Professional Documents
Culture Documents
18PO0040 CCS and DUPA
18PO0040 CCS and DUPA
Project Name and: 18PO0040, ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM – ASSET PRESERVATION PROGRAM – REHABILITAT
: UPGRADING OF DAMAGED PAVED ROADS KALINGA – CAGAYAN ROAD (CALANAN – ENRILE SECTION) K0503+900 – K0504+792, K0509+063 – K0509+46
K0517+904 – K0518+050, K0518+662 – K0520+022, K0520+234 – K0520+279, K0523+014 – K0523+654, K0523+720 – K0524+000, K0524+810 – K0524+888, K052
Location: : Tabuk City and Rizal, Kalinga
Contracting Parties: : DPWH - CORDILLERA ADMINISTRATIVE REGION (DPWH-CAR) represented by R.D. NERIE D. BUEÑO, CESO IV and J.C. BAAC CONSTRUCTION CORPORATIO
ROSE P. BAAC
Approved Budget for the Contract : ₱ 106,773,914.00
Contract Cost : ₱ 103,567,173.50
B.4(1) CONSTRUCTION SURVEY AND STAKING km 5.50 21,120.00 116,160.00 5.50 18,247.00 100,358.50 5.50 21,120.41
B.5 PROJECT BILLBOARD / SIGNBOARD each 3.00 6,960.00 20,880.00 3.00 5,003.00 15,009.00 3.00 6,079.69
B.8 TRAFFIC MANAGEMENT month 8.00 38,213.00 305,704.00 8.00 30,975.00 247,800.00 8.00 38,209.98
Page 1 of 37
Project Name and: 18PO0040, ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM – ASSET PRESERVATION PROGRAM – REHABILITAT
: UPGRADING OF DAMAGED PAVED ROADS KALINGA – CAGAYAN ROAD (CALANAN – ENRILE SECTION) K0503+900 – K0504+792, K0509+063 – K0509+46
K0517+904 – K0518+050, K0518+662 – K0520+022, K0520+234 – K0520+279, K0523+014 – K0523+654, K0523+720 – K0524+000, K0524+810 – K0524+888, K052
Location: : Tabuk City and Rizal, Kalinga
APPROVED BUDGET FOR THE CONTRACT
CONTRACT COST COA COST ESTIMATE
Item No. DESCRIPTION Unit
Qty. Unit Cost Total Qty. Unit Cost Total Qty. Unit Cost
B.9 MOBILIZATION / DEMOBILIZATION lumpsum 1.00 437,682.00 437,682.00 1.00 391,524.00 391,524.00 1.00 450,105.60
102(2) SURPLUS COMMON EXCAVATION cu.m 7,103.00 135.00 958,905.00 7,103.00 149.00 1,058,347.00 7,103.00 142.97
200(1) AGGREGATE SUBBASE COURSE cu.m 4,083.00 922.00 3,764,526.00 4,083.00 1,523.00 6,218,409.00 4,083.00 821.08
404(1)a REINFORCING STEEL, GRADE 40 kg 2,530.00 59.00 149,270.00 2,530.00 58.00 146,740.00 2,530.00 57.27
506(1) STONE MASONRY cu.m 1,285.00 4,199.00 5,395,715.00 1,285.00 2,948.00 3,788,180.00 1,285.00 4,172.81
Page 3 of 37
Project Name and: 18PO0040, ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM – ASSET PRESERVATION PROGRAM – REHABILITAT
: UPGRADING OF DAMAGED PAVED ROADS KALINGA – CAGAYAN ROAD (CALANAN – ENRILE SECTION) K0503+900 – K0504+792, K0509+063 – K0509+46
K0517+904 – K0518+050, K0518+662 – K0520+022, K0520+234 – K0520+279, K0523+014 – K0523+654, K0523+720 – K0524+000, K0524+810 – K0524+888, K052
Location: : Tabuk City and Rizal, Kalinga
Results of Evaluation:
The Approved Budget for the Contract and Contract Cost were found to be higher than the COA Evaluated Cost, hence both are deemed unreasonable.
Engr. BLUE SANDER A. FALAG-EY Engr. LYDIA E. VILORIA Engr. REYMAX F. BOSQUE
Techical Audit Specialist II Supervising Techical Audit Specialist Chief Techical Audit Specialist
OIC Service Chief
Page 4 of 37
IINFRA.TER.OC.WP.CCS
Total COST
136,080.00
181,440.00
94,711.68
452,499.60
113,702.40
116,162.26
18,239.07
130,496.96
305,679.84
Page 5 of 37
PROGRAM – REHABILITATION / RECONSTRUCTION /
92, K0509+063 – K0509+463, K0513+083 – K0513+483,
24+810 – K0524+888, K0525+096 – K0525+610
Total COST
450,105.60
4,305,133.65
1,015,515.91
94,165.50
81,455.85
808,901.73
3,352,469.64
*main source of
82,240,520.31
discrepancy
144,893.10
666,812.92
5,362,060.85
1,567,715.50
1,055,220.60
94,726.08
102,788,709.05
Page 6 of 37
PROGRAM – REHABILITATION / RECONSTRUCTION /
92, K0509+063 – K0509+463, K0513+083 – K0513+483,
24+810 – K0524+888, K0525+096 – K0525+610
Page 7 of 37
PROGRAM – REHABILITATION / RECONSTRUCTION /
92, K0509+063 – K0509+463, K0513+083 – K0513+483,
24+810 – K0524+888, K0525+096 – K0525+610
asonable.
Page 8 of 37
PROJECT NAME:
18PO0040, ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD
SYSTEM – ASSET PRESERVATION PROGRAM – REHABILITATION / RECONSTRUCTION /
UPGRADING OF DAMAGED PAVED ROADS KALINGA – CAGAYAN ROAD (CALANAN –
ENRILE SECTION) K0503+900 – K0504+792, K0509+063 – K0509+463, K0513+083 – K0513+483,
K0517+904 – K0518+050, K0518+662 – K0520+022, K0520+234 – K0520+279, K0523+014 – K0523+654,
K0523+720 – K0524+000, K0524+810 – K0524+888, K0525+096 – K0525+610
A.1.1(6) PROVISION OF COMBINED FIELD OFFICE, LABORATORY AND LIVING QUARTERS FOR THE ENGINEER
QUANTITY: 8.00 month
MATERIALS
A.1.1(11) PROVISION OF FURNITURES / FIXTURES, EQUIPMENT AND APPLIANCES FOR THE FIELD OFFICE
QUANTITY: 1.00 lumpsum
MATERIALS
A.1.1(15) OPERATION AND MAINTENANCE OF THE TEMPORARY FIELD OFFICE, LABORATORY AND LIVING
QUARTERS
QUANTITY: 8.00 month
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Laborer 43.50 1,920.00 83,520.00
Sub-total= 83,520.00
A.1.2(2) PROVISION OF 4x4 PICK UP TYPE SERVICE VEHICLE FOR THE ENGINEER ON BARE RENTAL BASIS
QUANTITY: 8.00 month
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Driver 56.40 1,920.00 108,288.00
Sub-total= 108,288.00
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Geodetic Engineer 117.34 171.00 20,065.14
2.00 Rodman 56.40 171.00 19,288.80
1.00 Recorder 56.40 171.00 9,644.40
Sub-total= 48,998.34
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 unit Total Station 312.50 171.00 53,437.50
Sub-total= 53,437.50
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 77.80 4.00 311.20
1.00 Skilled Laborers 56.40 4.00 225.60
1.00 Laborers 43.50 4.00 174.00
Sub-total= 710.80
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Part Time Practitioner 77.80 306.00 23,806.80
1.00 First Aider 56.40 960.00 54,144.00
Sub-total= 77,950.80
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
4.00 Flagman (70% of project duration) 43.50 1,344.00 233,856.00
Fabrication of Bollards
1.00 Construction Foreman 77.80 4.00 311.20
2.00 Labor 43.50 4.00 348.00
Sub-total= 234,515.20
MATERIALS
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
2.00 unit Payloader (1.50 cu.m) 1,733.00 16.00 55,456.00
3.00 unit Dump Truck (10 cu.m) 1,420.00 16.00 68,160.00
1.00 unit Bulldozer, D6H Series II PSDS/DD 3,379.00 16.00 54,064.00
1.00 unit Backhoe (0.80 cu.m) to be loaded to Lowbed Trailer
1.00 unit Motorized Road Grader (140 HP) 2,173.00 16.00 34,768.00
1.00 unit Vibratory Roller (10 m.t) to be loaded to Lowbed Trailer
1.00 unit Water Truck / Pump (16,000 L) 2,450.00 16.00 39,200.00
4.00 unit Transit Mixer (5.0 cu.m) 1,318.00 16.00 84,352.00
1.00 unit Cargo Truck (10 m.t) 1,212.00 16.00 19,392.00
2.00 unit Lowbed Trailer w/ Prime Mover 2,290.00 16.00 73,280.00
-
Other smaller equipment to be loaded to Dumptrucks and Cargo Trucks
-
Sub-total= 428,672.00
Note: As per DPWH Department Order No. 197, series of 2016, in no case shall mobilization and demobilization exceed 1% of the
Estimated Direct Cost (EDC) of the civil works items:
EDC of civil works items= 81,347,278.80
1% of EDC= 813,472.79
Item cost for mobilization and demobilization < 1% EDC; therefore adopt computed item cost
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 77.80 841.18 65,443.80
2.00 Laborers 43.50 841.18 73,182.66
Sub-total= 138,626.46
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit Backhoe w/ Breaker (0.80 cu.m) 1,998.10 841.18 1,680,761.76
1 1.00 unit Payloader (1.50 cu.m) 1,733.00 841.18 1,457,764.94
1.00 unit Dump Truck (10 cu.m) 1,420.00 129.25 183,535.00
Minor Tools (10% of Labor Cost) 13,862.65
Sub-total= 3,335,924.35
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 77.80 88.79 6,907.86
2.00 Laborers 43.50 88.79 7,724.73
Sub-total= 14,632.59
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit Bulldozer, D6H Series II PSDS/DD 3,379.00 88.79 300,021.41
1 1.00 unit Payloader (1.50 cu.m) 1,733.00 88.79 153,873.07
0.3 1.00 unit Payloader (1.50 cu.m) - disposal 1,733.00 26.64 46,167.12
3.00 unit Dump Truck (10.0 cu.m) 1,420.00 39.54 168,440.40
1 1.00 unit Backhoe (0.80 cu.m) 1,537.00 88.79 136,470.23
Sub-total= 804,972.23
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 77.80 16.50 1,283.70
3.00 Laborers 43.50 16.50 2,153.25
Sub-total= 3,436.95
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 2.00 unit Dump Truck (10.0 cu.m) 1,420.00 16.50 46,860.00
1 1.00 unit Backhoe (0.80 cu.m) 1,537.00 16.50 25,360.50
Minor Tools (10% of Labor Cost) 343.70
Sub-total= 72,564.20
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
A. Excavation Works
0.83 1.00 Construction Foreman 77.80 4.73 367.99
0.83 2.00 Laborers 43.50 4.73 411.51
B. Spreading and Compaction
1 1.00 Construction Foreman 77.80 5.70 443.46
1 2.00 Laborers 43.50 5.70 495.90
Sub-total= 1,718.86
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
A. Excavation Works
0.83 1.00 unit Bulldozer, D6H Series II PSDS/DD 3,379.00 4.73 15,982.67
0.83 1.00 unit Payloader (1.50 cu.m) 1,733.00 4.73 8,197.09
0.83 2.00 unit Dump Truck (10.0 cu.m) 1,420.00 4.73 13,433.20
B. Spreading and Compaction
1 1.00 unit Motorized Road Grader (140 HP) 2,173.00 5.70 12,386.10
1 1.00 unit Vibratory Roller (10 m.t) 1,846.00 5.70 10,522.20
0.25 1.00 unit Water Truck / Pump (16,000 L) 2,450.00 1.43 3,503.50
Sub-total= 64,024.76
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 77.80 136.11 10,589.36
2.00 Laborers 43.50 136.11 11,841.57
Sub-total= 22,430.93
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit Motorized Road Grader (140 HP) 2,173.00 136.11 295,767.03
1 1.00 unit Vibratory Roller (10 m.t) 1,846.00 136.11 251,259.06
0.25 1.00 unit Water Truck/Pump (16,000 L) 2,450.00 34.03 83,373.50
Sub-total= 630,399.59
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 77.80 81.66 6,353.15
2.00 Laborers 43.50 81.66 7,104.42
Sub-total= 13,457.57
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit Motorized Road Grader (140 HP) 2,173.00 81.66 177,447.18
1 1.00 unit Vibratory Roller (10 m.t) 1,846.00 81.66 150,744.36
0.25 1.00 unit Water Truck/Pump (16,000 L) 2,450.00 20.42 50,029.00
Sub-total= 378,220.54
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 77.80 710.14 55,248.89
4.00 Skilled Laborers 56.40 710.14 160,207.58
12.00 Laborers 43.50 710.14 370,693.08
Sub-total= 586,149.55
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 4.00 unit Transit Mixer (5.0 cu.m) 1,318.00 710.14 3,743,858.08
1 2.00 unit Concrete Vibrator 91.25 710.14 129,600.55
1 1.00 unit Batching Plant (30 cu.m) 1,759.50 710.14 1,249,491.33
1 1.00 unit Payloader (1.50 cu.m) 1,733.00 710.14 1,230,672.62
1 1.00 unit Concrete Screeder (5.5 HP) 545.00 710.14 387,026.30
1 1.00 unit Water Truck/Pump (16,000 L) 2,450.00 710.14 1,739,843.00
1 1.00 unit Concrete Saw (7.5 HP) 14" Ø Blade 32.63 710.14 23,171.87
0.1 1.00 unit Bar Cutter, Single Phase 219.75 71.01 15,604.45
Minor Tools (5% of Labor) 29,307.48
Sub-total= 8,548,575.68
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 77.80 14.06 1,093.87
2.00 Skilled Laborers 56.40 14.06 1,585.97
8.00 Laborers 43.50 14.06 4,892.88
Sub-total= 7,572.72
EQUIPMENT RENTALS
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
0.15 1.00 unit Cargo Truck (10 m.t) 1,212.00 2.11 2,557.32
0.5 1.00 unit Bar Cutter, Single Phase 219.75 7.03 1,544.84
0.5 1.00 unit Bar Bender 351.50 7.03 2,471.05
Sub-total= 6,573.21
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 77.80 63.57 4,945.75
4.00 Skilled Laborers 56.40 63.57 14,341.39
8.00 Laborers 43.50 63.57 22,122.36
Installation and Removal of Forms
4.00 Skilled Laborers 56.40 63.57 14,341.39
8.00 Laborers 43.50 63.57 22,122.36
Sub-total= 77,873.25
EQUIPMENT RENTALS
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit One Bagger Mixer 172.00 63.57 10,934.04
1 1.00 unit Concrete Vibrator 91.25 63.57 5,800.76
0.1 1.00 unit Water Truck/Pump (16,000 L) 2,450.00 6.36 15,582.00
Minor Tools (5% of Labor) 3,893.66
Sub-total= 36,210.46
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 77.80 803.13 62,483.51
2.00 Skilled Laborers 56.40 803.13 90,593.06
8.00 Laborers 43.50 803.13 279,489.24
Sub-total= 432,565.81
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit One Bagger Mixer 172.00 803.13 138,138.36
0.05 1.00 unit Water Truck/Pump (16,000 L) 2,450.00 40.16 98,392.00
0.1 1.00 unit Backhoe (Wheel Type 0.28 cu.m) 922.00 80.31 74,045.82
Minor Tools (10% of Labor) 43,256.58
Sub-total= 353,832.76
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 77.80 215.00 16,727.00
3.00 Laborers 43.50 215.00 28,057.50
Sub-total= 44,784.50
EQUIPMENT RENTALS
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit Diamond Drill, CP-8 w/ attachment 201.25 215.00 43,268.75
0.25 1.00 unit Cargo Truck (5 m.t) 783.00 53.75 42,086.25
1 1.00 unit Air Compressor (15-35 cfm) 205.00 215.00 44,075.00
Minor Tools (10% of Labor) 4,478.45
Sub-total= 133,908.45
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 77.80 47.60 3,703.28
2.00 Skilled Laborers 56.40 47.60 5,369.28
6.00 Laborers 43.50 47.60 12,423.60
Sub-total= 21,496.16
EQUIPMENT RENTALS
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit Cargo Truck (5 m.t) 783.00 47.60 37,270.80
1 1.00 unit Applicator Machine 93.75 47.60 4,462.50
1 1.00 unit Kneading Machine 187.50 47.60 8,925.00
Minor Tools (10% of Labor) 2,149.62
Sub-total= 52,807.92
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 77.80 3.84 298.75
2.00 Skilled Laborers 56.40 3.84 433.15
6.00 Laborers 43.50 3.84 1,002.24
Sub-total= 1,734.14
EQUIPMENT RENTALS
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit Cargo Truck (5 m.t) 783.00 3.84 3,006.72
1 1.00 unit Applicator Machine 93.75 3.84 360.00
1 1.00 unit Kneading Machine 187.50 3.84 720.00
Minor Tools (10% of Labor) 173.41
Sub-total= 4,260.13
MATERIALS
Prepared by:
A. Loading
Quantity= 38,000.00 kgs
Capacity of 1 Cargo Truck: 10,000.00 kgs (Assume 1 laborer can carry 40 kgs of RSB)
Loading Time (using 6 10,000.00 kgs x 1.00 man-min x 1.00 = 41.67 mins.
laborers): 40.00 kgs 6.00 lab.
B. Handling
Ave. Hauling Distance 14.50 kms
Paved Road: 12.00 kms; Ave. Loaded Speed: 30.00 km/hr (Rolling Terrain)
Ave. Unloaded Speed: 40.00 km/hr
Loaded Trip: 12.00 kms x 1.00 x 60.00 min = 24.00 mins.
30.00 km/hr 1.00 hr
Unloaded Trip: 12.00 kms x 1.00 x 60.00 min = 18.00 mins.
40.00 km/hr 1.00 hr
Paved Road: 2.50 kms; Ave. Loaded Speed: 20.00 km/hr (Mountainous)
Ave. Unloaded Speed: 30.00 km/hr
Loaded Trip: 2.50 kms x 1.00 x 60.00 min = 7.50 mins.
20.00 km/hr 1.00 hr
Unloaded Trip: 2.50 kms x 1.00 x 60.00 min = 5.00 mins.
30.00 km/hr 1.00 hr
1. Equipment Cost
Using: 1.00 Cargo Truck/s
No. of Days reqd: 38,000.00 kgs x 151.61 min/trip x 1.00 trip x 1.00
480.00 min/day 10,000.00 kg 1.00 CT's
No. of Days reqd: 1.20 day/s
Equipment Cost: 1.00 CT's x 9,696.00 Php/day x 1.20 days = 11,635.20
2. Labor Cost
Employing: 6.00 Laborers *Consider 25% of equipment duration
Labor Cost: 6.00 lab x 348.00 Php/day x 0.30 days = 626.40
A. Loading
Quantity= 9,053.55 bags
B. Handling
Ave. Hauling Distance 29.00 kms
Paved Road: 15.00 kms; Ave. Loaded Speed: 35.00 km/hr (Flat Paved)
Ave. Unloaded Speed: 55.00 km/hr
Loaded Trip: 15.00 kms x 1.00 x 60.00 min = 25.71 mins.
35.00 km/hr 1.00 hr
Unloaded Trip: 15.00 kms x 1.00 x 60.00 min = 16.36 mins.
55.00 km/hr 1.00 hr
Paved Road: 14.00 kms; Ave. Loaded Speed: 20.00 km/hr (Flat Paved)
Ave. Unloaded Speed: 30.00 km/hr
Loaded Trip: 14.00 kms x 1.00 x 60.00 min = 42.00 mins.
20.00 km/hr 1.00 hr
Unloaded Trip: 14.00 kms x 1.00 x 60.00 min = 28.00 mins.
30.00 km/hr 1.00 hr
1. Equipment Cost
Using: 1.00 Cargo Truck/s
No. of Days reqd: 9,053.55 bags x 214.95 min/trip x 1.00 trip x 1.00
480.00 min/day 250.00 bags 1.00 CT's
No. of Days reqd: 16.22 day/s
2. Labor Cost
Employing: 6.00 Laborers *Consider 25% of equipment duration
A. Loading
Quantity= 24,300.00 cu.m
B. Handling
Paved Road: 12.00 kms; Ave. Loaded Speed: 30.00 km/hr (Rolling Terrain)
Ave. Unloaded Speed: 40.00 km/hr
Loaded Trip: 12.00 kms x 1.00 x 60.00 min = 24.00 mins.
30.00 km/hr 1.00 hr
Unloaded Trip: 12.00 kms x 1.00 x 60.00 min = 18.00 mins.
40.00 km/hr 1.00 hr
Paved Road: 2.50 kms; Ave. Loaded Speed: 20.00 km/hr (Mountainous)
Ave. Unloaded Speed: 30.00 km/hr
Loaded Trip: 2.50 kms x 1.00 x 60.00 min = 7.50 mins.
20.00 km/hr 1.00 hr
Unloaded Trip: 2.50 kms x 1.00 x 60.00 min = 5.00 mins.
30.00 km/hr 1.00 hr
1. Equipment Cost
Using: 5.00 Dumptrucks
No. of Days reqd: 24,300.00 cu.m x 65.45 min/trip x 1.00 trip x 1.00
480.00 min/day 10.00 cu.m 5.00 DT's
No. of Days reqd: 66.27 day/s
2. Labor Cost
Employing: Laborers
Source: Manila
Ave. hauling distance: 512.50 kms from source to project site
A. Loading
Quantity= 15,000.00 kgs
Capacity of 1 Cargo Truck: 10,000.00 kgs (Assume 1 laborer can carry 40 kgs of RSB)
Loading Time (using 6 10,000.00 kgs x 1.00 man-min x 1.00 = 41.67 mins.
laborers): 40.00 kgs 6.00 lab.
B. Handling
Ave. Hauling Distance 512.50 kms
Paved Road: 442.50 kms; Ave. Loaded Speed: 35.00 km/hr (Flat Terrain)
Ave. Unloaded Speed: 55.00 km/hr
Loaded Trip: 442.50 kms x 1.00 x 60.00 min = 758.57 mins.
35.00 km/hr 1.00 hr
Unloaded Trip: 442.50 kms x 1.00 x 60.00 min = 482.73 mins.
55.00 km/hr 1.00 hr
Paved Road: 60.00 kms; Ave. Loaded Speed: 30.00 km/hr (RollingTerrain)
Ave. Unloaded Speed: 40.00 km/hr
Loaded Trip: 60.00 kms x 1.00 x 60.00 min = 120.00 mins.
30.00 km/hr 1.00 hr
Unloaded Trip: 60.00 kms x 1.00 x 60.00 min = 90.00 mins.
40.00 km/hr 1.00 hr
Paved Road: 10.00 kms; Ave. Loaded Speed: 20.00 km/hr (Mountainous)
Ave. Unloaded Speed: 30.00 km/hr
Loaded Trip: 10.00 kms x 1.00 x 60.00 min = 30.00 mins.
20.00 km/hr 1.00 hr
Unloaded Trip: 10.00 kms x 1.00 x 60.00 min = 20.00 mins.
30.00 km/hr 1.00 hr
1. Equipment Cost
Using: 1.00 Cargo Truck/s
No. of Days reqd: 15,000.00 kgs x 1,743.09 min/trip x 1.00 trip x 1.00
480.00 min/day 10,000.00 kg 1.00 CT's
No. of Days reqd: 5.45 day/s
2. Labor Cost
18PO0040 UNIT COST DERIVATION Page 36 of 37
Employing: 6.00 Laborers *Consider 100% of equipment duration
Labor Cost: 6.00 lab x 348.00 Php/day x 5.45 days = 11,379.60