguniang 2021 10,2021
floods Kabataan

Hire Workers including Brgy.Captain January January


Architect and Engineer 11,2021 15,2021

 Man Power Measure the length and


Engineer
January January
 Funds/Money height of the building 16,2021 18,2021
 Hollow Blocks
Make a blueprint of the January January
 Cement Architect
design of the Building 19,2021 25,2021
 Metals
 Shovels Start the Construction of January January
Workers
the building 25,2021 26,2021
 Woods and etc..
Start by building the January February
Foundation of the Workers 27,2021 5,2021
Building

Complete Rough Workers February February


Framing, Complete 6,2021 12,2021
Rough Plumbing,
Electrical HVAC

Install
Insulation,Complete
Drywall and Interior
Fixtures, Start Exterior
Finishes,Finish Interior February February
Workers
13,2021 18,2021
Trim, Install Exterior
Walkways and
Driveway

Install Hard Surface


Flooring, Countertops;
Complete Exterior
Grading, Finish February February
Workers
Mechanical Trims; Install 19,2021 25,2021
Bathroom Fixtures

A Multi Purpose Building Install Mirrors, Shower


that can use by the Doors; Finish Flooring,
community as a Exterior Landscaping, February April
evacuation center, People Workers
26,2021 5,2021
Gatherings, and etc... Final Walk-Through