ROAD REHABILITATION SECTOR PROJECT LOAN ADB No.

1798-INO
PACKAGE :
PROVINCE :

ACTIVITY LIST

DIVISION : 8. REINSTATEMENT AND MINOR WORKS

SECTION : 8.2 Reinstatement of Existing Shoulders on Sealed Roads

SCOPE : The work covered shall comprise the reconstruction or shape correction of isolated sections not exceeding 50 metres
in length in any one kilometre, the filling of large potholes and the removal and disposal of unwanted trees including
the stump and roots.

Activity Description of Activity Action Specification Level of Approval

No. Contractor Engineer Output Clause 1 2 3

PRELIMINARIES :-
PENDAHULUAN :
1 Related work :- 8.2.1(4)
Kerja Terkait :
Maintenance of Traffic Flow 1.8
Pemeliharaan Arus Lalu Lintas
Field Engineering 1.9
Rekayasa Lapangan
Materials and Storage 1.11
Bahan dan Penyimpanan
Grade Preparation 3.3
Persiapan Kelas
Shoulders 4.2
Bahu
Aggregate Base 5.1
Lapis Pondasi Agregat
Prime Coat and Tack Coat 6.1
Lapis Resap Pengikat dan Lapis Perekat
Single and Double Surface Dressing 6.2
Permukaan Dressing Single dan Double
Routine Maintenance of Pavement, Shoulders,
10.1
Drainage, Road Furniture and Bridges
Pemeliharaan Rutin Perkerasan, Bahu,
Drainase, Perlengkapan Jalan dan Jembatan
2 Ensure that the Contractor has all the relevant
- Verify Issue - X
data and drawings available at Contract start-up.
Pastikan bahwa Kontraktor memiliki semua
data yang relevan dan gambar yang tersedia
pada Kontrak awal.

3 Location of areas requiring reinstatement has to


Approval /
be surveyed showing sufficient detail of the Submission Check 8.2.1(2) X
Reject
existing shoulder condition.
Lokasi daerah yang membutuhkan perbaikan
harus disurvei menunjukkan detail yang cukup
dari kondisi bahu yang ada.

4 Determine areas to be reinstated and carry out


design based on field survey and visual - Design Issue 8.2.1(2) X
observations.
Tentukan area yang akan dipulihkan dan
melaksanakan desain berdasarkan survei
lapangan dan pengamatan visual.
5 Issue reinstatement works construction details to
- Issue Drawing 8.2.1(2) X
Contractor.
Memberikan pemulihan detail konstruksi kerja
untuk kontraktor.

6 Submit materials to be used in the construction for


Approval /
Submission Check 8.2.2(1) X
Reject
approval. Where required provide test certificates.
Kirim bahan yang akan digunakan dalam
pembangunan untuk persetujuan. Jika
diperlukan berikan sertifikat uji.
7 Traffic Flow :-
Arus Lalu Lintas :
The Constractor shall comply with the contract
- Verify - 8.2.2(1) X
requirements for Maintenance of Traffic Flow.
Kontraktor harus mematuhi persyaratan
kontrak untuk Pemeliharaan Arus Lalu Lintas.

CONSTRUCTION :-
KONSTRUKSI :
Preliminary activities shall be completed before
construction starts. Where construction is carried
out in stages the same shall apply to each stage.
Kegiatan awal harus diselesaikan sebelum
konstruksi dimulai. Dimana pembangunan
dilakukan secara bertahap yang sama berlaku
untuk setiap tahap.

1
ROAD REHABILITATION SECTOR PROJECT LOAN ADB No. 1798-INO
PACKAGE :
PROVINCE :

ACTIVITY LIST

DIVISION : 8. REINSTATEMENT AND MINOR WORKS

SECTION : 8.2 Reinstatement of Existing Shoulders on Sealed Roads

SCOPE : The work covered shall comprise the reconstruction or shape correction of isolated sections not exceeding 50 metres
in length in any one kilometre, the filling of large potholes and the removal and disposal of unwanted trees including
the stump and roots.

Activity Description of Activity Action Specification Level of Approval

No. Contractor Engineer Output Clause 1 2 3

8 The Contractor shall carry out method of


execution conforming to the requirements of the - Verify - 8.2.2 X
relevant activity.
Kontraktor harus melaksanakan metode
eksekusi sesuai dengan persyaratan dari
kegiatan yang bersangkutan.

9 isolated potholes shall be filled. - Verfiy - 8.2.1(3) X


  lubang terisolasi harus diisi.

10 Reshaped shoulder shall not be higher than, or


more than 1 cm lower than the adjacent - Verify - 8.2.2(3) X
carriageway.
Bahu yang dibentuk kembali tidak akan lebih
tinggi dari, atau lebih dari 1 cm lebih rendah
dari jalur lalu lintas yang berdekatan.

11 Shoulders shall not inhibit the flow of water from


- Verify - 8.2.2(3) X
the carriageway.
Bahu tidak akan menghambat aliran air dari
jalur lalu lintas.

12 Excavated materials shall be disposed of tidily in


locations which shall not inhibit sight distance,
- Verfiy - 8.2.2(4) X
interfere with any drainage or contribute to silting
of drains.
Bahan galian harus dibuang rapi di lokasi
yang tidak akan menghambat jarak pandang,
mengganggu drainase atau berkontribusi
terhadap pendangkalan saluran air.

2
ROAD REHABILITATION SECTOR PROJECT LOAN ADB No. 1798-INO
PACKAGE :
PROVINCE :

ACTIVITY LIST

DIVISION : 8. REINSTATEMENT AND MINOR WORKS

SECTION : 8.2 Reinstatement of Existing Shoulders on Sealed Roads

SCOPE : The work covered shall comprise the reconstruction or shape correction of isolated sections not exceeding 50 metres
in length in any one kilometre, the filling of large potholes and the removal and disposal of unwanted trees including
the stump and roots.

Activity Description of Activity Action Specification Level of Approval

No. Contractor Engineer Output Clause 1 2 3

13 Selected trees which obstruct sight distance or


are a safety hazard shall be removed. The holes
caused by the removal of stumps and roots must - Verify - 8.2.2(5)b X
be filled with suitable materials approved by the
Engineer.
Pohon tertentu yang menghalangi jarak
pandang atau bahaya keamanan harus
dihilangkan. Lubang-lubang yang disebabkan
oleh penghapusan tunggul dan akar harus
diisi dengan bahan yang cocok disetujui oleh
Direksi Pekerjaan.

14 Check and confirm compliance with specified Approval /


- Check 8.2.2(1) X
tolerances. Reject
Periksa dan pastikan sesuai dengan toleransi
yang ditentukan.

15 Where work fails to meet the requirements or is


otherwise considered unacceptable, remedial
- Check Instruction 8.2.2(1) X
works shall be as directed by and to the
satisfaction of the Engineer.
Di mana pekerjaan tidak memenuhi
persyaratan atau dinyatakan dianggap tidak
dapat diterima, pekerjaan perbaikan harus
seperti yang diarahkan oleh Engineer dan
untuk kepuasan Engineer.

MEASUREMENT :-
PENGUKURAN :
Measurement and payment shall be in
accordance with the requirements of the
Specifications.
Pengukuran harus sesuai dengan persyaratan
Spesifikasi.

16 Area measurement and survey shall be carried


Survey Verify Record 8.2.3 X
out on completed and accepted reinstatement.
Pengukuran luas dan survei dilaksanakan
setelah perbaikan lengkap dan diterima.

17 Quantities shall be calculated by the Contractor


Submission Verify Agreement 1.6 X
and checked by the Engineer.
Kuantitas dihitung oleh Kontraktor dan
diperiksa oleh Direksi Pekerjaan.