EGCO Cogeneration Company Limited

Tender Document – New EGCO Cogen Power Plant Part III-Section 3

3.2 SITE CONDITION

The net electrical output guarantee of the Project plant shall be the output of the unit measured at the
high side of generator transformers after deducting all balance of plant equipment including water
treatment system, admin./warehouse general usage at the specified condition of air temperature, relative
humidity and barometric pressure given below:

Normal Condition

Plant above mean sea level m +6.025

Ambient design pressure Mbar 1010

o
Ambient design temperature C
32.6
(for GT) (dry bulb)

o
Ambient design temperature C
40
(for BOP) (dry bulb)

Annual Rainfall mm 1308

1 Hr. Rainfall (10 years return) mm 80

15 minutes Rainfall (5 years return) mm 220

Relative Humidity Average % 80

Wind Speed km/hr 160

Seismic Zone 1

The performance rating of HRSG and other ancillary plant shall coincide with the above conditions
when operating with the gas and steam turbines.

The Project’s Guaranteed Net Electrical Output, Guaranteed Net Heat Rate, Guaranteed Net Steam
Output and all test specified in Part III, section 1.1 Performance Guaranteed shall be tested at this case.

2
EGCO Cogeneration Company Limited
Tender Document – New EGCO Cogen Power Plant Part III-Section 3

Extreme Condition

The Contractor shall propose and guarantee maximum net output (MW) of Project power plant
during extreme condition:

Plant above mean sea level m +6.025

Ambient design pressure Mbar 1010

o
Ambient design temperature C
40
(for GT) (dry bulb)

o
Ambient design temperature C
40
(for BOP) (dry bulb)

Annual Rainfall mm 1308

1 Hr. Rainfall (10 years return) mm 80

15 minutes Rainfall (5 years return) mm 220

Relative Humidity Average % 50

Wind Speed km/hr 160

Seismic Zone 1