Professional Documents
Culture Documents
Labc Warranty Technical Manual v8 Low Res
Labc Warranty Technical Manual v8 Low Res
INTRODUCTION
INTRODUCTION
The LABC Warranty Technical Manual V8 has been This Technical Manual (and previous versions) many instances go into greater depth due to
produced to assist the Developers of buildings and can also be viewed on our website claims experience. An example being basements,
dwellings in meeting technical requirements. www.labcwarranty.co.uk where the whole or a Warranty Surveyor will ask for strict compliance
part of the document can be downloaded for free. with the guidance in the British Standard, referred
LABC Warranty has always prided itself on offering The on line foundation depth calculator to in the Building Regulations, whereas the Building
flexible solutions to meet warranty requirements, (mentioned in chapter 5.2) can also be found on Control Surveyor may only require compliance in
and although there is substantial guidance within the website; follow the link from the home page. principle.
the manual, flexibility can still be maintained.
THE DIFFERENCE BETWEEN BUILDING CONTROL The Building Control Surveyor is interested mainly
AND WARRANTY
This Technical Manual is produced for the purposes in compliance on the day that they visit, or at
of identifying compliance with the defects the time that a completion certificate is issued.
What’s the difference between Building Control
insurance period of the New Homes, Private Rental Warranty Surveyors are generally required to
and Warranty? Why do Warranty Surveyors
and Social Housing policies. The guidance may be consider the performance on an ongoing basis,
sometimes ask for more information or more detail,
used to assist in other policies covered by LABC therefore have to be satisfied that a basement
than a Building Control Surveyor?
Warranty; however, the restrictions on the relevant waterproofing is appropriate for all ground
policy will prevail. conditions and water table events, or as another
It can be for a number of reasons, whilst it should
example that a flat roof will not pond excessively
HOW THE MANUAL STRUCTURE WORKS be remembered that on occasion the Building
and fail within a 15 year period due to increased
Control Surveyor will, for certain elements, require
pressure from ponding on joints in any membrane
The Technical Manual is divided into 13 chapters, more information than the Warranty Surveyor, for
or deflection of structure, whereas a Building
and each chapter has sections. Each section example smoke control to common areas of an
Control Surveyor may only be concerned that
has Functional Requirements, which must be met apartment type development.
Technical Manual V8: TS-11A-8.00-010117
available then it can be incorporated, providing the main from building failures.
that the alternative method of meeting the
requirement can be proven and agreed with the Warranty Technical Requirements are generally
Warranty Surveyor. founded upon the Building Regulations, but in
1
INTRO
INTRODUCTION
INTRODUCTION
MAIN CHANGES IN THE TECHNICAL MANUAL V8 Chapter 3: Modern methods of construction (MMC) Chapter 7: Superstructure
• New subsection 3.1.5 provides guidance for • Section 7.3 Timber frame: has been updated
All chapters: Functional Requirements Insulated Concrete Formwork. in line with current practice and standards.
• Clarification is made in the ‘Materials’ The use of Green Oak on warrantied projects
requirement in Chapters 2, 3, 7, 12 and 13 Chapter 5: Foundations is further clarified.
regarding the level of durability required for • Section 5.2 Foundations; trees and clay; • Section 7.4 Windows and doors: Further
certain building elements. Reference is now made to the use of the clarification of the requirements for
• Clarification is made in the ‘Design’ on line foundation depth calculator to workmanship and weather tightness are
requirement that the construction should determine depth of foundations for typical made in this section, this includes a
meet relevant regional Building Regulations. tree species. Table 4 in Appendix A has requirement for weather tightness of
• New ‘limitations of Functional Requirements’ been removed as the information is now bespoke and handmade window and doors.
paragraph added to all chapters. contained on the calculator. • Amended requirements also made to the
• Subsection 5.5.5 Structural design: new ‘security’ requirements of doors and windows
Chapter 1: Tolerances guidance is given where insulation boards to be in line with changes to Building
• Subsection 1.4 Floors; a distinction is now are used under raft foundations. Regulations.
made in the requirements between level of • Guidance on Nickel Sulphide inclusions in
floors and deflection of floors. Chapter 6: Substructure glazing now included.
• Subsection 1.7 painted and varnished • Section 6.1 Guidance has been updated • Sub section 7.7.1, Render: The guidance is
surfaces; clarification is added to text with to clarify that a general requirement for a substantially updated in line with current
regard to requirements for surface finishes. minimum Grade 2 standard is required practices and standards.
with the exception that a Grade 1 standard • Sub section 7.7.2 Curtain walling: The
Technical Manual V8: TS-11A-8.00-010117
Chapter 2: Materials for certain underground car parking areas guidance is substantially updated in line
• Subsection 2.3 Revised Tables 4 & 5 are may be acceptable; subject to following the with current practices and standards.
provided for durability and suitability of clay guidance in this section. • Subsection 7.7.3 Insulated render systems;
brickwork to compare between BS 3921 & EN • Further guidance provided for where land Additional guidance is provided.
771-1 and acceptable locations of use. drainage provision may not be achievable. • New subsection 7.7.5 Rain screen cladding
• Subsection 2.3.4 ‘Coastal Locations’ has
© LABC Warranty
• Section 7.9 Roof coverings – Traditional slate Chapter 12 Conversion and refurbishment MOVING FORWARD
and tiles: this section has been updated in • Sections 12.1 has been revised in line with
line with current standards and practice, current good practice. The Technical Manual will be updated regularly
including a new subsection 7.9.5.6 • A new section 12.3 is added to provide in line with changes to the construction industry
which gives reference to the thermal cycle guidance on conversions that are classed and to meet legislative requirements. If you would
and carbonate content tests required for as ‘Historic’ buildings. like to recommend that we consider the inclusion
natural slates. of additional guidance, please email technical.
• Section 7.10 Roof coverings – continuous Chapter 13 Developments within manual@labcwarranty.co.uk with your suggestions.
membrane roofing: updated in line with coastal locations
current standards and practices. • This is a new chapter to the Technical Please note that the LABC Warranty Technical
Manual to provide guidance on the risks Manual is protected under copyright, and all text
Chapter 9.1 Drainage below ground that aggressive environmental conditions and images are deemed to be correct at the time
• Additional guidance provided where have on developments. of printing.
Sustainable Urban Drainage Systems (SuDS)
are proposed to be used in a development. External contribution
It should be recognised that a large proportion of
Chapter 10 Finishes the updated Technical Manual has been written
• Section 10.2 Second and third fix finishes: by external consultants. The main reason for this
Additional guidance for ceramic tiling and is to ensure that the standards are buildable
walk in showers and wet room floors is and reasonable whilst providing an acceptable
provided. level of detail. LABC Warranty would like to thank
Technical Manual V8: TS-11A-8.00-010117
INTRO
INTRODUCTION
INTRODUCTION
Appendix B
Soil and Rock Classification 59 7.1 External Masonry Walls 124
Chapter 3: Appendix C 7.2 Steel Frame 138
Modern Methods Of Construction Laboratory Testing 61 7.3 Timber Frame 143
7.4 Windows and Doors 166
3.1.1 Introduction 35 7.5 Chimneys 175
© LABC Warranty
Chapter 11:
Chapter 8: External Works
Superstructures (Internal)
11.1 Paving and Driveways 318
8.1 Internal Walls 268 11.2 This Section has been removed 327
8.2 Upper Floors 275 11.3 Outbuildings 328
8.3 Stairs 280
8.4 Fire Stopping and Fire Protection
to Flats and Apartments 283 Chapter 12:
Conversion and Refurbishment
INTRO
Technical Manual V8: TS-11A-8.00-010117
Technical Manual V6: TS-011a-6.00-010413
© LABC Warranty
CHAPTER 1: TOLERANCES
CHAPTER 1: TOLERANCES
CONTENTS
1.1 MASONRY
1.2 INTERNAL WALLS AND CEILINGS
1.3 JUNCTIONS
1.4 FLOORS
1.5 DOORS AND WINDOWS
1.6 SKIRTINGS
1.7 FINISHES AND FITTED FURNITURE
1.8 EXTERNAL WORKS
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
CHAPTER 1
FUNCTIONAL REQUIREMENTS
INTRODUCTION
1.1 MASONRY 1.1.2 Level of bed joints 1.1.5 Plumb of wall: overall height
A 10mm deviation is suggested for walls 5m long There should be a maximum deviation of 20mm in
1.1.1 Brickwork: straightness on plan (a pro rata tolerance is applicable for walls less the overall height of a wall.
There should be a 10mm maximum deviation in than 5m long), and a 15mm maximum deviation
any length of wall up to 5m. for walls over 5m long. There should be no recurrent
variations in the level of the bed joint line.
CHAPTER 1
CHAPTER 1: TOLERANCES
CHAPTER 1: TOLERANCES
1.1.6 Plumb of wall: storey height 1.1.7 Straightness in section 1.1.8 Rendered walls (plain)
The maximum deviation is 10mm in a storey The maximum deviation is 10mm in any 2.5m Unless otherwise specified, apply the render coats
height of approximately 2.5m. Using a 50mm wide height of wall. Using 25mm wide spacing blocks, to produce as flat a surface as possible, and where
spacing block, the plumb bob should be between the masonry line should be anywhere between appropriate check the surface by measuring
40mm and 60mm away from the wall. 15mm and 35mm from the reference line. between the face and any point along a 1.8m
straight edge placed against it. The flatness of the
rendered finish will depend upon the accuracy
to which the background has been constructed,
the thickness of the render specified and whether
grounds and linings are provided and fixed to a
true plane. For render less than 13mm thick, a no
tolerance limit is realistic. Significant cracks in the
render, or other damage, such as chips and marks
greater than 15mm in diameter, are considered
unacceptable.
1.2.1 Walls and ceilings If there are changes in the construction materials
(plastered and dry lined) used due to shrinkage and the differential
There should be no sharp differences of more than movement of materials; small cracks (up to 3mm
4mm in any 300mm flatness of wall; the maximum wide) may become visible in the surface at wall,
deviation is +/-5mm from a 2m straight edge with floor and ceiling junctions.
equal offsets, horizontally and vertically, for all wall
and ceiling surfaces. 1.4 FLOORS
1.4.1 Level
Floors up to 6m across can be a maximum of 4mm
out of level per metre, and a maximum of 25mm
overall for larger spans. The effects of normal drying
shrinkage on screeded floors could cause some
fracturing. Shrinkage of timber floors and staircases
is a natural occurrence when drying out, which
could result in the squeaking of materials as they
move against each other. This again is a natural
occurrence, and cannot be eliminated entirely.
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
CHAPTER 1
CHAPTER 1: TOLERANCES
CHAPTER 1: TOLERANCES
1.4.2 Deflection
For upper floors (intermediate floors), designers
and engineers must observe our tolerances
requirements in this chapter for levelness of floors.
Although a joist might be designed using British
Standards or Eurocodes to meet permissible
deflections; our tolerances requirement will take
precedence.
1.5.1 Doors
Reference of +/-3mm maximum deviation in 1m
head and sill.
1.5.2 Windows
For square reveals, a maximum +/-8mm deviation
off square is applicable for a reveal up to 200mm
deep.
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
CHAPTER 1
CHAPTER 1: TOLERANCES
CHAPTER 1: TOLERANCES
1.5.3 Glazing 1.5.4 Scratches on doors, windows and frames 1.7.1 Painted and varnished surfaces
Glass must meet the visual assessment criteria of Factory-finished door and window components All surfaces should be reasonably smooth as
CWCT Technical Note 35 (TN 35). The total number should not have conspicuous abrasions or practicably possible when viewed in daylight from
of faults permitted in a glass unit shall be the sum scratches when viewed from a distance of 0.5m. a 2 metre distance and not by shining any artificial
total of those permitted by the relevant BS EN light onto the surface. Significant nail holes, cracks
Standard for each pane of glass incorporated into • Surface abrasions caused during the building- and splits should not be seen and should be filled
the unit concerned. in process should be removed in accordance to reduce their visible appearance. Colour, texture
with the manufacturer’s instructions, which may and finish should be reasonably consistent and
Faults include: include polishing out, re-spraying or painting. any joints are to be filled where necessary.
• In rooms where there is no daylight, scratches
• Bubbles or blisters should be viewed in artificial light from fixed wall 1.7.2 Knots in timber
• Hairlines or blobs or ceiling outlets, and not from portable equipment. Some seeping of resin from knots is a natural
• Fine scratches not more than 25mm long occurrence that may cause paintwork discolouration
• Minute particles 1.6 SKIRTINGS both internally and externally. The standard will be
met providing the Developer finishes the timber in
When assessing the appearance of glass: It is possible that there will be joints in skirtings on accordance with Functional Requirements.
long walls. When viewed from a distance of 2m
• The viewing distance used shall be the furthest in daylight, joints will need to show a consistent 1.8 EXTERNAL WORKS
stated in any of the BS EN Standards for the appearance. It is anticipated that there will
glass types incorporated in the glazed unit. In be some initial shrinkage of the skirting after 1.8.1 Drives and paths: standing water
the event of doubt, the viewing distance shall occupation of the building. Surface variation should not exceed +/-10mm
Technical Manual V8: TS-11A-8.00-010117
also function as designed by the manufacturer. the standards of Part M (Access to Dwellings).
magnification. Adjacent doors and/or drawers with any gaps
• The above does not apply within 6mm of the between them should be consistent. At the 1.8.2 Drainage system covers
edge of the pane, where minor scratching is intersection of adjacent worktops, there should not Drainage system covers in hard standing areas
acceptable. be a visible change in level. should line up neatly with the adjacent ground.
CHAPTER 2: MATERIALS
CHAPTER 2: MATERIALS
CONTENTS
2.1 TIMBER
2.2 CONCRETE
2.3 OTHER COMPONENTS
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
15
CHAPTER 2
FUNCTIONAL REQUIREMENTS
2.1 TIMBER
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
a suitably qualified expert.
Materials iii. The materials used for construction must meet the relevant Regional
i. All materials should be stored correctly in a manner that will not Building Regulations.
cause damage or deterioration of the product. iv. Specialist works must be provided and supported by structural
ii. All materials, products and building systems shall be appropriate calculations completed by a suitably qualified engineer where
and suitable for their intended purpose. necessary.
iii. External timber should be adequately treated or finished to resist v. Any engineered beams/posts manufactured off-site must have
insect attacks. Timber treatment should be in accordance with structural calculations endorsed by the manufacturer.
relevant British Standards and Codes of Practice.
iv. The structure shall, unless specifically agreed otherwise with the Limitations of Functional Requirements
Warranty provider, have a life of not less than 60 years. Individual i. The Functional Requirements are limited by the recommendations
Technical Manual V6: TS-011a-6.00-010413
CHAPTER 2
CHAPTER 2: MATERIALS
CHAPTER 2: MATERIALS
19
CHAPTER 2
FUNCTIONAL REQUIREMENTS
2.2 CONCRETE
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
iii. Concreting shall not take place during cold weather periods or a suitably qualified expert.
where ground conditions are frozen. iii. The materials used for construction must meet the relevant
regional Building Regulations.
Materials iv. Reinforced concrete elements must be supported by structural
i. All materials should be stored correctly in a manner that will not cause calculations and details produced by a suitably qualified Structural
damage or deterioration of the product. Engineer.
ii. All materials, products and building systems shall be appropriate v. Precast structural elements must have structural calculations that
and suitable for their intended purpose. prove their adequacy, as endorsed by the manufacturer.
iii. The structure shall, unless specifically agreed otherwise with the
Warranty provider, have a life of not less than 60 years. Individual Limitations of Functional Requirements
components and assemblies, not integral to the structure, may have i. The Functional Requirements are limited by the recommendations
Technical Manual V6: TS-011a-6.00-010413
2.2.1 Cold weather working 2.2.3 Site mixed concrete During cold weather it may be appropriate to
To meet the Functional Requirements of this Site mixing is acceptable at low temperatures, cover the ground to prevent freezing and, in some
chapter, the minimum working temperature should provided: extreme cases, heating of the ground may be
not fall below 2°C. It is important that during cold required.
weather periods, regular temperature readings • The minimum temperature is no less than 2°C
should be taken. Thermometers should be placed • The concrete is appropriately protected during Other concreting: Concrete reinforcing and
away from direct sunlight, preferably in a shaded curing formwork should not be frozen and be free from
area. When assessing the temperature, it is also • Ground conditions are not frozen snow and ice.
important to consider wind chill and weather
exposure, and make the necessary allowances for 2.2.4 Concreting of foundations and oversite 2.2.5 Curing of concrete
sites that have a higher level of exposure. Concrete should not be poured if the ground is Concrete may take longer to cure in cold
frozen as frozen ground can change in stability conditions, and an additional six days may be
and volume during thawing, and therefore may required in extreme cases. Concrete may be
cause damage to the recently poured concrete. covered with a rigid insulation to prevent freezing
during curing periods. This is particularly useful for
oversized slabs.
Technical Manual V8: TS-11A-8.00-010117
below 5°C at the time of delivery. Measures should Figure 4: Concrete pouring in cold weather conditions Figure 5: Concrete curing in cold weather conditions
also be put in place to ensure immature concrete
is prevented from freezing before sufficient strength
has been achieved.
21
CHAPTER 2
CHAPTER 2: MATERIALS
CHAPTER 2: MATERIALS
Delivery notes should be kept and made available 2.2.7.2 Site mixed concrete
for inspection if required. Site mixed concrete should generally be avoided
unless it is for non-structural applications, e.g.
Additional water should not be added to the backfilling or bedding of paving slabs, etc. There
concrete on-site, nor should the ready mixed may be exceptional circumstances where site
concrete be poured into water filled trenches mixing is unavoidable. Where this is the case, extra
unless the concrete has been specifically designed caution must be taken to ensure that the correct
for this purpose. mix proportion is used; delivery notes should be
provided if necessary, and a provision for testing
may be required.
23
CHAPTER 2
CHAPTER 2: MATERIALS
CHAPTER 2: MATERIALS
chairs or spacers, and can be made of concrete, usually will not assist in preventing concrete
admixture is applied to any mix. Any overdosing
plastic or steel. The thickness and depth of a from freezing; therefore, they should not be relied
may cause concrete deterioration or poor
concrete spacer should not exceed 50mm x upon to compensate for freezing conditions. The
workability.
50mm. Spacers should be placed at a maximum guidance for cold weather working should be
of 1m centres, and when supporting mesh should followed in these circumstances.
© LABC Warranty
be staggered.
CHAPTER 2: MATERIALS
CHAPTER 2: MATERIALS
Admixtures and reinforcing 2.2.12 Curing of concrete 2.2.13 Standards referred to:
Admixtures containing chloride will cause corrosion Concrete should be adequately cured before • BS 8110 Structural use of concrete
to occur, meaning they should not be used in loads are applied. It is acceptable that masonry • BS EN 1992 – 1-1 Design of concrete structures,
concrete containing reinforcing. walls may be built up to damp proof course (DPC) general rules and rules for buildings
on a foundation that is not fully cured; however, (incorporating UK National Annex to Eurocode)
2.2.10 Expansion/movement joints care must be taken to prevent any damage to • BS 8500 Concrete – Complementary British
Joints in concrete should be provided to prevent the foundation. The concrete should be at least Standard to BS EN 206-1
cracking caused by shrinkage; shrinkage will be durable enough to carry the masonry. • BS EN 206-1 Concrete. Specification,
less significant if the concrete is reinforced. performance, production and conformity
The speed at which concrete mixes cure depends • BS EN 12620 Aggregates for concrete
A larger number of expansion joints should be on the mix ratio and whether there are any • BS EN 197 Cement. Conformity evaluation
provided to concrete where weak spots may occur. additives within the concrete. Where curing time
This could include a narrowing width of floor slab is critical, such as cast in-situ upper floors, curing
for example. times should be indicated as part of the design
and formwork struck, as advised by a Structural
2.2.11 Vibration and compaction of concrete Engineer.
Reinforced concrete should be compacted using
a vibrating poker, but care must be taken to ensure To prevent concrete curing too rapidly after initial
the concrete is not over-compacted and the drying, exposed concrete should be covered
concrete mix separated. Tamping of floors by hand with hessian, polythene or sand. This prevents
is acceptable for floor slabs that do not exceed the surface drying too quickly and protects the
Technical Manual V8: TS-11A-8.00-010117
25
CHAPTER 2
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
a suitably qualified expert.
Materials iii. The materials used for construction must meet the relevant regional
i. All materials should be stored correctly in a manner that will not cause Building Regulations.
damage or deterioration of the product.
ii. All materials, products and building systems shall be appropriate and Limitations of Functional Requirements
suitable for their intended purpose. i. The Functional Requirements are limited by the recommendations
iii. The design of the structure shall, unless specifically agreed otherwise applied to the specific areas covered in this chapter.
with the warranty provider be based on an intended life of 60 years, ii. These Functional Requirements do not and will not apply to create
save that, and for the avoidance of doubt, nothing in this Technical any policy liability for any remedial works carried out by the contractor
Manual creates expressly or implicitly any ongoing responsibility for or otherwise, nor to any materials used in those remedial works.
roof coverings in this design life requirement. This is dealt with further
Technical Manual V6: TS-011a-6.00-010413
in Chapters 7.6, 7.9, 7.10, 7.11 and 7.12 relating to Roof Performance
Technical Manual V8: TS-11A-8.00-010117
Standards.
© LABC Warranty
CHAPTER 2: MATERIALS
CHAPTER 2: MATERIALS
2.3.1 Cold weather working 2.3.1.2 Protection of masonry 2.3.1.3 Finishes including rendering,
To meet the Functional Requirements of this Any new walls or other masonry construction will plastering and screeds
chapter, minimum working temperatures should require protection against frost where temperatures Rendering should only be completed if the outside
not fall below 2°C when working with masonry. are expected to drop below 2°C. Ideally, all temperature is at least 2°C; there should be no frost
It is important that during cold weather periods, masonry should be protected with polythene or within the construction that is to be rendered and,
regular temperature readings should be taken. hessian. If temperatures are expected to fall to where possible, rendering should not take place
an extremely low level, insulation boards may be where freezing weather conditions are anticipated
Thermometers should be placed away from required, and heating may even be considered. prior to adequate curing.
direct sunlight, preferably in a shaded area. When
assessing the temperature, it is also important to No plastering or screeding should take place
consider wind chill and weather exposure, and unless the building is free from frost. It is acceptable
make necessary allowances for sites that have a to use internal heating to warm the building
higher level of exposure. effectively; however, it is important to ensure that
heaters do not emit excessive vapour into the
2.3.1.1 Protection of materials dwelling. Adequate ventilation should be provided
Covers should be provided to protect materials to allow moist air to escape. The dwelling should
from frost, snow and ice, particularly bricks, blocks, be appropriately pre-heated before plastering, and
sand and cement. Frozen materials should never continue to be heated whilst the plaster dries.
be used under any circumstances.
Figure 11: Protection of masonry walls 2.3.2 Masonry
Technical Manual V8: TS-11A-8.00-010117
2.3.2.1 Bricks
Bricks should be of an appropriate durability to
meet the design intention. The type of brick to be
used will affect the specification of the mortar.
Bricks with greater durability should be used where
© LABC Warranty
CHAPTER 2
CHAPTER 2: MATERIALS
CHAPTER 2: MATERIALS
Note:
* Where S1 units are used in Class M6 mortar; sulphate resisting Portland cement should be used
in the mortar.
** Monitoring of batching is required to ensure the correct amount of cement is used to achieve
mortar strength class M4
*** Use Sulphate resisting Portland cement.
**** Sulphate resisting Portland cement is recommended in the mortar and (where in areas of severe
© LABC Warranty
Manufacturers recommendations should be check to confirm suitable for the conditions proposed.
to BS 1200
cappings and sills
Loadbearing
masonry Air entrained with plasticiser, Portland cement: lime: sand
As specified
designed to 1:1:5.5 by volume
BS 5628:1
Notes:
© LABC Warranty
CHAPTER 2
CHAPTER 2: MATERIALS
CHAPTER 2: MATERIALS
2.3.5 Suitability of materials Construction products that do not meet the Note: To determine the corrosion rates for
It is important to ensure materials used in requirements of this Technical Manual may not aluminium, copper, steel and zinc, please refer to
construction: be acceptable for Warranty approval. It is advised the standards listed above.
that the design team must approach the Warranty
• Meet the requirements of British Standards provider early in the design stage to discuss
or Codes of Practice or equivalent European the viability of the use of such a material, and
Standards current at the time of application determine what further independent third-party
• Have approval from an independent third-party testing may be required in advance of the final
technical approval body which is accepted by design proposal.
the Warranty provider. This would either be
a UKAS or European equivalent accredited 2.3.6 Corrosion protection of steelwork
organisation, such as ILAC (International Guidance for the protection of structural steel is
Laboratory Accreditation Co-operation). given in BS EN ISO 12944 ‘Paints and varnishes.
Details of the testing body accreditation will Corrosion protection of steel structures by
need to be supplied, as well as the certification protective paint systems’ and BS EN ISO 14713
document. ‘Protection against corrosion of iron and steel in
structures’.
In addition:
All metals must have a suitable protective coating
• The independent third-party testing to minimise or prevent corrosion during its life
information must recognise UK Building and be selected to comply with the appropriate
Technical Manual V8: TS-11A-8.00-010117
Regulation requirements and additional standards and with the corrosion category
Warranty standards. Details of the performance described in table 7.
and the limitations of use of the material/
product or system tested must be provided The classification of environmental corrosion
• Where bearing a CE marking in accordance conditions below has been taken from BS EN ISO
with the Construction Products Directive, this
© LABC Warranty
Corrosion Corrosion
Indoor Environment Outdoor Environment
Category C Level
Heated spaces with low relative humidity and insignificant pollution,
C1 Very Low Dry or cold zones with a very low pollution environment or times of wetness
e.g. offices, schools museums
Unheated spaces with varying temperature and humidity, low pollution
Temperate zones to dry or cold zones with a low pollution environment e.g.
C2 Low and where condensation may occur e.g. storage depots, light industry,
Rural areas and small towns more than 10km from the coast or an estuary.
sports halls
Temperate zones with a medium pollution environment or small
Spaces with moderate frequency of condensation and pollution from
effects from chlorides, e.g. Urban and industrial areas with moderate
C3 Medium production processes e.g. Residencies, food processing plants, laundries,
sulphur dioxide pollution, coastal areas and estuaries with low salinity
breweries, dairies.
(approximately 5-10km)
Temperate zones, atmospheric environment with medium pollution and
Spaces with a high frequency of condensation and pollution from
medium effects from chlorides e.g. polluted urban areas, industrial areas,
C4 High production processes e.g. Boatyards, industrial processing plants and
coastal areas and estuaries with moderate salinity (approximately 1-5km)
swimming pools
and areas exposed to de-icing salts
Spaces with very high frequency of condensation and pollution from Temperate to sub-tropical zones, high pollution area or a substantial
C5 Very High production processes, e.g. Buildings with high levels of pollution and effect from chlorides, e.g. Industrial areas, coastal areas (approximately
condensation 500m-1km), sheltered positions on the coastline (without salt spray)
Tropical zones with high sulphur dioxide pollution including the effects
Spaces with almost permanent condensation or periods of exposure to of chlorides, e.g. industrial areas with high humidity and an aggressive
CX Extreme
extreme humidity effects and with a high concentration of pollution atmosphere, coastal (approximately 0-500m) and offshore areas with high
salinity (occasional salt spray)
Table 7: Devon Building Control, c/o Teignbridge District Council, Forde House, Brunel Road, Newton Abbot, Devon, TQ12 4XX
protected steel which is then cut or drilled fire protection should be compatible with any
corrosivity of C4 or C5 to BS EN ISO 12944,
must be provided with appropriate remediation corrosion protective coating applied and the
including sites within 500m from a coastal
to the exposed parts of steel to ensure manufacturer’s guidance should be followed
shoreline (See chapter 13), should be
adequate corrosion protection is maintained. • In coastal locations (see chapter 13) Steel
galvanised to a rate of 710 g/m2.
• The designer should specify the protective lintels, used in both leaves of an external wall
• Decorative finishes must be compatible with the
© LABC Warranty
coating system where any steelwork is to be should be austenitic stainless steel and in
protective coat specification. Refer to BS EN 12944
welded. addition, protected by a separate damp proof
‘paints and varnishes: corrosion protection of steel
• Surface preparation should be to BS EN 12944-4. system / cavity tray (as described in chapter 7).
structures by protective paint systems’ and the
manufacturers recommendations.
31
CHAPTER 2
Technical Manual V8: TS-11A-8.00-010117
Technical Manual V6: TS-011a-6.00-010413
© LABC Warranty
CHAPTER 3: MODERN METHODS OF CONSTRUCTION (MMC)
CONTENTS
3.1.1 INTRODUCTION
3.1.2 SUITABILITY OF SYSTEMS AND COMPONENTS
3.1.3 TYPES OF MODERN METHODS OF CONSTRUCTION (MMC)
3.1.4 SUITABILITY OF SYSTEMS TO MEET WARRANTY REQUIREMENTS
3.1.5 INSULATED CONCRETE FORMWORK
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
33
CHAPTER 3
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in a ii. Structural elements outside the parameters of regional Approved
workmanlike manner. Documents must be supported by structural calculations provided by
iii. Certification is required for any work completed by an approved a suitably qualified expert.
installer. iii. The construction must meet the relevant regional Building
Regulations.
Materials iv. All MMC systems must be assessed and have a product approval by
i. All materials should be stored correctly in a manner that will not cause a recognised third-party assessment body.
damage or deterioration of the product.
ii. All materials, products and building systems shall be appropriate and Limitations of Functional Requirements
suitable for their intended purpose. i. The Functional Requirements are limited by the recommendations
iii. The structure shall, unless specifically agreed otherwise with the applied to the specific areas covered in this chapter.
Warranty provider, have a life of not less than 60 years. Individual ii. These Functional Requirements do not and will not apply to create
components and assemblies, not integral to the structure, may have any policy liability for any remedial works carried out by the contractor
Technical Manual V6: TS-011a-6.00-010413
3.1.1 Introduction • MMC take advantage of standardised • Carry independent third-party testing that
Modern methods of construction (MMC) are being construction, and may not be adaptable recognises UK Building Regulation requirements
used in the construction industry, particularly for for complex architectural or planning design and additional Warranty standards. Details
housing, as they potentially represent savings in requirements. Additional testing may be of the performance and the limitations of use
time and materials, and provide higher standards necessary to ensure standards for durability of the material/product or system tested must
of quality than more conventional methods of and weather tightness can be achieved, e.g. be provided.
construction. incorporating flat roof drainage outlets through • Bear (Where a corresponding Euro Standard
closed panel parapet extensions. exists) a CE marking in accordance with the
Key points to note are: Construction Products Directive. This shall be
3.1.2 Suitability of systems and components supported by evidence of testing carried out
• Off-site assembly means quick erection times It is important to ensure that MMC, products or on the product.
on-site and a quick, weather tight construction systems:
achieved. Construction methods that cannot meet the
• The accurate setting out of foundations, etc. • Meet the requirements of British Standards requirements of this Technical Manual must be
needs to be managed. or Codes of Practice or equivalent European approved in advance by the Warranty provider
• MMC, particularly modular systems and large Standards current at the time of application. at the design stage, well before commencement
panel systems, will require advanced planning • Are materials/products or systems covered by on-site.
of the site for access, off-loading, installation a current approval from an independent third-
and possibly storage of systems. party technical approval body which is MMC, products or systems that have third-party
• The construction, design and layout of a accepted by MDIS. This would be either a UKAS approval will still need to be structurally approved
typical system is planned in advance, so last- accredited or a European equivalent on a site-by-site basis depending on the layout and
Technical Manual V8: TS-11A-8.00-010117
minute changes have to be avoided by good accredited organisation, such as ILAC loading of the component. Thermal properties and
project management and what is known as a (International Laboratory Accreditation measures to prevent condensation will also require
‘design freeze’, imposed in advance of Co-operation). Details of the testing body specific assessment depending on exposure,
production commencing in the factory. accreditation will need to be supplied, together orientation, etc.
• The quality of the final product will rely on with the certification document.
accurate assembly on-site by factory-trained or
© LABC Warranty
35
CHAPTER 3
CHAPTER 3: MODERN METHODS OF CONSTRUCTION (MMC)
CHAPTER 3: MODERN METHODS OF CONSTRUCTION (MMC)
3.1.3 Types of modern methods Alternatively, traditional masonry cladding may ‘Conventional’ timber frame panels are typically
of construction (MMC) need to be constructed; in this case, specific classed as ‘open panel systems’, and would
MMC (this applies to systems and components) detailing for the support of claddings, cavity normally arrive on-site with the sheathing board
usually fall into the following categories: barriers and DPCs must be pre-agreed and fixed but without insulation or internal boards. For
checked by Site Managers. Warranty purposes, these types of open panel
• Volumetric or modular construction systems can normally be classified as established
• Panelised 3.1.3.2 Panelised or traditional construction, providing that such
• Hybrid (semi-volumetric) The panel units are produced ‘off-site’ in a factory open panel systems have quality assured
• Site-based systems under a quality controlled process, and assembled systems in place and are registered either with
on-site to produce a three-dimensional structure. the Structural Timber Association or BM TRADA
Most MMC components are usually site-based, e.g. The panels may consist of wall, floor or roof units, (see chapter 7 of this Technical Manual for
Insulated Concrete Formwork systems. sometimes referred to as cassettes. general guidance on conventional timber frame
construction).
3.1.3.1 Volumetric 3.1.3.3 Closed panels
Volumetric construction (also known as modular These involve the factory installation of lining Note: Bespoke timber frame open panel systems
construction) involves the ‘off-site’ production of materials and insulation, and may be constructed that do not have such QA procedures will need
three-dimensional units. Quality controlled systems of timber, steel frame or concrete panels. Panels either third-party accreditation or independent
of production in the factory should be in place and can often include services, windows, doors and Structural Engineer supervision to be provided to
expected as part of any third-party approval. finishes. monitor the installation, erection and completion
(sign off) of the system. (See chapter 7 Section 7.3)
Modules may be brought to site in a variety of 3.1.3.4 Open panel systems
Technical Manual V8: TS-11A-8.00-010117
different forms, ranging from a basic structural shell Open panel systems do not include insulation, Structurally Insulated Panels (SIPs) are a form of
to one where all the internal and external finishes lining boards, vapour control layers, etc. These composite panel. Only systems with independent
and services are already installed. are applied to the frame system on-site, together third-party approval will meet the requirements of
with the external cladding and internal finishing. the Technical Manual.
Volumetric construction can consist of timber Therefore, careful control of on-site finishing will
frame, light gauge steel and concrete or
© LABC Warranty
be required, and the panels must be protected Rain screen systems should have third-party
composite constructions. External cladding may against the elements until weather tight. certification confirming satisfactory assessment,
form part of the prefabricated system, with only and comply with the requirements of the CWCT
localised on-site specialist sealing required. Standard for Systemised Building Envelopes,
including the following sections:
CHAPTER 3: MODERN METHODS OF CONSTRUCTION (MMC)
CHAPTER 3: MODERN METHODS OF CONSTRUCTION (MMC)
• Part 1: Scope, terminology, testing and 3.1.3.7 Site-based systems • Structural integrity
classification These are structural systems that fall outside • Performance in fire situations
• Part 2: Loadings, fixings and movement the ‘off-site manufactured’ categories, such as • Resistance to water penetration (consider
• Part 3: Air, water and wind resistance Insulated Concrete Formwork (ICF). Only systems exposure rating of location), vapour
• Part 4: Operable components, additional with independent third-party approval will meet permeability and dangerous substances
elements and means of access the requirements of the Technical Manual. The • Safety in use
• Part 5: Thermal, moisture and acoustic acceptability of these systems relies heavily on the • Acoustic characteristics
performance quality procedures in place for the installation of • Thermal and movement characteristics
• Part 6: Fire performance the system on-site, in accordance with third-party • Compatibility of materials (interaction between
• Part 7: Robustness, durability, tolerances and approval. components, structural or otherwise)
workmanship • Durability and longevity of materials (60-year
• Part 8: Testing 3.1.4 Suitability of systems to meet lifespan in accordance with CML requirements)
Warranty requirements • Maintenance issues
3.1.3.5 Hybrid (Please also refer to the requirements in chapter 2
Again off-site manufactured, this combines of this Manual.) Structural performance must be identified against
both panelised and volumetric approaches, appropriate BS EN standards. The developer must
and typically volumetric units, e.g. student An independent third-party assessment of the provide structural calculations for each project on
accommodation or hotel pods. system/product must recognise UK Building a case-by-case basis, and the design shall allow for
Regulation requirements and our additional robustness to disproportionate collapse.
3.1.3.6 Sub-assemblies and components Warranty standards.
This category covers factory-built sub-assemblies Where the independent certification does not
Technical Manual V8: TS-11A-8.00-010117
or components in an otherwise traditionally built Details of the performance and the limitations of recognise our Warranty requirements, additional
structural form, typically schemes incorporating use of the material/product or system testing must checks may be required to confirm the system is
the use of floor or roof cassettes, precast concrete be provided to determine if the requirements of this acceptable, e.g. the need to provide a drained
foundation assemblies, preformed service Manual are met. cavity behind some insulated cladding systems
installations and cladding systems, etc. and to external cladding systems on timber and
© LABC Warranty
CHAPTER 3
CHAPTER 3: MODERN METHODS OF CONSTRUCTION (MMC)
CHAPTER 3: MODERN METHODS OF CONSTRUCTION (MMC)
Durability and weather tightness are key aspects of with a third-party assessment for a particular use For the purposes of this Technical Manual:
the Technical Manual requirements, and the track may not be acceptable in a different form of
record of the MMC will need to be established. construction. • The system proposed must have a current third
party ‘product approval’
Evidence of experience gained elsewhere, where The continuation of Quality Management Systems • ICF systems will be acceptable for a maximum
environmental conditions may be significantly from manufacture to erection on-site must be of 3 storeys in height (including the ground
different, will need to be assessed, in comparison demonstrated. The level of supervision of the floor level) and must be accompanied with a
with conditions here in the UK. systems on-site is critical to meet the requirements full structural engineers design package.
of this Technical Manual.
Treatment of timber components will need to be 3.1.5.1 Types of ICF structure:
assessed with regard to the species of timber used. 3.1.5 Insulated concrete formwork The formwork is usually one of the following four
The natural durability and the need for preservative Insulated concrete formwork (or ICF) utilizes formats; Blocks, planks, panels or composites
treatment are dependent on the component’s polystyrene (mainly) as a temporary formwork, with With planks or panels tie devices are used to
location in the construction and the Warranty concrete poured into the formwork core at staged secure the ‘outer and inner’ components together.
requirement for durability. Treatment for insect lifts to provide the structural ‘wall’ component It is expected that all ICF type structures are to
attack in certain parts of the country will also be to carry the loads of the building down to be erected by the ICF manufacturer’s approved
required. foundations, this can be both external and internal contractors.
walls.
Detailing is critical in providing integrity to the
building, e.g. connections between a wall panel The insulation form work (usually either expanded
and a window unit. Supporting documentation or extruded polystyrene (EPS or XPS)) is left in place
Technical Manual V8: TS-11A-8.00-010117
must show the make-up of the tested system. When after the concrete has cured to form a permanent
assessing projects, a particular design detail may integral part of the insulation of the building. An
not have been covered by the MMC certification, external weather proof cladding system will be
e.g. a balcony junction. This information must be required as the ICF system alone is not proven to
made known at an early stage. be resistant to weather.
© LABC Warranty
39
CHAPTER 3
Technical Manual V8: TS-11A-8.00-010117
Technical Manual V6: TS-011a-6.00-010413
© LABC Warranty
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
CONTENTS
4.1 INTRODUCTION
4.2 ROLES AND RESPONSIBILITIES
4.3 FLOW CHART OF SITE INVESTIGATION PROCESS
4.4 PHASE 1: GEOENVIRONMENTAL ASSESSMENT (DESK STUDY)
4.5 PHASE 2: GEOENVIRONMENTAL ASSESSMENT (GROUND INVESTIGATION)
4.6 MAIN REFERENCES
41
CHAPTER 4
FUNCTIONAL REQUIREMENTS
4.1 Introduction
This chapter sets out the requirements for an
acceptable site investigation. It is intended to
be flexible and user-friendly, and includes simple
checklists aimed at ensuring compliance. The aim
is to raise standards in the interests of both the
Warranty provider and the builder or developer. This
will lead to a safe and economic design that will
minimise the risk to all those involved in the project.
43
CHAPTER 4
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
4.2 Roles and responsibilities 4.3 Flow chart of site investigation procedures
The roles and responsibilities of those parties
involved in the development are the owner,
developer, builder and self-builder.
Desk Study
4.2.1 Owner/developer/builder/self-builder
See text for
The provision of clear development proposals for the sources of
Site description information
site, and the implementation of a competent site
Site history
investigation using appropriately qualified personnel, Geology and mining
Any Geoenvironmental /
Hydrogeology and flooring
is now a priority for regulators. These demonstrate Geotechnical hazards known
Environmental setting
or suspected
that any geotechnical and contaminated land risks Radon
Geoenvironmental risk assessment
can be safely dealt with. Specific Health and Safety Geotechnical assessment
responsibilities, in particular the CDM Regulations
Yes No No further action
also require compliance. None - No significant
geotechnical or
plausible pollution
4.2.2 Environmental Health/Contaminated Phase 2 Geoenvironmental Commence construction
Assessment (intrusive Ground
Land Officer or remediation
Investigation)
The provision of advice to the local Planning Refine brief and objectives
No further action
Department on technical matters and planning although an intrusive
investigation would Unforeseen hazards
conditions requires a competent and comprehensive always be advisable to
site investigation and associated risk assessment. The investigation - scope minimise later costs
and methodology
Technical Manual V8: TS-11A-8.00-010117
Phase 3 Geoenvironmental
Have the geotechnical
4.2.4 Health and Safety Executive Assessment
and geoenvironmental risks Yes
(please note: that Phase 2 can be
The HSE are responsible for health and safety at been adequately defined
preliminary investigation)
work, including the CDM Regulations.
No
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
4.4 Phase 1: Geoenvironmental The type and distribution of vegetation can 4.4.3 Site history
assessment (desk study) indicate soil and ground water conditions, and The history of the site and the surrounding areas is
note should be made of any invasive plants, such extremely important when assessing the likelihood
4.4.1 Introduction as Japanese Knotweed and Giant Hogweed. of contamination or geotechnical hazards.
The aim of the Phase 1 Geoenvironmental Adjacent features and land use should be Historical Ordnance Survey maps date back
Assessment is to identify and assess the reported if there is likely to be an impact on the to the mid-19th Century and often specify the
potential geotechnical and geoenvironmental development. It is not uncommon for features such actual industrial use of particular sites or buildings.
(contamination) hazards on the site. Since all sites as tanks to be known about but unrecorded. They may show areas of quarrying or infilling,
are different, it is important to identify the scope and indicate where buried obstructions, such as
and purpose of the desk study. This will include The walkover should note any potential sources underground tanks or old foundations, can be
who commissioned the work, the development of contamination and geotechnical hazards, expected.
proposals, the relevant procedures followed and such as slopes, excavations, land slipping, ground
the objectives. Any issues specifically excluded subsidence, soft ground or desiccated/shrinkable The influence or impact of off-site past industrial
should also be noted if these might normally be soils. use will depend upon the type of industry, the
expected as part of the desk study. underlying geology and the topography. However,
All structures on the site should be inspected consideration should normally be given to any
4.4.2 Site description both internally and externally for any evidence such features within a 250m radius of the site (or
The site description should define the exact extent of structural damage, such as tilting, cracking or further where appropriate) with the potential to
of the site, and should include a site address, grid chemical attack. Any evidence of underground affect it.
reference and elevation. The boundaries and features should be noted. Where practical, the
topography of the site should be also defined. local residents can often give valuable information, Historical maps are available from libraries and
Technical Manual V8: TS-11A-8.00-010117
although caution should be used in respect of their commercial providers, such as Ground Sure or
A site inspection should always be carried out ‘memories’. Local place names can give useful Envirocheck. The latter provide a cost-effective
not only of the site itself, but also the immediate indications of former uses, e.g. Gas Works Lane, method of obtaining maps, and include the
surrounding area. This should include any Water Lane, Tannery Road, etc. Aerial photographs ability to superimpose current site boundaries on
information not apparent from the maps and and their interpretation can also prove helpful. older maps. Issues regarding possible breaches
describe what currently occupies the site, such as
© LABC Warranty
CHAPTER 4
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
taken when interpreting what may have occurred likely ground conditions should be given, together deposits) are commonly found in chalk, caused by
in the intervening years. For example, a quarry may with reference to any other mapped geological water draining through the chalk and dissolving it.
be shown on one map and infilled on the next. features, particularly if there are likely to be any The risk of solution features should be addressed
However, in the intervening period, it could have natural cavities or solution features. in the site investigation report (commonly from an
expanded prior to infilling; similarly, industrial uses Envirocheck or Ground Sure report on geological
may not always be recorded while many military or 4.4.4.1 Mining areas hazards, both on site and locally).
sensitive uses may have been omitted. Other sources In former coalfields, or other areas of mineral
of information may include the ubiquitous internet extraction, the maps may not always record the Hazard maps are available with different coloured
search and historical aerial photographs. Additionally, presence of old or active workings.The likelihood of areas representing different levels of risk. Where the
it may be necessary to search the libraries of Local shallow coal workings affecting surface stability should risk is moderate or high, special precautions should
Authorities and Local History departments. be established in conjunction with a Coal Authority be taken, which for strip foundations would include
report. Such reports also record areas that have been careful inspection of the excavation, probing and
4.4.4 Geology and mining affected by the extraction of brine, which is particularly use of reinforcement to span potential voids.
The geology of the site should be recorded by prevalent in the Cheshire area. Other forms of mineral
reference to published geological maps, which extraction will require site-specific research. Where piled foundations are used, CIRIA PR 86
most commonly exist at 1:50,000 (1 inch to 1 recommends “that a CPT (Cone Penetration
mile) and 1:10,000 (6 inch to 1 mile). The British The potential for mine workings and mine entries Test) is undertaken at each pile location at sites
Geological Survey Geo-Index also provides existing within an influencing distance of the proposed identified during desk studies to be prone to
ground investigation records, including logs and development should be addressed by a suitably dissolution”. Alternatively, in some instances it can
reports. It should be noted that these records qualified and experienced engineer prior to be appropriate to design the pile for shaft friction
can relate not only to the surrounding areas but commencement of works, and in accordance with alone, assuming that the pile has no end bearing
Technical Manual V8: TS-11A-8.00-010117
may also include previous investigation of the CIRIA SP 32: Construction Over Abandoned Mine due to a solution feature below it. In extreme
site itself. The information on the geological maps Workings, 2002. circumstances where a site investigation borehole
can also be supplemented with British Geological has encountered an extensive solution feature, the
Survey technical reports, flood risk appraisals and Reference should be made to reports on shaft friction may also be reduced to take account
memoirs. geological hazards, such as Envirocheck or Ground of this.
© LABC Warranty
CIRIA C574: Engineering in Chalk, 2002 gives the lies on a Principle Aquifer and/or Source Protection Current industrial operations rarely provide a risk
following recommendations: Zone, which are both susceptible to pollution of of pollution to a site. Pollution is most likely to have
ground water. The presence of surface water features been caused by historical activities and processes
Concentrated ingress of water into the chalk can and drainage should be described, and the overall that were often deemed normal practice in the past,
initiate new dissolution features, particularly in risks of flooding to the site should be determined, but which are considered unacceptable today.
low-density chalk, and destabilise the loose backfill primarily with reference to the Environment Agency In this regard, the past history is invariably highly
of existing ones. For this reason, any soakaways flood map data and Local Authority-commissioned significant in respect of possible ground pollution.
should be sited well away from foundations for Strategic Flood Risk Assessments. Flood risk data
structures or roads, as indicated below: is continually being updated by the Environment The site should be considered in relation to
Agency and Local Authority. any designated environmentally sensitive sites,
• In areas where dissolution features are known such as Special Areas of Conservation, Special
to be prevalent, soakaways should be avoided Any ground water or surface water abstraction Protection Areas, Nature Reserves and Sites of
if at all possible but, if unavoidable, should be points ‘downstream’ of the site, particularly any Special Scientific Interest. In particular, could
sited at least 20m away from any foundations potable (drinking water) abstraction points, should contamination on the site be affecting such
• Where the chalk is of low density, or its density is be recorded, as this may have liability implications sensitive areas, whether these are on or adjacent
not known, soakaways should be sited at least should the development cause any pollution. to the study site?
10m away from any foundations.
• For drainage systems, flexible jointed pipes 4.4.6 Environmental setting Data relating to current industrial licensing,
should be used wherever possible; particular The question as to whether a site poses an actual consents and the like, together with information
care should be taken for the avoidance of leaks or potential environmental risk, or is at some relating to environmentally sensitive sites, is typically
in both water supply and drainage pipe work. external risk from pollution, will be determined by available through commercial data suppliers.
Technical Manual V8: TS-11A-8.00-010117
• As the chalk is a vitally important aquifer, the its environmental setting. This will in turn depend As with the historical maps, this is usually a cost-
Environment Agency and Local Authority upon the site’s topography, geology, hydrogeology effective method of obtaining data.
must be consulted when planning soakaway and hydrology, amongst other site-specific
installations where chalk lies below the site, considerations. For both the historical maps and datasets, there is
even where it is mantled with superficial usually little or no interpretation of the information, and
deposits.
© LABC Warranty
It is necessary to consider other potential sources it is essential that this interpretation is carried out by
of contamination, such as pollution control an experienced and qualified individual. Automated
4.4.5 Hydrogeology and flooding licenses, discharge consents, hazardous sites risk assessments do not include appraisal by qualified
The assessment should include the flood risk and (COMAH, NIHHIS), pollution incidents, landfills, waste staff, and should therefore be viewed with caution and
hydrogeology of the site, particularly whether the site treatment sites and past and current industrial sites. are not usually acceptable to Regulators. 47
CHAPTER 4
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
4.4.7 Radon
The need to incorporate Radon protection
measures should be determined by reference
to risk maps produced by the Health Protection
Agency. Such information is also usually included
within commercially available datasets.
4.4.8.1 Human health all combustible. Both underground fires and 4.4.8.3 Natural environment
(pathways 1 - 5, receptors A - C) biodegradation of organic materials may produce (pathway 6, receptors D - E)
There is an uptake of contaminants by food plants toxic or flammable gases. Methane and other
grown in contaminated soil. The uptake will depend gases may explode if allowed to accumulate in Phytotoxicity (prevention / inhibition of plant growth)
on their concentration in the soil, their chemical confined spaces. Some metals essential for plant growth at low levels
form, soil pH, plant species and prominence in diet. are phytotoxic at higher concentrations. Methane
4.4.8.2 Buildings (pathways 7 and 8) and other gases may give rise to phytotoxic effects.
Ingestion and inhalation
Substances may be ingested directly by young Fire and explosion Contamination of water resources
children playing on contaminated soil if they Underground fires may damage services and Soil has a limited capacity to absorb, degrade
eat plants that have absorbed metals or are cause ground subsidence and structural damage. or attenuate the effects of pollutants. If this is
contaminated with soil or dust. Ingestion may Accumulations of flammable gases in confined exceeded, polluting substances may enter surface
also occur via contaminated water supplies. spaces leads to a risk of explosion. and ground waters.
Metals, some organic materials and radioactive
substances may be inhaled from dusts and soils. Chemical attack on building materials Ecotoxological effects
and services Contaminants in soil may affect microbial, animal
Skin contact Sulphates may attack concrete structures. Acids, and plant populations. Ecosystems or individual
Soil containing tars, oils and corrosive substances oils and tarry substances may accelerate the species on the site, in surface waters or areas where
may cause irritation to the skin through direct corrosion of metals or attack plastics, rubber and migration has occurred may also be affected.
contact. Some substances, e.g. phenols, may be other polymeric materials used in pipework and
absorbed into the body through the skin or through service conduits or as jointing seals and protective For any contaminant source identified, judgement
Technical Manual V8: TS-11A-8.00-010117
cuts and abrasions. coatings to concrete and metals. is required to assess the probability of a pollution
linkage occurring and the potential consequences
Irradiation Physical of that linkage. Based on the probability and likely
As well as being inhaled and absorbed through Blast-furnace and steel-making slag (and some consequences, the overall risk (significance) can
the skin, radioactive materials emitting gamma natural materials) may expand. Degradation of fills be established.The definitions that are used for this
rays can cause a radiation response.
© LABC Warranty
may cause settlement and voids in buried tanks, purpose should be clearly stated.The probability of a
and drums may collapse as corrosion occurs or hazard, combined with its consequences, can be used
Fire and explosion under loading. to assess risk, and this forms the so-called Conceptual
Materials such as coal, coke particles, oil, tar, Site Model.This is in accordance with the Statutory
pitch, rubber, plastic and domestic waste are Guidance for Contaminated Land (Defra 2006). 49
CHAPTER 4
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
The following tables may be used to explain the Final overall risk is based on an assessment of in respect of the geotechnical matters set out
decision-making process: probability of a hazard and its consequences. below:
Risk categories are shown shaded in the table
Damage to human health above and defined below: Are normal to deep strip footings
Substantial pollution of controlled waters likely to be suitable or might piling or
Severe Foundations ground improvement be necessary?
Significant change in ecosystem population
Risk Description of risk levels Will made ground, old foundations,
Irreparable damage to property
cellars or services be encountered?
Non-permanent damage to human health Site probably or certainly unsuitable
for present use or environmental Will the possibility of shallow mine
Minor pollution of controlled waters Mining and
Moderate setting. Contamination probably or workings or quarrying on the site
Change in ecosystem High quarrying
certainly present and likely to have need to be addressed?
Damage to property an unacceptable impact on key Are soakaways likely to be suitable
Short term health effects targets. Urgent action needed. based on the mapped geology?
Slight pollution of controlled waters Site may not be suitable for present Soakaways (Actual on-site permeability tests
Mild would need to be carried out to
Slight effect on ecosystem use or environmental setting.
Medium / Contamination may be present, and determine suitability or not.)
Minor repairable damage to property
Moderate likely to have unacceptable impact hat is the sub-grade strength (CBR)
No noticeable effect on human health
on key targets. Action may be likely to be? (The actual design will
No significant pollution to controlled waters Roads
Near zero needed in the medium term. be dependent on the CBR measured
No measurable effect on ecosystem densities. on-site.)
Site considered suitable for present
Non-structural cosmetic damage to property use and environmental setting. Will soft ground plant be suitable
Contamination may be present Excavations or will rock breakers be needed for
Table 1: Consequences of pollution linkage
Low
but unlikely to have unacceptable deeper excavation?
impact on key targets. Action Groundwater Is shallow groundwater expected?
unlikely to be needed in present use.
Probability Are any significant earthworks
Consequences of a pollution linkage Earthworks
of a Site considered suitable for present anticipated?
(hazard-pathway-target)
hazard use and environmental setting.
and an Contamination may be present Will gas protection measures be
Technical Manual V8: TS-11A-8.00-010117
associated Severe Moderate Mild Near zero Negligible but unlikely to have unacceptable Gas protection required or would they be prudent in
linkage impact on key targets. No action accordance with good practice?
Very Medium Low / needed while site remains in present
High High use. Table 4: Geotechnical assessment – preliminary indicators
High / Low Negligible
Low /
Medium High Medium Low Table 3: Overall risk
Negligible
High / Medium
© LABC Warranty
Low Low Negligible The above can only be provided on the basis of
Medium / Low
4.4.9 Geotechnical assessment limited site data, and it is recommended that the
High /
Medium Although no intrusive investigation may have been
Unlikely Medium
/ Low
Low Negligible scope of any intrusive ground investigation is set
/ Low carried out on the site at the desk study stage, it out here if the desk study is to be presented as a
Table 2: Decision making should be possible to give preliminary indications stand-alone document.
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
4.5 Phase 2: Geoenvironmental • BS EN 1997-1: 2004 Eurocode 7 – Geotechnical 4.5.2.2 Window sampling
assessment (ground investigation) design – Part 1: General rules Window sampling consists of driving a series of
• BS EN 1997-2: 2007 Eurocode 7 – Geotechnical 1m and 2m long tubes into the ground using
4.5.1 Pre-ground investigation design – Part 2: Ground investigation and testing a dropping weight. On completion of each
The initial investigation should comprise a desk • BS 5930: 2015 and BS 10175: 2001 run, the tube is withdrawn. The next tube is then
study as described in section 4.3 of this chapter. inserted and the process repeated to provide a
It will also require the full-time supervision of a continuous profile of the ground. On each run, the
4.5.2 The investigation Chartered Geologist or Chartered Engineer. tube diameter is reduced in order to assist in its
After the desk study has been carried out, the recovery. When complete, the borehole is normally
objective of the intrusive investigation is to provide The dates of the investigation and the methods backfilled. It is also possible to carry out standard
detailed information for the safe and economic used should be stated, with the exploratory hole penetration tests (SPT) using the window sampling
development of the site at minimum cost. Clearly, positions being shown on a drawing. equipment.
no guarantee can be given that all relevant
conditions will necessarily be identified, but the An intrusive investigation may comprise the 4.5.2.3 Shell and auger boring
work carried out should be aimed at reducing risk following: This technique uses a tripod winch and a
to acceptable levels. percussive effect with a variety of boring tools,
4.5.2.1 Trial pitting where disturbed and undisturbed samples can
Increasing expenditure on the site investigation Normally, these should be at least three times the be taken. This is the most suitable method for soft
will reduce the risk of unforeseen conditions, but foundation depth where possible, or sufficient ground investigation as it enables the maximum
professional judgement and experience is also to prove competent bedrock. They should be amount of information to be obtained. However,
required. Not all forms of investigation will be excavated outside proposed foundation positions minor changes in lithology may be overlooked
needed, and that which is necessary in the best
Technical Manual V8: TS-11A-8.00-010117
where possible. On completion, the excavations unless continuous undisturbed sampling is used.
interests of the client should be carefully assessed are normally backfilled.
for each individual project. Disturbed samples of soils can be taken for
This method enables soil conditions to be closely identification and classification purposes. In
The investigation must be designed to provide the examined at any specific point and samples to cohesive soils, ‘undisturbed’ samples 100mm in
appropriate level of information on ground and
© LABC Warranty
be taken. It also gives useful information on the diameter can be taken by an open drive sampler
ground water conditions on the site, together with stability of excavations and water ingress. In-situ for laboratory testing of strength, permeability and
identifying potential areas of contamination. The gas, strength and California Bearing Ratio (CBR) consolidation characteristics.
investigation should be undertaken in accordance tests can also be carried out.
with the principles of:
51
CHAPTER 4
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
SPT are used in granular and cohesive materials 4.5.2.5 Geophysics manual identification as per recognised descriptive
and in soft or weathered rocks. The resulting ‘N’ Geophysics can be used in certain situations and methods. The methodology for soil and rock
value can be compared to empirical data on is useful where significant anomalies exist in the description is given in more detail in Appendix B.
strength and relative density. Difficulties in obtaining ground. Ground-penetrating radar is probably the
true ‘N’ values mean they should only be used as a most common for defining near-surface features. 4.5.5 In-situ and laboratory testing
guide, and not as an absolute value in foundation The results from geophysics can be variable and,
design. combined with the relative high cost, should be 4.5.5.1 In-situ gas monitoring
used advisedly. Methane is the dominant constituent of landfill
4.5.2.4 Rotary drilling gas, and can form an explosive mixture in air at
Two main types of rotary drilling can be carried out 4.5.3 Strata profile concentrations of between 5% and 15%. Thus, 5%
in rock. Rock coring using a diamond or tungsten Full strata descriptions should be given based on methane in air is known as the Lower Explosive
carbide-tipped core bit provides samples and visual identification and in accordance with the Limit (LEL). Concentrations less than this do not
information on rock types, fissuring and weathering. requirements of: normally ignite. Carbon dioxide can also be a
Open-hole drilling only produces small particles potential problem, especially where it occurs in
for identification purposes, and the information • BS EN ISO 14688-1: 2002 Geotechnical concentrations greater than 1.5%.
gained is therefore limited. The latter is, however, investigation and testing – Identification and
useful as a quick method of detecting major strata classification of soil – Part 1 In-situ gas tests should be carried out in the
changes and the location of coal seams and old • BS EN ISO 14688-2: 2004 Geotechnical boreholes on completion, and in probe holes
workings. Water, air, foam or drilling muds may be investigation and testing – Identification and made in the sides of the trial pits. Testing is with a
used as the flushing medium in either case. classification of soil – Part 2 portable meter that measures the methane content
• BS EN ISO 14689-1: 2003 Geotechnical as its percentage volume in air. The corresponding
Technical Manual V8: TS-11A-8.00-010117
Rotary open-hole drilling is carried out to determine investigation and testing – Identification and oxygen and carbon dioxide concentrations are
the existence of any voids or broken ground that classification of rock – Part 1 also measured. Care is needed with this, since the
could affect surface stability. Due to the risk of rapid mixing and dilution of any gases within the
combustion, the drilling is normally done using 4.5.4 Soil description atmosphere can occur very quickly.
a water flush. On completion, the boreholes are Samples from boreholes or trial pits should be fully
backfilled with bentonite cement. A Coal Authority
© LABC Warranty
described in accordance with the latest guidance A more accurate method used to monitor over the
Licence is required in advance of any exploratory from the British Standards and Eurocodes. They longer term consists of gas monitoring standpipes
work intended to investigate possible coal should include colour, consistency, structure, installed in boreholes. These typically comprise
workings. weathering, lithological type, inclusions and origin. slotted UPVC pipework surrounded by single sized
All descriptions should be based on visual and gravel. The top 0.5m to 1m of pipework is usually
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
not slotted and is surrounded by bentonite pellets intersecting permeable soils or naturally occurring including the presence of Volatile Organic
to seal the borehole. Valves are fitted and the fissures within bedrock. Compounds (VOCs). Samples should be selected
installations protected by lockable stopcock covers from the trial pits and boreholes based on those
normally fitted flush with the ground. Monitoring is Soakaway testing involves filling the trial pits with most likely to be contaminated, and those that
again with a portable meter and is usually done water from a bowser or such like, and measuring will give the most appropriate indication of the
on a fortnightly or monthly basis, with at least six the fall in water over time. Where possible, two spread of any contaminants. The samples should
visits being appropriate for most sites. tests should be carried out to allow the immediate be stored in either glass or plastic containers
surrounding ground to become saturated. and where necessary kept in cooled conditions.
The risks associated with the gases should be By knowing the dimensions of the trial pit, the Testing should be carried out by a UKAS accredited
considered in accordance with documents permeability and/or rate of dissipation can be laboratory, in accordance with the Environment
such as: calculated. Agency’s Monitoring Certification Scheme; MCERTS
performance standards.
• BS 8485: 2015 Code of Practice for the Soakaway test results obtained from small
characterisation and remediation from ground hand-dug pits or shallow boreholes should be The aim of this is to make a preliminary assessment
gas in affected developments treated with caution. of the level of any contamination on the site, in
• CIRIA Report C665 Assessing risks posed by order to determine if there are any significant risks
hazardous ground gases to buildings 4.5.5.4 Geotechnical laboratory testing associated with contaminants in respect of both
• NHBC Report No. 4 Guidance on evaluation of Soil testing should be carried out to BS 1377: human health and the environment, including
development proposals on sites here methane 1990 Methods of test for soils for civil engineering controlled waters. In addition to the soil, ground
and carbon dioxide are present purposes, and the laboratory used should be water samples should be tested where appropriate.
recorded and conducted by an approved UKAS
Technical Manual V8: TS-11A-8.00-010117
4.5.5.2 In-situ strength testing laboratory. Normally, the results are summarised 4.5.6 Geoenvironmental risk assessment
Hand vane and MEXE cone penetrometer tests and the full results appended; a summary of the (conceptual site model)
can be carried out in trial pits in order to assess the main types of test is presented in Appendix C. The qualitative health and environmental risk
strengths and CBR values of made ground, soils assessment carried out as part of the desk study
and heavily weathered bedrock materials. 4.5.5.5 Contamination laboratory testing should be revised, based on the findings of
© LABC Warranty
As with the investigation, the sampling should be the ground investigation and the results of the
4.5.5.3 Soakaway testing under the full-time direction of either a Chartered contamination testing, to produce a Detailed
If sustainable drainage is being considered, Engineer or Chartered Geologist. All the recovered Quantitative Risk Assessment (DQRA).
soakaway testing should be carried out. This soil samples should be screened on-site for any
is preferably done in trial pits, with the aim of visual or olfactory evidence of contamination, 53
CHAPTER 4
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
The DQRA is again based on the conceptual site Source Potential pollutant Pathways Receptor Risk
model, and might look similar to the following A. Present occupants Site unoccupied
example summary of hazards, pathways and Low risk involved with excavation
receptors. On sites with known contamination, work, provided personnel adopt
B. Ground workers
suitable precautions, together with
further investigation and testing may be necessary, 1-5
washing facilities
together with recommendations for remediation Low risk for residential use,
C. Future residents /
and its validation. provided made ground is capped
occupants
Potentially by clean subsoil and topsoil
4.5.7 Construction contaminated made Low to moderate risk at present.
Oils, fuels, grease,
ground Provided on-site monitoring
During construction, if unforeseen conditions are hydraulic fluid, metals,
asbestos undertaken throughout the piling
Possible past minor D. Controlled waters
encountered then the builder/developer should and ground work phases of
spillages and metals 6 development shows no adverse
seek additional advice from the consultant as effects, the risk will be low
to whether the new conditions will affect the Low risk as leaching is not a
E. Ecosystems
continued development of the site, and whether problem
any additional investigation or testing is necessary. Low to moderate. Install pipes
F. Building materials in clean bedding materials.
7
and services Adequate precautions to be taken
4.5.8 Recommendations in respect of buried concrete
The report must include a site location plan and a Low to moderate. Low values of
ground gases present during
plan showing any special features plus borehole Organic Landfill gases, radon,
8 A-F the investigation, although basic
material VOCs, SVOCs
and trial pit locations (factual reports will describe gas protection measures are
recommended
the work carried out, and will include borehole/trial
All waste materials to be removed
pit logs and the results of all in-situ and laboratory Waste materials Fly-tipping
Technical Manual V8: TS-11A-8.00-010117
from site
testing, but there will be no interpretation of the
data and no recommendations). Table 5: Example detailed quantitative risk assessment
© LABC Warranty
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
• Normal strip or deep trench footings BS 3882: British Standard Specification for Topsoil
• Piling BS 5930: British Standard Code of Practice for Site Investigations, 1999
• Vibro replacement
BS 8485: British Standard Code of Practice for the characterisation and remediation from ground gas in
• Raft foundation affected developments, 2007
• Building near trees
BS 10175: British Standard Code of Practice for the Investigation of Potentially Contaminated Sites, 2001
• Landfill and Radon gas British
Standards
• Existing drains and services Institution
BS EN 1997-1: 2004 ‘Euro-Code 7 – Geotechnical Design – Part 1: General Rules’
• Road construction
BS EN 1997-2: 2007 ‘Euro-Code 7 – Geotechnical Design – Part 2: Ground Investigation and Testing’
• Sustainable surface water drainage
BS ISO 14688-1: 2002 ‘Geotechnical Investigation and Testing – Identification and Classification of Soil –
(soakaways)
Part 1’
• Excavations and ground water
• Reuse of materials BS ISO 14688-2: 2004 ‘Geotechnical Investigation and Testing – Identification and Classification of Soil – Part 2’
• Contamination BS ISO 14689-1: 2003 ‘Geotechnical Investigation and Testing – Identification and Classification of Rock –
• Capping mine shafts Part 1’
Radon: Guidance on protective measures for new dwellings, BR 211
• Site soil reuse
• Slope stability and retaining walls Protective measures for housing on gas-contaminated land, BR 414, 2001
• Further geotechnical considerations BRE
Cover systems for land regeneration, 2004
Technical Manual V8: TS-11A-8.00-010117
• Change of use
Concrete in aggressive ground. Special Digest SD1, 3rd Edition, 2005
CIEH The LQM / CIEH Generic Assessment Criteria for Human Health Risk Assessment (2nd Edition)
Advice in respect of specific recommendations is
Assessing risks posed by hazardous ground gases to buildings, CIRIA C665
given in Appendix A.
CIRIA Shaft friction of CFA piles in chalk 2003, CIRIA PR 86
Engineering in chalk 2002, CIRIA C574
© LABC Warranty
DoE Waste Management Paper No. 26A ‘Landfill completion: A technical memorandum…’
CHAPTER 4
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
• Register of abandoned mine plans and • Local history records, books and photographs Boreholes
opencasts (where relevant and practicable) • Cable percussive, window sampling, dynamic
• Shaft register • Aerial photographs (where relevant) probing or rotary drilling to BS 5930
• Other mining, e.g. Sand, sandstone, limestone, • Archaeological register (where relevant) • Use of British Drilling Association accredited
brine, etc. drillers
Contamination • Full description of ground and ground water to
Geology • Likely contaminants based on past history BS 5930
• Geological maps (1:50,000 and 1:10,000 scale) • Hazard-Pathway-Receptor scenario • Installations for long-term gas and water
• Memoirs • Preliminary Conceptual Site Model monitoring (if required)
• Technical reports • Geotechnical laboratory testing (BS 1377) and
• Engineering geological maps Environmental database contamination testing if suspected by
• Existing trial pit or borehole logs and reports • Operational and former landfill sites, scrapyards accredited laboratories
• Subsidence features and waste processing sites
• Radon protection measures Other methods of investigation
Hydrogeology and hydrology • Geophysics
• Ground water vulnerability Checklist for Phase 2: Geoenvironmental • Cone penetrometer
• Aquifer status assessment (ground investigation)
• Abstraction licences (within 1km) Recommendations for reports
• Flood risk, drainage and watercourses (within 1km) Trial pits
• Strata profile and description Foundations and retaining walls
Local Authority consultation • In-situ gas testing for methane, carbon dioxide • Foundation type, depth, bearing capacity
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 4
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
Mining Earthworks
• Precautions for foundations in respect of past • Compaction characteristics
or future mining • Surcharging and self-settlement
• Treatment of shallow mine workings • CBR at formation level
• Capping of shafts • Slope stability and slope stabilisation
• Suitability of excavated material for re-use
Landfill/mine gas/Radon
• Requirements for long-term monitoring Contamination
• Protection measures for structure • Full assessment of contamination testing
• Venting measures • Hazard-Pathway-Target scenarios/conceptual
model
Road construction • Risk assessment and liability
• CBR of subgrade and its preparation • Precautions or remediation of contamination
• Sub-base type and thickness
• Excavation of unsuitable material Further investigation
• Soil stabilisation • Is further investigation needed?
• Frost susceptibility • Nature of further investigation
APPENDIX B Fine soils can also be classified according to their iii. Matrix
sensitivity, which is the ratio between undisturbed iv. Weathering
Soil and rock descriptions and remoulded undrained shear strength:
Term Description
Sensitivity Ratio No visible sign of weathering /
Fine soils (cohesive soils) Fresh
alteration of the rock material.
Low 8
The following field terms are used: The colour of the original fresh
Medium 8 - 30 rock material is changed
High >30 with evidence of weathering
Soil Type Description / alteration. The degree of
Quick >50
Very soft Exudes between fingers change from the original
Discoloured
colour should be indicated.
Soft Moulded by light finger pressure
Granular soils (non-cohesive) If the colour change is
Cannot be moulded by the fingers but confined to particular mineral
Firm
can be rolled in hand to 3mm threads The following descriptions are used for granular constituents, this should be
Crumbles and breaks when rolled to 3mm soils: mentioned.
Stiff
threads but can be remoulded to a lump The rock material is broken up
Description Normalised blow count (N1) 60
No longer moulded but crumbles under by physical weathering, so that
Very stiff Very loose 0-3 bonding between grains is lost
pressure. Can be indented with thumbs
Loose 4-8 and the rock is weathered /
Disintegrated altered towards the condition
Medium 9 - 25
The following terms may be used in accordance of a soil, in which the original
Dense 26 - 42 material fabric is still intact. The
with the results of laboratory and field tests: Very dense 43 - 58 rock material is friable but the
grains are not decomposed.
CHAPTER 4
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
vii. Unconfined compressive strength viii. Structure xii. Rock mass permeability
Note:
Completely All rock material is decomposed and/or disintegrated to soil. The original mass structure is
4
weathered still largely intact
(a) Some extremely weak rocks will behave as soils and should All rock material is converted to soil. The mass structure and material fabric are destroyed.
Residual soil 5
© LABC Warranty
be described as soils. There is a large change in volume, but the soils have not been significantly transported
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
APPENDIX C and becomes friable. The moisture content of the soil Bulk density
at this point is known as the ‘plastic limit’ of the soil. The bulk density of a material is the weight of that
Laboratory testing material per unit volume, and includes the effects
The water content range over which a cohesive soil of voids whether filled with air or water. The ‘dry
Natural or in-situ moisture content behaves plastically, i.e. the range between the liquid density’ of a soil is defined as the weight of the
The natural or in-situ moisture content of a soil and plastic limits, is defined as the plasticity index. solids contained in a unit volume of the soil.
is defined as the weight of water contained in
the pore space, expressed as a percentage A cohesive soil with natural water content towards Permeability
of the dry weight of solid matter present in the its liquid limit will, in general, be an extremely soft The permeability of a material is defined as the rate
soil. Soil properties are greatly affected by the material, whereas a cohesive soil with natural water at which water flows through it per unit area of soil
moisture content and the test can help provide an content below its plastic limit will tend to be a firm under a unit hydraulic gradient.
indication of likely engineering behaviour. or stiff material.
Consolidation characteristics
Liquid and plastic limits Particle size distribution When subjected to pressure, a soil tends to
Two simple classification tests are known as Knowledge of particle size distribution is used consolidate as the air or water in the pore
the liquid and plastic limits. If a cohesive soil is to classify soils and indicate likely engineering space is forced out and the grains assume a
remoulded with increasing amounts of water, a behaviour. more densely packed state. The decrease in
point will be reached at which it ceases to behave volume per unit of pressure is defined as the
as a plastic material and becomes essentially a British Standards define soils in relation to their ‘compressibility’ of the soil, and a measure of the
viscous fluid. The moisture content corresponding particle size, as shown below: rate at which consolidation proceeds is given by
to this change is arbitrarily determined by the liquid Coarse sand the ‘coefficient of consolidation’ of the soil. These
Technical Manual V8: TS-11A-8.00-010117
limit test. ‘Fat’ clays, which have a high content of Boulders 2mm - 0.63mm two characteristics, Mv and Cv, are determined
colloidal particles, have high liquid limits; ‘lean’ >200mm Medium sand in the consolidation test, and the results used to
Cobbles 0.63mm - 0.2mm
clays, having low colloidal particle content, have calculate settlement of structures or earthworks by
200mm - 63mm Fine sand
correspondingly low liquid limits. An increase in the 0.2mm - 0.063mm a qualified person.
organic content of clay is reflected by an increase Coarse silt
Coarse gravel 0.063mm - 0.02mm
in the liquid and plastic limits.
© LABC Warranty
63mm - 20mm
Medium silt
Medium gravel 0.02mm - 0.0063mm
If a cohesive soil is allowed to dry progressively, a 20mm - 6.3mm
Fine silt -
point is reached at which it ceases to behave as a Fine gravel 0.0063mm - 0.002mm
6.3mm - 2m
plastic material, which can be moulded in the fingers, Clay <0.002mm 61
CHAPTER 4
CHAPTER 4: SITE INVESTIGATION REPORTS, GEOLOGY AND CONTAMINATION
CHAPTER 4: SITE INVESTIGATION REPORTS , GEOLOGY AND CONTAMINATION
Strength characteristics The undrained triaxial test gives the apparent California Bearing Ratio (CBR) Test
The strength of geological materials is generally (cohesion) Cu and the angle of shearing (resistance) In flexible pavement design, knowledge of the
expressed as the maximum resistance that they Øu. In dry sands, Cu = 0 and Øu is equal to the bearing capacity of the sub-grade is necessary
offer to deformation or fracture by applied shear angle of internal friction, whereas with saturated to determine the thickness of pavement for
or compressive stress. The strength characteristics non-fissured clays Øu tends to 0 and the apparent any particular combination of traffic and site
of geological materials depend to an important cohesion Cu is equal to one-half the unconfined conditions. The quality of the subgrade can
degree on their previous history and on the compression strength qu. On site, the vane test gives be assessed by means of the CBR test, or
conditions under which they will be stressed in an approximate measure of shear strength. approximately by the MEXE cone penetrometer.
practice. Consequently, it is necessary to simulate
in laboratory tests, the conditions under which the For some stability problems, use is made of a Chemical tests
material will be stressed in the field. variant of the undrained triaxial test in which the Knowledge of the total soluble sulphate content
specimen is allowed to consolidate fully under the and pH of soils and ground water is important in
In general, the only test carried out on hard rocks hydrostatic pressure, and is then tested to failure determining the protection required for concrete
is the determination of their compressive strength, under conditions of no moisture content change. or steel in contact with the ground. Other specialist
but consideration must also be given to fissuring, This is known as the consolidated undrained triaxial tests may be carried out on sites suspected of
jointing and bedding planes. test. Pore water pressures may be measured during being contaminated by toxic materials.
this test, or alternatively a fully drained test may
The tests currently used for soils and soft rocks fall be carried out. In either case, the effective shear
into two main categories. First, those in which the strength parameters C’ and Ø’ can be obtained,
material is stressed under conditions of no moisture which can be used to calculate shear strength at
content change, and second, those in which any given pore water pressure.
Technical Manual V8: TS-11A-8.00-010117
equilibrium) tests. The tests are normally carried factors can be studied in compaction tests, which
out in the triaxial compression apparatus, but can determine the maximum dry density (MDD)
granular materials may be tested in the shear box achievable at a certain optimum moisture content
apparatus. (OMC).
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
CONTENTS
5.1 GROUND IMPROVEMENT
5.2 FOUNDATIONS, TREES AND CLAY
5.3 STRIP AND MASS FILLED FOUNDATIONS
5.4 PILED FOUNDATIONS
5.5 RAFT FOUNDATIONS
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
63
CHAPTER 5
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Site investigation by an appropriately qualified person should be
a workmanlike manner. supplied and provide the following information:
iii. Ground improvement schemes should be appropriately tested a. Depth of original soil types below the structure.
to confirm that the completed works meet design specifications. b. Details of any filled ground and its suitability to accept ground
The testing regime must be agreed with the Warranty Surveyor prior to improvements techniques.
commencement of work. c. Gas generation or spontaneous combustion from ground
iv. The developer shall ensure that adequate quality control procedures conditions.
are in place. The quality control must identify that site work meets the The investigation must be endorsed by the Specialist Foundations
design intention. All procedures should be auditable and available for Contractor.
inspection. iii. Structural elements outside the parameters of Approved Document
A (England and Wales) must be supported by structural calculations
Materials provided by a suitably qualified expert.
i. All materials should be stored correctly in a manner that will not cause iv. The ground improvement works must meet the relevant regional
Technical Manual V6: TS-011a-6.00-010413
Building Regulations.
ii. All materials, products and building systems shall be appropriate and
suitable for their intended purpose. Limitations of Functional Requirements
iii. The structure shall, unless specifically agreed otherwise with the i. The Functional Requirements are limited by the recommendations
Warranty provider, have a life of not less than 60 years. Individual applied to the specific areas covered in this chapter.
components and assemblies, not integral to the structure, may have a ii. These Functional Requirements do not and will not apply to create
© LABC Warranty
lesser durability, but not in any circumstances less than 15 years. any policy liability for any remedial works carried out by the contractor
or otherwise, nor to any materials used in those remedial works.
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
5.1.1 Introduction 5.1.3 Vibratory ground improvement Dry bottom feed method
Ground improvement enables sites with poor load- The dry bottom feed method is used in weaker soil
bearing capacity to be strengthened, meaning 5.1.3.1 Introduction conditions or where there is a high water table and
the loadings of the proposed building can be Vibro displacement using vibro stone columns is the borehole is liable to collapse between vibroflot
adequately supported off suitable foundations. a method of enhancing ground bearing capacity insertions. The vibroflot penetrates using its mass, air
The guidance detailed in this chapter will be and limiting settlement. Typical applications flush and vibration, but at design depth, the stone
accepted as a satisfactory method of meeting include the support of foundations, slabs, hard is introduced via a hopper into a pipe fixed to the
the Functional Requirements. standings, pavements, tanks or embankments. side of the vibroflot. The stone usually 40mm in size,
Soft soils can be reinforced to achieve improved exits the pipe at the tip of the vibroflot and reaches
5.1.2 Limitations of guidance specification requirements, whilst slopes can be the bottom of the borehole. The stone is then
The following situations are beyond the scope of treated to prevent slip failure, both natural soils and compacted into the surrounding soil by repeated
the guidance in this chapter: made ground can be improved. withdrawal and insertion of the vibroflot.
• Where the original ground or sub-strata is Vibro treatment should be carried out in
unstable or will continue to settle. accordance with the ‘Institute of Civil Engineers:
• Sites with soft clays with a low bearing capacity 1987 Specification for ground treatment: Notes for
(30kN/m2 undrained). guidance’ and to a depth sufficient to reach an
• Filled ground where high levels of voids are adequate bearing stratum.
anticipated.
• Clay fill, where the water will influence the 5.1.3.2 Vibratory techniques
foundation or where collapse may occur. The vibratory process is applied to weak natural
Technical Manual V8: TS-11A-8.00-010117
in the UK. These are known as the ‘dry bottom feed’ the weak soil or fill again using its mass, air flush
and ‘dry top feed’ methods; a third technique, and vibration to form a borehole. Once refusal or
less frequently used in the UK, is known as the ‘wet design depth is reached, the vibroflot is removed
bottom feed’ method. and stone fill is introduced into the bore, the
‘charge’ is typically 500mm - 800mm deep. 65
CHAPTER 5
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
The vibroflot is re-inserted and ‘packs’ the stone into Wet bottom feed method first establish whether there are any contaminated
the surrounding strata. Successive charges of stone Where the ground contains fines and silts, water substances or gases present. Data should be
are added and compacted bringing the column jetting from the tip of the vibroflot is used to remove gathered using a suitable method for comparison
up to working level. Typically the stone grading is loose materials and form a cavity for charges of with the site post treatment. Investigations should
40mm - 75mm. stone to be added to replace and densify the be made into the presence, level and nature of
soft ground. The carbon footprint of this activity is any ground water, and if it is likely to rise and cause
generally less than for comparable piling solutions. heave or collapse by saturation.
5.1.3.3 Suitability of ground conditions The extent of any areas of made-up ground on the
Through the process of a site investigation, it should site should be established, including:
first be established by the appointed engineer
or suitably qualified specialist that the ground is • The proportions, compaction and distribution of
capable of being improved by a vibratory ground constituent materials throughout its depth.
improvement technique. The site investigation should • The grading and particle size distribution of
determine the depths and properties of the natural fill materials.
materials under the site, including the presence of • The potential for gas generation from fill materials,
cavities, mines, rocks or soils that may dissolve or and the risk of combustion of natural deposits.
Figure 2: Vibratory techniques: dry top feed method erode when water passes over them. It should also
be established at an early stage whether the site The appointed specialist contractor should be
has previously contained any buildings or structures, satisfied that the site investigation report provides
and whether they have been completely removed, adequate and representative information in order
Technical Manual V8: TS-11A-8.00-010117
including basement walls, floor slabs, etc. The to design the ground improvement. The results of the
presence and extent of any existing or redundant investigation should be presented to the Warranty
services and drains should be investigated, and the Surveyor prior to the commencement of the work.
associated backfill to the excavations. In addition,
the effect that any proposed sustainable drainage The developer shall obtain written confirmation
© LABC Warranty
system (SuDS) might have on the ground conditions from the engineer and specialist contractor
should be identified. that the site is suitable for the proposed ground
improvement system, and that all detrimental
The engineer should supervise the site investigation, factors associated with the site and the proposed
Figure 3: Vibratory techniques: wet bottom feed method taking account of the findings of the desk study, and development have been taken into account. This is
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
to be made available to the Warranty Surveyor prior movements can occur. Engineered fill should • A well-constructed excavation, safely executed,
to the commencement of any work on the site. be designed and placed in accordance with with all soft and hard spots removed, and made
recognised good practice, as noted in references reasonably dry and well drained.
Site workmanship at the end of this section. • Sound fill without undesirable material and
The specialist contractor should appoint an capable of compaction as specified, provided
engineer to supervise the vibratory foundation Engineered fills used to produce suitably shaped with starter and capping layers as necessary.
works at all times and ensure that: landforms for structures should be constructed • Placement and compaction to ensure that the
to high standards to minimise the risk of ground performance of the fill will meet required criteria
• The required depth and bearing capacity of movements causing damage to property built on as a foundation fill.
stone columns are achieved. shallow foundations. • Appropriate monitoring; the designer must
• The stone columns are correctly located ensure that all work can be carried out
beneath the proposed foundation and in In designing and specifying a fill to form a safely as required by the Health and Safety
accordance with design drawings. foundation for buildings, the following technical Executive Construction Design and
requirements should be established: Management Regulations.
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 5
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
5.1.4.2 Fill selection walls. Where possible though, granular soils should If the fill is too wet, there could be excessive
Fill should be clearly categorised into material that be used as general fill since these materials drain consolidation settlement, and if the fill is too dry, it
may and may not be used: unsuitable fill, general readily and consolidate quickly. The smaller the might be vulnerable to collapse compression.
fill, restricted fill and special fill. Fill materials must predominant particle size, the longer the potential
not present an environmental or health hazard. time required for consolidation under the self- 5.1.4.4 Placing engineered fill
weight of the fill. A successful engineered fill requires not only an
Unsuitable fill should not be used at any location appropriate specification but also adequate control
on the site. 5.1.4.3 End product criteria during placement. All the work must be carried
The greatest threats to successful in-service out with due regard to safety, as required by the
General fill is all material except that which is performance are: Construction Design and Management Regulations.
unsuitable, restricted or special, and is normally
the majority of the material used. It may include • Collapse settlement due to inundation of dry 5.1.4.5 Site preparation and disposition of fill
natural soils as well as some waste products. or inadequately compacted fills. The site should be cleared of all topsoil and other
• Excessive consolidation settlement of wet unsuitable material.
Restricted fill is material that would be general fill compressible fill.
except that it contains minerals hostile to the built • Heave or settlement of clay fill due to Soft spots and hard spots, such as derelict
environment. It can include natural materials such climatic changes or vegetation. foundations, should be removed, together with ponds
as pyritic shales, sulphate-bearing clays and waste and surface water from depressions. Removing water
materials, including burnt colliery discard and steel These ground movements depend on moisture by pumping may be necessary when filling some
slag. Its use is precluded where ground water could movement, so by reducing the voids in a fill, the excavations below the ground water level.
rise to the underside of the deepest foundation, or opportunities for excessive in-service movements
Technical Manual V8: TS-11A-8.00-010117
where it is rejected for pollution reasons. For some should be restricted. A maximum allowable air- When a variety of material types are used as fill,
developments, such as housing with gardens, voids content of 5% is a suitable criterion for most they should be deposited in horizontal layers
restricted fills would include fills that are harmful clay fill. However, specifying 5% air-voids content is across the site. If there is only a limited amount
to people. insufficient, as this value may easily be achieved of good granular material, it will be best to use it
by adding water to the fill without increasing in layers interspersed between layers of poorer
Special fill is high-quality material, such as well-
© LABC Warranty
Feather-edges, resulting in foundations set partly areas form part of a development, they need less the possibility of insufficient strength and high
on fill and partly on natural ground, should be compaction than the load-bearing areas. There compressibility. It will be difficult to achieve air-voids
avoided, and the site worked in such a way that should be a transition zone around the load- content of 5% or less when the moisture content
structures are located either directly on natural bearing area, as shown in Figure 5. is low. In the same way that the addition of too
ground or directly over fill of a consistent thickness. much water can detract from the performance of
5.1.4.6 Fill placement engineered fill, soil can be over-compacted.
If fill is to be placed over sloping natural ground, Fill should be placed in horizontal layers, with each
some stepping of the ground may be necessary. layer separately compacted. For a given item of Granular soils and cohesive soils drier than
Construction over the face of a quarry or an plant, compaction performance will be determined optimum, when rolled excessively, become over-
opencast mining high wall should be avoided. by fill layer thickness, fill moisture content and the stressed, and what should have been a firm
number of passes of the compaction equipment. compacted surface becomes a loose tilth. This
Special measures may have to be taken by There are, however, other factors such as the need should be avoided whenever possible. Where a
providing flexible connections for services at to avoid excessive handling. fill containing a large proportion of fine grained
the location of high walls and by thickening cohesive material (for example, clay) is used, filling
construction for service and estate roads. Whenever possible, site trials should be undertaken during wet weather should be avoided.
to determine the correct criteria. Some general
If the natural ground on which the fill rests is soft information about placing fills is given in BS 6031. 5.1.4.7 Quality control
and compressible (for example, layers of peat Each layer should be of a thickness that allows the Quality control procedures should be implemented
or soft clay), the surface of the fill may settle compactive energy to spread throughout the layer, to ensure compliance with the specification. The
appreciably and unevenly as a result of the weight producing the specified fill density and low air-voids nature of the control procedure will depend on the
of the fill consolidating the soft layers below. This content. Loose layers with a thickness greater than type of specification adopted. The end product
Technical Manual V8: TS-11A-8.00-010117
settlement will, of course, be additional to that 250mm are unlikely to be satisfactory for earth fills specification requires an appropriate type and
resulting from the compression of the fill itself. compacted to support low rise structures. quantity of testing of the fill during placement
to ensure that the desired end product is being
Sensitive structures may warrant a surface (or It may be necessary to use layers of 200mm or achieved. Depending upon the type of contract,
capping) layer formed from special fill compacted less. Moisture content at the time of placing a quality control may be the responsibility of the
to more onerous standards than the underlying fill.
© LABC Warranty
fill is fundamental to subsequent performance, engineer or of the contractor working under the
This should help minimise the differential settlement particularly where the fill contains a large supervision of the engineer. Control parameters
suffered by the structure. proportion of fine grained cohesive material. If should be the same as those determined during
the fill is too dry, there is the possibility of heave the site investigation stage. Both design and control
Where landscaped or other non load-bearing or collapse settlement; if it is too wet, there is parameters must be reproducible, a term that 69
CHAPTER 5
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
denotes the range within which measurements It is important for the method of testing to be
made on the same fill by different operators using strictly specified. Where a cohesive fill contains
different equipment should agree. gravel, it may not be possible to obtain sufficiently
undisturbed samples for strength tests. On larger
The following are the most significant control sites, employing in-situ methods, such as the
parameters: cone penetrometer (BS 1377: Part 9), could be
considered.
• Moisture content, in respect of an optimum
moisture content established at the site Small sites are generally more difficult to work than
investigation stage. large sites, as finished work may be damaged
• Dry density, in respect of the already established more easily in confined working areas and
maximum dry density. deficiencies in site preparation usually reflect more
• Air-voids content, which depends on moisture readily in poorer quality compaction than on larger
content and dry density. sites. Consequently, it is necessary to test more
• Undrained shear strength, which is an frequently on a small site than on a large one. Figure 6: Number of tests
applicable approach. For cohesive soils, undrained testing may be required. Tests in visually doubtful operation. The required documentation includes:
shear strength forms an alternative basis for areas, and re-tests of failed areas, should be
specification and control testing. carried out in addition to those recommended in • Summary of the specification requirements
Figure 6. and the end product in terms of the selected
However, different methods of measuring the geotechnical parameters for the various fills
undrained shear strength, such as the unconfined
© LABC Warranty
• Suitability test results for each borrow pit. Surface levelling stations are easy to install and 5.1.5.1 Plate tests
• List of the required control tests. very effective. By optical levelling of the stations, This test will not determine the design but will allow
• Results of the control tests on each fill type, layer measurement can be made of the total vertical for an assessment of the workmanship on the
or area, as appropriate. movement of the fill upon which they rest, together stone columns. Plate tests should be carried out on
• A list of post-compaction monitoring with any movement of the underlying natural stone columns or treated ground at a frequency of
requirements. ground, although this is unlikely to be large if all soft at least one test per day per rig.
• The results of post-compaction monitoring; all material has been removed prior to compaction.
completed forms should be signed and dated The plate tests should be carried out with a
by the person responsible, and a list prepared Levelling stations should be sufficiently robust to 600mm diameter plate and minimum test load
of any required action or remedial work to be resist damage due to construction traffic. A round of 11 tonnes.
carried out. headed bolt cast into a 1m concrete cube set
300mm into the fill has been found to be effective. 5.1.5.2 Mini zone tests
5.1.4.8 Monitoring of fill performance Magnet extensometers are unlikely to be necessary A mini zone test (dummy footing) can be used as
Monitoring provides a check on the performance in shallow-depth fill. Standpipes or piezometers will a limited substitute for zone tests. The test should
of the fill after compaction, and is particularly be of advantage if there is reason to suspect that be applied to at least two stone columns and the
important where vulnerable structures are to be built ground water will rise into the fill at any time in the area of foundation they support. To be useful, mini
or foundation loading is unusually large. It is also future, with consequent settlement. zone tests should be continued for long enough to
required where the fill is relatively deep or substantial establish the presence of creep behaviour.
ground water rise within the fill is expected. 5.1.5 Testing
Testing is carried out to confirm that the ground Mini zone tests (dummy footing) should be carried
Monitoring techniques include: improvement works meet the design criteria. The out at a rate of one test per 1000m2–3000m2 of
Technical Manual V8: TS-11A-8.00-010117
tests are usually completed to determine the treated ground, along with penetration tests at a
• Surface levelling stations to measure the ground bearing capacity. rate of one test for 20–50 stone columns, or one test
settlement of the fill surface. for not more than 500m2 of treated ground, with a
• Magnet extensometers to measure the The engineer shall require the specialist contractor minimum of one test per structural unit.
settlement of incremental depths of fill. to verify that the ground treatment has been
• Standpipe piezometers to measure the rise in the Alternatively, in the absence of penetration tests,
© LABC Warranty
CHAPTER 5
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
5.1.5.3 Zone tests 5.1.6 Fill materials 5.1.8 Suitable foundations for sites
An isolated pad or strip footing is used to test up to The following materials require testing to ensure with improved ground
eight stone columns and the intervening ground. their suitability for use as fill to support structural Foundations on sites with improved ground should
Loadings, which should simulate the dwelling loads, foundations and slabs, or as backfill to associated either be of a reinforced strip or raft type. Both
are held for 24 hours at predetermined stages to trenches: foundations will require a full design by a Structural
examine creep behaviour. Engineer.
• Acid wastes
5.1.5.4 In-situ tests • Reactive materials For ‘low rise structures’, the foundations should
Where vibration will improve the ground itself, • Materials that include sulphates (e.g. gypsum) be designed to ensure a maximum settlement of
e.g. granular materials, then in-situ testing is • Organic materials 25mm is not exceeded. In relation to differential
appropriate. The improvement can be assessed • Toxic materials settlement, a design limit for maximum tilt of 1/500
when the test results are compared with the in-situ • Materials that cause noxious fumes, rot, undue is appropriate. More stringent values may be
test results recorded during the pre-treatment settlement or damage to surrounding materials required due to the particular circumstances (e.g.
investigation. medium and high rise structures).
The sample tests should be carried out by a
5.1.5.5 Trial pits suitably qualified person, and it may be necessary Functional Requirement 5.2 must be met where
Trial pits can be excavated around trial stone to take a number of samples to identify the the foundations are bearing on cohesive soils or
columns to prove that they are fully formed and material characteristics of the fill accurately. cohesive fill materials and trees nearby.
to the required depth and diameter. This is a
destructive test, and allowance should be made 5.1.7 Sources of fill material 5.1.9 Relevant British Standards and
accordingly. Where the material is of a stable and uniform guidance documents
Technical Manual V8: TS-11A-8.00-010117
type from one source, the testing regime may be Relevant British Standards, Codes of Practice and
On completion of the treatment, the engineer is reduced. However, if the material is variable or from authoritative documents include:
to confirm that the treated ground has achieved a number of sources, then regular inspections
the anticipated condition assumed in the design, and/or testing may be required. Recycled • BS 6031 Code of Practice for earthworks
and provide evidence in writing to the Warranty aggregate or other building materials, such as • BS 1377: Part 9 Methods of tests for soils for civil
Surveyor.
© LABC Warranty
crushed brick, should only be used following an engineering purposes. In-situ tests
inspection by the Warranty Surveyor. Colliery shale • BS 10175 Investigation of potentially
and any other residue from mineral extraction or contaminated sites – Code of Practice
industrial process bi-products should only be used • BS EN 1991 Actions on structures
with specialist approval.
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
73
CHAPTER 5
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance;
ii. All work is to be carried out by a technically competent person in ii. Foundation type and depth must be suitable to resist movement due
a workmanlike manner. to the influence of nearby trees.
iii. Strip foundations should be of a suitable depth in order to achieve iii. Structural elements outside the parameters of Approved Document
a satisfactory level of performance. A (England and Wales) must be supported by structural calculations
provided by a suitably qualified expert.
Materials iv. The design and construction of the foundations must meet
i. All materials should be stored correctly in a manner that will not cause the relevant regional Building Regulations
damage or deterioration of the product.
ii. All materials, products and building systems shall be appropriate and Limitations of Functional Requirements
suitable for their intended purpose. i. The Functional Requirements are limited by the recommendations
iii. The structure shall, unless specifically agreed otherwise with applied to the specific areas covered in this chapter.
the Warranty provider, have a life of not less than 60 years. Individual ii. These Functional Requirements do not and will not apply to create
components and assemblies, not integral to the structure, may have a any policy liability for any remedial works carried out by the contractor
Technical Manual V6: TS-011a-6.00-010413
5.2.1 Introduction extends below the foundations, they will subside or The extent of risk depends on:
This chapter gives guidance on foundation design heave respectively. If the movements are in excess
when building near trees. The details described of those that can be tolerated by the building, • The soil
in chapter 5 will be accepted as a satisfactory damage is likely to occur. • The potential for the tree species to cause soil
method of meeting the Functional Requirements. drying
Although all vegetation can cause soil drying, • The size of the tree
5.2.2 Limitations of guidance the roots of trees extend deeper and further and • The proximity of the tree to the foundations
The following situations are beyond the scope of are thus particularly prone to causing damage. • The likely climatic conditions in the locality
the guidance in this chapter, and will require a Large shrubs can also root to considerable depths,
site-specific assessment by a suitably qualified and but their influence is more localised. Herbaceous These factors are considered in greater detail in the
experienced expert: plants and grass can also cause soil drying down following sections.
to 1.5m, and require some precautions.
• Foundations with depths greater than 2.5m 5.2.4 The soil
within the influence of trees Damage is best avoided by increasing foundation Soils may be broadly classified into two types:
• Ground with a slope greater than 1:7 depth to below the level where significant changes
• Manmade slopes, such as embankments and in moisture content are likely to occur. Root barriers • Cohesive soils comprise mainly of clay or fine
cuttings are not acceptable as an alternative solution. silt particles. When moist they are plastic and
• Underpinning can be moulded, and will remain intact if
• Engineered foundation designs This chapter defines the depths that are required, placed into water. As they dry, they will become
and the most suitable types of foundations. stiffer, and will eventually crumble if dried
Each development site has its own specific The extent of soil drying can be variable and beyond a certain point. These soils can
Technical Manual V8: TS-11A-8.00-010117
characteristics, and where conditions do not unpredictable. If all risk of damage is to be potentially cause problems.
clearly fall within the guidance given, clarification avoided, the required depths would be punitive; • Non-cohesive soils, comprised mainly of sand
should be sought from the Warranty Surveyor or a instead, the guidance seeks to minimise the risk by or with only a proportion of clay or silt, cannot
suitably qualified expert. striking a balance between the extent of risk and be moulded and will break up if placed in
the costs of increasing foundation depth. water. They are not subject to significant swelling
5.2.3 The nature of the problem
© LABC Warranty
or shrinkage.
The roots of all vegetation take water from the soil
to make good the water lost from the leaves. If the
soil contains clay, it will shrink as it is dried, or swell if
it is allowed to rehydrate. If the shrinking or swelling 75
CHAPTER 5
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
The clay component of cohesive soils can vary 5.2.5 Potential of the tree species to cause 5.2.6 Size of tree
widely, very few soils are pure clay but they soil drying The amount of water taken by the roots relates to
contain varying quantities of sand or silt. Clay soils Tree species differ in the ability of their roots to the leaf area and the vigour of the tree. With open
are defined by their particle size (less than two grow and exploit the available water in a cohesive grown trees, height is usually considered the best
microns), and it is only these clay particles that soil, particularly if it has high clay content. This is indicator of leaf area. The greatest water uptake
will shrink or swell. The particles are made-up of a commonly referred to as their ‘water demand’. occurs as the tree reaches maturity, and so ‘mature
complex molecular lattice structure that is capable Species such as Oak, Poplar and Eucalyptus height’ is the determining factor. Individual trees
of absorbing water, and as it absorbs water the are deemed as high water demand as they are within a group or row will have a smaller leaf area,
particles will swell, and vice versa. There are many particularly efficient at exploiting clay soils, rooting but as they compete with each other, the mature
different types of clay with different molecular to considerable depth. A few species only rarely height of the individual trees remains the relevant
structures, and all of which have different swelling cause damage and are deemed of low water factor.
characteristics. The extent of swelling and shrinkage demand, whilst the majority fall into the moderate
that can occur will therefore depend on the type category. Although some trees are managed as pollards or
of clay particles and the proportion of clay, as are subject to periodic reduction to control their
opposed to silt or sand, within the soil. Hardwood species tend to have a broad spreading size, unless such treatment can be assured in the
root system, extending considerable distances future, mature height should be used.
The potential of soil to swell or shrink can be laterally as well as to depth. By contrast, the
determined by simple tests to determine its plastic influence of most conifers is more localised, but just 5.2.7 Proximity
limit (the moisture content below which it changes as deep. A few species (of both hardwoods and The closer the tree, the deeper the potential
from being plastic and mouldable, and starts to conifers) have intermediate characteristics. The influence, and the guidance indicates the required
crumble) and liquid limit (the moisture content guidance takes account of the different patterns foundation depth at any distance. The parts of the
Technical Manual V8: TS-11A-8.00-010117
above which it changes from being plastic, and of rooting, but it must be emphasised that the foundations closest to the tree require the greatest
starts to flow like a liquid). The plastic and liquid distribution of roots can be variable, meaning the depth, but if preferred can be stepped down for
limits can be determined by simple laboratory guidance should not be taken as indicating a more distant parts.
tests in accordance with BS 1377. The difference ‘zone of influence’ of a tree.
between the plastic and liquid limits is the plasticity
© LABC Warranty
5.2.8 Likely climatic conditions the soil strata, but specialist site investigation Science and Plants for School (particularly useful
Weather conditions play a major role in reports are preferred if available. for winter identification, using twig characteristics)
determining the extent of soil drying. Hot sunny www-saps.plantsci.cam.ac.uk/trees/index.htm
weather will increase the rate of water uptake Soil samples should be taken from at least two
by the roots, whereas rainfall during the summer depths, at 1.5m and 2.5m (or the base of the trial If a tree cannot be identified, it must be assumed
can restore the water that has been taken. As the hole, whichever is the shallower), and sent to a to have high water demand (deep rooting).
hottest and driest conditions tend to be in South soil laboratory for determination of plastic and
East England, it has the greatest risk. For other, liquid limit (and thus plasticity index). In addition, 5.2.9.3 Mature height of tree
wetter, parts of the country, the guidance allows for the moisture content of the samples is usually The mature heights of common tree species are
reducing the required foundation depth. determined. The highest value of plasticity index provided in our online foundation depth calculator.
should be used for determining foundation depth. (See the introduction pages of this Technical
5.2.9 Information required for determining Manual for the website details).
the foundation depth 5.2.9.2 Identification of trees
Many local authorities will require a Tree Survey Mature height should be used unless:
5.2.9.1 Establishing ground conditions and Arboricultural Method Statement as part of
The British Geological Survey website the planning application. This will usually serve • An Arboricultural report is obtained, indicating
(www.bgs.ac.uk) can indicate the likely soil to identify all relevant trees both on and off-site. that a lesser height is appropriate for the
conditions in any locality. Enter the postcode to If a tree survey is not available, assistance with conditions of the site.
locate the site, and a left click on the location identification of all of the more common trees can • Assurance can be provided that the tree will be
brings up a box that shows the bedrock geology be obtained from various websites: maintained at a lesser height at all times in
and the superficial deposits (if present). The name future.
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 5
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
5.2.9.5 Regional and climatic conditions 5.2.10.2 Foundation depths to allow for future 5.2.11 Woodlands, groups or rows
The foundation depth calculator (see 5.2.10.1) tree planting with mixed species of trees
will allow for regional and climatic conditions Where there is a landscape plan specifying Foundation depth should be determined on
by entering the details of the post code of the future tree planting, foundation depths should be the basis of the individual tree that requires the
proposed site. calculated on the basis of the proposed species greatest depth.
of tree and its proximity. If no species has been
5.2.10 Determining foundation depth specified, they should be assumed to be moderate 5.2.12 Foundation design
water demand.
5.2.10.1 Foundation depth calculator 5.2.12.1 Depths in excess of 2.5m
Foundation depth can be determined using the Even if no tree planting has been specified, it is Where the required foundation depths, as
foundation depth calculator found on our website. advisable to allow for reasonable future tree or determined in chapter 5.3, are in excess of 2.5m,
The depth of foundation is determined by inputting shrub planting, or for the growth of self-seeded foundations must be designed by a suitable
the; trees or shrubs, as shown in column 2 of Table 1. expert, i.e. a Chartered Structural Engineer, taking
account of the likely effect of soil movement on
• Plasticity index of soil (see chapter 5.2.1) If the building design or location is such that no the foundations and substructure. Short bored
• Tree type (this will determine the water demand tree planting is likely at any time in the future, piles with ground beams are recommended, and
of the tree) minimum foundation depths, as shown in column 3 may prove to be the most economical form of
• Mature height of the tree will automatically of Table 1 should be used. construction. Short bored piles are an essential
be determined. requirement for depths in excess of 3m.
• Distance of the relevant tree to the nearest part Minimum depth
Minimum depth if
to allow for
of foundations and distances elsewhere if Plasticity no future tree/ 5.2.12.2 Foundation depths less than 2.5m
reasonable future
index shrub planting
Technical Manual V8: TS-11A-8.00-010117
stepping foundations (see chapter 5.2.4) tree/shrub Conventional strip foundations may be
likely (m)
• Allowance for climatic conditions (see chapter planting (m) constructed practically and economically
> 40 1.5 1.0
5.2.9.5) to a maximum depth of 1.5m. However, strip
20 – 40 1.25 0.9
foundations will not be suitable where heave
10 - 20 1.0 0.75
precautions are required (see 5.2.12.3). In this
situation Mass concrete fill or piled foundations
© LABC Warranty
Trench fill foundations are likely to be most be capable of compressing to allow for lateral Depth of void
economic at depths below 1.5m, but can be swelling, in accordance with column 3 of Table 2. below the
underside
economic to depths up to 2.5m. Ground bearing slabs should not be used in of edge
Thickness of
ground conditions where heave can occur or beam or floor
void against
Plasticity Required construction
For foundation depths in excess of 2m, short bored where the foundation depth is greater than 1.5m. index of foundation
side of
(mm) (or
foundation
piles with ground beams are recommended. All Under these circumstances, a suspended floor soil depth (m)
or ground
minimum
resulting
pile designs should be undertaken by a suitable construction should be used (e.g. cast in-situ beam (mm)
thickness of
expert, i.e. a Chartered Structural Engineer. concrete, precast concrete or timber). This must compressible
material / void
incorporate either a clear minimum void of a
former
Structural raft foundations are not accepted as specified depth under the suspended floor or a > 2.5 Engineer design
a suitable foundation on sites with a high risk of proprietary compressible material / void former > 40 2.0 – 2.5 35 100
shrinkage/heave due to adjacent trees. below the underside of the floor construction. Note 1.5 – 2.0 25 75
the compressible material / void former must have > 2.5 Engineer design
5.2.12.3 Heave precautions a third party approval for use in this situation. 20 – 40 2.0 – 2.5 25 75
Allowance must be made for the probability that 1.5 – 2.0 25 50
any existing tree is likely to die sometime during The depth of the void should be in accordance 2.0 – 2.5 - 50
< 20
the life of the building. If the tree has dried the soil with Table 2, or if a compressible material is used, < 2.0 No special precautions
prior to the foundations being laid, when it dies (or it should be capable of compressing to provide
Table 2: Minimum void dimensions for foundations, ground beams
becomes over-mature) the soil will rehydrate and a void of this thickness. The manufacturer’s and suspended floor slabs
swell, causing upward or lateral heave movement specifications must be checked to establish the
of the foundations. Severing roots within the actual thickness of compressible material required
Technical Manual V8: TS-11A-8.00-010117
footprint of a building foundation will also allow the to both accommodate movement and be able to
soil to rehydrate. compress to the dimensions in Table 2.
CHAPTER 5
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
Typical foundation designs to allow for heave are 5.2.13 Special situations
shown in Figures 8–10.
5.2.13.1 Trees removed prior to construction
If trees have been removed prior to construction,
precautions must be taken against potential
rehydration and swelling of the soil. If they have been
removed within 12 months of the foundations being
laid, the design should be drawn up as if the tree was
still present. If the height of the former trees is known,
the depth should be determined using actual height.
If the identity is not known, it should be assumed to
be of high water demand, and if height is not known,
it should be assumed to be 20m.
Depth of void
below the
underside
of edge
Figure 8: Heave protection: section through a typical mass filled Thickness of
Time beam or floor
foundation void against
since construction
Technical Manual V8: TS-11A-8.00-010117
Plasticity side of
tree (mm) (or
index foundation or
felled minimum
ground beam
(years) resulting
(mm)
thickness of
compressible
material / void
former)
© LABC Warranty
2-3 35 100
>40
4-5 25 75
20-40 2-3 25 75
5.2.13.2 Sloping sites 5.2.13.4 Varying foundation depths heave protection. It is also important to establish
If the slope is greater than 1:7, foundations should As foundation depth depends on the proximity the depth of the made-up ground, because if it is a
be engineer-designed (see chapter 5.1.2). For slopes of the tree, the depth can be reduced in steps relatively shallow depth, the original soil below may
less than 1:7, distance should be measured down the with increasing distance. Steps should be in be cohesive and within the zone of influence of the
angle of the slope. If there is a retaining wall, include accordance with chapter 5.3 of this Manual. tree.
the height of the retaining wall in the distance.
5.2.13.5 Protection for drains 5.2.15 Strip or trench fill foundations in
In addition to the requirements of chapter 9 of this non-shrinkable soils overlying
Manual, drainage near trees should incorporate shrinkable soils
additional provisions. Where there is a volume If non-shrinkable soils, such as sand and gravels,
change potential within the ground, the provisions overlie shrinkable clays, increased foundation
include: depths are not required if the depth of the non-
shrinkable soil is greater than 0.8 of the depth that
• Increased falls to cater for any ground would be required for the underlying shrinkable soil.
movement. See Figures 12 and 13 for further clarification.
• Deeper and wider backfill of granular material.
Figure 11: Measuring foundation distance on sloping sites
• A drainage system that is capable of
5.2.13.3 Changes in level movement should heave and shrinkage occur;
Changes in ground level (either raising or lowering • Drainage pipes should not be encased in
soil levels) beneath the branch spread of the tree can concrete.
damage the tree, and should be avoided if possible. • Additional clearance is required where drains
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 5
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
iii. Strip foundations should be of a suitable depth in order to achieve a suitably qualified expert.
a satisfactory level of performance. iii. Strip foundations must meet the relevant regional Building Regulations
© LABC Warranty
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
5.3.1 Introduction For ‘low rise structures’, the foundations should 5.3.5 Foundation depths
Strip and mass filled foundations are usually the be designed to ensure a maximum settlement of The depth of all foundations should be determined
most simplistic and cost-effective foundation for 25mm is not exceeded. In relation to differential by specific site conditions. All foundations must
low rise buildings on original ground, and the settlements, a design limit for maximum tilt of bear onto virgin stable subsoil and, except where
guidance in chapter 5.3 provides details of how to 1/500 is appropriate. More stringent values may be strip foundations are founded on rock, the strip
meet the Functional Requirements. required due to the particular circumstances (e.g. foundations should have a minimum depth of
medium and high rise structures). 450mm, measured from finished ground level
5.3.2 Limitations of guidance to their underside, to avoid the action of frost.
The following situations are beyond the scope of 5.3.4 Minimum foundation dimensions This depth, however, will commonly need to
the guidance in this chapter: Strip foundations should be of a 600mm minimum be increased in areas subject to long periods
width for external walls. For single leaf internal walls of frost or in order that loads are transferred to
• Traditional strip and mass filled foundations for up to 150mm thick, foundations may be reduced suitable ground. Where trees are situated close to
buildings other than dwellings. in width to 450mm. The minimum thickness of strip a proposed building founded on a clay soil, the
• Dwellings greater than three storeys. foundations should be 150mm. Foundations should foundation depth/design will be affected; further
• Foundations on filled ground. be situated centrally below the wall. guidance is available in chapter 5.2.3.
• Strip and mass filled foundations where
foundation depths exceed 2.5m. In clay soils with a plasticity index greater than or
equal to 10%, strip foundations should be taken to
5.3.3 Design a depth where anticipated ground movement will
Strip and mass filled foundations shall be designed not impair the stability of any part of the building,
to ensure that the building is appropriately taking into account the influence of vegetation
Technical Manual V8: TS-11A-8.00-010117
supported at all times without excessive settlement. and trees on or adjacent to the site. The depth
This foundation type should only bear onto original to the underside of foundations on clay soils
ground if the foundation has been designed by a should not be less than 750mm, as measured from
Structural Engineer and is appropriately reinforced. finished ground level, and depths may need to
It is therefore important that site conditions are be increased in order that loads are transferred to
appropriately assessed prior to the building design.
© LABC Warranty
CHAPTER 5
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
Volume change Minimum 5.3.6 Setting out foundations Where the depth of trench fill foundations is in
Modified
potential 40% foundation The accuracy of setting out foundations should be excess of 2.5m, they must be designed by a
plasticity index
and greater depth (m)
checked by set controlled trench measurements, Chartered Structural Engineer in accordance with
40% and greater High 1.0
including their location relative to site borders current British Standards and Codes of Practice.
>20% - <40% Medium 0.9*
and neighbouring buildings. Levels should be For trench fill, it is imperative to check that the
<20% Low 0.75
checked against benchmarks, where appropriate. finished foundation level is correct and horizontal.
*If the modified plasticity index is not confirmed minimum In particular, for excavations check: It will be difficult to adjust for discrepancies in the
foundation depths should be 1m.
small number of brick courses between foundation
• trench widths and DPC level.
Table 5: Minimum foundation depths
• trench lengths
• length of diagonals between external corners Prior to concreting, excavations should be
‘bottomed out’ to remove any debris that may
Walls should be located centrally upon the have fallen into the trench; the excavations should
foundation, unless specifically designed otherwise. be free from water, and if it has been left open for
Any discrepancy in dimensions should be reported a long period of time, further excavation may be
promptly to the designer. Resulting variations required to a non-weathered strata.
should be distributed to all concerned with site
works, including the Warranty Surveyor. Note: It is important that Health and Safety
obligations are met and that excavations are
5.3.7 Excavations appropriately supported to prevent collapse.
Excavation should be to a depth that gives
Technical Manual V8: TS-11A-8.00-010117
spots, the engineer’s advice should be taken prior 5.3.11 Standards referred to:
to placing the concrete. • BS 8004 Code of Practice for foundations
• BS 5950-1 Structural use of steelwork in buildings
5.3.9 Foundation joints • BS 6399 Loadings for buildings
If construction joints are necessary, they should not • BS 8103 Structural design of low rise buildings
be positioned within 2m of a corner or junction in • BS 8110 Structural use of concrete
the foundation. All shuttering should be removed
before work progresses beyond the construction
joint.
Technical Manual V8: TS-11A-8.00-010117
Where foundations are stepped (on elevation), Figure 17: Steps in foundations
they should overlap by twice the height of the step,
by the dimension of the foundation or by 300mm,
whichever is the greater, as shown in Figure 17.
85
CHAPTER 5
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Piled foundation designs must be supported by structural calculations
a workmanlike manner. provided by a suitably qualified expert. Calculations for full piling
iii. Pile foundations schemes must be tested to confirm that the systems must be provided by, or endorsed by, the piling manufacturer.
installation meets the design requirements. iii. Piled foundations must meet the relevant regional Building
Regulations
Materials
i. All materials should be stored correctly in a manner that will not cause Limitations of Functional Requirements
damage or deterioration of the product. i. The Functional Requirements are limited by the recommendations
ii. All materials, products and building systems shall be appropriate and applied to the specific areas covered in this chapter.
suitable for their intended purpose. ii. These Functional Requirements do not and will not apply to create
iii. The structure shall, unless specifically agreed otherwise with the any policy liability for any remedial works carried out by the contractor
Warranty provider, have a life of not less than 60 years. Individual or otherwise, nor to any materials used in those remedial works.
components and assemblies, not integral to the structure, may have a
Technical Manual V6: TS-011a-6.00-010413
5.4.1 Introduction • Bored and dug, including short bored and • Friction piles, on the other hand, develop most
Piles are used to transfer loads from buildings to the secant (replacement piles). of their support from friction between the shaft
supporting ground, and are utilised in a wide range • Driven and jacked piles, steel, concrete and and the soil, usually firm clay.
of applications where conventional strip footings are timber (displacement piles).
inappropriate. They are particularly employed where 5.4.5 Choosing the right piled solution
soft or loose soils overlay strong soils or rocks at The choice of piling system to support the structure
depths that can be reached conveniently by driving will depend entirely upon the ground conditions.
or boring. They are often the most economical It is important to have the appropriate site
type of foundation when very heavy loads must be investigation works carried out to determine depths
supported or uplift forces need to be resisted. Large of filled ground, the bearing capacity of soils, soil
piles are extremely useful for limiting the settlements type and any existing workings or services that
of large structures on deep stiff clays; smaller may clash with pile locations. Further guidance
versions can provide appropriate foundations for for ground condition assessment can be found in
houses and other small buildings on stiff clays liable chapter 4 – Site Investigation.
to shrinkage and swelling. The technique has been
in use for many years. Analysis of the site investigation report should be
completed by a Specialist Piling Contractor and
5.4.2 Limitations of guidance Structural Engineer, as they are best placed to
The following situations are beyond the scope of design the most economical piling system.
the guidance in this chapter:
Figure 18: The range of piling types (BRE publication)
Piles are particularly appropriate for heave sites
Technical Manual V8: TS-11A-8.00-010117
• Innovative foundation systems that do not have 5.4.4 How piling systems work (trees removed), for which they are strongly
third-party approval or accreditation. There are basically two groupings of piles, based recommended.
• Piling systems where the structural design is not on the way that they transfer loads to the ground:
endorsed by the Specialist Piling Contractor. Pile layouts can be readily designed to
• End bearing piles derive the greater part of their accommodate an individual plot. A good design
5.4.3 Pile classification
© LABC Warranty
support from bearing forces at the base. They will seek to achieve cost savings in foundation
Piles of many different types and methods of act largely as columns transferring loads. excavation and materials through incorporation
installation have been developed to suit the wide through soft deposits, usually to dense granular of large ground beam spans between piles and a
variety of soils. Piles generally fall into two main soil or rock at the foot of the pile. small number of piles.
types: 87
CHAPTER 5
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
The Piling Contractor should take care to ensure • Driving records from driven piles, including
that the piles are inserted vertically and pile tops hammer type, weight, drop height, sets, hammer
are correctly aligned to support the foundation efficiency.
beams. An acceptable level of tolerance is for a • Pile verticality confirmation, which should be
pile to be offset in plan from the theoretical position no more than 1:75 from vertical.
by no more than 75mm, with vertical alignment no
worse than 1m in every 75m (1:75). For CFA and concrete screw piles, we should be
given the computer output for concrete volume
5.4.6 Ground beams and rig performance.
Piles should be capped with an appropriate
ground beam system. There should be adequate 5.4.8 Testing
connections between the beam and the pile to Piled foundation installation should be
ensure that the loads are transmitted effectively appropriately tested to ensure that the installed
or that the beams are adequately restrained to foundations meet the design requirement. A testing Figure 19: Pile and beam detail
the pile to resist uplift on sites that are susceptible strategy plan should be agreed at the design
to heave. All external, internal, partition and party stage that is representative of the complexity of
walls can be accommodated using this system. the piling system. Further guidance is available 5.4.9 Test methods
The ring beam and its connections should be part from the Federation of Piling Specialists, which has The engineer shall require the specialist contractor
of the piled foundation design, and should be produced the Handbook on Pile Load Testing. to verify that the piling works have been completed
supported by structural calculations provided by a to a satisfactory standard. This will usually include
Structural Engineer. Static load testing of preliminary and working piles carrying out suitable testing to establish the
Technical Manual V8: TS-11A-8.00-010117
should be undertaken. Working pile testing is to degree of ground improvement, its load-bearing
5.4.7 Pile construction records be carried out at a rate of not less than 1 working characteristics and settlement potential.
Pile construction records should be made pile per 100 piles or part thereof (not less than 1%).
available for all piles installed. The records should However, additional tests may be required on sites These tests may include:
include the following information: with more unstable ground or where workmanship
© LABC Warranty
site investigation report, the ground conditions 5.4.10 Relevant Standards and
and the factor of safety applied to the pile design. Guidance Documents:
Please submit this information at the time of the • BS 8004 Code of Practice for foundations
Warranty application and prior to commencement • BS EN 1997 – 1 Eurocode 7
on site. • BS EN 1997 – 2 Eurocode 7
• BS 5950-1 Structural use of steelwork in buildings
5.4.9.2 Integrity tests • BS 6399 Loadings for buildings
Also known as low strain testing, there are two types • BS 8103 Structural design of low rise buildings
of tests used solely for assessing pile integrity: • BS 8110 Structural use of concrete
• Piling: A Good Practice Guide
• Cross hole sonic logging (please refer to our website for further details)
• Pulse echo
89
CHAPTER 5
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in a ii. Raft foundation designs must be supported by structural calculations
workmanlike manner. provided by a suitably qualified expert.
iii. Raft foundation design and construction must meet the relevant
Materials regional Building Regulations.
i. All materials should be stored correctly in a manner that will not cause
damage or deterioration of the product. Limitations of Functional Requirements
ii. All materials, products and building systems shall be appropriate and i. The Functional Requirements are limited by the recommendations
suitable for their intended purpose. applied to the specific areas covered in this chapter.
iii. The structure shall, unless specifically agreed otherwise with the ii. These Functional Requirements do not and will not apply to create
Warranty provider, have a life of not less than 60 years. Individual any policy liability for any remedial works carried out by the contractor
components and assemblies, not integral to the structure, may have a or otherwise, nor to any materials used in those remedial works.
lesser durability, but not in any circumstances less than 15 years.
Technical Manual V6: TS-011a-6.00-010413
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
5.5.1 Introduction capacity or where there are pockets of filled • The insulation product must have third party
A raft foundation consists of a reinforced concrete ground. It is therefore important to complete a product approval certification for use below a
slab, whose thickness and stiffness are designed suitable site investigation to meet the requirements structural raft foundation (including below
to spread the applied wall and column loads over of chapter 4 of this Manual and ascertain the external walls)
a large area. For domestic applications, rafts are bearing capacity and suitability of the ground.
often built with thickened perimeters to provide The design should provide sufficient information
protection against frost heave, in which case 5.5.5 Structural design to ensure correct installation of the raft and
they are effectively trench fill foundations with Structural calculations should be provided by a its reinforcing. The minimum recommended
integral ground bearing floor slabs. Down stand suitably qualified Structural Engineer, confirming information is as follows:
edge beams also serve to stiffen the foundation’s that the raft design is suitable for bearing onto the
structure. ground and that the ground bearing capacity • Plans and details of the proposed raft showing
safely supports the structure. For ‘low rise structures’, reinforcing positions, etc.
Rafts are used where it is necessary to limit the the foundations should be designed to ensure a • Structural calculations confirming that the raft is
load applied to the underlying soil or to reduce the maximum settlement of 25mm is not exceeded. suitable for the proposed loads applied.
effects of differential foundation movements due to In relation to differential settlement, a design limit • A bar schedule, to be used by the reinforcing
variable soil conditions or variations in loading. for maximum tilt of 1/500 is appropriate. More steel supplier and installer.
stringent values may be required due to the
5.5.2 Limitations of guidance particular circumstances (e.g. medium and high 5.5.6 Ducts and sleeving
Rafts are not considered an accepted method rise structures). Any service penetrations that pass through the
of foundations where the ground conditions are raft should be appropriately sleeved to protect
susceptible to heave or shrinkage (e.g. where trees Where thermal insulation products are used below the service duct. Service duct positions should
Technical Manual V8: TS-11A-8.00-010117
are present or have been removed). the structural raft they should: be planned and indicated on drawings to
prevent reinforcing bars from being cut, unless the
5.5.3 Materials • Meet the requirements of BS EN 1606: structural design has catered for this.
Materials and workmanship should meet the 2013 Thermal insulation products for building
requirements set out in chapters 1 and 2 of this applications 5.5.7 damp proof membranes (dpm), damp
Manual. proof courses (dpc) and floor finishes
© LABC Warranty
CHAPTER 5
CHAPTER 5: FOUNDATIONS
CHAPTER 5: FOUNDATIONS
external toe and lapped into the internal DPC; 5.5.8 Standards referred to:
however, this detail can be difficult to implement • BS 8004 Code of Practice for foundations
on-site, and puncturing of the membrane can • BS 5950-1 Structural use of steelwork in buildings
commonly occur when placing reinforcing. The • BS 6399 Loadings for buildings
preferred method is to place the DPM on top of the • BS 8103 Structural design of low rise buildings
raft slab beneath the floor insulation or screed, as • BS 8110 Structural use of concrete
indicated in Figure 20.
Plasterboard on dabs
Skirting board
Lap DPM into
Perimeter insulation
DPC
DPC Insulation
Screed
Technical Manual V8: TS-11A-8.00-010117
DPM
Reinforcing as designed
by a Structural Engineer
CHAPTER 6: SUBSTRUCTURE
CONTENTS
6.1 BASEMENTS
6.2 WALLS BELOW GROUND
6.3 DAMP PROOFING
6.4 GROUND FLOORS
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
93
CHAPTER 6
FUNCTIONAL REQUIREMENTS
6.1 BASEMENTS ii. Basements shall be appropriately designed to ensure that they
adequately provide a suitable barrier against contaminants, ground
Definition gases and ground water.
For the purposes of this chapter, a basement is defined as a storey or iii. Basement design and construction must be supported by structural
storeys of a building that is constructed partially or entirely below ground. calculations provided by a suitably qualified expert.
iv. Design details of the basement waterproofing techniques must be
Workmanship provided prior to commencement onsite.
i. All workmanship must be within the tolerances defined in chapter 1 v. Basements must meet the relevant regional Building Regulations.
of this Manual. vi. All basements must be designed and constructed to meet the
ii. All work is to be carried out by a technically competent person in requirements of BS 8102: 2009 and achieve a minimum of a Grade 2
a workmanlike manner. standard, except where defined in the guidance to this chapter.
iii. Certification is required for any work completed by an approved vii. The basement waterproofing design should be completed by a
installer. suitably qualified Waterproofing Specialist. The Waterproofing Specialist
must take responsibility for the design liability of the waterproofing
Materials system and have appropriate professional indemnity cover which
i. All materials should be stored correctly in a manner that will not cause covers their business activities. They must also have an understanding
damage or deterioration of the product. of hydrogeology and soil mechanics and hold a relevant professional
ii. All materials, products and building systems shall be appropriate and qualification i.e. Certificated Surveyor in Structural Waterproofing
Technical Manual V6: TS-011a-6.00-010413
iii. The structure shall, unless specifically agreed otherwise with the
Warranty provider, have a life of not less than 60 years. Individual Limitations of Functional Requirements
components and assemblies, not integral to the structure, may have a i. The Functional Requirements are limited by the recommendations
lesser durability, but not in any circumstances less than 15 years. applied to the specific areas covered in this chapter.
ii. These Functional Requirements do not and will not apply to create
© LABC Warranty
Design any policy liability for any remedial works carried out by the contractor
i. Design and specifications shall provide a clear indication of the or otherwise, nor to any materials used in those remedial works.
design intent and demonstrate a satisfactory level of performance.
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
6.1.1 Introduction experienced parties. An appropriate structural Specialist be sought for assessment of
This chapter provides guidance on the design must be undertaken by a Chartered the geology and hydrogeology, and that a
requirements associated with the design and Structural Engineer. Waterproofing Specialist be included as part of
construction of basements and other below the design team from the earliest stages, so that
ground structures. Principally, this concerns 6.1.3 General principle of an integrated and practical waterproofing
the process by which the risk of ground water waterproofing design solution is created.
penetration is appraised and addressed, so The approach detailed within BS 8102 involves
that problems associated with penetration do assessment of a given site to determine the • The Waterproofing Specialist must take
not occur, while consideration is also given to characteristics that influence risk. With the benefit responsibility for the design liability of the
economic construction. of knowledge gained through this investigation waterproofing and have appropriate
and assessment, suitable designs for dealing with professional indemnity cover which covers
This process and rationale is primarily detailed ground water, gases and contaminants can then their business activities. They must also have
within BS 8102 (2009) Code of Practice for be devised and constructed. an understanding of hydrogeology and soil
protection of below ground structures against mechanics and hold a relevant professional
water from the ground (and other associated 6.1.4 Design responsibility qualification i.e. Certificated Surveyor in
design guides). However, further practical • Production of a suitable design is one of the Structural Waterproofing (CSSW) or similar.
guidance on this and compliance with Warranty most important aspects of achieving a
requirements is included herein. successful outcome, where the required • Designers must have ongoing involvement
standard of environment is created within the during the build, maintaining good
6.1.2 Limitations of guidance basement space and maintained in the long communication with site management and
This document is not intended as a standalone term. providing supervision and guidance wherever
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 6
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
Note: 3. The early involvement of a Waterproofing • Where standing water levels are not noted
1. The need for a dedicated Waterproofing Designer is an important consideration during a pre-start site investigation, the
Specialist within the design team is intended because the waterproofing design typically has drainage characteristics of the ground must
to reduce the incidence of issues where an influence on elements of the structural and/ receive particular attention.
systems are designed without following the or architectural design. Early involvement • Soils with low permeability represent a risk
advice and considerations detailed within BS allows the waterproofing to be duly considered of waterlogging or encouraging a ‘perched
8102 and associated design guides. in association with these other aspects water table’, where water stands temporarily or
and prevents situations where design fees are permanently within the ground against a
Such scenarios may occur where Project increased as a result of necessary redesign, or structure, and arguably this affects more
Designers take on the role of Waterproofing where waterproofing is compromised by properties with basements versus the true water
Designer without sufficient reference to the working within the constraints of an ill- table level.
stated guides, commonly relying on standard considered structure relative to achieving the
design details and without considering all required standard of environment. Other factors, such as topography and orientation,
appropriate factors. Please refer to BS 8102 for may have an impact on the propensity for
a list of requirements that a designer must meet 6.1.5 Site and risk assessment pressure to come to bear and should also
in order to fulfil the Waterproofing Designer role The degree of water present within the ground receive consideration. Further guidance on the
which includes carrying professional indemnity and the propensity for waterlogging to occur over drainage characteristics associated with different
insurance cover appropriate to the project. the lifetime of a structure is a principal driver in types of ground is included within the Basement
assessing risk and the degree of waterproofing Information Centre publication Basements:
2. Where relying on the use of waterproofing required. Simplistically, if a basement is constructed Waterproofing – General Guidance to BS 8102:
product manufacturer ‘standard details’, into a permanently high water table then the 2009.
Technical Manual V8: TS-11A-8.00-010117
they typically disclaim design responsibility, degree of protection required will be greater than
so it is incumbent on the Waterproofing Design a similar structure constructed into a generally dry Ground gases and contaminants must also be
Specialist to ensure that such details are correct site. considered within the risk assessment.
and appropriate for the site and structure, or
offer suitable variation. • An assessment of a site must be based on
© LABC Warranty
Note: • The Warranty Surveyor may request a copy 6.1.6.2 Exclusion of surface water
1. While the site investigation forms part of what of the s ite investigation report, design and Surfaces external of the basement structure
guides the waterproofing design, an equally associated design rationale at ground level can act to limit or attenuate
important consideration is the intended use of penetration into vulnerable positions, i.e. the
the space and implicit consequences in 6.1.6 Water-resisting design more permeable excavated and backfilled
the event that water penetration occurs. For The principle of this is to consider and design for ground directly around the basement structure.
example, in properties where the consequences the pressures that the structure/waterproofing The inclusion of surface and cut-off drains which
of penetration would be severe, such as in must resist based upon the site investigation and remove standing water away from the vulnerable
habitable space, suitably low-risk methods must risk assessment detailed above. However, it also areas are also of benefit.
be provided. concerns the means by which the degree of water
in the ground can be influenced by design. 6.1.6.3 Sub-surface drainage
2. Whilst in theory it could be assumed that, The use of land drainage can act to remove water
based upon a site investigation, the risk of water 6.1.6.1 Structural resistance from around the structure, thus alleviating pressure
pressure ever occurring is low, BS 8102 advises The ability of the structure to provide resistance and should be considered in all cases to reduce
that consideration is given to the effects of to the penetration of water has a bearing upon the risk of water ingress where practical.
climate change and burst water mains and all forms of waterproofing. Retaining walls in plain
sewers, as well as stating that it should be or reinforced masonry provide comparatively However, the use of land drainage might not be
assumed that there is risk of waterlogging “even little resistance to the penetration of water under viable on all sites, examples being:
where site examination indicated dry conditions”. pressure because of the crack pattern associated
with the degree of joints (mortar beds) present. • Where there is no available location to
In summary: discharge collected ground water.
Technical Manual V8: TS-11A-8.00-010117
The degree of water excluded by concrete • Where high water tables and permeable
• The site investigation guides the design, but it elements (walls and slab) is influenced by the ground conditions make it impractical to
should never be assumed that some degree of nature of the design and construction. While sufficiently remove the quantities of water
water pressure will not occur. concrete itself is relatively impermeable, the present.
• If no site investigation has been undertaken degree to which water is excluded will be greatly • Restrictions on the site curtilage due to
or there is reasonable doubt as to ground water
© LABC Warranty
influenced by crack sizes and the detailing of adjacent buildings close to or on the site
conditions, pressure to the full height of the construction joints and service penetrations. boundary.
below ground structure must be assumed at • Draw down i.e. affecting the stability of other
some point in the life of the structure. structures by the introduction of a land drain.
97
CHAPTER 6
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
Depending on the required ‘environment’ (see • Land drains must be positioned at a low
chapter 6.1.7), if land drainage is not feasible, a enough position to prevent pressure from
combination of at least two systems in order to bearing upon the structure and waterproofing.
mitigate the risk of water ingress will need to be (see Figure 1)
adopted. The Waterproofing Specialist will be • The use of geo-drainage membranes applied
required to provide a solution specific to the site to the external face of a retaining wall can
conditions. provide a continuous drainage space external
of the structure, which assists in encouraging
Notwithstanding such conditions, the provision of water to drain down to the level of the land
effective land drains is often an economic means drains without pressuring the structure.
of greatly reducing risk and must be included • Land drains must link to a reliable point
where viable. of discharge. Where sump pump systems
are employed, the implications of power cuts
The following considerations apply: should be considered in that land drains may
in such scenarios not function as intended. The
• Perforated land drains must be surrounded in effectiveness of battery back-up systems, where
clean graded stone and wrapped in a suitable employed in sumps servicing land drains,
geo-textile filter fabric to reduce the risk of should be considered in relation to assessment
clogging. This is particularly important in fine of the likely degree of ground water.
granular and clay soils where land drains are • Land drains must not be directly linked to
susceptible to clogging. soakaways by gravity, unless it is not possible
Technical Manual V8: TS-11A-8.00-010117
• Rodding points must be included (ideally at for water to surcharge i.e. where the top of the
changes in direction) to facilitate maintenance, soakaway is below the level of the actual land
which will allow the system to function in the drains.
long term. (This particularly applies to land
drains where there is no viable access for
repair)This maintenance should be undertaken
© LABC Warranty
99
CHAPTER 6
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
6.1.7 Intended use and required standard • For Warranty purposes we require all basements For this type of use, a design by water proofing
of environment to be designed and constructed to a minimum design specialist to a BS 8102 Grade 1 standard
Usage dictates the required ‘grade’ of environment, of Grade 2, with Grade 3 being necessary could be accepted. For plant rooms (that do
i.e. how ‘dry’ a given basement space must be in for occupied space. An exception to this is a not house items of plant that directly service the
order to be suitable for a given usage. basement used solely for underground car home), lifts / escalators, access stairs and lobbies
parking, where a Grade 1 could be accepted; that are associated within an underground car
The designer must therefore consider how this see note 6.1.7.1 below for specific guidance. park, a Grade 2 standard is the minimum grade to
will be achieved in a particular site and structure. • Habitable space is Grade 3 where water be expected.
BS 8102: 2009 Table 2 provides three definitions penetration is unacceptable. Appropriately
of environmental grades (Grades 1, 2 and 3) as designed environmental controls, such as The degree of seepage or dampness (water
follows: vapour barriers, insulation, heating, ventilation tightness) that can be tolerated for this particular
and dehumidification must be included end use needs to be established and agreed
Example of use of to control vapour introduced via occupation with all interested parties, including the Warranty
Grade Performance level
structure
sufficiently thereby preventing problems of Surveyor at the design stage. To assist with
Car Parking; Some seepage
condensation. quantifying an acceptable level of moisture
plantrooms and damp
1 (excluding electrical areas tolerable, • An example usage for Grade 2 includes ingress, the following definitions of water tightness
equipment); dependent on
store rooms, and again water penetration is not are provided. These are taken from the publication
workshops. intended use.
acceptable however, heating and ventilation ‘Specification for piling and embedded retaining
Plant rooms and No water
workshops requiring penetration is not necessarily required, albeit that some walls’.
a drier environment acceptable. degree of ventilation is recommended even in
2
(than Grade 1); Damp areas
storage areas tolerable; ventilation basic storage space, which may otherwise • Damp patch: When touched, a damp patch
might be required.
Technical Manual V8: TS-11A-8.00-010117
stores; some seepage, dampness or condensation • Beading of water: Beading of water is the state
appropriate to the
intended use. as well as standing water (from vehicles) is to be in which individual droplets of water (held by
expected. surface tension effects) form on the surface of
Table 3: Grades of waterproofing protection the wall and adhere to the wall. The water
beads do not coalesce and do not flow.
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
• Weeping of water (seepage): Weeping of water • Damp air may cause electrical installations A higher waterproofing specification may be
is the state in which droplets of water form on to malfunction. Permanently damp conditions required if the walls are to be painted, etc. It is
the surface of the wall and coalesce with other may encourage biological degradation of normally expected that the construction
droplets. The coalesced water does not remain plastic insulation. Ventilation of the plant space materials will not be wetter than 85% RH.
stationary on the wall surface, but instead flows is therefore important. • Wetness: Minor seepage would be acceptable
down the wall. • Water ingress to underground car parks must through the walls and joints if the basement is
similarly be controlled. Cars are likely to not to be decorated.
Section 2.2.3 of CIRIA Report 139 provides guidance introduce significant amounts of water on • The need for drainage within the basement, i.e.
on quantifying the required internal environment wet days, which should be drained away. There channels along perimeter walls and across car
and places limits on Grade 1 basements: is also the danger of corrosion and parking areas, should also be determined,
discoloration of paintwork on the cars due to together with requirements for ventilation.
It identifies: seepage through the ceiling slab (podium deck). • Where necessary, consideration should also be
given to whether additional protection
• The functioning of mechanical plant and Summary of environmental parameters: measures are required to plant and equipment,
electrical switchgear is not normally unaffected electrical switchgear, support brackets etc.,
by seepage through walls and floors, provided • Relative humidity: Items stored in such
the water does not impinge directly onto the basements should not normally be unduly Once the most appropriate level of water tightness
equipment. However, a wet floor can be hazard affected by high relative humidity. Ventilation has been determined, the Waterproofing Specialist
to maintenance staff as well as increase the provision draws air directly from the atmosphere should factor this into his design and specify a
rate of corrosion of steel casings and frames and conditions equivalent to prevailing suitable waterproofing system that will achieve the
in contact with it. Generally, a raised working atmosphere, RH greater than 65% (normally UK required level of performance. Full design details and
Technical Manual V8: TS-11A-8.00-010117
area may be desirable, and all equipment external range), are therefore acceptable. justification of the proposed method of waterproofing
should be mounted on plinths. • Temperature: Grade 1 basement would not must be submitted and approved by the Warranty
• Atmospheric moisture is unlikely to affect normally be heated. Surveyor prior to work commencing on site.
mechanical plant unless it is continually at such • Dampness: The requirements for dampness
a level as to cause an unreasonable fast rate will depend on whether the basement is to 6.1.8 Defects and remedial measures
of corrosion. One exception is that air
© LABC Warranty
be decorated in any way and the sensitivity Within BS 8102 designers are advised to consider
compressors need to be fitted with air-driers if of any electrical equipment to be installed the probability that systems may not be installed
they are to operate in constantly damp (i.e. light fittings, switches, cable runs/conduits perfectly, and that defects may occur as a result
conditions. Ferrous pipes, conduits, wall brackets etc.). If the basement is not to be decorated of this or defects may be present in the supplied
and their fixings etc. will corrode if unprotected. then visible damp patches may be tolerated. materials. 101
CHAPTER 6
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
Designing on the assumption that a system will not 6.1.9.1 Type A barrier protection • ‘Buildability’, namely whereby sheet membrane
be totally perfect or free of defects necessitates This form of waterproofing relies on the inclusion of products are proposed, with the consideration
that consideration is given to the feasibility of a physical barrier material applied on or within the being the practicality of wrapping a flat sheet
repairing those defects, or ensuring that they structure, often where the structure itself provides around complex three dimensional shapes
are of no consequence i.e. where systems are little resistance to the penetration of water. A variety such as external corners and beneath raft slab
not accessible for repair. Different structures, of considerations apply: thickened toe details.
waterproofing systems and sites have a bearing
upon this consideration. For Warranty purposes a • Suitability of the substrate, primarily applicable
Grade 3 environment basement must be designed where tanking products are applied internally
so that the consideration of reparability is essential. in that the bond between the product and the
substrate on which it is applied must be
Strategies for repair of a Grade 1 or 2 environment sufficient to resist hydrostatic ground water
basement must be considered as part of the pressure.
design process, further commentary is provided • The requirement for preparation of substrates to
within each of the specific system type sections. accept tanking mediums.
• Movement which in rigid tanking systems may
The detail of an appropriate repair strategy may be encourage cracking through which water may
requested by the Warranty Surveyor in relation to a penetrate, where pressure comes to bear.
given waterproofing design. • Loading, where hydrostatic pressure is applied
to the structure as a result of exclusion via the
6.1.9 Forms of waterproofing tanking medium, i.e. structures must be
Technical Manual V8: TS-11A-8.00-010117
BS 8102 defines three forms of waterproofing designed to resist loads applied to them.
protection, Type A barrier protection (commonly • Continuity in that systems must in virtually all
referred to as ‘tanking’), Type B, structurally integral cases be ‘continuous’, as a gap in a barrier
protection and Type C drained protection. system represents a point at which water under
pressure can penetrate.
© LABC Warranty
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
Commentary on 6.1.9.1:
• Whilst BS 8102 advises that ‘reparability’ must
be considered, the use of external adhesive
membrane tanking systems on permeable
constructions is precluded, unless employed in
association with long-term strategies for
preventing ground water from pressuring, e.g.
serviceable land drains.
• External systems have a greater implication, in
that accessibility for repair is typically
impractical post-construction and where
combined with relatively permeable wall
constructions, makes it difficult to confidently
determine the point of a defect externally,
because water can track within the wall
construction to show itself internally at a
position not local to the external defect.
• Internal systems have the benefit of greater
accessibility meaning that repair is more
feasible. Where this system is chosen, the
strength of the substrate, its surface preparation
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 6
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
Concrete without additives and including typical As with any structure that aims to entirely block • Appropriate specialist site supervision to ensure
levels of steel reinforcement (with cracking out water, this must be free of defects which would high standards of workmanship.
<0.3mm); whilst providing good resistance to the otherwise allow water to penetrate. In achieving • Good placement and compaction.
penetration of water, will allow seepage given this, the following must be considered: • Curing.
hydrostatic pressure, and as such is not suitable
in isolation unless forming basic (non-habitable, • Structural design and specification of materials Particular consideration must be given to the
© LABC Warranty
non-storage) standards of environment. Further (based in part on-site assessment). formation of construction joint details, which form a
guidance can be found on controlling crack • Water stop detailing at construction joints. typical weak point in Type B structures. Furthermore,
widths in BS EN 1992-3: 2006 and CIRIA publication • Service penetration detailing. specialist supervision is required on site during
C:660. construction.
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
Systems which function by excluding water may 6.1.9.3 Type C drained protection Whilst the drainage channel is intended only
not be tested until the ground water pressure This method of waterproofing differs from Type A to deal with minor seepage water and could
comes to bear. Therefore, it is advantageous where and Type B as the structure is employed to limit alternatively be linked into deeper fixed drains to
external water pressure comes to bear prior to penetration while an internal drainage system drain out via gravity, the risks associated with the
completion that any areas of penetration can be collects and removes any seepage water. surcharge of external drains are high and this
remedied during construction. practice is excluded from Warranty cover.
6.1.9.3.1 The Structure
Commentary to 6.1.9.2 • The ‘structure’ provides the primary resistance
• With regard to appraisal of repair, this method to ground water pressure. A Type C drainage
has a benefit in that; the point of penetration system is designed to mitigate the risk by
is typically the point of the defect or pathway removing any minor water seepage through the
through which water penetration occurs. structure and in doing so maintains the
Coupled with the impermeable nature of the required internal environment.
structure generally, this allows localised repair • An assessment of the structure is required
to be undertaken via resin injection, grouting to ensure it provides the primary level of water
and associated repair methods resistance by the Waterproofing Specialist.
• The main consideration is locating the point
of any penetration, and it is therefore beneficial 6.1.9.3.2 Internal drainage
where reasonable access to the concrete The internal drainage system comprises of three
structure remains viable elements:
• Product guarantees, quality assurance schemes
Technical Manual V8: TS-11A-8.00-010117
and product certification does not negate • A drainage channel detail recessed into the
the Functional Requirement that a floor construction.
waterproofing specialist is required to take • A means of water discharge, which in a
responsibility for the design liability of the basement fully below ground requires a sump
waterproofing pump system or in a sloping site may be via
© LABC Warranty
gravity.
• Vapour barrier drainage membranes included
above or internal of the drainage system which
isolate the internal environment from the damp
substrates behind. 105
CHAPTER 6
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
Drained protection systems are reliant on their ability to remove seepage water
and so the mechanism by which water is removed requires careful consideration.
The extent of seepage water penetration also has a bearing on the capacity
required, with the degree of penetration being influenced by the permeability of
the structure and the ground water conditions externally.
Notwithstanding the above, the capacity of such systems to remove water must be
adequate to deal with a worst-case scenario and should be engineered with this in
mind to provide a suitably low-risk system.
systems to function and protect in the long term. Where larger footprints are
involved cross floor channels must be included, ideally local to construction
joints where the structure is more vulnerable to ground water penetration.
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
6.1.9.3.3 Maintenance • Where basements are formed under existing • Continuity of the structure must be considered
Systems must be maintained annually as a buildings in conjunction with new under because the resistance to water provided by
minimum. The detail of this requirement must pinning works; the choice of dry packing should a given structure is reduced by apertures
be included in the documentation provided to be carefully specified and a waterproof through which water can freely move. Examples
the homeowner who will then be responsible expanding type mortar is recommended to could include holes present within existing
for ongoing operation and maintenance of the help avoid free lime occurrences.Substrates buildings, or in new construction where land
system, the ongoing maintenance should include: should be clean and free of loose or friable drains are linked to sump pump systems, with
materials prior to the application of membrane the sumps being installed internal of the
• The service records of the maintenance of linings. retaining shell, e.g. in light wells, thus providing a
the system. pathway for water to enter.
• Accessibility to drainage channels and sumps 6.1.9.3.5 General • Temporary 110v pumps should be included
are available at all times. • Flood testing of a system should be undertaken during construction to address water
• That the drainage channels and sumps are during construction to check efficiency and penetration as necessary; 240v systems should
checked at the service intervals to ensure they that water flows freely to the discharge point. be installed and commissioned as soon as
are clear and free of any free lime build up. Testing in this manner to prove that the system viable once the 240v supply is installed.
• Ensure that the electrical supply, battery back functions as intended, is a key benefit of this • Systems must not link directly by gravity to
up and alarm systems are fully operational at method of waterproofing and must be part of soakaways where any of the previously
all times. the process. stated scenarios occur because of the
• Systems creating a habitable space require the danger of backflow of water through the pipes
6.1.9.3.4 Free lime inclusion of vapour barrier drainage or waterlogging of the local ground above
Water moving over and through new concrete membranes within the wall and floor slab/DPM level. However, where such conditions
Technical Manual V8: TS-11A-8.00-010117
walls and floors leaches free lime within the early construction. are not present, sump pump systems may be
life of the structure, and suitable treatments should • Where elements of the drained protection employed to lift water up to ground level
be applied to concrete to minimise this. system are included within cavities, the cavities externally, discharging into gullies linked to
must be kept clear of mortar snots and debris. soakaways. This detail should be designed by
• The Waterproofing Specialist should provide the Waterproofing Specialist.
a specification of the treatments to be used
© LABC Warranty
107
CHAPTER 6
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
Commentary to 6.1.9.3:
• In consideration of the repair of defects, the
inclusion of drained protection systems
internally generally ensures that systems can be
accessed for localised repair; however, this may
be lessened where systems are sandwiched
within the structure, i.e. within cavities.
• Part of the underlying rationale of drained
protection is that water is removed continuously,
so that it does not collect and removes
pressure upon membrane linings installed over
the drainage. If water does not place pressure
upon such membranes, then the incidence
of any defects within them is generally of no
consequence, and so maintaining the
efficiency of the drainage in the long term
ensures that such defects are negated.
• Product guarantees, quality assurance schemes
and product certification does not negate
the Functional Requirement that a waterproofing
specialist is required to take responsibility for the
Technical Manual V8: TS-11A-8.00-010117
6.1.11 Ground gases and contaminants Figure 5.1 below shows a typical situation with a Type A barrier protection. The Waterproofing Specialist must
Aggressive ground conditions may require the advise the Designer of the correct detailing for the project allowing for any sloping site conditions which may
inclusion of a suitable ground barrier to protect necessitate a stepped DPC provision.
the structure appropriately. Specialist advice
must be sought in respect of dealing with ground
gases, and designers are advised to check current
standards at the time of construction for suitable
guidance.
DPC
6.1.12 Existing structures
Waterproofing existing structures differs from new DPC Cavity Tray Externally applied
construction in that designers must work within the waterproofing system
confines of the existing structure. However, many of Full height open perpends to taken above basement
provide drainage to cavity wall and lapped behind
the same considerations apply in that the required cavity tray at least 150mm
GL above ground level
standard of environment appropriate to usage
must be created and maintained in the long term.
109
CHAPTER 6
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
a suitably qualified expert.
Materials iii. The design and construction must meet the relevant regional
i. All materials should be stored correctly in a manner that will not cause Building Regulations.
damage or deterioration of the product.
ii. All materials, products and building systems shall be appropriate and Limitations of Functional Requirements
suitable for their intended purpose. i. The Functional Requirements are limited by the recommendations
iii. The structure shall, unless specifically agreed otherwise with the applied to the specific areas covered in this chapter.
Warranty provider, have a life of not less than 60 years. Individual ii. These Functional Requirements do not and will not apply to create
components and assemblies, not integral to the structure, may have any policy liability for any remedial works carried out by the contractor
a lesser durability, but not in any circumstances less than 15 years. or otherwise, nor to any materials used in those remedial works.
Technical Manual V6: TS-011a-6.00-010413
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
6.2.1 Bricks and blocks below ground Brick / block type Use / minimum standard of brick or block
The selected bricks should be appropriately Walls up to DPC Walls up to DPC (sulphates in soils)
durable against saturation in accordance with Clay bricks FL,FN,ML,MN (a) FL,FN,ML,MN (a)
EN 771-1 (See tables 4 and 5 in chapter 2 of Calcium silicate bricks Class 3 (b)
Class 3 (b)
this Technical Manual). Where brick and block Concrete bricks Min strength 20N/mm
2 (c)
Min strength 20N/mm2 (c)
classifications under BS 3921 are still made; Table Block work Min strength 7N/mm and density greater
2
Min strength 7N/mm2 and density greater
than 1500kg/m3 (d) than 1500kg/m3 (d)
1 can be referred to in conjunction with Table 4 in
chapter 2. Notes:
(a) If the site is wet or saturated at ground level use FL or FN bricks only.
If there are sulphates in the ground and/or there (b) Denotes a minimum standard - higher classifications may be used.
(c) For Class 1 and Class 2 sulphates, check with manufacturers to confirm suitability of brick; for Class 3 sulphates,
is ground water present, confirmation by the use engineering quality concrete bricks.
manufacturer that the brick or block is suitable for (d) Autoclaved aerated blocks with independent appropriate third party certification are acceptable.
use below ground should be provided. Table 1: Suitability of bricks and blocks below ground
level (ii) (a) 1:0.5:4-4.5 (b) 1:3-4 (b) 1:2.5-3.5 (b) 5.0N/mm2
Notes:
(a) For concrete or calcium silicate brick use a designation (iii) mortar.
(b) Where soil or ground water sulphate levels are appreciable (Class 3 or higher) use sulphate resisting Portland Cement.
111
CHAPTER 6
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
Figure 6: Concrete cavity fill: traditional ground bearing slab Figure 7: Concrete cavity fill: beam and block floor
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in a ii. Damp proofing works should prevent any external moisture passing
workmanlike manner. into the internal environment of the dwelling.
iii. Certification is required for any work completed by an approved iii. Structural elements outside the parameters of regional Approved
installer. Documents must be supported by structural calculations provided by
a suitably qualified expert.
Materials iv. The design and construction must meet the relevant regional Building
i. All materials should be stored correctly in a manner that will not cause Regulations.
damage or deterioration of the product.
Technical Manual V6: TS-011a-6.00-010413
ii. All materials, products and building systems shall be appropriate and Limitations of Functional Requirements
suitable for their intended purpose. i. The Functional Requirements are limited by the recommendations
iii. The structure shall, unless specifically agreed otherwise with the applied to the specific areas covered in this chapter.
Warranty provider, have a life of not less than 60 years. Individual ii. These Functional Requirements do not and will not apply to create
components and assemblies, not integral to the structure, may have a any policy liability for any remedial works carried out by the contractor
lesser durability, but not in any circumstances less than 15 years.
Technical Manual V8: TS-11A-8.00-010117
113
CHAPTER 6
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
a suitably qualified expert.
Materials iii. The design and construction must meet the relevant regional
i. All materials should be stored correctly in a manner that will not cause Building Regulations.
damage or deterioration of the product. iv. Precast structural elements must have structural calculations that
ii. All materials, products and building systems shall be appropriate and prove their adequacy endorsed by the manufacturer.
suitable for their intended purpose.
Technical Manual V6: TS-011a-6.00-010413
iii. The structure shall, unless specifically agreed otherwise with the Limitations of Functional Requirements
Warranty provider, have a life of not less than 60 years. Individual i. The Functional Requirements are limited by the recommendations
components and assemblies, not integral to the structure, may have applied to the specific areas covered in this chapter.
a lesser durability, but not in any circumstances less than 15 years. ii. These Functional Requirements do not and will not apply to create
any policy liability for any remedial works carried out by the contractor
Technical Manual V8: TS-11A-8.00-010117
115
CHAPTER 6
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
6.4.1 Ground supported concrete floors Hard core material should not be saturated, and an additional DPM to protect the surface of the
caution should be taken to ensure that new walls insulation. It is important that this additional
6.4.1.1 Site preparation are not disturbed by compaction of the hard core. membrane is incorporated, which is shown in
The site beneath the floor should be stripped of all Figure 9.
topsoil, organic matter or tree roots prior to filling 6.4.1.2 Damp proof membranes (DPM)
and compaction. DPM can be laid either above or below the floor 6.4.1.4 Concreting of floors
slab depending on the finish of the floor. The Prior to concreting, any water or debris that may
Suitable hard core would include inert quarried membrane should be lapped into the DPC by at have collected on top of the DPM should be
material such as limestone or granite. Recycled least 100mm. removed. Concrete should ideally be ready mixed
aggregates may be used, which include crushed and be of at least GEN3. Expansion joints should
concrete or broken brick; however, these must be be provided in accordance with chapter 2.2 of this
completely free of contaminants and plaster and Manual.
should be delivered to site from a supplier that has
a quality audit process in place. 6.4.2 Suspended reinforced in-situ slabs
6.4.2.2 Site preparation 6.4.2.4 Insulation is removed once the concrete has set) or a
The material below the proposed floor slab should Insulation that is to be provided to ground floor proprietary shuttering system.
be compacted sufficiently to support the slab should be placed above the concrete slab.
during the pouring and curing stages. Any backfill Insulation should be installed in accordance 6.4.2.6 Reinforcing
material should not contain any organic matter, or with the manufacturer’s instructions and be
contaminants that could react with the concrete or durable enough to withstand floor loadings and Reinforcing cover
be susceptible to swelling, such as colliery waste. moisture. A number of insulation products require The main reinforcing bars must have a minimum
an additional DPM to protect the surface of the concrete cover of 40mm. Suitable spacers should
6.4.2.3 Damp proof membranes (DPM) insulation. be provided to support the reinforcing prior to
DPM can be laid either above or below the floor concreting.
slab depending on the finish of the floor. If the 6.4.2.5 Concreting floors
membrane is to be placed beneath the concrete, The depth of concrete will vary depending upon
extra caution should be taken to ensure the the load conditions and the span of the floor. The
membrane is lapped into the DPC by at least overall reinforced concrete slab design should be
100mm, as shown in Figure 9. designed by a suitably qualified Structural Engineer.
suspended floors.
CHAPTER 6
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
thickness of mesh reinforcing, and is identified in Fabric type Minimum lap (mm)
6.4.3.2 Floor joists Floor joists can be supported internally by sleeper Floor area of building Minimum ventilation
All floor joists must be of a suitable durability and walls. Sleeper walls should be built of an adequate (m2) provision (mm2)
Technical Manual V8: TS-11A-8.00-010117
strength grade (minimum C16), be of the correct foundation if the ground is of suitable bearing 40 20,000
size and stress grade and be laid at the correct strata, or can be built of a reinforced thickened 60 30,000
specified centres as indicated on plans and slab where designed by a Chartered Structural 80 40,000
specifications. The joists should have consistent Engineer. 100 50,000
dimensions and be securely nailed to timber wall 120 60,000
© LABC Warranty
CHAPTER 6
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
Air bricks should be evenly spaced along the two heating is provided the maximum moisture content Particle boards should be either screwed or nailed
opposing walls that meet the ventilation provision. of the floor must be limited to 6 -8%, whereas in an to the joists at 250mm centres. Nails should be
Typical ventilation areas for various types of air unheated building the maximum moisture content annular ring shank, which are at least three times
bricks care are identified in Table 6. of the floor is 15 – 19%).. All boards must be double the depth of the board.
nailed or secret nailed to each joist using nails that
Dimensions Net area are at least three times the depth of the board. A 10mm expansion gap should be provided
Air brick type
W x H (mm) (mm2) The boards must have a minimum thickness, as around the perimeter of the floor against a wall
225 x 75 1400 indicated in Table 7. abutment.
Clay air brick
225 x 150 4300
square holes
225 x 225 6400 Finished board Maximum
Typical nail Thickness Thickness Maximum Typical
Clay air brick 225 x 150 2000 thickness centres of
fixing (mm) (mm) (mm) span nail fixing
louvered (mm) joists (mm)
225 x 225 6400 (chipboard) (OSB) (mm) (mm)
45
PCV air brick 225 x 75 4645 15 450
lost head nail 60mm
Table 6: Typical air brick net ventilation area capacities 60 18 and 19 15 450 annular
18 600
(ventilation rates will vary between different manufacturers) lost head nail ring shank
Table 7: Softwood floor boarding 65mm
18 and
The cross flow of air must not be interrupted by 22 600 annular
19
ring shank
internal walls or low hanging insulation. All internal 6.4.3.6 Particle floor boarding
walls must have air bricks to allow the free flow of Acceptable particle boards consist of oriented Table 8: Particle floor boarding
air, or be built using a honeycomb technique. strand board (OSB) or chipboard.
6.4.3.7 Sound insulation and air tightness
Technical Manual V8: TS-11A-8.00-010117
6.4.3.5 Floor boarding or decking Chipboard should be tongue and grooved and Due to the construction methods, it is more likely
Suitable floor boards and decking include tongue all joints glued. The boards should be laid so that to be difficult to demonstrate satisfactory levels of
and grooved softwood flooring with a maximum the shortest length is laid parallel to the span. The air tightness and sound insulation for suspended
moisture content at the time of fixing of between OSB boards should be type 3 or 4 to BS EN 300 and timber ground floors. In ensuring that a reasonable
6 -19% in accordance with BS 8103 – 3 2009. (See should be laid with the major axis at right angles level of air tightness and sound resistance is
© LABC Warranty
Table A1 in Annex A of the standard which gives to the joists (the major axis is indicated on the OSB achieved, the following provisions should be
a range of moisture content for softwood flooring board by a series of arrows). incorporated:
dependant on the intensity of the heating to be
provided in the building. E.g. Where under floor
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
• All joists to be supported off proprietary joist • Specifications for the blocks infilling between 6.4.4.3 Resistance to ground moisture
hangers at the junction with party walls and the beams, including compressive strength and The precast beam and block substructure floor
external perimeter walls. thickness of the block. shall be designed to prevent water ingress, there
• Floor boarding to be sealed against the wall are two common methods of achieving this:
using a sealant or proprietary tape. All beam and block floors shall be installed
ensuring that the following standards are met: Method 1 – Damp Proof Membrane (DPM)
6.4.4 Precast beam and block floors A DPM should be provided beneath the screed or
• Floor beams and blocks are grouted together insulation; the floor void beneath the beams should
6.4.4.1 Site preparation using cement/sand slurry with a mix ratio of be appropriately vented, ensuring that a cross flow
All topsoil and organic matter should be removed 1:6 respectively. of air between two external walls is achieved. The
from beneath the precast suspended floor. The • The beam and block floor should not be used minimum area of ventilation should equate to at
ground level should be at least the same as the to support load-bearing walls . least 1500mm2 per metre run of external wall. This
external ground level unless the ground below the • All walls should be built off an appropriate roughly equates to an air brick every 3m centres
floor is free draining. Alternatively, a DPM linked to foundation, as indicated in chapter 5. for a typical PVC 225mm x 75mm air brick. The
the DPC can be provided. • A suitable mortar bed is required where block ventilated void must have a minimum depth of
work between the floor beams bear onto load 150mm from the underside of the floor.
6.4.4.2 Suitability of beam and block floors bearing walls, e.g. perimeter walls.
All beam and block flooring systems must • Holes must not be made through the floor
have appropriate third-party certification beams and any service penetrations should
or accreditation that meets the Functional pass through the holes made in the infill blocks.
Requirements of this chapter. Any gaps around service penetrations should
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 6
CHAPTER 6: SUBSTRUCTURE
CHAPTER 6: SUBSTRUCTURE
Figure 14: Typical pre-cast beam and block floor with DPM
Method 2 – No damp proof membrane (DPM) The minimum area of ventilation should equate 6.4.4.4 Insulation
Where no DPM is incorporated into the precast to at least 1500mm per metre run of external
2
Insulation provided to ground floor should be
beam and block floor, the following provisions will wall. This roughly equates to an air brick every 3m placed above the beam and block. Insulation
apply: centres for a typical PVC 225mm x 75mm air brick. should be installed in accordance with the
© LABC Warranty
The ventilated void must have a minimum depth of manufacturer’s instructions and be durable
The beam and block floor must be laid above the 150mm from the underside of the floor. The solum enough to withstand floor loadings and moisture.
DPC. The floor void beneath the beams should be level must be at the same level as the external A number of insulation products require an
appropriately vented to ensure that a cross flow of ground level. additional DPM to protect the surface of the
air between two external walls is achieved. insulation.
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
CONTENTS
7.1 EXTERNAL MASONRY WALLS
7.2 STEEL FRAME
7.3 TIMBER FRAME
7.4 WINDOWS AND DOORS
7.5 CHIMNEYS
7.6 BALCONIES
7.7 CLADDING
7.8 ROOF STRUCTURE
7.9 ROOF COVERING – TRADITIONAL SLATE AND TILES
7.10 ROOF COVERING – CONTINUOUS MEMBRANE ROOFING
Technical Manual V8: TS-11A-8.00-010117
123
CHAPTER 7
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
iii. Cavities should be clear from mortar droppings to prevent moisture a suitably qualified expert.
ingress. iii. The design and construction of masonry walls must meet the relevant
iv. Masonry walls should not be laid in extreme weather conditions. regional Building Regulations.
iv. The structure shall, unless specifically agreed otherwise with the
Technical Manual V8: TS-11A-8.00-010117
7.1.1 Protection 7.1.2 Brick and block suitability prevents the possibility of standing water within
All new masonry work should be protected during the structure, which could freeze. Bricks with a
construction by covering it to ensure that walls are Exposure directional surface texture are intended to be laid
not allowed to become saturated by rain water or Facing bricks must have a suitable level of frog up.
dry out too quickly in hot weather, are protected durability and particular attention should be paid
against frost attack, the risk of efflorescence and to the brick’s resistance to frost and moisture. Care should be taken with the use of perforated
line staining and movement problems are reduced. Further guidance can be found in this Manual bricks where the exposure rating of the wall is high,
under chapter 2 – Materials. as water retention/collection has been found to
Any temporary cover should not disturb the new exist in the perforations.
masonry. Non-rendered blockwork
All external blockwork should be rendered Efflorescence
or otherwise finished with a cladding that Efflorescence is a white deposit on the face of
is appropriately durable, unless the block masonry brought about by water moving through
manufacturer can provide third-party certification the wall, dissolving soluble salts and depositing
confirming that the blockwork can be left them when the water evaporates during drying out.
unfinished, or finished in an alternative way.
Efflorescence is best prevented by:
Colour variation of bricks
There is usually a variation in the colour of bricks of • Keeping all units dry prior to use.
the same style. To prevent patching of colour, it is • Protecting the head of newly constructed work
Figure 1: Protection of masonry
recommended that at least three packs of bricks with some form of cover to prevent saturation
Technical Manual V8: TS-11A-8.00-010117
are opened at any one time and mixed randomly (see chapter 2 – Materials).
Stability during construction to ensure that the wall is of an even colour.
Gable walls should be appropriately propped prior
to the construction of any roof. When a floor or roof Frogs and perforations
slab of a building is used for the temporary storage Frogged bricks have a depression in the face of
of building materials, the loading should not
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Notes:
• (1) In very severe exposure locations, fair-faced masonry with full cavity insulation is not permitted;
• (2) Render on an external leaf of clay bricks (F2, S1, or F1,S1 designation bricks BS EN 771) in severe
or very severe exposures is not permitted where the cavity is to be fully filled with insulation;
• This table covers walls where the external leaf does not exceed 12m in height;
• The exposure category of the dwellings is determined by its location on the map showing
categories of exposure to wind driven rain; (See also BRE Report 262)
© LABC Warranty
• Fair-faced masonry includes clay, calcium silicate and concrete bricks and blocks and dressed
natural stone laid in an appropriate mortar, preferably with struck, weathered or bucket handle
joints. Cavity walls of random rubble or random natural stone should not be fully filled;
• Recessed mortar joints should not be used.
Figure 2: Map showing exposure to wind-driven rain categories Table 1: Suitable cavity wall construction depending on exposure, for use with full fill cavity insulation. 127
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Warranty is to design and construct walls to the included in the design. hangers as the thermal insulation of the wall
relevant Approved Document depending on the • The hanger is suitable for the loadings and may be reduced unless similar units to the
region. For example, in England and Wales, the masonry strength. blocks are used.
masonry units should be built in accordance with
Approved Document A (Structure). Alternatively,
justification of design by a Chartered Structural
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Timber packing
It is important to note that only BS EN 845-1 type
wall ties or specifically manufactured (and tested)
party wall ties are permitted in cavity separating
walls between dwellings to reduce the transfer of
sound.
Noggings (minimum 38mm
wide and be at least half the
depth of the joist)
Notes:
1. Bracing strap omitted for clarity
2. Returns on straps should be fastened to uncut blocks
outer leaf and have the ability to hold insulation Wall tie specification and design to be provided by a Chartered Structural Engineer, or
Greater than 150mm in accordance with appropriate third party certification. Design will be determined by
against an internal leaf for partial fill scenarios. location and site specific conditions.
• Where a partial fill cavity insulation solution is
Table 2: Wall tie spacing
proposed, a 50mm minimum residual cavity is
to be provided.
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Figure 10: Block bonding internal masonry walls to inner leaf Figure 12: Typical corbelling arrangements 131
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
outer leaf)
thermal bridging.
Fibreboard or cork are not acceptable materials for Stone 12m 15mm
The first joint from a return should be not more than half the cut block and make-up pieces.
material is used to control the sealant depth, it will dimension indicated in the table. Movement joints are not
• Apply load to the lintels or beam before the
acceptable in solid party or separating walls; however where
also provide a compressible space into which the
cavity wall construction is adopted, offset movement joints with masonry supporting has hardened.
sealant can deform. a solid rubber compressible strip may be acceptable.
tray
• Continuously above lintels where openings are
separated by short piers
• Above openings where the lintel supports a
brick soldier course
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.1.14 Weep-holes droppings and debris as the work proceeds. 7.1.16 Steps and staggers
Weep-holes must be installed at no more than Particular care is needed in adequately preventing
900mm centres to drain water from cavity trays Ring beams or floor slabs that partially bridge the the ingress of water in a terrace of dwellings with
and from the concrete cavity infill at ground level. cavity, e.g. when dimensional accuracy cannot be steps and staggers. A proprietary cavity tray system
When the wall is to be cavity filled, it is advisable to guaranteed, should be protected by a continuous should be used, or alternatively, a suitable tanking
reduce this spacing. cavity tray, especially when full cavity insulation is system. Stepped cavity trays are required at all
employed. pitched (stepped) roof abutments with external
At least two weep-holes must be provided to drain cavity walls, e.g. attached garages or staggered
cavity trays above openings. terraces. The bottom (last) cavity tray must be
supplied with two stop-ends and an associated
Where the wall is externally coated with a weep-hole, allowing all water to escape over the
‘High Performance’ polymer modified factory lower roof covering. For brickwork, blockwork and
manufactured render system, the weep-holes are stonework, lead cover flashings should be linked
not deemed necessary for cavity wall construction. into the cavity tray (lapped in below).
Weep-holes in exposure zones 3 and 4 should be Other perforations of the building envelope
designed to prevent ingress of wind-driven rain Proprietary elements, such as ventilators, soil
(including ground level). pipes, etc. which perforate the building envelope
should be installed and sealed to prevent ingress
7.1.15 Stop-ends of moisture or vermin in accordance with the
Figure 18: Stop-end to cavity tray
Cavity trays should have water tight stop-ends manufacturer’s instructions. External meter boxes
Technical Manual V8: TS-11A-8.00-010117
to prevent water from running into the adjacent should be of a type approved by the Service
cavity. Stop-ends need to be bonded to the cavity Supply Authority and provided with a cavity tray
tray material or clipped to the lintel, so that a stop and a vertical DPC between the back of the box
to the structural cavity of at least 75mm high is and the wall.
provided. Normally, the stop-end is located to
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
It is important that the stone is laid with the grain Figure 24: Masonry cavity wall with stone outer leaf
Figure 23: Fixing of copings to sloping parapets Walls constructed with a cavity are essential where
the location is likely to be of moderate exposure or
worse. A sawn bed of 100mm minimum thickness
is to be used as the outer leaf of a cavity wall,
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Insulation
Full fill cavity insulation should only be considered
where the outer leaf is backed by brick/blockwork,
although this is still dependent on exposure, i.e.
Technical Manual V8: TS-11A-8.00-010117
prevent any staining to the stone. Figure 25: Stone jamb and mullion, fixing to walls Figure 26: Joining stone jambs to sills and head
137
CHAPTER 7
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. The design of the steel frame must be supported by structural
a workmanlike manner. calculations completed by a suitably qualified engineer. The design
and construction must meet the relevant regional Building Regulations
Materials
i. All materials should be stored correctly in a manner that will not cause Limitations of Functional Requirements
damage or deterioration of the product. i. The Functional Requirements are limited by the recommendations
ii. All materials, products and building systems shall be appropriate and applied to the specific areas covered in this chapter.
suitable for their intended purpose. ii. These Functional Requirements do not and will not apply to create
iii. Steel frames should be appropriately treated to prevent corrosion. any policy liability for any remedial works carried out by the contractor
iv. The structure shall, unless specifically agreed otherwise with the or otherwise, nor to any materials used in those remedial works.
Warranty provider, have a life of not less than 60 years. Individual
components and assemblies, not integral to the structure, may have a
lesser durability, but not in any circumstances less than 15 years.
Technical Manual V6: TS-011a-6.00-010413
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.2.1 Steel frame The design should detail how joints between the wall • Level of base of wall frame: +/-5mm over
Galvanised strip steel should be designated panels and other elements are to be securely fixed: complete wall line.
either grade S280GD or 350GD to BS EN 10326.
The structural design should be in accordance • To the structure Some packing may be needed to achieve the
with BS 5950–5: 1998, and imposed loads should • To adjacent panels required tolerances:
be calculated in accordance with BS EN 1991, • To the floor and roof
including: • Less than 10mm; pack under each steel with
The design should ensure that the structure is pre-galvanised steel shims.
• Dead loads adequately protected from the effects of moisture. • 10mm–20mm; pack under each steel with steel
• Imposed loads Exterior claddings should be compatible with the shims and grout over length of sole plate.
• Wind loads steel frame. Suspended floors should be designed • Over 20mm; refer to Frame Designer.
to support and transmit loads safely to the
Steel and fixings should be suitable for the design supporting structure without undue deflection. 7.2.3 Fixing of frames to substructures
and adequately protected against corrosion. Load- The oversite DPM should be attached to the side
bearing walls should be designed to support and Services should be adequately protected from of the slab and returned under the DPC on which
transfer loads to foundations safely and without damage, walls and floors should resist the spread the frame is placed. The DPC/DPM detail requires
undue movement. of fire. Internal walls and floors should be designed careful attention to prevent the cavity being bridged
to resist the passage of sound adequately. and providing a ledge for mortar droppings.
Wall panels may provide resistance to racking
forces using one or more of the following 7.2.2 Site tolerances Holding down anchors may be galvanised, or
techniques: It is essential that the accuracy of setting out preferably stainless steel straps that are fixed to the
Technical Manual V8: TS-11A-8.00-010117
foundations and ground beams are checked well stud wall and attached to masonry supports or
• Internal bracing in advance of materials being delivered to site. concrete foundation, or holding down bolts fixed to
• Cross flat bracing the concrete slab.
• External sheathing board For accurate erection of the frame the following
• Internal sheathing board tolerances are required at the level of the base of
• Rigid frame action
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.2.4 Walls 7.2.5 Metal stud framework provided in accordance with relevant Building
If stainless steel straps are used, they should be The wall panel usually consists of a head rail, base Regulations, and steel joists should be spaced at
grade 1.4301 steel to BS EN 10088 and isolated rail (sole plate) and possibly horizontal noggins at centres no greater than 600mm.
from the studs with neoprene gaskets or similar. mid-height, together with vertical wall studs:
Non-stainless connections should be isolated from Cutting holes for services on-site is not
the straps with suitable grommets and washers. • Recommended site connections include self- recommended, but where essential should be
Resin or expanding anchors should be used in drilling, self-tapping screws or 10mm–12mm carried out with specialist tools. The maximum size
an in-situ concrete raft of a minimum C20/GEN3 diameter grade 4.6 bolts. Welding is not of rectangular holes should not exceed 40% of the
grade concrete, if required, steel frames can be recommended on-site. overall section, and length should not exceed 60%
fixed to timber sole plates. • Workmanship should comply with BS 8000: 5. of the overall section or be the depth of the section
• Framed walls should be accurately aligned, apart. No holes should be closer than 1.5 times
For guidance on fixing sole plates refer to the plumb, level without twist and securely fixed to the depth of the section to the end of the member,
timber frame section in chapter 7.3 of this Manual. adjacent elements. notches are not acceptable.
The metal frame should be located entirely
above DPC level. Where this is not possible at Vertical tolerances are: 7.2.6 Thermal insulation
level entrance ramps to the principal entrance Rigid thermal insulation material should be fixed
door to dwellings only; a thickness of corrosion • +/-15mm in overall height of wall 3 storey or to the outside face of the steel studs to create a
protection equivalent toZ460 galvanising or a • +/-10mm in overall height of wall 2 storey or ‘warm frame’ construction.
suitable bituminous coating could be applied • +/-5mm in storey height (approx. 2.5m)
to all components below DPC level. However, Where the condensation risk has been assessed
the access ramp should only be limited to the A lintel should be provided where one or more and shown to be negligible additional insulation
Technical Manual V8: TS-11A-8.00-010117
entrance door area only (not the entire perimeter) studs is cut or displaced to form an opening. may be placed between the studs. The additional
and provision for a slotted drainage and the ramp A lintel is not required where an opening falls insulation should be placed in contact with the
provided with a gradient away from the door between studs. Non-load-bearing walls should studs to minimise air gaps and prevent local
should be provided. (See chapter 7.4 & 11.1 for have adequate strength and support. condensation.
level threshold guidance) It is recommended
© LABC Warranty
that the inner leaf DPC is turned up approximately Non-load-bearing walls should not bridge The following are acceptable:
30mm above the screed to protect the bottom of movement joints in the main structure. A movement
the studs from construction moisture and spillage, joint should be constructed between the frame • Mineral wool to BS EN 13162
and weep-holes are provided at 900mm centres to and any chimney flue lift shaft to prevent load • FR (flame retardant) grade expanded
drain cavities at ground level. transfer. Cavity barriers and fire stops should be polystyrene to BS EN 13163
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
• FR (flame retardant) grade extruded polystyrene 7.2.8 Vapour control layers (VCL) 7.2.9 Plasterboard
to BS EN 13164 VCL resist the passage of water vapour from Plasterboard should be to BS 1230 and not less
• Rigid polyurethane foam and polyisocyanurate within the dwelling and should be a minimum of than;
to BS EN 13166 500-gauge polyethylene sheet or vapour control
• Cellular glass to BS EN 13167 plasterboard. The vapour resistance (not resistivity) • 9.5mm for stud spacing up to 450mm or
of the vapour control material should not be less • 12.5mm for stud spacing up to 600mm.
7.2.7 Breather membranes than 250 MN.s/g or 0.25 Pa/m2.
Breather membranes should be capable of To provide fire resistance, fire rated boards should
allowing water vapour from within the frame to Installation be used and installed in accordance with the
pass out into the cavity and protect the sheathing A sheet membrane vapour control layer (VCL) manufacturer’s instructions.
and frame from external moisture. These should be; should be;
• Vapour-resistant to less than 0.6MNs/g when • lapped and sealed by at least 100mm at joints.
calculated from the results of tests carried out • lapped over studs, rails or noggins.
in accordance with BS 3177 at 25ºC, and with a • sealed around service penetrations.
relative humidity of 75%. • lapped and sealed fully into window and door
• Capable of resisting water penetration. reveals.
• Self-extinguishing. • lapped and sealed with DPM/DPC at the
• Durable. junction with the ground floor/foundation.
• Adequately strong when wet to resist site • able to accommodate differential movements.
damage.
Technical Manual V8: TS-11A-8.00-010117
• Type 1 to BS 4016 in areas of very severe Small holes in the VCL should be sealed with a
exposure to wind-driven rain. suitable self-adhesive tape. Larger holes should be
re-covered with new laps located over adjacent
If foil faced insulation is not used, then an studs and rails.
independent breather membrane should be
provided to the ‘cold side’ of the insulation.
© LABC Warranty
141
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.2.10 Masonry cladding Additional studs may be needed to achieve this; Other claddings should only be used if they
are provided with an acceptable third-party
• Cavity trays must be provided above all cavity • Ties should be inclined away from the frame. accreditation certificate.
barriers, windows and door openings, etc. • Ties should be fixed to the studs, not the
• Cavity trays should extend 150mm either side of sheathing.
the door or window openings and have • Ties should accommodate differential
stopped-ends. movement between the frame and the
• A continuous cavity tray should be provided cladding.
where intermediate floors meet the external wall. • Soft joints should be provided to allow for
• External skin of brickwork should be attached differential movement. A gap of 1mm per metre
to the metal frame with either epoxy coated of masonry should be provided at openings
galvanised ties or austenitic stainless steel ties and soffits.
(to DD 140, BS 1243, BS 5268, BS 8200). • All brick support angles should be installed by
• Ties are normally fixed in vertical channels, the manufacturer or Specialist Contractor.
these channels are then fixed directly to
sheathing boards or attached through 7.2.11 Claddings
insulation boards with stand-off screws (screws More traditional claddings can include, amongst
should be isolated from the channels with others, timber boarding, plywood and tile hanging.
neoprene or similar washers). These types of cladding should be fixed to battens
• Ties should be spaced at jambs of openings, a and suitably attached at stud positions. For further
maximum of 300mm vertically within 225mm of details, refer to the timber frame section of this
Technical Manual V8: TS-11A-8.00-010117
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of
of this Manual. the design intent and demonstrate a satisfactory level of performance,
ii. All work is to be carried out by a technically competent person in supported by structural calculations provided by a suitably qualified
a workmanlike manner. expert.
iii. Certification is required for any work completed by an approved ii. The materials, design and construction must meet the rrelevant
installer. regional Building Regulations
iii. Any off-site manufactured engineered beams/posts must have
Materials structural calculations endorsed by the manufacturer.
i. All materials should be stored correctly in a manner that will not cause
damage or deterioration of the product. Timber frame elements Limitations of Functional Requirements
Technical Manual V6: TS-011a-6.00-010413
should be appropriately protected to keep components dry. i. The Functional Requirements are limited by the recommendations
ii. All materials, products and building systems shall be appropriate and applied to the specific areas covered in this chapter.
suitable for their intended purpose. ii. These Functional Requirements do not and will not apply to create
iii. The structure shall, unless specifically agreed otherwise with the any policy liability for any remedial works carried out by the contractor
Warranty provider, have a life of not less than 60 years. Individual or otherwise, nor to any materials used in those remedial works.
components and assemblies, not integral to the structure, may have
Technical Manual V8: TS-11A-8.00-010117
143
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.3.1 Specifications
7.3.1.1 Introduction
This chapter refers to ‘conventional’ timber frame
open panel systems made off-site under factory
conditions. Such panel systems are required to be
manufactured and erected on-site under quality
assured systems and be either Structural Timber
Association or BM TRADA registered.
7.3.1.2 General specifications requirements of the Technical Manual, please refer All load-bearing solid timber studs, rails, binders and
to chapter 3. All detailing requirements for timber sole plates should be of a minimum dry graded C16.
Note: Bespoke timber frame open panel systems frame contained within this chapter will also be
that do not have such QA procedures as the applicable to SIPs.
‘conventional’ timber frame open panel systems
described in chapter 7.3.1.1 will need either third- 7.3.1.3 Structural design
party accreditation or independent Structural Wind, roof and floor loads should be considered
Engineer supervision and monitoring of the in the design and all timber frame structures shall
installation, erection and completion (sign off) of be designed in accordance with Eurocode 5.
the system. All load-bearing timbers will have to be Structures designed in accordance with BS 5268 Figure 2: Typical grading stamp
preservative treated in accordance with BS 8417 may still be acceptable, although these standards
according to their position within the frame, and have now been superseded by Eurocode 5.
evidence of treatment must be provided. Sizing of structural timber
Quality assurance Timber studs and rails shall be a minimum of 37mm
Green Oak is not acceptable for use in external All timber Frame Designers, Manufacturers and in width.
wall, frame or internal wall or roof constructions, Erectors should possess current certification from at
regardless of whether it forms part of the least one of the following quality assurance schemes: Treatment of structural timber
waterproof envelope or not. Projects incorporating All load-bearing timber components shall be either
‘green Oak’ will not be acceptable for Warranty • BM TRADA QMark for timber frame naturally durable or treated in accordance with
BS 8417: Preservation of wood Code of Practice.
cover. Green Oak is defined for Warranty purposes • ISO 9001
Sole plates and load-bearing timber studwork are
as ‘Oak that has been freshly cut or air dried’. • CE Marking when EN 14732 is published
considered to be in ‘Use Class 2’. Sole plates are
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Sole plates
The sole plate is the first structural timber
component installed on site. Its purpose is to set
out the building, transfer loads to the foundations
and provide a level base for erecting the wall
panels. All structural timber should be located
at least 150mm above finished external ground
level, except for localised ramping (incorporating
satisfactory drainage and ventilation detailing)
around door openings.
Sheathing boards
Figure 3: Sole plate/foundation junctions
Sheathing boards are fixed to the timber frame in
order to provide racking resistance to the structure.
Structural sheathing board materials may be any
© LABC Warranty
of the following:
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
• Orientated Strand Board (OSB) 7.3.1.5 Other material specifications Breather membranes should be;
• Plywood
• Impregnated soft board Fixings • Minimum Class W2 or better in accordance with
• Other board material with suitable All sole plate fixings and holding down products BS EN 13859: Flexible sheets for waterproofing –
third-party certification should be austenitic stainless steel. Definitions and characteristics of underlays.
• Securely fixed to protect the outside face of the
All wood-based panel products should comply Timber framing components and structural timber frame structure with austenitic stainless
with BS EN 13986: Wood-based panels for use sheathing boards may be fixed with; steel staples.
in construction – characteristics, evaluation of
conformity and marking. • Nails Cavity barriers
• Staples Cavity barriers are required to prevent the spread
OSB should be grade 3 or 4 in accordance with BS of smoke and flame within concealed spaces.
EN 300: Oriented Strand Boards (OSB) – Definitions, Nail fixings should be;
classification and specifications. Cavity barriers may be constructed from;
• Austenitic stainless steel
Plywood should be at least Class 2 Structural in • Steel at least 0.5mm thick
• Galvanised
accordance with BS EN 636: Plywood Specifications. • Timber at least 38mm thick
• Sheradised
• Polythene sleeved mineral wool
Impregnated soft boards should be Type SB.HLS • Mineral wool slab
Staple fixings should be austenitic stainless steel or
in accordance with BS EN 622-4: Fibreboards, • Calcium silicate, cement-based or
similar.
specifications and requirements for soft boards. gypsum-based board at least 12mm thick
• An independently assessed and certified
Breather membrane
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Thermal insulation products typically used are; Special consideration should be given to Subject to a favourable condensation risk analysis,
condensation risk where non-breathable insulation a novel or reverse wall construction may not
• Mineral fibre (glass or rock) products are installed on the outside of the timber require the use of a high moisture vapour-resistant
• Wood fibre/wool frame structure. Joints between foil faced external vapour control membrane.
• Blown cellulose insulation boards, must not be taped as this forms a
vapour control layer on the cold side of the insulation. Wall linings
Other insulation materials may be used subject to The internal lining of the timber frame wall may be
relevant third-party certification. Vapour control layer (VCL) required to perform four functions;
A VCL is a moisture vapour-resistant material
Insulation may be specified in any or all of the located on or near the warm side of the thermal • Provide the finish or a substrate to accept the
following locations; insulation. finish on the inner face of the wall.
• Contribute to the racking resistance of the wall.
• Between the load-bearing studs Its purpose is to; • Contribute to the fire resistance of the wall.
• On the outside of the timber frame • Contribute to the acoustic performance
• On the inside of the timber frame • Restrict the passage of moisture vapour through of the wall.
the structure of the wall
Insulation installed to the outside of the timber • Mitigate the risk of interstitial condensation Wall linings are typically:
frame structure should have third-party certification
for this application and retain a clear cavity The VCL should have a minimum vapour resistance • Gypsum plasterboard
dimension, as detailed in Table 1 in chapter 7.3.4. of 250 MN.s/g or 0.25 Pa/m . It is also typically used
2
• Fibre reinforced gypsum board
The outer layer of insulation should also be covered as an air tightness layer. • Cement bonded particle board
Technical Manual V8: TS-11A-8.00-010117
time of the year, and it fulfils the minimum National • A minimum 125 micron thick (500 gauge)
requirement for thermal performance. polythene sheet.
• A third-party approved proprietary vapour
control membrane product.
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Wall ties
External wall ties and fixings between the timber
frame and masonry cladding shall:
149
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.3.2.4 Sheathing
The fixings securing the structural sheathing board
Technical Manual V8: TS-11A-8.00-010117
Sheathing fixings must not be over-driven through • A lintel may be required where openings do Special precautions must be taken to protect
the face of the sheathing board. not fall between studs, unless vertical load is closed panels from moisture during storage,
adequately transferred by other elements. transportation and erection on-site.
Wood-based board materials used for sheathing • Lintels will require support by cripple studs.
should be fixed to the studwork frame leaving a • Studs should be provided around window 7.3.3 Site preparation and erection
3mm minimum gap between boards to allow for and door openings and adjacent to movement
moisture-related movement. joints to allow the installation of wall ties or other 7.3.3.1 Pre-commencement
cladding fixings. To allow the building to be constructed as
7.3.2.5 Studs designed all necessary drawings, specifications
Studs should be accurately cut to length and bear 7.3.2.7 Breather membrane and fixing schedules shall be provided to site
tightly against the wall panel top and bottom rails. Breather membranes should be lapped by a before work commences.
minimum of 100mm at horizontal joints, and a
Any point load imparted onto the timber frame minimum of 150mm at vertical joints. If breather Foundations
should be transferred down through the building membranes are trimmed flush with the edges It is important that the tight tolerances for timber
to the foundations with the use of multiple studs. of wall panels, additional strips of breather frame are understood, getting the location and
If these are not installed during the manufacture membrane, at least 300mm wide, should be level of the foundation correct is one of the most
of the panels the requirement for installation must supplied and site fixed over panel junctions. important parts of the build process.
be clearly conveyed to site.
The location of solid timber studs should be The foundations or upstands that support the
Wall panels should be designed to minimise clearly marked on the outer face of the breather timber frame should be set out to the dimensions
thermal bridging. Gaps between studs within the membrane to ensure that cladding fixings are noted on the timber frame drawings:
Technical Manual V8: TS-11A-8.00-010117
wall panel and at wall panel junctions should be installed into solid timber.
large enough to allow the installation of insulation. • Within +/-10mm in length, width and line
7.3.2.8 Closed panel construction • Diagonals should be within +/-5mm up to 10m,
7.3.2.6 Openings If wall panels are to be of closed panel and +/-10mm more than 10m
All openings including doors, windows, flues construction, the guidance in chapter 7.3.4 applies • Levelled to +/-5mm from datum
and ventilation ducts should be designed and
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Location
Sole plates should;
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
• Be located under sole plates to provide full • +/-5mm from line at mid height of wall panel.
width bearing to studs. • Inside faces of adjacent wall panels should be
• Provide full bearing under point loads. flush.
• Not exceed a total of 10mm in height without • Adjacent wall panels should be tightly butted.
a Structural Engineer’s approval. Figure 9: Packing of sole plates
© LABC Warranty
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
binders should not occur together. • If no head binder is present, floor joists must
• Head binder laps should wherever possible bear directly over studs.
occur over a stud, preferably at least 600mm • Waistbands and alignment of floors over walls
from the panel junction. should remain within tolerances for wall panels.
155
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Cavity barriers/firestopping
at head of party wall Cavity barriers are required
Flats at eaves and verge
Installation A cavity tray should be provided directly above Timber cavity barriers should be protected from
Technical Manual V8: TS-11A-8.00-010117
Cavity barriers shall be installed: a horizontal cavity barrier and lapped at least masonry and lightweight render cladding by the
100mm behind the breather membrane (except at use of a DPC. The cavity face of the barrier should
• So they fully close the cavity. eaves and verges). be left uncovered to allow drainage and ventilation
• So the ends are tightly butted to form a of the timber. The use of timber cavity barriers
continuous barrier. around openings allows for effective sealing to be
© LABC Warranty
• Backed by solid timber studs, rails or floor joist at installed between them and the opening frame.
least 38mm wide.
• In accordance with manufacturer or
independent certifier’s guidance.
157
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.3.4 Main contractor • Cavity trays should be fixed and lapped over 7.3.4.2 Services
the cavity facing breather membrane to deflect In addition to general provisions for the installation
7.3.4.1 Insulation cavity moisture away from the timber frame. of services, the following are of particular note for
If insulation is specified between external walls • Allowance should be made for differential timber frame construction external walls:
studs all voids shall be filled with insulation to movement to occur at floor zones.
maintain the thermal envelope of the building. • Cavity barriers should be tightly fitting and • The routing and termination of services should
When noggins or boards are installed between remain effective in a fire. Depending in the type not affect the fire resistance of the structure.
studs to support services or heavy fittings the void of insulation used, cavity barriers may need to • Electrical services are to be rated for their
behind them shall be fully insulated. pass through the insulation, back to solid timber location with consideration for insulation.
within the timber frame structure behind. • Wet services are not to be installed on the cold
Insulation should not be installed until the structural • It should not retain or transmit moisture to side of the insulation.
timber frame is below 20% moisture content and cause the timber structure to exceed 20% • Service penetrations through the VCL should be
the building is weather tight, as wet insulation can moisture content. tight fitting to reduce air leakage and the
retain moisture. If closed panel timber frame is • Stud locator marks should be transferred onto passage of moisture vapour.
specified additional care must be taken to protect the outer face of the breather membrane • Avoid running electrical services in the external
the panels from exposure to moisture during adjacent to the external wall cavity. wall cavity, except for meter tails.
construction with moisture content checks carried • Wall ties should transfer loads to the timber • Services should be protected with metal plates
out before full closure. frame structure. To achieve this, wall ties will if they pass within 25mm from face of stud.
typically need to be installed through the • Adequate allowance for differential movement
Note: The above also applies equally to insulated external insulation rather than bearing onto it. to occur without causing damage should be
party wall cavities • Joints between foil faced insulation boards must provided for rigid services rising vertically
Technical Manual V8: TS-11A-8.00-010117
7.3.4.3 Vapour control layer (VCL) Vapour control plasterboard should be;
A VCL should not be installed until the structural
timber frame is below 20% moisture content and • Fixed in accordance with the plasterboard
the building is weather tight. manufacturer’s installation guidance.
• Tightly cut and fitted around service
Installation penetrations.
A sheet membrane (polythene or proprietary) • Discarded if the vapour control backing is
VCL should be; damaged.
159
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.3.4.5 Openings • The element being installed into the opening is Figure 17: Window/wall junction (jamb)
All openings including doors, windows, flues likely to have a minimum thermal performance.
and ventilation ducts, should be designed and • Seal gaps between the timber frame wall and
constructed to maintain: the element being installed into the opening to 7.3.4.6 Claddings
provide thermal performance, weather tightness All external wall claddings should be separated
Fire performance and air tightness. from the timber frame structure by a drained and
Technical Manual V8: TS-11A-8.00-010117
• Cavity trays should be installed over the heads ventilated clear cavity. If partial fill cavity insulation
• Internal reveals require equal fire resistance to of all openings, lapped behind the breather is to be used, the same width of clear cavity is to
the rest of the structure. membrane by a minimum of 100mm. A flashing be maintained in addition to the insulation depth.
• Window fixing straps should not compromise may be acceptable for some types of
the integrity of any fire-resistant reveal linings. claddings. In some locations, for example close to boundaries,
• Cavity barriers should be installed in the National Regulations require claddings to provide
© LABC Warranty
Self-supporting claddings (masonry) • Be fitted in the brick or block course below the frame wall. These should be fixed into structural
Self-supporting (masonry) claddings should be lowest timber sole plate above external finished timber not just through the sheathing to the
connected to the timber frame using wall ties: ground level and below DPC. Structural Engineer’s specification.
• Be provided to ensure drainage and ventilation
• Installed into studs provided around openings to each external wall concealed space directly Cavity drainage and ventilation should provide an
and movement joints, not just through above horizontal cavity barriers/trays. open area of not less than 500mm2 per metre run:
sheathing. • Be installed over openings in the external wall
• Angled to drain moisture away from the timber cavity e.g. windows and doors at a maximum • At the base of the external wall concealed
frame even after differential movement has of 900mm centres. space.
occurred. • Maintain a clear cavity with care taken to • Above horizontal cavity barriers/trays.
• Installed at a minimum density of 4.4/m2 reduce mortar droppings at the base of the wall. • Over openings in the external wall cavity, e.g.
(a maximum of 375mm vertically with studs windows and doors.
at 600mm centres and a maximum of 525mm Weep-holes alone are unsuitable for timber frame • Allowing differential movement to occur while
vertically where studs are at 400mm centres), construction, and open perpends should be used. retaining an adequate gap.
closer centres may be required in exposed Proprietary open perpend inserts are available with • With openings protected by a mesh to prevent
locations. insect screening incorporated. Their equivalent the passage of insects.
• Installed at a maximum of 300mm centres open area must be considered and installation
vertically and 225mm horizontally around centres reduced accordingly. Timber frame external wall minimum cavity widths
openings and movement joints. Masonry 50mm
• Installed within 225mm of the head of a wall. In areas of severe or very severe exposure, Render on unbacked lath 50mm
• Studs should be provided in the timber frame check reveals should be constructed to provide Render on backed lath or board 25mm
Technical Manual V8: TS-11A-8.00-010117
structure to provide support for wall ties at additional weather protection. Timber 19mm
vertical movement joints in the masonry Tile hanging 25mm
cladding. Vertical loadings from masonry claddings must not
Table 1: Minimum cavity widths
be supported by the timber frame structure.
Cavity drainage and ventilation in masonry
7.3.5 Differential movement
cladding should: Claddings supported on the timber frame
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Anticipated differential movement can be The size of the gap should be calculated by
calculated using the allowance of 1mm for every allowing 1mm for every 38mm of horizontal cross
38mm of horizontal cross grain timber. As solid grain timber present between the gap location
timber joists contribute significantly to anticipated and the lowest structural timber. Gaps will therefore
differential movement, engineered timber joists increase in size up the building. The dimensions
should be considered where it is desirable to provided in Figure 19 should be used if site-specific
reduce differential movement. calculations have not been provided.
differential movement to take place, thus avoiding Figure 22: Differential movement at verge
163
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.3.6 References BS EN 14081-1: 2005 Timber structures. Strength EN 14732: 2011 Timber structures. Prefabricated wall,
BS EN 1995-1-1: 2004+A1: 2008 Eurocode 5 Design graded structural timber with rectangular cross floor and roof elements. Requirements Draft
of timber structures. General. Common rules and section. General requirements. for comment.
rules for buildings.
BS 8417: 2003 Preservation of timber.
BS 5268-2: 2002 Structural use of timber. Code of Recommendations.
Practice for permissible stress design, materials and
workmanship. BS EN 13986: 2006 Wood-based panels for use
in construction. Characteristics, evaluation of
BS 5268-3: 2006 Structural use of timber. Code of conformity and marking.
Practice for trussed rafter roofs.
BS EN 300: 2006 Oriented strand boards (OSB).
BS 5268-4 Section 4.1: 1978 Structural use of Definitions, classification and specifications.
timber. Part 4 Fire resistance of timber structures.
Section 4.1 Recommendations for calculating fire BS EN 636: 2003 Plywood. Specifications.
resistance of timber members.
BS EN 622-4: 2009 Fibreboards – Specifications.
BS 5268-4 Section 4.2: 1990 Structural use of Requirements for softboards.
timber. Part 4 Fire resistance of timber structures.
Section 4.2 Recommendations for calculating fire BS EN 622-3: 2004 Fibreboards – Specifications.
resistance of timber stud walls and joisted floor Requirements for medium boards.
Technical Manual V8: TS-11A-8.00-010117
constructions.
BS EN 622-2: 2004 Fibreboards – Specifications.
BS 5268-6.1: 1996 Structural use of timber. Code Requirements for hardboards.
of Practice for timber frame walls. Dwellings not
exceeding seven storeys. BS 4016: 1997 Specification for flexible building
© LABC Warranty
CHAPTER 7
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
iii. Certification is required for any work completed by an approved a suitably qualified expert.
installer. iii. The materials, design and construction must meet the relevant
regional Building Regulations.
Materials
i. All materials should be stored correctly in a manner that will not cause Limitations of Functional Requirements
damage or deterioration of the product. i. The Functional Requirements are limited by the recommendations
ii. All materials, products and building systems shall be appropriate and applied to the specific areas covered in this chapter.
suitable for their intended purpose. ii. These Functional Requirements do not and will not apply to create
iii. Whilst there is and can be no Policy responsibility and/ or liability for any policy liability for any remedial works carried out by the contractor
a window and/ or door performance life of 60 years or less, windows or otherwise, nor to any materials used in those remedial works.
and / or doors shall be designed and constructed so they have an
Technical Manual V6: TS-011a-6.00-010413
7.4.1 Windows and doors Doors and windows should be selected to Roof lights should be proprietary components, fixed
Timber used for external joinery should be a withstand the design weather conditions and within prepared openings in accordance with the
species classified as suitable in BS EN 942 and be classified and tested in accordance with the manufacturer’s instructions and have effective
preservative treated; if not, use a moderately following weather performance standards weather sealing.
durable species or better (sapwood excluded).
Guidance on selection is provided in TRADA Wood • BS 6375-1 Weather tightness Non-timber components should comply with the
Information Sheets 3.10 and 4.16. • Air permeability - BS EN 12207 - Classification & following British Standards (as appropriate), and
BS EN 1026 - Test method be installed and fixed in accordance with the
Workmanship should follow the recommendations • Water resistance - BS EN 12208 - Classification & manufacturer’s recommendations:
of BS 1186: 2. The design and construction BS EN 1027 - Test method,
of factory assembled windows must meet BS • Wind resistance - BS EN 12210 - Classification & • BS 4873 Aluminium alloy windows and doorsets
644:2009. Non factory assembled units and BS EN 12211 – Test method • BS EN 514 PVC-U windows
‘bespoke’ units are also expected to meet the • BS 7412 PVC-U windows
same standard. Bespoke / handmade window and door units must • BS 6510 Steel windows and doors
be designed and constructed to meet the same
Preservative-treated joinery cut or adjusted on-site level of weather tightness as factory made tested PVC-U windows and doors should also be subject
should be brushed liberally with an appropriate units. Where these are proposed, there must be a to independent third-party certification.
and coloured preservative. Where the colour detailed specification of the design, construction
of the preservative will adversely affect the final and durability of the proposed units submitted to Windows and doors should comply with the current
appearance of the joinery, an appropriate clear the Warranty provider before installation on site. Building Regulations taking into consideration:
preservative should be used. Where a painted
Technical Manual V8: TS-11A-8.00-010117
finish is proposed to the window / door frame and For bespoke / handmade windows; Site testing • Means of escape in the event of a fire
opening units; the primer coat should be applied for water penetration of the joints to windows and • Thermal insulation
to all final exposed parts, including rebates prior to doors in accordance with the CWCT test methods • Ventilation
glazing installed or bottoms of doors, is recommended to check the site workmanship of • Safety
the building envelope as constructed. See CWCT • Security
Bay, oriel and dormer windows require particular
© LABC Warranty
167
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.4.2 Thresholds and sills It is recommended that a mat well be constructed • BS 4787: 1 Internal and external wood door sets,
Thresholds and sills should be at least 150mm within the entrance hall to accommodate the door leaves and frames
above finished ground level. However, where a swing of the door without fouling the carpet • BS 6262 Code of Practice for glazing for building
level (threshold) access is required, builders can and/or the proprietary door seal to maintain the • BS 6375: 1 Performance of windows
follow the general guidance given in Figures integrity of the seal. • BS 644: 1 Wood windows
1, 2 and 3, ensuring a high level of supervision • BS 8213: 1 Windows, doors and roof lights
and workmanship, together with the correct External doors and opening lights to windows
specification of materials and consideration to should be reasonably air tight by ensuring that
design, location and exposure. effective draught seals are fitted.
Wherever possible locate the entrance door away External joinery should be designed and
from the prevailing weather and provide a storm constructed in accordance with the requirements
porch. Where a drainage channel is provided, this of the following British Standards:
must be connected to the storm drainage system
to prevent flooding occurring and water ingress
into the building.
External
wall Perimeter Non-deformable suitable
insulation cavity closer (insulated)
Landing area
Floor finish
Technical Manual V8: TS-11A-8.00-010117
Figure 1: Typical level threshold suspended beam and block floor Figure 2: Typical level threshold suspended concrete slab Figure 3: Typical level threshold with canopy protection
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
provided at the main door to the dwelling to In the absence of an assessment by a suitably
allow means of seeing callers. The same door qualified person, any glass which is required to
sets should also have a securely fixed door provide containment must meet with BS EN 12600
chain or door limiter fitted Class 1(C)1. 169
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
• The water drip to window and door sills, projects Proprietary materials with third-party certification
beyond the wall or sub-sill by at least 10mm should be used to close cavities at window
and the sill edge by at least 25mm and door openings. They should also be
• The reveal should be protected throughout its installed in accordance with the manufacturer’s
width by a continuous dpc. The width of the recommendations.
dpc should be sufficient to be fixed to / or
overlap, the frame and fully protect the reveal. 7.4.9 Fire doors
Alternatively, an insulated finned cavity closer Any door between a dwelling and an attached or
with third-party certification may be used. integral garage should be a half-hour fire-resisting
door and frame.
Figure 5: Emergency egress window provision
Frames should be fixed in accordance with • Small panes thickness as the area of the panel increases to
the manufacturer’s recommendations or, if no • Robust be considered ‘safe’. As an alternative to any of
instructions are given, with the following guidance: • Break safely the above solutions it is possible for the material
to break ‘safely’ when tested to BS EN 12600 which
• Fixings should be at 600mm maximum centres If permanent protection is provided, there is no would mean that:
and within 150mm of corners of the frame.
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
• The pane disintegrates with only small Glazing should be in accordance with BS • Any glazing on-site must have a drained and
detached particles. 6262. Insulated glass units (IGU) should meet ventilated bottom bead with a minimum gap of
requirements of BS EN 1279 – Glass in building – 5mm between the edge seal of the insulated
A glazing material would be suitable for a critical insulating glass units, be CE marked and carry glass unit and the bottom channel of the
location if it meets the requirements of BS 6262 – 4 third-party accreditation. This includes windows frames glazing rebate.
Table 1 when tested in accordance with BS EN in possession of a BBA certificate and timber • Any glazing with an area greater than 1m2
12600. Glass installed in a door or in a side panel windows. must have a drained and ventilated bottom
to a door that exceeds 900mm wide must meet the bead with a minimum gap of 5mm between
relevant requirements of BS EN 12600 and BS 6262 - • They should have continuous dual seals; single the edge seal of the insulated glass unit and
4. (See figure 9 below for the critical locations) seal units are not acceptable. the bottom channel of the frames glazing
• Desiccant should be provided to spacer bars. rebate.
• Glazing with an area less than 1m2 may be
solid bedded.
• All spacer bars should be stamped with
BS EN 1279.
• PVC-U frames and spacer bars should be
Doors and side panels stamped with BS 7412, 7413 and 7414.
Windows
Linseed oil glazing putty should not be used when
the joinery is finished with vapour permeable paint
or stain. Glazing putty should also not be used with
Technical Manual V8: TS-11A-8.00-010117
External glazing beads should be pinned at a • Housing window boards into frames to prevent Faults include;
maximum of 150mm centres (a maximum of condensation entering the joint.
50mm from corners) or screwed at 200mm centres • Providing thermal insulation to walls at lintels, • Inclusions, bubbles, spots and stains.
(maximum 50mm from corners). sills and jambs. • Residues within the insulated glass unit cavity.
• Using trickle ventilators, or similar, to provide Fine scratches not more than 25mm long
The preferred method of installation for double- background ventilation where required by the • Minute particles
glazed units is either; Building Regulations. Further guidance on this
subject is provided in BRE report BR 262, Thermal When assessing the appearance of glass:
• Drained and ventilated frames, as insulation: Avoiding risks 2002.
recommended by the Glass and Glazing • The viewing distance used shall be the furthest
Federation (GGF), where possible this method Nickel sulphide inclusions in glazing stated in any of the BS EN Standards for the
should be adopted for external glazing. Toughened glass which is installed in windows glass types incorporated in the glazed unit. In
• Solid bedding of units in 16mm–18mm deep and patio doors which are externally beaded in the event of doubt the viewing distance shall
frame rebates; 18mm rebates are buildings that exceed 3 storeys in height must be three metres.
recommended by the GGF to allow for be Heat Soak Tested in accordance with BS EN • The viewing shall commence at the viewing
tolerances. In all cases, sealants should not 14179-1. The glass must be permanently marked distance and shall not be preceded by viewing
be sensitive to ultraviolet light. External glazing in accordance with BS EN 14179-1, or copies of at a closer distance.
beads should be fixed at a maximum of 150mm test certificates must be disclosed for all affected • The viewing shall be undertaken in normal
centres, and the glazing bedded in non-setting panes. daylight conditions without use of
putty. Louvre windows should not be used and magnification.
double-glazing should be fixed and bedded as Appearance of glazing
Technical Manual V8: TS-11A-8.00-010117
recommended by the GGF. Glass must meet the visual assessment criteria The above does not apply within 6mm of the edge
of the Glass and Glazing Federation and CWCT of the pane, where minor scratching is acceptable.
Control of condensation Technical Note 35 (TN 35). The total number of Scratches on doors, windows and frames and
Minimise the effects of condensation on glazing faults permitted in a glass unit shall be the sum factory finished door and window components
and frames by; total of those permitted by the relevant BS EN should not have conspicuous abrasions, or
© LABC Warranty
Standard for each pane of glass incorporated into scratches when viewed from a distance of 0.5m.
• Using insulated or thermally broken metal the unit concerned.
frames.
• Using details that prevent condensation running
onto walls or floors. 173
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.5 CHIMNEYS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
iii. Certification is required for any work completed by an approved a suitably qualified expert.
installer. iii. The materials, design and construction must meet the relevant
regional Building Regulations.
Materials
i. All materials should be stored correctly in a manner that will not cause Limitations of Functional Requirements
damage or deterioration of the product. i. The Functional Requirements are limited by the recommendations
Technical Manual V6: TS-011a-6.00-010413
ii. All materials, products and building systems shall be appropriate and applied to the specific areas covered in this chapter.
suitable for their intended purpose. ii. These Functional Requirements do not and will not apply to create
iii. The structure shall, unless specifically agreed otherwise with the any policy liability for any remedial works carried out by the contractor
Warranty provider, have a life of not less than 60 years. Individual or otherwise, nor to any materials used in those remedial works.
components and assemblies, not integral to the structure, may have a
lesser durability, but not in any circumstances less than 15 years.
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
175
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.5.1 Support 7.5.2 Chimneys and flues A suggested checklist for these reports is provided
If a chimney is not provided with adequate Ensure that all gas flues terminate to the open air, in Approved Document J. Special blocks are made
support using ties or not securely restrained, its i.e. flue blocks must terminate at an appropriate to accommodate gas fire flues, which tend to be
height (measured to the top of the chimney) ridge vent or similar even where no appliance is slightly thicker than normal units. When used in
should not exceed 4.5 times its least horizontal fitted prior to the sale/occupancy of the property. external walls care should be taken not to reduce
dimension when measured from the highest point To demonstrate that flues comply with Building the clear cavity width below 50mm.
of intersection with the roof surface (density of Regulations, reports showing that flues have
masonry must be a minimum of 1,500kg/m3). passed appropriate tests are to be made available. If the chimney is in a severe exposure zone the
cavity should extend around the outside of the
stack and be continuous up to roof level, as per
BS 5628, Part 3: 2001. Where the chimney breast
is gathered in the lower projecting masonry
should be protected with a suitable capping and
cavity trays. A 50mm cavity at the back of the
chimney breast is maintained to prevent rainwater
penetration.
• Non-combustible.
• Reasonably smooth internally.
• Correctly jointed with mortar with the space
between the liners and the brickwork filled with
weak insulating concrete, unless the
manufacturer recommends an alternative
© LABC Warranty
specification.
• Properly jointed at the junctions with the starter
block or lintel and outlet terminal.
Figure 1: Typical chimney details
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
A notice plate containing safety information about 7.5.4 Chimney tray, low level (or European equivalent) valid third-party
any hearths and flues should be securely fixed in an A chimney tray is required at low level where a accreditation (e.g. British Board of Agrément,
unobtrusive but obvious position within the home. cavity-walled chimney with brick shoulders is built BRE, etc.) which demonstrates adequacy and
onto an external wall. The tray prevents water that durability for use (see chapter 2.3.5).
Where a chimney forms part of a wall, the may enter the shoulders from penetrating to the
foundation should project at least 100mm wider inner leaf of the wall.
than the chimney base and should be the same
depth as the adjacent wall foundation. Factory- The material used is 1mm aluminium alloy sheet to
made insulated chimneys should have a life of at BS EN 485-2: 1995 Aluminium and Aluminium Alloys.
least 30 years and be designed in accordance Sheet Strip and Plate, Mechanical Properties. This
with BS 4543 and BS EN 1859, and installed in has a higher melting point than lead, so is suitable
accordance with BS 7566. Where a chimney is not for installation close to a heat source.
directly over an appliance or opening, a soot box
accessible for emptying should be formed. A high level may be required to prevent the entry of
water at high level where a chimney rises through
7.5.3 Corrosion of lead work a pitched roof; suitable for new build or remedial
Where free lime from mortar comes into contact work, this minimises disturbance to surrounding
with lead trays or flashings (due mainly to the construction in remedial work. Figure 2: Typical flashing to chimneys
paint covering the faces likely to be in contact purposes. Code 4 as standard. Standard sizes
with the mortar. The protection against corrosion are 800mm x 800mm, 900mm x 900mm, 950mm x
of lead work buried in mortar is suggested in 950mm, to suit either a 195mm square or 195mm
guidance issued by the Lead Sheet Association. diameter circular flue.
This treatment can also reduce the staining of lead
and brickwork. It is unnecessary to treat flashings 7.5.5 Lead work
© LABC Warranty
buried only 40–50mm into mortar joints (cover Lead sheet used for roofs, flashings and
flashings), as this close to the drying surface the weathering’s should in terms of suitability meet
carbonation of free lime is rapid and there is no risk the requirements of the Technical Manual, or
of corrosion in such circumstances. be in accordance with BS EN 12588 or a UKAS Figure 3: Flashings to chimneys at ridge 177
CHAPTER 7
FUNCTIONAL REQUIREMENTS
7.6 BALCONIES
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
a suitably qualified expert.
Materials iii. Balconies must have appropriate guarding meeting the relevant
i. All materials should be stored correctly in a manner that will not cause regional Building Regulations.
damage or deterioration of the product.
ii. All materials, products and building systems shall be appropriate and Limitations of Functional Requirements
suitable for their intended purpose. i. The Functional Requirements are limited by the recommendations
iii. The structure shall, unless specifically agreed otherwise with the applied to the specific areas covered in this chapter.
Warranty provider, have a life of not less than 60 years. Individual ii. These Functional Requirements do not and will not apply to create
components and assemblies, not integral to the structure, may have any policy liability for any remedial works carried out by the contractor
a lesser durability, but not in any circumstances less than 15 years. or otherwise, nor to any materials used in those remedial works.
iv. Whilst there is and can be no Policy responsibility and/ or liability for a
Technical Manual V6: TS-011a-6.00-010413
Figure 1: Warm roof (section) Figure 2: Inverted warm roof (section) Figure 3: Cold roof (section) 179
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Resistance to wind load 7.6.3.2 British and industry standards Fall at mitre will be less than
fall in each roof plane
In all situations, including ballasted and inverted The requirements of BS 6229 should prevail in
roofs, a calculation of wind load to BS EN 1991-1-4 respect of balconies and terraces, whether or 1:80 Finished 1:80 Finished
Fall Fall
should be undertaken by a suitably competent not they form part or the entire roof to occupied
person. Wind load acting on a balcony will be parts of a building, and irrespective of the type of
affected significantly by the design of the perimeter waterproof membrane.
RWO RWO RWO
and by the geometry and finishes on the elevations Falls are not required for podium decks, provided:
of the building. Any changes to these elements will
1:80 Finished
necessitate a review of the calculation output. • They are designed with pedestrian finishes, Fall
RWO
which allow rainwater to drain rapidly from the
Resistance to imposed loads finished surface and not to accumulate upon it. Separate gutter
RWO
At the earliest possible stage the employer should • The waterproof membrane has current
to fall
define the range of potential imposed loads certification (see chapter 7.10 Roof Coverings –
for which the balcony is to be designed such Continuous Membranes) for use at zero falls in 1:80 Finished
Fall
as planters, storage and public access. In the this application.
absence of such a performance requirement the
RWO Box Gutter
loading limits of the balcony should be defined.
Wherever practical, balconies and terraces should
This design is not
be designed to fall away from the building elevation. acceptable
7.6.3 Falls and drainage
If this is not practical for reasons of continuity of
rainwater services, the falls should be arranged Figure 4: Drainage layout options
7.6.3.1 Statutory requirement
across the balcony, parallel to the elevation.
Design for drainage should comply with the
Technical Manual V8: TS-11A-8.00-010117
7.6.3.3 Creation of falls Where rainwater downpipes from other higher roof 7.6.6.2 Edge protection
Roof falls may be created either during the areas or balconies discharge via a lower balcony The guarding to the perimeter of balconies,
construction of the deck or alternatively through or terrace, an open downpipe shoe is not permitted. terraces and podium decks should be designed
the use of tapered insulation systems (warm deck The downpipe should be connected directly to the to provide the simplest means of achieving
roof systems only). downpipe serving the lower balcony or terrace. waterproofing integrity, given that installation of
balustrade or glazing stanchions may occur after
Where the roof finish is to include paving on The drainage design (including the number and the installation of the roof system.
supports, consideration should be given to the size of outlets) should be based on calculations Acceptable examples include the following, in
height difference created by the falls and spacing in accordance with BS EN 12056 part 3. The order of preference:
of rainwater outlets so that the maximum height drainage above the waterproof covering and
of paving supports is not exceeded, the minimum below any raised decking finishes must not be • Full-height parapet walls.
height of upstands is not affected or trip hazards restricted or blocked by the decking supports. The • Stanchions or rails secured to low parapet walls
created. On large balconies and terraces it may decking supports must allow free drainage of all above the level of the waterproof membrane
be necessary to increase the number of outlets in areas of the roof to the designated outlets. (incorporated in copings or secured to
order to reduce maximum roof zone depth. elevation).
7.6.4 Thermal performance • Stanchions secured, clamped and sealed to
7.6.3.4 Drainage Design for thermal performance must comply with stainless steel bolts set in raised plinths, which
If a balcony is served by a single rainwater outlet, the current Building Regulations as appropriate. were constructed prior to application of the
an overflow facility of equivalent capacity and waterproof membrane (suitable for warm deck
clearly visible externally should be provided at 7.6.5 External fire performance and inverted warm deck roof systems).
or near the same location, no more than 50mm • Stanchions secured, clamped and sealed to
Technical Manual V8: TS-11A-8.00-010117
above the level of the waterproof membrane. 7.6.5.1 Statutory requirement stainless steel bolts set at deck level, which were
Design for external fire performance must comply installed prior to application of the waterproof
Rainwater outlets should be readily accessible with the current Building Regulations. membrane (suitable for warm deck roof systems
without disruption to the pedestrian finish. On only).
finishes raised above the waterproof membrane 7.6.6 Provision for access
(warm deck roofs) or water control membrane
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.6.6.3 Protection of waterproof system Roof system type Waterproof membrane type
during construction Cold Single ply Bitumen Mastic Liquid
Finish Warm Inverted
At the earliest possible stage, the anticipated (Podium) membrane membrane asphalt applied
loading of the balcony, terrace or podium area Porous concrete tiles adhered to
Y N Y N Y Y (2) Y
waterproof membrane (1)
by plant and access during service should be
Fired tiles bedded in screed and grouted (1) Y N Y Y Y Y (2) Y
assessed in terms of:
Precast concrete paving slabs on
Y Y Y Y Y Y Y
adjustable supports (3)
• Load, e.g. foot traffic, equipment Timber decking on timber supports (4) Y(6) Y (5, 6) N Y(7) Y Y Y
• Frequency
• Risk of impact
Notes:
(1) Product should be certified for use with waterproof membrane (see chapter 7.10);
If such usage is intense or long-lasting during the
(2) Consideration should be given to the effects of solar gain on the stability of mastic asphalt under point loading in this situation;
construction phase, consideration should be given
(3) Paving support pad bearing area should be suitable for the compressive strength of the insulation under design loadings;
to temporary works only, with completion occurring
(4) Bearers should not impede drainage and should be sized to suit the compressive strength of the insulation under design loadings;
after all non-roofing usage has ceased as follows:
(5) Decking should be of sufficient dead load to provide resistance to wind load and temporary flotation of insulation;
7.6.7 Detailing • Upstands to extend 150mm above finished The total roof zone depth should be assessed at
roof level, except at door access to balconies critical points, such as the top of drainage slopes,
7.6.7.1 General principles and terraces (see Details section below). to ensure there is enough free upstand available
At an early stage in the design process, an audit • Downstands (of separate metal or other to create the minimum required 150mm of
of balcony, terrace or podium geometry should be flashings) should lap the upstand by a waterproofing protection above finished roof level.
carried out to establish what types of details will minimum of 75mm. It is important that this minimum 150mm upstand is
be required and whether they are to be weather • Where the balcony or terrace forms part of the maintained at all points around the waterproofed
proof (incorporating an upstand/cover flashing entire roof of an occupied building, a area, except at door access to balconies (see
arrangement) or waterproof (providing continuous continuous barrier to air leakage should be continuous water checks and verges). Balconies are
waterproofing across the detail). maintained. a frequent and acceptable exception due to the
• Reliance on sealant as the sole means of need for level or unobstructed access, provided the
The following key principles should be followed in protection should be avoided. recommendations in this section are followed.
the design of all details;
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.6.8 Design for sustainability in the absence of cross falls between rain water 7.6.11 Testing
As per chapter 7.10 Roofing. outlets.
7.6.11.1 Final inspection
7.6.9 Materials It is recommended that concrete paving is laid on At practical completion of the balcony, terrace or
As per chapter 7.10 Roofing. support pads as this allows adjustment, reducing podium deck all areas should be clear of stored
risk of trip hazard. Recommendations are as follows: material, other site operations and all protection.
7.6.10 Installation A thorough recorded, visual inspection of all
• The height of support pads should not exceed areas including details, should be carried out with
7.6.10.1 Protection of the roof the maximum recommended by the manufacturer. representation from the general contractor and
• Paving should not be cut. roofing contractor in attendance.
Temporary protection (during construction) • Paving should be firmly butted up against
Responsibility for temporary protection and a support pad separating pegs. 7.6.11.2 Procurement of testing services
method statement for its use should be agreed • Support pad separating pegs should provide If testing to demonstrate waterproofing integrity is
prior to the commencement of works. Suitable clear space for rapid disposal of rain water required it should be undertaken by a third-party
materials should be selected in consultation with between paving slabs. that is independent of the roofing contract. The
membrane manufacturers as appropriate, for • Provision for movement at perimeters should testing service provider should provide evidence of
example; comprise either a 75mm margin of washed the following:
stone or a compressible rubberised fill. In either
• Linked recycled thermoplastic sheets. case, drainage should not be obstructed and • Efficacy of the method proposed in the
• Rolled recycled thermoplastic or elastomeric a suitable restraint trim should be used to ensure circumstances of the project.
sheets. stone does not fall beneath the paving • Experience and training of operator.
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 7
FUNCTIONAL REQUIREMENTS
7.7 CLADDING
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. The cladding materials, design and construction must meet the
a workmanlike manner. relevant regional Building Regulations
iii. Certification is required for any work completed by an approved iii. The backing materials must be confirmed as suitable for the proposed
installer. render mix and/or system.
iv. The design of primary framing members (e.g. mullions and transoms,
Materials backing wall framing sections, etc.) and the connections of these
i. All materials should be handled and stored correctly in a manner that members/panels to the structure must be supported by structural
will not cause damage or deterioration of the product. calculations provided by a suitably qualified professional.
ii. All materials, products and building systems shall be appropriate and
suitable for their intended purpose. Limitations of Functional Requirements
iii. The structure shall, unless specifically agreed otherwise with the i. The Functional Requirements are limited by the recommendations
Warranty provider, have a life of not less than 60 years. Individual applied to the specific areas covered in this chapter.
components and assemblies that can be inspected and replaced ii. These Functional Requirements do not and will not apply to create
Technical Manual V6: TS-011a-6.00-010413
and which are not integral to the structure may have a lesser
Technical Manual V8: TS-11A-8.00-010117
any policy liability for any remedial works carried out by the contractor
durability, but not in any circumstances less than 15 years. or otherwise, nor to any materials used in those remedial works.
iv. ‘Decorative Claddings’: Whilst there is and can be no Policy
responsibility and/ or liability for a performance life of 60 years or less
for a ‘cladding’ which has a ‘decorative function only’ (i.e. with the
main substrate wall construction providing the main weather proof
© LABC Warranty
7.7.1 Render 2) For masonry substrates (e.g. solid brickwork, • Other project specific requirements
Rendering should be in accordance with BS EN blockwork, concrete, terracotta, stone etc.) including
13914-1:2005 and workmanship in accordance the masonry should be adequately prepared specification of fixings suitable for the
with BS 8000. In particular the following should be and be of a thickness which would resist environment, breather membranes,
considered: damp ingress to the internal finishes based allowance for movement due to shrinkage,
on the recommendations of BS 5628 Part appropriate weather seals at movement
With traditional renders the quality of the sands 3 2005 for the given exposure zone. Please joints, adequate protection to rendering at
used and design mix is as critical as is the reliance note: Where the thickness of the masonry cills, parapets etc.
on good mixing techniques by the applicator. is less than that recommended in BS 5268, is • The installation should be completed by a
Poor mixing ratios and low quality materials is a single skin construction or is in a high competent, registered and carded installer
often the reason traditional renders fail. For the exposure zone or coastal location, then the that has been approved and accredited
purposes of this chapter, traditional hand mix requirements of condition 6 (below) must also by the render system manufacturer before
using standard sand and cement is not accepted. be met. work commences.
Only a pre-blended bagged render system will be • Where the specification is in a high exposure
accepted as a suitable render system that has 3) For timber or steel framed supporting structures, zone or coastal location, then the
a third party accreditation such as a BBA or ETA a drained cavity is required as detailed in requirements of condition 6 (below) must
certification and backed up with a manufacturer’s Sections 7.2 Steel frame & 7.3 Timber frame also be met.
specification. of chapter 7 of this Technical Manual. A
manufacturer’s fully detailed project specific Note: Non drained cavity cladding constructions
Where a specialist render system is being used the render system specification must be provided, for timber frame and steel frame external walls
following conditions must be met: which should include; would not meet the requirements of sections 7.2 &
Technical Manual V8: TS-11A-8.00-010117
187
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
4) For ICF structures that have a joint UKAS or ETA 5) For all other ICF substrate structures regardless 6) For all render installations (including brick
third party approval between the ICF of the location, the ICF company and render slip system applications) on all substrates
manufacturer and a specialist render system: manufacturer must provide evidence of a third types located in an exposure zone where the
party product approval for the specialist render wind driven rain is expected to be more than
• The approved specification may be acceptable system, to confirm that it is compatible with 75 litres per m²: A 10 year ‘insurance backed’
to this warranty, providing the conditions of the the ICF system and proven to provide a weather manufacturer’s system guarantee is required,
joint approval certificate are met. In addition: resistance for 15 years. And: together with a full project specific specification
• Details for all junctions, openings and project that has also been accepted and approved
specific requirements for the window and door • A project specific specification will by the Warranty provider. The proposal will
systems installed within the ICF system must be be required and for the render system that require full system details to deal with all
provided. demonstrates that it suits the site location, junctions, openings etc. together with other
• The render installation on ICF structures should desired finish etc. project specific requirements provided by the
be completed by a competent, registered and • Provide details for all junctions, openings render system company. The render system will
carded installer that has been approved and and project specific requirements for the need to be installed by a registered and carded
accredited by the render system manufacturer window and door systems installed within installer who has been approved and
before work commences. the ICF system. accredited by the render system manufacturer
• Where the specification is in a high exposure • The installation should be completed by a before work commences.
zone or coastal location, then the requirements competent, registered and carded installer
of condition 6 (below) must also be met. that has been approved and accredited In all instances where a render system
by the render system manufacturer before manufacturer’s guarantee is required, full project
Note: Where the specification exceeds or work commences. specification and details are to be obtained
Technical Manual V8: TS-11A-8.00-010117
differs from the joint third party approval, then • Where the specification is in a high exposure from the render system manufacturer before any
a manufacturer’s fully detailed project specific zone or coastal location, then the installation commences to ensure that conformity
render system specification must be provided requirements of condition 6 (below) must is met. Once work commences, the installation
also be met must be inspected and signed off by a render
system representative throughout the installation
© LABC Warranty
Alternatively, a render system with a drained stage and at completion of the installation and
cavity will be required, or an alternative confirm that the specification has been met.
independent cladding system adopted.
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
The render system together with the backing wall • 5-6mm is considered the minimum finished • Rendering products should be stored separately
to which they are applied should satisfactorily thickness of render for applications to specialist from other building and concreting sands.
resist the passage of moisture to the inside of the insulated render systems. The render thickness • For bellcasts, PVCu bead or stainless steel bead
building. will need to be increased where structures are is acceptable.
located in very severe weather rating locations • For other beads and stops, a PVCu bead or
General render conditions or within coastal locations and a specialist stainless steel bead is acceptable.
• Ensure the render being used is suitable for the manufacturer’s specification will be required to • Render systems which include a cavity as a
substrate and is not too strong. Due to shrinkage support this; approved by the Warranty provider. secondary defence system should also
differentials, avoid applying a thin base • When ashlar detailing is required, it is incorporate cavity barriers within the cavity to
coat and a thicker top coat application as the recommended that a minimum depth to the prevent the spread of fire. The cavity barriers
shrinkage values of a thicker top coat could back of the ashlar cut should be no less should not obstruct more than 50% of the cavity
cause the render to delaminate from the base than 15mm & 20 – 25mm for applications and should be installed to the internal leaf to
coat. The same effect is also caused by in very severe exposure zones or within coastal retain its ability to drain. The cavity barrier must
applying a very hard render over a softer base locations. To achieve this depth, it will require activate and fully close the cavity when
coat. the finished thickness of the main render to be exposed to fire.
• 15mm is considered the minimum finished increased to accommodate this feature. • Renders will be reinforced as a minimum with
thickness of render applied to a masonry wall, • Abutments between cement render and other an appropriate certified alkaline resistant
either as a single spray coat or as a two coat cladding materials or components should be fibreglass mesh at corners of all openings
hand application. Where structures are located weather tight and allow for differential and penetrations. For substrates that are prone
in very severe weather rating locations. or within movement. to movement, an appropriate certified alkaline
coastal locations, the depth of render may • Any joints in the wall where movement may resistant fibreglass mesh will need to
Technical Manual V8: TS-11A-8.00-010117
need to be increased to a minimum of 20mm occur should be continued through the incorporated throughout the substrate
and a specialist manufacturer’s specification rendering. • Where different materials are being rendered
will be required to support this. • Render should not bridge the Damp Proof over, the incorporation of an appropriate
Course (DPC) and must be finished onto a certified alkaline resistant fibreglass mesh
durable render stop profile such as a proprietary will be necessary to assist with the possibilities
© LABC Warranty
PVCu bead or stainless steel bead. of differential movement. The mesh must extend
• External rendering should comply as a sufficiently over the different materials to resist
minimum with BS.EN 13914-1:2005 but against differential movement.
should also conform with the specialist render
manufacturers recommendations. 189
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
• Renders installed between pedestrian level • When applying in hot weather it is advisable • Care must be taken to protect cement and
and 6.0m above ground level will be designed that work coincides with the shaded areas of synthetic products soon after the application
to accommodate higher maintenance and the building. During longer periods of hot and from rapid freezing and heavy rainfall. For other
impact loads in accordance with Table 2 of BS dry weather it may be appropriate and drying conditions i.e. where there is direct
8200. necessary to apply an even mist spray of clean exposure to sunlight or drying winds the render
• For exposure zones where the wind driven rain is water to the substrate before application and may require to be protected from the elements.
expected to be more than 75litres per m² to surface finish for a couple of days afterwards This process is important to ensure complete
(classed as very severe) then checked reveals subject to site and weather conditions. hydration of the products can take place.
will be required. • Cement products should not be applied to • Where an application is not covered in
• All surfaces must be clean, suitably dry and free substrates which are frost laden or which have these conditions further advice from the
from anything that may interfere with the recently been subject to prolonged rain. render manufacturer must be sought and
adhesion of the material to be applied. The • Do not render onto saturated substrates as submit a suitable manufacturer’s specification
manufacturer’s product data sheets should this may affect the bond strength and cause to the warranty provider for approval
be followed including the manufacturer’s lime bloom (discolouration), salts to occur and
surface preparation and suitability checks in full. patchiness due to uneven suction. 7.7.1.1 Timber frame background
• All blockwork mortar joints are to be flush • Local weather and site conditions must be Unless designated otherwise as detailed in 7.7.1
pointed and should be fully cured before the taken into account by the applicator before any above, a drained and vented cavity should be
application of the render. cement product is applied. provided behind the render system on timber
• Only clean water should be used for mixing. • The quantity of material required for a given frame construction. The render board should have
• Protection must be provided when applying area should be of the same batch number or if the capability to be directly rendered to. It should
renders in rain or other inclement weather. not the different batches must be thoroughly not be a wood based board or cement particle
Technical Manual V8: TS-11A-8.00-010117
Application should cease in temperature below mixed together to avoid shade variations. board unless confirmed by a UKAS or European
5°C or where rapid freezing is considered to be • Full masking must be used to give protection to equivalent third party product approval body that
a potential threat. adjacent areas of work, windows, doors etc. confirms it is acceptable for use in the conditions
and to give clean straight edges. It should be proposed. It should also not be a board that is not
removed immediately after finishing coat has approved by the render system manufacturer.
© LABC Warranty
dried.
• Carefully remove splashes of material, in
particular from glass or aluminium immediately
as they may etch the surface and leave a
permanent mark.
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
For metal lathing, these should be a proprietary • Take particular note of movement joint and 7.7.1.1.2 Movement joints
BBA, BRE etc. or ETA certified non-corrosive mesh fire break requirements and specific application Where cement render spans across an
system and must be fully installed in accordance details. intermediate floor zone in timber frame
with the mesh system manufacturer to vertical • Ensure all door, window and other openings are construction, allow for differential movement due
battens at the stud centres. fully sealed using an appropriate to timber shrinkage by incorporating a movement
manufacturer’s weatherproof system to joint. Vertical movement joints should also be
The minimum size of the cavity should be provide a primary weather barrier and to resist provided at maximum 5m centres.
19mm for both the render board or metal to movement.
lathing applications. Unless proven otherwise, 7.7.1.2 Masonry background
all applications should be used with a water- Battens should be either 25mm x 38mm or The walls which are to be rendered should be
resistant membrane. When the render board or 50mm x 50mm, preservative treated (BS 8417 or examined for excessive moisture content prior to
metal lathing system is unbacked, the minimum equivalent, hazard class 2) and fixed at spacing’s rendering. This is particularly important where the
cavity should be 50mm. A DPC should be provided recommended in BS EN 13914-1: 2005. Fixings and masonry background has no upper limit on its
between unbacked render and timber battens. preservatives should be compatible. soluble salts content, e.g. N designation clay bricks.
When using external render board you should: Battens should be fixed to each stud with annular A specialist render system and mortar should
ring nails of length at least twice the batten be employed for parapets, chimneys, retaining
• Fix with the manufacturer’s recommended thickness plus the sheathing thickness. Nails should walls and walls below DPC level with this masonry
non-corrosive fixings and all in accordance with be hot dipped galvanised stainless steel or equally background type.
the manufacturer’s installation details, ensuring durable.
the vertical board joints are staggered and do Ensure that all joints are finished flush with the
Technical Manual V8: TS-11A-8.00-010117
not follow directly in line with window, door 7.7.1.1.1 Cavity barriers surface to avoid shade variations.
reveals and other openings. Where cavity barriers are required, they should be
• Take care to ensure there are no gaps between correctly fitted without gaps, the cavity filled and To minimise the potential for differential thermal
the boards and appropriate weather seals are fixed with stainless steel staples or equally durable movement and effects that the different suction
incorporated against walls and frames. fixings, the settlement joints below the external that each type of background material may
• Ensure the boards are cut neat and square;
© LABC Warranty
frames and soffits must be maintained. create; the section of walling to receive the render
follow the building lines and the screw heads should be constructed using the same type and
are recessed just below the surface. density of material throughout.
191
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
When rendering is required to be applied to wet • Rendering to chimneys should only be Check whether the rendering can be applied
masonry substrates, a specialist sealer key coat carried out where the masonry contains little directly onto the wall, or whether any preparatory
prior to applying the main coat of render should or no sulphates. An appropriate specialist sealer treatment is required in accordance with the
be applied, to control suction and reduce the / bonding key coat should be applied prior to manufacturer’s instructions.
impact of lime blooming occurring through the applying the main coat of render. A proprietary
render. The key coat should provide a sound alkaline resistant mesh should be embedded The surface should be checked for suction by
substrate and be compatible with the subsequent throughout the render, the key coat should dampening the wall with clean water.
render system. provide a sound substrate and be compatible
with the subsequent render system. In accordance with a structural engineers
For high absorption e.g. lightweight blockwork, • As before; horizontal DPC and damp proof requirements, cracking of the substrate could be
common bricks etc. and smooth dense substrates membranes (DPM) must not be bridged. significantly reduced by introducing a specialist
(such as engineering bricks); direct rendering • Rendering below DPC should only be carried proprietary bed joint reinforcement within the
should be avoided as the moisture can be out using a specialist render manufacturer’s mortar joints. Ideally this should be applied
extracted by the substrate from the wet render specification. No render system should bridge throughout the building during construction and
which affects its curing and bonding capability, or the DPC and a proprietary PVCu bead or in accordance with the substrate manufacturer’s
it does not bond to the substrate respectively. stainless steel bead should be used above and recommendations. Ensure that the reinforcement is
To control suction always apply a specialist sealer below where the renders meet at the DPC. continuous and joints are lapped in accordance
key coat or suitable render preparatory coat. Allow with the manufacturer’s requirements (generally
a minimum of 48 hours for the key coat to fully dry 7.7.1.3 Other construction detailing 450 - 500mm laps and continued around corners).
before applying the next coat. Ensure that drips and throating to sills, coping, etc. Specialist corner units are likely to be required,
project beyond the face of the finished render check with the manufacturer.
Technical Manual V8: TS-11A-8.00-010117
7.7.1.4 Vertical and horizontal flatness Dead and live loads should be transferred safely to • External and internal air and water seals.
Rendering should have a maximum vertical and the building structure without undue permanent • Drained and ventilated glazing rebates.
horizontal deviation from flatness of +/-10mm in 5m, deformation or deflection of any component.
and is measured in a similar way to straightness on Sealants should be specified in accordance with
plan and plumb of masonry. Imposed loads should be calculated in BS 6213 or BS EN 15651 and the performance
accordance with BS EN 1991. Movement should determined by BS EN 11600 and the manufacturer’s
7.7.2 Curtain walling be accommodated without any reduction in recommendations.
performance.
7.7.2.1 General The system should be designed to minimise the
Curtain walling systems should have third-party Fixings and supports should be designed to risk of surface and interstitial condensation by the
certification confirming satisfactory assessment, accommodate specified loads and take account use of thermal breaks and a continuous vapour
and comply with the requirements of the CWCT of the product manufacturer’s recommendations. control layer. It should be designed to resist the
Standard for Systemised Building Envelopes, passage of airborne and impact sound within the
including the following sections: CE marking is to be provided for all curtain walling building with particular attention given to flanking
covered by EN 13830 in buildings constructed after transmission at;
• Part 1: Scope, terminology, testing and July 2013, and will therefore include the following
classification. curtain wall types: • The edges of separating floors.
• Part 2: Loadings, fixings and movement. • The outer edges of separating walls.
• Part 3: Air, water and wind resistance. • Stick construction • The outer edges of partition walls.
• Part 4: Operable components, additional • Unitised construction • The junctions with roof constructions and
elements and means of access. • Double skin walls parapets.
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
The system should comply with BS 7671 7.7.2.2 Testing time to allow testing to be planned in advance
requirements for electrical installations for electrical The curtain wall system will have either been tested and made available to the Warranty Surveyor when
continuity and earth bonding, where it is required and provided with a classification given in BS completed.
to form part of a lightning protection system it must EN 13830, or if the curtain walling is of a custom
be designed to comply with the requirements of BS design, it would be tested to the CWCT Standard Site testing for water penetration of the joints
6651. by an independent UKAS accredited test facility to windows and doors in accordance with the
to ensure that the system meets or exceeds the CWCT test methods is recommended to check
The risk of bimetallic corrosion should be avoided weather performance classification for the building the site workmanship of the building envelope as
through the isolation of dissimilar metals. Fixings taking into account the design parameters and constructed. See CWCT Technical Note No. 41 for
and finishes to curtain walling must take into location. guidance on site hose testing.
account the location and corrosion category to
ensure corrosion is avoided. Pull-out or destructive testing of anchors should be 7.7.2.3 Tolerances
carried out in accordance with BS 5080 and the Design should allow for the line, level, plumb and
The curtain wall system should not include Construction Fixings Association Guidance Note, plane of the completed curtain wall to be within
materials liable to infestation attack by micro- Procedure for Site Testing Construction Fixings. the acceptable tolerances of:
organisms, fungi, insects or vermin. The number of fixings to be assessed must be
agreed on a project by project basis, as an • Line: +/-2mm in any one storey height or
Packing of brackets to achieve surface tolerance understanding of the scope and size of the project structural bay width, and +/-5mm overall.
should be permitted only in accordance with the would determine the number of fixings tested. In • Level: +/-2mm of horizontal in any one structural
manufacturer’s recommendations, and should addition, if there are varying types of fixings then bay width, and +/-5mm overall.
not exceed the maximum depth stated in the each type should be tested. If the fixing is the same • Plumb: +/-2mm of vertical in any one structural
Technical Manual V8: TS-11A-8.00-010117
designer’s calculations. but the structure varies, then each type of structure bay width, and +/-5mm overall.
should be tested. • Plane: +/-2mm of the principle plane in any one
All packers for brackets supporting or restraining storey height or structural bay width, and +/-
the curtain wall must be metal. BS-5080 requires 5 tests per type, however if a 5mm overall.
very large project is proposed, this could be
© LABC Warranty
7.7.3 Insulated render systems receive the desired base coat and reinforcement. Movement within the insulated render system
These are systems applied to the exterior walls of The insulated render system should be designed should be accommodated without any reduction
existing or new buildings, comprising of an insulant to minimise the risk of interstitial condensation and in performance.
and a weather protective finish, of which there are the effects of thermal bridging. A condensation risk
three main types: analysis should be carried out in accordance with Movement joints in the backing substrate
BS 5250 to ensure the building fabric meets the should be mirrored through the insulated render
• Traditional renders and finishes. required performance standard. If a vapour control system and formed in accordance with the
• Thin coat renders and synthetic finishes. layer is required then this must be installed to the manufacturer’s recommendations.
• Pre-formed cladding materials. warm side of the insulation and the type must be
approved and suitable for the application. When required an approved proprietary fixing
All insulated render systems must have appropriate should be used in accordance with the design
third-party certification and a full manufacturer’s In accordance with the render system requirements calculated. This generally consists of
specification suitable for the substrate must manufacturer’s recommendations appropriate a minimum of 5 fixings per full insulation board / 8/
be provided. Ensure all building criteria’s are trims should be provided at openings, corners, m² elsewhere with additional fixings to corners and
maintained, e.g. vented cavities should not be angles and interfaces etc. Reinforcement mesh reveals. A pull out test report confirming fixing type
blocked, the use of timber supports and blocks should be accommodated throughout the base and length will be required in accordance with
within the insulated render system should not coat application with additional reinforcement the Construction Fixings Association and made
be used unless absolutely necessary. Ensure all to vulnerable areas and corners of openings etc. available to the Warranty Provider.
fixtures and fittings which penetrate the insulation If there are any concerns regarding straight line
system e.g. flues, ventilation pipes, water pipes joints or other areas where there are unusual Proprietary preparation works
etc. are appropriately sleeved and fully sealed constructions requirements an additional layer of
Technical Manual V8: TS-11A-8.00-010117
in accordance with the system manufacturer’s mesh should be installed to these locations. • Ensure all fixings, cables, fence posts, light fitting,
recommendations. satellite dishes and other ancillary fittings and
The dead and live loads should be transferred fixtures are temporarily removed to enable the
All the render and cladding guidance/information safely to the buildings structure without easy application of the insulated render system.
stated in this chapter must be adhered to when deformation or deflection of any component. • Remove existing and provide temporary
applying an insulated render system.
© LABC Warranty
Ensure the insulation continues around openings downpipes, avoid allowing the temporary
and other penetrations to maintain the thermal downpipes to spill water over the render system.
The insulation type for the structure and benefits. • If required reset all drainage gulley’s to
application should be suitable for the intended accommodate the insulation system thickness.
purpose and, when required should be keyed to 195
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
• If required ensure that any gap around the Where cavity barriers are required, they should be Boards should be fixed to battens by face or secret
window and door frames is correctly sealed correctly fitted without gaps, fill the cavity and be nailing with annular ring nails at least twice the
against rain penetration before application of fixed with stainless steel staples or equally durable board thickness or plain shank nails at least 2.5
the insulated render system. fixings. times the board thickness.
Where an insulated render system is used as a Abutments between cladding and other weather- Butt joints at board ends should occur at battens.
cladding to a timber or light gauged steel framed resisting elements should be neatly made, Nails should be either hot dipped galvanised,
structure a drained and vented cavity will be weather tight and allow for differential movement. stainless steel or equally durable. Aluminium nails
required. A suitable breather membrane must also Workmanship should comply with BS 8000: 5. should not be used with timber treated with a
be provided to protect the sheathing board and preservative containing copper. Galvanised nails
framing system from water penetration reaching 7.7.4.1 Timber boarding should not be used with Western Red Cedar.
the internal finishes. (As described in chapter 7.2 Timber boarding should be at least 16mm thick,
& 7.3). and allowance for moisture movement in boarding 7.7.5 Rainscreen cladding systems
should be achieved by making tongues, joints or A rainscreen cladding system consists of a multi-
7.7.4 Timber cladding overlaps at least 10% of the board width. layer construction of materials which is designed to
Timber and boards for exterior use should be of provide a barrier to the weather on new or existing
a durable species, with sapwood excluded, or Timber boarding should be battened off the buildings. The typical build-up would consist of a
preservative treated by pressure impregnation supporting background to provide a minimum supporting airtight backing wall and rainscreen
using preservatives suitable for use in hazard Class 19mm cavity for draining and venting. system.
3 in compliance with BS 8417: 2003, or equivalent.
Further guidance on the durability of timber is Battens should be a minimum of 38mm wide, The rainscreen should comprise of supporting
Technical Manual V8: TS-11A-8.00-010117
provided in chapter 2 – Materials. preservative treated and at maximum 600mm brackets fixed to the backing wall, insulation
centres. A breather membrane should always between the brackets, a breather membrane over
Where timber boarding or plywood spans across be installed when horizontal battens are located the front face of the insulation, carrier support rails
an intermediate floor zone in a timber frame against the sheathing. Battens on timber frame fixed to the brackets, a ventilated and drained
construction, allow for differential movement should be fixed to each stud (and not to the cavity and the rainscreen panels.
caused through timber shrinkage by incorporating
© LABC Warranty
Rainscreen systems should have third-party • Line: +/-2mm in any one storey height or performance criteria stipulated in the BRE Report
certification confirming satisfactory assessment structural bay width, and +/-5mm overall. for fire performance of external thermal insulation
and comply with the requirements of the CWCT • Level: +/-2mm of horizontal in any one structural for walls in multi-storey buildings (BRE135) for
Standard for Systemised Building Envelopes. The bay width, and +/-5mm overall. cladding systems using full scale test data from BS
collation of individual testing of components • Plumb: +/-2mm of vertical in any one structural 8414-1 or 2.
does not provide an overall performance of the bay width, and +/-5mm overall.
rainscreen system or backing wall. • Plane: +/-2mm of the principle plane in any one Where no test data is available for a rainscreen
storey height or structural bay width, and +/- cladding system, it is acceptable to submit a
Dead and live loads should be transferred 5mm overall. desktop study report undertaken by a suitably
safely to the building structure without undue qualified fire specialist, stating whether in their
permanent deformation or deflection of any Cavity barriers within a ventilated rainscreen opinion, BRE135 criteria would be met with the
component. Imposed loads should be calculated system must be appropriately selected, suitable proposed system. Test data from a suitable
in accordance with BS EN 1991 and movement for use and be aligned with the compartment independent UKAS accredited test body must
should be accommodated without any reduction wall and floor. The cavity behind a rainscreen be referenced in the report. Further details of this
in performance. Fixings and supports should is deemed to be a moist zone and materials approach can be found in the Building Control
be designed to accommodate specified loads selected must not corrode, deteriorate or affect Alliance published best practice guidance for
and take account of the product manufacturer’s the performance of the cavity barrier during its the use of combustible cladding materials on
recommendations. design life. Horizontal cavity barriers must allow buildings exceeding 18m in height (BCA Technical
for drainage and ventilation in the rainscreen Guidance Note 18).
Rainscreen panels are generally lightweight and cavity and there must be a minimum 25mm
vulnerable to impact damage. The rainscreen gap between the intumescent front face of the
Technical Manual V8: TS-11A-8.00-010117
must be able to resist impacts without causing horizontal cavity barrier and the back face of the
safety hazards. Testing and classification to rainscreen material.
CWCT Technical Note 75 & 76 may be required
to demonstrate the rainscreen’s material impact Rainscreen systems and their materials must
performance. comply with the Building Regulations Approved
© LABC Warranty
CHAPTER 7
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
a suitably qualified expert.
Materials iii. The materials, design and construction must meet the relevant
i. All materials should be stored correctly in a manner that will not cause regional Building Regulations.
damage or deterioration of the product.
ii. All materials, products and building systems shall be appropriate and Limitations of Functional Requirements
suitable for their intended purpose. i. The Functional Requirements are limited by the recommendations
iii. The structure shall, unless specifically agreed otherwise with the applied to the specific areas covered in this chapter.
Warranty provider, have a life of not less than 60 years. Individual ii. These Functional Requirements do not and will not apply to create
components and assemblies, not integral to the structure, may have any policy liability for any remedial works carried out by the contractor
a lesser durability, but not in any circumstances less than 15 years. or otherwise, nor to any materials used in those remedial works.
Technical Manual V6: TS-011a-6.00-010413
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.8.1 Statutory requirements For advice on ‘sizing of certain timber members in Allowances for wind loading
floors and roofs for dwellings’, the Designer should The need for a roof to withstand wind pressure and
Roof structure and loading refer to the following sources: suction will be met if the proposed roof is braced
Roof framing and rafter design must be in effectively, as discussed elsewhere in this Manual,
accordance with current regional Building • Span tables for solid timber members in floors, and secured to the structure, as detailed below,
Regulations. ceilings and roofs (excluding trussed rafter with walls adequately restrained.
roofs) for dwellings. Published by TRADA.
The roof of the building shall be constructed so Note: Reference should be made to the version The securing of roofs to the supporting structure
that the combined dead, imposed and wind loads of the TRADA document current at the time of roof timbers normally involves a timber wall plate
are sustained and transmitted by it to the ground construction of the floor / timber or roof. or similar, which should be levelled using a spirit
safely, and without causing such deflection or • BS 8103-3, Structure design of low rise buildings, level so that loadings from the roof are directed
deformation of any part of the building, or such Code of Practice for timber floors and roofs for perpendicularly down the supporting wall.
movement of the ground, as to impair the stability dwellings.
of any part of another building. • BS EN 1995-1: 2004+A1, Eurocode 5 design of The wall plate may, as good practice, be fixed to
timber structures. General. Common rules and ensure correct positioning when roof timbers or
The roof structure should be of such construction rules for buildings. trusses are being installed by means of galvanised
that it has adequate interconnection with the mild steel holding down straps (30mm x 5mm x
walls, allowing it to act as a horizontal diaphragm Design Criteria 1,000mm long at maximum 2m centres) nailed
capable of transferring the wind forces to The design criteria set out is intended to be to the wall plate and securely fixed to the inner
buttressing elements of the building. adequate for imposed roof loads of 1.00kN/m 2
surface of the wall with compatible fixings.
for spans not exceeding 12m, and 1.50kN/m2 for
Technical Manual V8: TS-11A-8.00-010117
In this respect, it is acknowledged that a traditional spans not exceeding 6m. There is a need to ensure that holding down straps
cut roof, i.e. using rafters, purlins and ceiling joists, are provided in areas of severe wind exposure
generally has sufficient built-in resistance to instability All structural timber used in a conventional cut roof, where required by the roof design.
and wind forces, e.g. from either hipped ends, i.e. rafters, purlins, ceiling joists, binders and other
tiling battens, rigid sarking or the like. However, the timber elements, should be stress graded. All such 7.8.2 Treatment of timber
need for diagonal rafter bracing equivalent to that timber must be stamped as either ‘DRY’ or ‘KD’ (Kiln Preservative treatment of roof timbers is normally
© LABC Warranty
recommended in BS EN 1995-1: 2004+A1, or Annex Dry). The use of ungraded, or ‘green’, timber is not unnecessary, except where specifically required
H of BS 8103-3 for trussed rafter roofs, should be acceptable. under relevant standards and Codes of Practice,
considered, especially for single-hipped and non- and in the following circumstances;
hipped roofs of more than 40° for detached houses. 199
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
• Roof timbers should be preservative treated • The Borough of Woking 7.8.3 Trussed rafter design
where the insulation and ceiling line follow the
roof pitch. The treatment should be impregnation with a 7.8.3.1 Design responsibility
• Trussed rafter construction which is cut back at preservative suitable for use in ‘Use Class 1’in The Building Designer is responsible for the ‘framing’
eaves or where the rafter ‘feet’ is trimmed to sit pitched roofs and ‘Use Class 2 flat roofs’, in of any given roof as a whole. This means that he or
into the external walls. Preservative treatment accordance with BS 8417, for a 60 year anticipated she must take responsibility for the bracing together
will be required to the cut ends. service life. Cut ends must be liberally brushed or (framing) of the trussed rafter configuration, which
• The Approved Document of Regulation 7 of dipped with an end-grain preservative. then supports the roof covering and the tying
the Building Regulations for England requires together of the supporting walls.
that in certain geographical areas, all softwood It is strongly recommended that, where punched,
roof timbers should be treated against attack metal fasteners are proposed to roof trusses. Only Whilst it is the supplier of the rafters who generally
by the House Longhorn Beetle. micro-emulsion or organic solvent preservatives has the knowledge and expertise required to
should be used for timber treatment, to limit the achieve the best engineering solutions, the
The areas at risk are: possibility of corrosion of the fasteners and so as Designer must be certain that the loading
not to adversely affect glued joints. calculations and resultant configuration is fit for
• The District of Bracknell Forest purpose.
• The Borough of Elmbridge
• The Borough of Guildford (other than the area The following checklists, derived from BS EN 1995-1:
of the former Borough of Guildford) 2004+A1, set out:
• The District of Hart (other than the area of the
former Urban District of Fleet) • Information required by the manufacturer from
Technical Manual V8: TS-11A-8.00-010117
of Godalming and Haslemere) • The height and location of the building, with
• In the Royal Borough of Windsor and reference to any unusual wind conditions.
Maidenhead, the parishes of Old Windsor,
Sunningdale and Sunninghill Figure 1: Timber treatment
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
• The profile of the trussed rafter, including • The positions and sizes of all bearings. 7.8.3.3 Loads
camber if required. • Loadings and other conditions for which the Trussed rafters and the framed roof must support
• The span of the trussed rafter. trussed rafters are designed. the dead loads as specified in BS EN 1991-1 and
• The pitch or pitches of the roof. • The spacing of trussed rafters. BS EN 1991-1-7, the wind loads in BS EN 1991-1-4:
• The method of support and position of supports. • The positions, fixings and sizes of any lateral 2005+A1 and the imposed loads in BS EN 1991-1-
• The type or weights of roof tiles or covering, supports necessary to prevent buckling of 3. Loads acting on rafters are dead loads (tiles/
including sarking, insulation and ceiling compression members, such as rafters and slates, battens, underlay and rafter self-weight),
materials. struts. (Details of the permanent bracing imposed loads (snow load and maintenance) and
• The size and approximate position of any water necessary to ensure the overall stability of the the wind uplift load. Other dead loads that act on
tanks or other equipment to be supported on complete roof structure and supporting walls the ceiling ties (ceiling, insulation, water tanks and
the trussed rafters. should be provided by the building designer). the tie self-weight) and imposed loads (loft access
• The overhang of the rafters at eaves, and other • The method of support for tanks and ancillary and weight of storage) will also have to be taken
eaves details. equipment, together with the capacity or into account by the Designer.
• The positions and dimensions of hatches, magnitude of additional load assumed.
chimneys and other openings. • The range of reactions to be accommodated BS EN 1991-1 and BS EN 1991-1-7 specify the
• The service use of the building, with reference at the support positions, including those following limits for imposed loads on the rafters
to any unusual environmental conditions and required to resist wind uplift forces. uniformly distributed over the whole roof, measured
the type of preservative treatment where • The basis of the design. on plan:
required. • Details of any changes in spacing to
• The spacing of trussed rafters and special accommodate chimneys or openings. • Roofs pitched 10° to 30°: 0.75kN/m2.
timber sizes where these are required to match • Any special precautions for handling and • Roofs pitched 31° to 75°: 0.75kN/m2 – 0 kN/m2
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.8.3.4 Bracing, support and typical roof • Anticipated loading of the roof structure, i.e. the To prevent any distortion, there is a need to ensure
openings (BS EN 1995-1-1: 2004+A1) weight of the roof tiles and the exposure of the that the trusses are stored in a vertical position, as
As stated above, the Designer is responsible for site should it attract excessive wind loads. in Figure 2.
framing the roof. The correct bracing configuration • Position and size of water tanks.
locks all timber supporting roof elements into • Position and size of openings, i.e. Loft hatches,
a single structural, load-bearing unit. Standard roof windows, chimneys.
bracing details are given in BS 5268-3. • Due to the site locality, any particular
preservative treatment necessary for the timber,
Appendix A and further information can be found e.g. to protect against House Longhorn Beetle.
in BRE Defect Action Sheets 83 and 84. • Eaves details i.e. overhang required, etc.
Where recovering of existing roofs occurs: In return, the Trussed Rafter Designer should supply
Approved Document A Section 4 deals with the the following details for site use:
requirements for checking the structural integrity
of the roof and supporting structure when • Position, bearing and spacing of trussed rafters
considering the re-roofing of buildings. • Position, fixings and sizes of lateral supports to
prevent buckling of compression members such Figure 2: Site storage of trusses
For information and design criteria necessary for as rafters and struts.
ordering: BS 5268: 3, provides a comprehensive list • Deviations from standard spacing’s, etc.
Horizontal storage is sometimes possible, as in
of criteria that should be supplied by the Building to accommodate openings.
Figure 3. In both cases, stacks of trusses should
Designer or Site Supervisor to the Trussed Rafter • Support details for water tanks.
be covered with a weather proof cover, whilst
Technical Manual V8: TS-11A-8.00-010117
walls and scaffolding must be avoided. Individual used to withstand the sling force.
designs and site conditions may dictate different
requirements in order to install trusses in their final
position.
203
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
The International Truss Plate Association Technical material will also contribute to the bracing process.
Handbook, available from trussed rafter suppliers, Sarking boards, such as moisture-resistant plywood
provides additional advice on trussed rafter (minimum thickness 9mm) and moisture-resistant
erection. chipboard (minimum thickness 12mm), may
provide adequate bracing without the need for
7.8.3.8 Bracing to duo-pitched roofs additional wind bracing to the roof. Sarking boards
should be laid with staggered joints and nailed at
Fixing 200mm centres on every truss with 50mm long x
To achieve a stable and wind-resistant roof and 3mm diameter galvanised round wire nails.
gable wall structure, the roof must be secured to
the gable wall, if applicable, and fully braced by Longitudinal bracing
Figure 7: Trussed roof installation 100mm x 25mm timber, twice nailed to roof timbers Longitudinal bracing is shown in Figure 7; it should
using 65mm long x 3.35mm diameter galvanised be positioned tightly to abut separating and
wire nails. Where nail guns are used, 75mm long gable walls. In timber frame construction, you
• Before placing first truss, mark required position x 3.1mm diameter annular ring-shank nails are should ensure that longitudinal braces are fixed to
of trussed rafters on opposing wall plates. allowed. They do not need to be galvanised. timber frame gables/separating walls to provide
• Erect and brace first trussed rafter (A) (only one additional lateral restraint.
shown but fix others as necessary). Types of bracing
• Erect next adjacent trussed rafter (B) and brace There are three main types of wind bracing, which Chevron bracing
back to (A) using brace (C). should be fixed: Chevron bracing is only required for roof spans
• Erect other trussed rafters as with (B). exceeding 8m, and it can be identified as
• When the final accurate positioning of the
Technical Manual V8: TS-11A-8.00-010117
• Diagonal rafter bracing. diagonal bracing to the web members of the roof
trussed rafters has been confirmed, the rafter • Longitudinal bracing. truss.
feet can be fixed into position. • Chevron bracing (only necessary on trussed
• Fix permanent diagonal bracing (D) (only one rafter spans over 8m). For spans of between 8m and 11m, such bracing
brace shown for clarity). may only be required to a single web member on
• Fix longitudinal bracing (E) (only three shown Diagonal and longitudinal bracing are required
© LABC Warranty
Mono-pitched roof bracing 7.8.3.10 Mono-pitch and girder trusses on may be extended to accommodate an opening.
In mono-pitched trussed rafter roofs, the diagonal trussed rafter hipped-end roofs The Roof Designer should provide all necessary
bracing pattern for narrow-fronted houses should Mono-pitch trussed rafters can be used in details. This is applicable particularly for where
be adopted. The requirement for longitudinal conjunction with girder trusses on trussed rafter roof lights and dormers are formed. Detailed
bracing is the same as for duo-pitched trussed hipped roofs. specifications of the trimming joists at the side,
rafter roofs. head and base of the opening must be provided to
Mono-pitched trusses are fixed to girder trusses ensure the roof is safely supported.
Chevron bracing is required to the webs in using metal shoes. The bearing of mono-pitched
roofs exceeding a 5m span, and also to upright trusses onto the mild steel proprietary girder shoe
members where inadequate lateral restraint is should be confirmed with the Roof Designer before
provided at the apex of the roof. site installation is attempted.
main truss with two no 3.35mm diameter x necessary, in which case it will be necessary to get
75mm galvanised wire nails. full details of the fixing specification from the Roof
• Where the diminishing truss has a square Designer. Figure 8: Roof trusses trimming around a chimney
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
should be skew-nailed to supports as appropriate. 7.8.3.15 Combined trussed rafter and wall and supported by struts onto the load-bearing
Alternatively, proprietary joist hangers can be traditionally framed roofs structure at centres specified in the design.
used. Tank bearers should be situated as close Extra care is necessary where the two principal
as possible to the node or intersection points of timber pitched roof types are used in conjunction. Always ensure that the correct strength class of
the trussed rafter. The dimensions of the bearers The trussed rafters should be specifically designed timber is both ordered and used. Structural timbers
depend upon the size of the supported tank and to accept any additional loadings imposed by an are allocated a strength class by BS 5268: 2. The most
the span of the trussed rafters. adjacent traditional roof. Similarly, account should common strength classes used are C16 and C24.
be taken of any loadings imposed by trusses on
traditional roofs where only nominal loadings • The timber supplier will require the following
have been allowed for. If in doubt, consult the Roof information before supplying timber:type and
Designer. strength class of timber required.
• Required sizes of timber.
7.8.4 Traditional pitched roofs • Any treatment required.
7.8.4.1 General
7.8.3.14 Modifications to trussed rafters All openings formed in the roof structure for
Trussed rafters should never be cut, altered or dormers, rooflights etc. must be carefully designed
repaired for use without the full agreement of the to ensure the roof remains safely supported and
© LABC Warranty
Trussed Rafter Designer. Remedies for defects to weather tight (see 7.9.7.6)
erected trusses can be found in BS 5268: 3, but the
Roof Designer’s advice should be sought prior to The purlins/binders should be adequately supported
repairs being carried out. to contribute fully to the roof structure. For example,
they could be built into the inner leaf of a gable end
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Figure 11: Close couple roof Figure 12: Raised collar roof
structurally limited, as heavy supporting walls are allows a smaller timber section to be used. Rafter so that the rafters and collars support the ceiling.
required to resist outward spread. When a steep and ceiling joist dimensions for typical spans are To resist eaves spread, the height of the collar
pitch is combined with low eaves, the resulting given in the TRADA document, Span Tables for Solid should be no higher than a third of the vertical
clear roof space can be used to advantage. Where Timber Members in Floors, Ceilings and Roofs for height between the wall plate and ridge. Rafters
such roofs are designed, full structural calculations Dwellings. supporting collar ties should be designed by a
© LABC Warranty
prepared by a Chartered Structural Engineer Chartered Structural Engineer, taking into account
should be provided to demonstrate how eaves the additional point load imposed by the collar.
spread will be prevented. The collar should be fixed to the rafters using 10mm
bolts and incorporating large washers to prevent
the bolt from being pulled through the timber. 207
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.8.5 Fire stopping • At junctions of separating wall and external junction to maintain the continuity of fire resistance.
cavity wall. The compartment wall should also be continued
Compartmentation • At junctions of compartment wall and across any eaves cavity. If a fire penetrates a
The spread of fire within a building can be compartment floor (not illustrated). roof near a compartment wall, there is a risk
restricted by sub-dividing it into compartments • At junctions of separating wall with roof, under that it will spread over the roof to the adjoining
separated from one another by walls and/or roof tiles. compartment.
floors of fire-resisting construction. The roof void, • Within boxed eaves at separating wall position.
like most spaces within a building, can provide To reduce this risk, a roof zone 1,500mm wide on
a route for the spread of fire and smoke. As an Junctions of compartment walls with roof either side of the wall should have a covering of
often-concealed space, it is particularly vital that A compartment wall should be taken up to meet designation AA, AB or AC on a substrate or deck of
fire-resistant cavity barriers are provided at the the underside of the roof covering or deck, with a material of limited combustibility.
following points: fire stopping, where necessary, at the wall/roof
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Roof coverings must prevent any external moisture from passing into
a workmanlike manner. the internal environment of the dwelling.
iii. Certification is required for any work completed by an approved iii. Structural elements outside the parameters of regional Approved
installer. Documents A must be supported by structural calculations provided
by a suitably qualified expert.
Materials iv. The materials, design and construction must meet the rrelevant
i. All materials should be stored correctly in a manner that will not cause regional Building Regulations.
damage or deterioration of the product.
Technical Manual V6: TS-011a-6.00-010413
ii. All materials, products and building systems shall be appropriate and Limitations of Functional Requirements
suitable for their intended purpose. i. The Functional Requirements are limited by the recommendations
iii. Whilst there is and can be no Policy responsibility and/ or liability for a applied to the specific areas covered in this chapter.
roof covering performance life of 60 years or less, roof coverings shall ii. These Functional Requirements do not and will not apply to create
be designed and constructed so they have an intended life of not less any policy liability for any remedial works carried out by the contractor
than 15 years.
Technical Manual V8: TS-11A-8.00-010117
209
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.9.1 Legislation and planning Certain advisory bodies, such as the Loss Exposure to driving rain
Tiled and pitched roof coverings should be in Prevention Council, Building Research The UK has a high risk of severe driving rain, and
accordance with the relevant Building Regulations. Establishment Ltd (BRE) and Timber Research even in some sheltered locations may be subject
and Development Association (TRADA), also to high levels of deluge rainfall. BS 5534 defines four
The principal British Standards relevant to this produce recommendations and guidance on roof categories of exposure, based on the driving rain
document are: construction. data given in BS 8104 and BR 262, and should be
used for buildings up to 12m in height. For buildings
• BS 5534 Code of Practice for slating and tiling 7.9.2 Weather exposure over 12m in height, the influence of increased wind
(including shingles). This gives speeds should be taken into account using BS EN
recommendations for the design, materials, 7.9.2.1 Rain and snow 1991-1-4.
application, installation and performance The roof of the building shall adequately protect
of slates and tiles (BS 5534 should be read in the building and people who use the building Performance of tiles and slates
conjunction with BS 8000-6). from harmful effects caused by precipitation and Rain penetration of the roof covering is dependent
• BS 8000-6 Workmanship on building sites. wind-driven spray. Roofs are required to resist the on a combination of the rainfall rate, wind speed
Code of Practice for slating and tiling of roofs penetration of precipitation (rainfall) to the inside and the ability of the roof tile or slate to resist the
and claddings. This applies to the laying and of the building, thereby preventing damage to any ingress of snow and rain water. The Designer should
fixing of clay and concrete tiles, natural and part of the building where it might be carried. therefore be aware of the various means by which
fibre cement slates and their associated fixings rain and snow can, under certain conditions,
and accessories. Most pitched roofs keep the rain and snow out of penetrate the roof covering.
• BS 5250 Control of condensation in buildings. the building and give a satisfactory performance.
This describes the causes and effects of surface However, it is acknowledged that similar roofs These include:
Technical Manual V8: TS-11A-8.00-010117
and interstitial condensation in buildings, built to the same design and using identical
and gives recommendations for control of roof materials, but in different locations, may not • Capillary action and rain water creep.
condensation in roofs. necessarily provide the same level of assurance • Raindrop bounce and negative pressure rain
since they will be subject to different weather suction.
To ensure safe working practices during construction, conditions and exposure. • Driving rain, deluge rain and flooding.
the Designer should consider relevant safety
© LABC Warranty
Roof pitch 7.9.2.2 Wind factor and the withdrawal resistance of batten nail
When determining the pitch, head-lap and/or fixings are therefore important when determining the
side-lap of a tile or slate, the roof pitch is taken to Design for wind loading overall resistance to wind uplift of the roof system.
be equal to the rafter pitch. Hence, all references When considering the wind loading on the roof
to pitch refer to the rafter pitch, with the laid angle covering, Designers should consult BS 5534. This Ridges, hips, verges and valleys
of the roof tile or slate always being less than roof provides calculation methods to assess the wind The use of mortar for the bedding of concrete,
pitch. load on each tile or slate as a uniformly distributed clay ridge, ridged hip tiles on concrete, lay tiles
load, and also takes into account the porosity or fibre cement slates does not provide sufficient
The actual pitch of a slate or tile should be of the tiles or slates and the effectiveness of the tensile bond strength to resist wind uplift, as it can
determined in accordance with the following substrate (boarding or sarking), and/or underlay be affected by a number of factors, such as wind
guidelines: shielding, when calculating wind uplift loads. The loadings, mix of mortar, design and movement
standard method in BS EN 1991-1-4 Eurocode of the roof structure. The tensile strength of
• Tile/slate to rafter pitch angles. 1. Actions on structures. General actions. Wind mortar should not be taken into account as the
• Plain tiles: 7° less than rafter pitch. actions should be used to determine the basic mechanical fixings should provide the resistance.
• Interlocking single-lap tiles and slates: 5° less wind speed of the site, which is then used to
than rafter pitch. calculate the effective wind speed and dynamic Note: Dry fix ridge and hip systems are available to
• Double-lap fibre cement slates: 1.25° less than wind pressure on the roof by applying a series of provide full mechanical fixing of all ridge and hip
rafter pitch. factors to account for terrain, topography, building tiles to meet BS 5534 recommendations.
height and length, etc.
If the design rafter pitch is less than the minimum Aircraft vortices
recommended rafter pitch for the particular tile Control of internal pressure Roofs near airports can experience high local
Technical Manual V8: TS-11A-8.00-010117
or slate, then they can be considered as having The total wind force on a roof is dependent on wind load forces due to air vortices created by
an aesthetic function only. In such cases, the true the pressure differential between the inner and certain aircraft when taking off and landing, which
weather proofing of the roof system must rely on outer faces of the roof covering. Such pressures may be greater than the wind loads calculated
a fully supported waterproof membrane with an are significantly reduced by the use of underlay or to BS 5534. Designers should seek advice from
uninterrupted drainage path between counter boarding beneath tiling or slating. Its contribution the Airport Authority Planning Department when
battens to the eaves gutter.
© LABC Warranty
towards shielding the underside of the tiles or slates designing roof fixings in these locations, and refer
from the full transmission of internal pressures means to the guidance contained in BRE Digest 467 Slate
the underlay is required to have an adequate and tile roofs: avoiding damage from aircraft wake
tensile strength for the specific application. The vortices.
tensile strength of the underlay, its air permeability 211
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Calculating the fixing specification Sealed ceilings There is advice found in BS EN 13141-1 Ventilation
The procedures for calculating the wind loads BS 9250 emphasises the importance of well-sealed for buildings. Performance testing of components/
and determining the fixing specification for tiles ceilings as a means of curbing the transfer of products for residential ventilation. Externally and
and slates in accordance with BS EN 1991-1-4 and moisture into a roof space by means of moisture- internally mounted air transfer devices:
BS 5534 are complex to undertake. Designers are laden air.
advised to obtain a full roofing fixing specification • Seal all services and roof lights.
from the slate or tile manufacturer. This means: • Use recessed light fittings rated IP60 to IP65 to
BS EN 60529.
7.9.3 Condensation and ventilation • The avoidance of gaps and holes in a ceiling. • Seal the head of cavity walls to prevent the
• The siting of access doors or hatches into the transfer of warm moist air into the loft.
7.9.3.1 Statutory requirements roof space away from moisture-producing
The roof should be designed and constructed in areas, such as bathrooms or kitchens. It is recommended that Designers should
accordance with clause 8.4 of BS 5250 and BS • That hatch covers must be effectively sealed. undertake a Condensation Risk Analysis in
EN ISO 13788. Detailed information on methods • High levels of workmanship. accordance with BS 5250 to determine the level of
to control harmful condensation is provided in BS ventilation required.
5250 Code of Practice for control of condensation Air tightness of ceilings
in buildings Annex H. Air leakage through gaps in a ceiling transfer more 7.9.3.2 Cold roof
heat and moisture into the roof by convection than The following suggest the correct positioning of
Prevention of condensation in roof voids is best passes through the ceiling materials by diffusion. vents and the precise amount of free airspace
achieved through the provision of natural air Sealing the ceiling is therefore an essential required for four types of ‘cold roof’ construction,
ventilation. BS 5250 states that the Designer should requirement when considering the design of the in accordance with current Building Regulations
Technical Manual V8: TS-11A-8.00-010117
take account of the following moisture sources in roof envelope. and BS 5250.
buildings;
Key design issues to consider are as follows: These recommendations apply if a high water
• Water incorporated during the construction vapour resistance (type HR) underlay is used.
process (including precipitation). • Avoid construction gaps.
• Precipitation after construction.
© LABC Warranty
Duo-pitch roof A
On each side of the roof, a free airspace of
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Vapour permeable (type LR) underlays 7.9.3.3 Roof with sloping ceilings Mansard roof
If an LR underlay is used, interstitial condensation The following illustrations suggest the correct Mansard ventilation is similar to that for duo-
is unlikely to occur, provided the ceiling is well positioning of vents and the precise amount of pitch constructions, requiring a free airspace of
sealed and the eaves have a minimum continuous free airspace required for three types of ‘warm roof’ 25,000mm2/m on each side at the eaves or at low
ventilation opening of 3mm. If the ceiling is not construction, in accordance with BS 5250. level (equivalent to a continuous 25mm opening),
well sealed, openings equivalent to 7mm should and 5,000mm2/m at the ridge or at high level
be used; 10mm eaves vent systems will satisfy both Duo-pitch roof (equivalent to a continuous 5mm opening).
requirements. On each side of the roof, a free airspace of
25,000mm2/m is required at the eaves or at low A minimum 50mm clear air path must be
BS 5250 does not consider the situation where it is level (equivalent to a continuous 25mm opening). maintained between the insulation and the
proposed to provide no ventilation to the roof void, A free airspace of 5,000mm2/m should also be underlay at mansard level to ensure effective
or ventilation more limited than described above. provided at the ridge or at high level on each through-ventilation.
Should Designers wish to adopt this principle, slope (equivalent to a continuous 5mm opening).
they should refer to the conditions attached to A minimum 50mm clear air path must always
Technical Approvals given by UKAS (or European be maintained between the insulation and the
equivalent) accredited technical approval bodies. underlay to ensure effective through-ventilation.
Figure 5: Duo pitch roof with sloping ceilings Figure 6: Mansard roof
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Pitched roof with pitched and flat dormers Tiled and slated roofs containing rooms
For the main roof, a free airspace of 25,000mm /m 2
These should be ventilated in accordance
is required at the eaves or at low level (equivalent with Figures 5–7, but if an obstruction to a
to a continuous 25mm opening), plus 5,000mm /m 2
ventilation path occurs, such as fire-separating
at the dormer sills and 5,000mm2/m on each walls, additional ventilation openings should be
side of the ridge or at high level on each slope provided:
(equivalent to a continuous 5mm opening). For
dormers with cold pitched roofs, a free airspace • Immediately below the obstruction, equivalent
of 10,000mm2/m is required at the dormer eaves to 5mm along the length of the obstruction.
(equivalent to a continuous 10mm opening). • Immediately above the obstruction, equivalent
For dormers with flat roofs, a free airspace of to 25mm along the length of the obstruction.
25,000mm /m is required at the roof edges
2
Figure 7: Pitched roof with pitched and flat dormers Figure 9: Warm roof construction (vapour breathable underlay) 215
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.9.4 Thermal insulation 7.9.5 Materials A nominal 10mm drape should be provided
between supports to allow a drainage path for
7.9.4.1 Building Regulations 7.9.5.1 Underlay moisture and to prevent excessive deflection under
Thermal insulation must be installed to meet wind load. Refer to BS 5534 6.2 Underlays.
current Building Regulations, to an acceptable Underlay nails
level of workmanship, to avoid cold bridges and Nails for use with roofing underlays should be clout Classification of underlays
to meet the following provisions: head nails of no less than 3mm shank diameter Underlays should be classified in accordance
and 20mm length made of copper, aluminium with their geographic location and wind zone.
• If required by BS 5250, use a vapour control alloy or steel coated by any of the zinc or zinc alloy Underlays should only be used in those wind zones
plasterboard or a separate VCL behind the coating methods specified in BS EN 10230-1. for which the design wind pressure is not greater
plasterboard. than the declared wind uplift resistance. Refer to
• Use a proprietary eaves ventilator to ensure Underlay BS 5534 A8. Figure A.4 for design wind pressures for
ventilation is in accordance with BS 5250. These types of underlay should comply with BS EN geographical wind zones location map.
• The use of over joist and under rafter insulation 13859-1 or have third-party accreditation, i.e. a BBA
is considered best practice, as it eliminates the certificate.
cold bridge caused by the joist/rafter.
• The installation of the eaves ventilator must There are two categories of underlay: HR, non-
not prevent free water drainage below the tiling vapour permeable and LR, vapour permeable.
battens. These types of underlay should comply with BS EN
13859-1 or have third-party accreditation, i.e. a BBA
7.9.4.2 Compliance certificate. They should also have sufficient tensile
Technical Manual V8: TS-11A-8.00-010117
The requirements of the regulations are designed and nail-tear strength, and low extensibility, to
to reduce carbon emissions from new buildings produce the required resistance to wind uplift.
and improve the performance of existing buildings
where new work is carried out. Underlays for use beneath tiles and slates are
either fully supported over boarding, sheathing or
© LABC Warranty
* HR (high water vapour resistance) and their characteristics and defects should not preservative treatments may corrode steel, zinc or
underlay > 0.25MN.s/g exceed the permissible limits given in Annex C of aluminium.
† LR (low water vapour resistance) BS 5534.
underlay < 0.25MN.s/g
Sizes
(LR underlays are sometimes referred to as ‘vapour
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
(e.g. British Board of Agrément, BRE, etc.) that long x 12 gauge. Screws should be brass or
demonstrates adequacy and durability for use stainless steel, minimum 25mm long x 10 gauge. A copy of the consignment documentation or
(see chapter 2.3.5). “accompanying commercial document” (ACD)
from the supplier / producer should be provided
to confirm these test performances.
© LABC Warranty
219
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
plain tiles, allow no more than three joints together Fiber cement Drape in underlay between supports is to be a
38 25 50 25
in any twelve consecutive battens on the same Slates nominal of 10mm. Fix underlay with the fixings
support. The batten sizes given in Table 2 should be Natural slates 50 25 50 25 specified, keeping the number of perforations to
taken as minimum dimensional requirements. Take * All dimensions subject to re-sawing allowance: width + 3mm a minimum. Handle and fix underlay with care to
care that nails used to secure tiles do not penetrate depth - 0 or + 3mm based on measurement at a reference ensure there are no tears or punctures, and repair
moisture content of 20%.
the underside of battens or the underlay. any tears or punctures prior to tiling. Ensure that the
© LABC Warranty
Table 2: Minimum sizes of timber battens underlay does not obstruct the flow of air through
Recommended batten sizes for pitched roofs and ventilators located at eaves, ridge or in the main
vertical work (BS 5534 in accordance with clause roof, and appropriately weather all holes formed
4.12.4.1): in underlays for soil vent pipes, etc. Avoid contact
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
between the underlay and the underside of tiles, • Fix underlay protector trays, fascia vents and • Carry underlay over gable wall or bargeboard,
while to prevent wind uplift, fix additional battens comb fillers (profiled tiles) and fit undercloak.
or timber strips where laps occur between tiling • Clip eaves course where required. • Use the correct mortar mix.
battens (refer to BS 5534 6.2 Underlays).. • Ensure vent path to roof space is achieved. • Bed and point tiles in one operation.
• Ensure exposed materials are UV resistant. • Keep mortar clear from the ends of tiling
Minimum horizontal lap for underlays (BS 5534 in battens.
accordance with clause 6.2.1.1): • Fix all perimeter tiles and slates
(clip and/or nail).
Not fully Fully supported
Rafter pitch
supported (mm) (mm)
Undercloak
12.5° to 14° 225 150 Where an undercloak is used it should comprise
15° to 34° 150 100 plain tiles, slates or fibre cement sheet strip. It
35° and above 100 75 is usually fixed at verges beneath the battens
Figure 15: Eaves and bottom edge details
and on top of the underlay to support the
Table 3: Minimum horizontal laps for underlays 7.9.7.2 Verge (in accordance with BS 5534 mortar onto which the verge tiles or slates are
and BS 8000-6) bedded, If batten ends are cut, treat with a
7.9.7 Slate and tile details – key check points Battens should overlap onto the outer skin of the suitable preservative. A 100mm wide bed of fully
brickwork or the undercloak material; for plain tiles, compressed width should be neatly laid on the
7.9.7.1 Eaves and bottom edge (in accordance the verge should project 38mm–50mm; interlocking undercloak, this should be bedded solidly and
with BS 5534 and BS 8000-6) tiles can project 30mm–60mm. Where the distance finished neatly.
At the eaves (bottom edge), the batten should of the nearest batten fixing to the rafter is greater
Technical Manual V8: TS-11A-8.00-010117
be set to provide the required overhang of than 300mm, an additional mechanical fixing is
the tiles, slates or shingles into the gutters. The recommended.
recommended overhang is 45mm–55mm
horizontally, or to the centre of the gutter, whichever Note: Where proprietary verge tiles or systems are
is less. specified, the detailing should be in accordance
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.9.7.3 Valley (in accordance with BS 5534 • Avoid discharge of valleys onto roofing wherever • Ensure top course tiles or slates are
and BS 8000-6) possible, but where inevitable use a lead mechanically fixed.
The design of pitched valley gutters is just one roof saddle. • Mitre tiles neatly at hip ridge junctions, and use
detail where the latest guidance is much improved • Avoid direct contact with lead when using a lead saddle underneath for protection.
over previous Codes of Practice. The valley is the mortar; provide a fibre cement undercloak or • Use the correct mortar mix.
most vulnerable area of a pitched roof in respect tile slips. • Use dentil slips in deep profiled tiles in all joints
to potential water ingress, as it drains all of the • Do not block tile laps with mortar to avoid water more than 25mm thick to reduce mortar and
water from adjacent roof slopes. damming. risk of shrinkage.
• Where fibre glass valleys are used only products • All mortar bedded ridge tiles must also be
Consequently, the design data is related to the supported by a third party product approval mechanically fixed by proprietary fixings in
pitch of the roof, the rainfall rate, the length of the will be acceptable and the installation and accordance with the roof covering
valley and the catchment area or area of the roof support of the fibre glass valley unit must follow manufacturer’s recommendations.
to be drained. Designers are able to determine the the manufacturers guidance
width of valley trough appropriate for discharging • Mechanically fix all tile and slates adjacent Note: Dry fix ridge systems are available to provide
the rain water from the adjacent roof covering to to valleys. full mechanical fixing of all ridge and hip tiles to
the eaves gutter. meet BS 5534 recommendations.
7.9.7.4 Ridge (in accordance with BS 5534
• Check roof pitch, area to be drained and and BS 8000-6)
rainfall rate to determine width of valley gutter. The ridge or top course batten should be set to
• Consider length of valley when choosing allow the ridge tiles, ridge units or metal ridge to
proprietary valley troughs (over 8m). overlap the top course of tiles, slates or shingles
Technical Manual V8: TS-11A-8.00-010117
• Ensure ground work provides adequate support by the overlap necessary for the main tiles, slates
for valley lining; make flush with top of rafter. or shingles. For interlocking tiles, this should be not
• Do not place bitumen underlay beneath a lead less than 75mm. For double-lap products, the top
sheet valley. batten should be set to allow the ridge to overlap
• Keep open gutter width 100mm–250mm the penultimate course by the required head-lap.
(correct width to be determined by reference to
© LABC Warranty
7.9.7.5 Hip (in accordance with BS 5534 and 7.9.7.6 Flashings and weatherings Side abutment (stepped cover flashing)
BS 8000-6) The following is a brief summary of metal flashing
• Check hip tile is suitable for pitch of roof. details. For the best advice on the use of lead • Turn roofing underlay a minimum of 50mm
• Mitre tiles neatly at hip ridge junctions and use including typical detailing, reference may be made up at the abutment.
a lead saddle underneath for protection. to the Lead Sheet Association (visit their website • Finish the tiling battens as close to the
• Use the correct hip iron at base of hip. www.leadsheet.co.uk) or check the metal flashing abutment as possible.
• Use the correct mortar mix. manufacturer’s recommendations. • Lay the tiles to butt as close as possible to
• Use dentil slips in deep profiled tiles in all joints the wall.
more than 25mm thick to reduce mortar and A coat of patination oil should be applied to lead • Cut a piece of Code 4 lead to form a
risk of shrinkage. flashings after fixing. Lead can be used in contact combined step and cover flashing.
• All mortar bedded hip tiles must also be with other metals, such as copper and stainless • Flashing should not exceed 1.5m in length, and
mechanically fixed (screws, nails, clips, etc.). steel, without risk of bimetallic corrosion, but should should be 150mm–200mm in width or wide
not be used with aluminium in a marine or coastal enough to cover the first roll, whichever gives
Note: Dry fix ridge systems are available to provide environment. the greater cover.
full mechanical fixing of all ridge and hip tiles to • Chase out brickwork mortar joints and push
meet BS 5534 recommendations. Lead sheet used for roofs, flashings and folds of flashing into chases; wedge in with small
weathering’s should, in terms of suitability to meet pieces of lead.
the requirements of the Technical Manual, be in • Dress cover flashing as tightly as possible to tile
accordance with BS EN 12588 or a valid UKAS (or profile.
European equivalent) third-party accreditation • Repoint brickwork.
(e.g. British Board of Agrément, BRE, etc.) that • In areas of high exposure, or when dressing
Technical Manual V8: TS-11A-8.00-010117
demonstrates adequacy and durability for use lead over flat tiles, use clips to hold cover
(see chapter 2.3.5). flashing in place; when using this type of
flashing with flat tiles below 25°, increase cover
Figure 18: Hips Interlocking tile of flashing over tile to 200mm.
Side abutments
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Side abutment before and dressed over vertical upstand. • Dress lead to the profile of the tiles.
(secret gutter with and without cover flashing) • Turn roofing the underlay up the side of the • Secure lead flashings with copper or
A secret gutter may be formed as an alternative to counter battens and butt the tiling battens up stainless steel clips, with frequency dependent
a step and cover flashing when using single-lap flat to the counter batten. on exposure (see the Lead Sheet Association
interlocking tiles and slates. In view of the increased recommendations).
risk of water penetrating under the lead, especially • Lay tiles to leave a gap of 15mm by the side of
on low pitches in exposed locations, maximum the abutment. Double-lap plain tiles
security can be achieved using a combination of • A lead cover flashing above the secret gutter
both secret gutter and cover flashing. is advisable for interlocking tiles and slates, Side abutment (soakers and step flashings)
particularly in areas of high exposure or on Soakers are used where double-lap plain tiles abut
• Form secret gutters before starting tiling. roofs under trees, where the risk of blockage is a wall.
• Fix a support between the last rafter and the high. If this is done, the width of the secret gutter
abutment; this should be a minimum of 75mm may be reduced to 50mm. • Turn underlay 50mm up the abutment and cut
wide and run the full length of the abutment. tiling battens 10mm–25mm short of the wall and
• Fix a splayed timber fillet at the discharge Top edge abutment fix securely.
point to raise lead lining to the right height; • Lay tiles close to the abutment with a soaker
avoid backward falls. • Turn roofing underlay a minimum of 50mm fitted between each tile.
• Fix a counter batten along the outer edge up at the abutment. • Form code 3 lead soakers with an upstand of
of rafter. • Fix the top tiling batten as close as possible 75mm to place against the abutment. They
• Line gutter with Code 4 or 5 lead, in lengths of to the abutment. should be 175mm wide and 190mm long,
no more than 1.5m. • Complete tiling in the usual way. allowing a 25mm downturn over the back of the
Technical Manual V8: TS-11A-8.00-010117
• Lap each strip offered over the lower one by a • Chase abutment and insert lengths of code 4 tile. After all tiles and soakers have been fixed,
minimum of 150mm, and fix with copper nails lead, no more than 1.5m long; wedge in with insert a stepped flashing into the abutment wall
at head. small pieces of lead, no less than 450mm apart. and dress down over the upturned edges of the
• Turn up lead welts to provide a weather check • Lead should be wide enough to give at least soakers.
and exclude birds and vermin from entering tile 150mm cover to top course of tiles, below 30°.
© LABC Warranty
Fibre cement and natural slates • Dress Code 4 lead cover flashing over the top base of the unit. The head and base trimming joists
course slates and turn up the wall face a should be fixed to the doubled rafters according
Side abutment minimum of 100mm, with the top edge turned to the structural design requirements (for trussed
(step and cover flashing with soakers) into the brickwork bed joint and secured with roof construction follow guidance in 7.8.3.12). If
wedges. a flashing kit is not provided, the flashing should
• Continue the underlay across the roof and
• Extend lead down over the slate to lap the be installed following the Lead Sheet Association
turn up the wall by a minimum of 50mm. Cut
surface a minimum of 150mm, and secure the good practice guide.
the battens 10mm–25mm short of the wall, and
bottom edge with a clip to resist wind uplift.
fix securely.
• Finish the slating with alternate courses of slates
Dormers
and slate-and-a-half slates, cut as necessary to
Treat tiled dormer roofs in a similar way to the main
maintain the bond.
roof work. However, single-lap tiling is less suitable
• Code 3 lead soakers, with a minimum width of
for small covered areas, and for a dormer, it is
175mm and length equal to gauge + lap +
generally preferable to adopt an alternative form of
20mm, are to be interleaved with the slates and
covering.
turned 75mm up the wall.
• The Code 4 stepped lead flashing should be
When dormer cheeks are tile hung, close cut
secured in the brickwork bed joints with lead
vertical tiles to the roof rake over a flashing fixed
wedges and dressed neatly over the soakers.
to the side of the dormer, and dress well into the
adjacent tiles. The formation of a secret gutter is
Top edge abutment flashings
not recommended.
Technical Manual V8: TS-11A-8.00-010117
the full length slate. with ‘flashing kits’ which should be installed in
• Head nail the top course slate and use a disc accordance with the manufacturers instructions.
rivet to secure the tail in the usual manner. Roof lights formed in traditional cut roofs should
Centre nail and rivet the full length slate below have doubled up rafters either side of the opening
Figure 19: Section through roof light
in the normal way. to support the trimming joists at the head and (image supplied by Marley Eternit Ltd) 225
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Back gutters • Make perforations for pipes, chimney stays, • Slate-and-a-half should be used in alternate
Back gutters may be lead welded off-site and supports for ladders, etc. weather tight by courses at internal and external corners and
positioned when tiling is undertaken. A gutter dressing over and under tiling with a lead adjacent to openings.
should be formed where the bottom edge of tiling or copper slate to which a sleeve is burned or • Use Code 3 lead soakers to weather internal
meets an abutment. Form the gutter before tiling, soldered. and external corners.
but after felting and battening is complete. • Boss sleeve around pipe or stay, and seal at top • Fix slates by two nails and one rivet, and slate-
with a collar. and-a-half by three nails and two rivets.
• Fix a lay board to support lead lining, with a • Code 4 lead cover flashings should be used
tilting fillet, close to the abutment to flatten the Saddles above and below openings, in accordance with
pitch of the lead. The following details can apply to any type of Lead Sheet Association recommendations.
• Dress a sheet of Code 5 lead (width of valley or hip/ridge intersection:
abutment plus 450mm) into position with Vertical tiling with plain tiles
a vertical upstand of at least 100mm up the • Use Code 4 lead no less than 450mm square Plain tiling is an excellent, weather proof and
abutment. and large enough to give a lap of at least attractive cladding to the vertical walls of any
• Dress the extra width of lead around the 150mm over the gutter lining on each side. building. Feature and ornamental tiles may also be
corner of the abutment after any side abutment • Saddles should be capable of being readily used with normal plain tiles to create decorative
weathering has been fitted. dressed down when in position. patterns. Fibre cement slates can also be used for
• Dress the upper edge of lead over the tilting vertical cladding.
fillet and turn it back to form a welt. 7.9.7.7 Vertical tiling and slating
• Chase abutment, insert a cover flashing of Vertical slating with fibre cement slates • Use counter battens over masonry construction
Code 4 lead and dress it over the vertical Fibre cement slates can be fixed to vertical (38mm x 25mm minimum) to reduce direct
Technical Manual V8: TS-11A-8.00-010117
upstand of the gutter. surfaces and provides an attractive and weather fixing. Special masonry fixings may be required.
proof cladding on both timber frame and masonry • Ensure tiling details do not interfere with the
Roof protrusions constructions. opening of windows and doors.
The treatment of tiling against chimney stacks, • Lead flashings and soakers should be used
skylights and other similar projections through the The following guidance notes apply to this detail: around openings, in accordance with Lead
roof surface should be similar to that described for
© LABC Warranty
227
CHAPTER 7
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Roof coverings must prevent any external moisture passing into the
a workmanlike manner. internal environment of the dwelling.
iii. Certification is required for any work completed by an approved iii. Structural elements outside the parameters of regional Approved
installer. Documents must be supported by structural calculations provided by
a suitably qualified expert.
Materials iv. The materials, design and construction must meet the relevant
i. All materials should be stored correctly in a manner that will not cause regional Building Regulations.
damage or deterioration of the product.
ii. All materials, products and building systems shall be appropriate and Limitations of Functional Requirements
suitable for their intended purpose. i. The Functional Requirements are limited by the recommendations
iii. Whilst there is and can be no Policy responsibility and/ or liability for a applied to the specific areas covered in this chapter.
roof covering performance life of 60 years or less, roof coverings shall ii. These Functional Requirements do not and will not apply to create
be designed and constructed so they have an intended life of not less any policy liability for any remedial works carried out by the contractor
Technical Manual V6: TS-011a-6.00-010413
than 15 years.
Technical Manual V8: TS-11A-8.00-010117
7.10.1 Definitions Vapour control layer (VCL): construction material The design should ensure that:
For the purposes of this Technical Manual, (usually a membrane) that substantially reduces
the following definitions shall apply: the movement of water vapour through the roof • The structural deck is maintained at a
system. temperature above that which could cause
Flat roof: a roof having a pitch no greater than 10º condensation to occur at this level during
to the horizontal. Water control membrane (WCM): construction service.
material (usually a sheet membrane) that • A VCL is provided by the deck or by a
Condensation: process whereby water is substantially reduces the transfer of rain water to membrane placed above the deck.
deposited from air containing water vapour when the insulation in an inverted warm deck roof. • The insulation has sufficient mechanical
its temperature drops to or below dew point. characteristics to resist loading.
Protection layer: construction material (usually • The waterproof membrane has sufficient
Interstitial condensation: condensation occurring a geotextile all rigid board) that isolates another resistance to temperature to suit the conditions
within or between the layers of the building construction material from mechanical damage. created by a substrate of insulation.
envelope.
Filter layer: construction material (usually a
Insulation cricket: wedge of shallow- fall insulation geotextile) that substantially reduces the transfer
material, designed to divert the flow of rainwater on of mineral and organic material to the insulation in
a roof an inverted warm deck roof.
Thermal bridge: part of a roof of lower thermal Separation layer: construction material (usually
resistance than its surrounding elements, which a geotextile) that separates two construction
Technical Manual V8: TS-11A-8.00-010117
may result in localised cold surfaces on which materials that are not chemically compatible.
condensation, mould growth or staining may
occur. 7.10.2 Design criteria – system type
Figure 1: Warm roof section above vapour control layer
Structural deck: continuous layer of the Warm deck roof (if shown by calculation to be required)
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Inverted warm deck roof Cold deck roof ensure that the deck is above dew point during
A variant of the warm deck roof in which the The principal thermal insulation is placed at service.
principal thermal insulation is placed above the or immediately above the ceiling, i.e. below
waterproof membrane, resulting in the waterproof the structural deck, resulting in the waterproof
membrane, structural deck and structural support membrane and structural deck being substantially
being at a temperature close to that of the interior colder in winter than the interior of the building.
of the building. Generally, the principal insulation is The structural support will typically form a thermal
secured by separate ballast (paving or stone). bridge between the high and low temperature
zones of the construction. It is very difficult to
A filter membrane or WCM should be provided insulate a cold roof system to current mandatory
to control mineral and organic material passing levels without introducing thermal bridges and/
into and below the insulation joints. A WCM is or increasing the risk of interstitial condensation in
recommended because it will provide improved the system. In addition, the mandatory requirement
rain water run off, which may allow for a reduced for uninterrupted external air circulation limits Figure 3: Cold roof section ‘under ventilation’
(to/from external air. Minimum height of void 50mm)
thickness of insulation and reduced loading of the application of the system where abutting
ballast. If a WCM is included, it is essential that the elevations or changes in building geometry occur.
drainage design facilitates the rapid transfer of rain Therefore, it is not recommended. Hybrid roof
water across the product and to rain water outlets. Many roofs combine the features of two or more
If an existing cold deck roof is refurbished, of the roof types previously described. Examples
it is important to ensure that the ventilation include structural decks of high thermal resistance
requirement is achieved, whether or not the level of combined with additional insulation, and existing
Technical Manual V8: TS-11A-8.00-010117
insulation is to be increased. It is also not feasible to roofs to which thermal insulation is added. Once
introduce vapour control and insulation below an assessed in terms of their thermal and water
existing structural deck of concrete, e.g. if during vapour transmission characteristics, such roofs will
refurbishment, a cold deck roof is converted to a generally fall into one of the categories described.
warm deck roof by placing insulation above the
In some constructions, the waterproof membrane
© LABC Warranty
7.10.3 Loading 7.10.4.2 British and industry standards Consideration should also be given to;
BS 6229 states that a minimum finished fall at any
7.10.3.1 Statutory requirement point of 1:80 (1.25%) should be achieved. Since • The available upstand height at the high
Design for loading complies with the current adjoining roof planes at 1:80 will meet at a mitre end of the falls. This may be a limiting factor on
Building Regulations. of less than 1:80, the intended finished fall at such the length/size of the roof area to be drained.
intersections should be considered at an early stage. If necessary additional rainwater outlets should
7.10.3.2 Resistance to wind load be provided.
In all situations, including ballasted, green and Design falls should take account of any potential • Avoidance of ponding behind wide
inverted roofs, a calculation of wind load at each deflection and construction tolerances. In the obstructions to the drained slope such as plant
zone of the roof to BS EN 1991-1-4 should be absence of detailed calculations, this may plinths or roof lights. Additional rainwater outlets
undertaken by a suitably competent person. necessitate design falls of twice the minimum finished and / or insulation crickets should be provided.
falls (1:40 or 2.5%). • Avoidance of gutters by designing with
7.10.3.3 Resistance to imposed loads intersecting roof planes.
At the earliest possible stage, the employer should Cut-to-falls systems are often produced to a 1:60 • Falls between rain water outlets along a perimeter.
define the range of potential functions of the (1.7%) fall or 1:40 (2.5%) fall. However the use of
roof with regards loading with equipment, e.g. these systems does not remove the need to check Since the primary function of the roof is to exclude
air handling, renewable energy capture and the that deck deflection and tolerance is overcome water, it is important to consider how best to direct
intensity and frequency of foot traffic. This should and that a resulting fall in the waterproof membrane this into the drainage system.
inform the selection of the deck, insulation, safety of a minimum of 1:80 is achieved. Allowance for
guarding and protection. deflection is particularly important in designing Ponding on membrane roofs should be avoided
inverted roofs where calculation of dead loading because:
Technical Manual V8: TS-11A-8.00-010117
7.10.4 Falls and drainage should be based upon the ballast type and depth to
be used. • It encourages the deposition of dirt and leaves,
7.10.4.1 Statutory requirement which can be unsightly, may obstruct outlets
Design for drainage should comply with the current The manufacturers of certain waterproofing products and/or become a slip hazard.
Building Regulations. have certification for their use in ‘completely flat’ • In the event of damage, the interior will suffer
© LABC Warranty
or ‘zero falls’ applications. For the purposes of this increased water ingress.
standard the design conditions of BS 6229 shall be • The load may cause progressive deflection of
assumed to prevail in all warm and cold deck roof the deck.
systems. • Ice or algae may create a slip or wind hazard,
particularly on walkways. 231
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Independent research has shown that roofs with Cementitious screeds provide a stable substrate Fall at mitre will be less than
fall in each roof plane
extensive ponding require increased maintenance to mitred falls with minimal tolerances, and are
input. recommended. Screeds should be in accordance
with BS 8204. Lightweight screeds should be 1:80 Finished 1:80 Finished
Fall Fall
Waterproof coverings of all types are tested for overlaid with a 1:6 (cement to sand) screed
water absorption and water tightness as part of topping of a minimum 10mm thickness.
third-party certification. However, the construction
process, including the installation of components Tapered insulation schemes, suitable for warm RWO RWO RWO
and the forming of seams, is clearly facilitated in deck roofs only, have the following advantages:
dry, well-drained conditions.
1:80 Finished
• It is possible to create effective drainage layouts Fall
The creation of falls in the deck should always Where falls are created by tapered insulation, the
1:80 Finished
be attempted because it has the following design should ensure that the average U-value Fall
advantages: and maximum U-value at any point, required by
SBEM or SAP calculation, is achieved.
RWO Box Gutter
• There will be a consistent thermal environment
Technical Manual V8: TS-11A-8.00-010117
across the roof. Where the roof finish is to include paving on access
This design is not
• The VCL will also be to a fall, and will act as a routes, consideration should be given to the height acceptable
temporary line of defence to water ingress difference created by the falls and spacing of rain
Figure 4: Drainage layout options
during construction. water outlets in order that the maximum height of
• If mechanical fasteners are to be used for paving supports is not exceeded or trip hazards
the waterproof membrane, their length will
© LABC Warranty
created.
be constant, which facilitates planning and
installation.
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.10.5 Drainage For further information see www.siphonic-roof- In particular, allowance should be made for the
Drainage design should be based upon drainage.co.uk effect of:
calculations in accordance with BS EN 12056 Part
3 given a design head of water (typically 30mm). Roof systems designed to attenuate the discharge • Thermal bridging by metal fasteners used to
Rain water outlet capacity should be taken from of rainwater to surface water drainage are secure insulation and/or membrane. Thermal
properly certificated information provided by becoming more common. Any such designs must break telescopic tube fasteners are
manufacturers, and the resulting number and consider not only the effect upon loading but also recommended to avoid this.
layout of outlets should allow for obstruction and the effect of hydrostatic pressure on the waterproof • Thermal bridging due to drainage of rain
drag due to any additional surface finishes, such membrane. Where a head of water is deliberately water or snow-melt through insulation in
as walkways. retained on the roof, appropriate certification of the inverted roofs. The use of WCMs beneath ballast
It is not generally necessary to provide separate waterproof membrane product must be supplied to reduce thermal bridging is recommended.
box gutters where two planes of roofing intersect, which demonstrates fitness for purpose in this • The locations of above-average thermal
or where a single plane falls to an abutment. In the application. transmittance at sumps, gutters or areas of
latter case, there will be no fall between outlets, so minimum thickness of tapered insulation.
consideration should be given to creating these 7.10.6 Thermal performance
in the structure or insulation. Box gutters are slow, Manufacturers of thermal insulation and WCMs
difficult to construct and introduce unnecessary 7.10.6.1 Statutory requirement provide certification and calculations of the effects
complexity. The need to maintain a fall in gutters Design for thermal performance must comply with of thermal bridging by fasteners and drainage
and comply with the energy requirements of the current Building Regulations, as appropriate. respectively. Further advice is available in Building
Building Regulations may be difficult to achieve. Research Establishment BR 262 Thermal insulation:
7.10.6.2 Thermal transmittance avoiding risks, 2002 edition.
Technical Manual V8: TS-11A-8.00-010117
All waterproof membranes are compatible with Design for thermal transmittance should take
siphonic roof drainage systems, which for larger account of the effect of thermal bridging within the 7.10.6.3 Air permeability
roofs offer many advantages: roof field and at interfaces between the roof system Relevant contract drawings should define the
and adjoining elements, such as parapet walls or position of the component – the air barrier – that
• Very high capacity, enabling fewer outlets and abutments. determines resistance to air permeability. This may
therefore less detailing work on-site.
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.10.6.4 Control of condensation 7.10.8.2 Edge protection • Polymeric single ply and reinforced bitumen
Any provision required to control interstitial In the absence of suitable parapet walls, membranes: galvanised steel sheet with
condensation within the roof should be permanent edge protection should be provided additional covering with slip-resistant finish.
determined to the calculation method defined by along roof-level pedestrian routes to equipment
BS 5250, but with ambient conditions set in that requires regular access for servicing. 7.10.9 Detailing
BS 6229. The calculated maximum accumulation
of moisture within thermal insulation should 7.10.8.3 Protection of roof system 7.10.9.1 General principles
not exceed 350g/m and there shall be no net
2
At the earliest possible stage, the anticipated At an early stage in the design process, an audit
accumulation in any annual cycle.. loading of the roof by plant and access during of roof geometry should be carried out to establish
service should be assessed in terms of: what types of details will be required and whether
7.10.7 External fire performance they are to be weather proof (incorporating
• Load, e.G. Foot traffic, equipment an upstand/cover flashing arrangement) or
7.10.7.1 Statutory requirement • Frequency waterproof (providing continuous waterproofing
Design for external fire performance must comply • Risk of impact across the detail).
with current Building Regulations.
The design should include protection to suit the The following key principles should be followed in
7.10.7.2 Certification of system anticipated conditions as appropriate: design of all details:
The manufacturer of the waterproof membrane
must demonstrate by reference to independent • Slip-resistant walkway material. • Upstands to extend 150mm above the finished
test certification that the system of waterproofing • Polymeric single ply membranes: compatible roof level.
and insulation (type and thickness) for a particular sheets or tiles welded to the membrane. • Downstands (of separate metal or other
Technical Manual V8: TS-11A-8.00-010117
project meets or exceeds the minimum level of fire • Reinforced bitumen membranes: heavy-duty flashings) should lap the upstand by a
performance defined by the Building Regulations. mineral surfaces sheets or tiles. minimum 75mm.
7.10.8 Provision for access • Liquid-applied membranes: additional coating • Construction should achieve independence
with textured finish. between different elements and trades.
7.10.8.1 Statutory requirement • Mastic asphalt: heavy-duty mineral surfaces • Thermal and fire performance should be
Design for access should comply with current
© LABC Warranty
The total roof zone depth should be assessed at Special design features are essential, depending
critical points, such as the top of drainage slopes, upon the generic type of waterproof membrane,
to ensure that there is enough free upstand including:
available to create the minimum required 150mm
of waterproofing protection above finished roof • Minimum clearances to enable the waterproof
level. membrane to be installed.
• Termination of the waterproof membrane at
It is important that this minimum 150mm upstand is interfaces to other elements.
maintained at all points around the waterproofed • Penetrations.
area, except at continuous water checks and • Supports.
verges. Balconies are a frequent exception due
to the need for level or unobstructed access (see
chapter 7.6 – Balconies). Designers should carefully
consider the risks of any departure from this
criterion. In the event of this being unavoidable, a
written justification should be provided.
Figure 5: Principles of detailing. An example of warm deck roof at Figure 6: Penetration through roof system Figure 8: Detail: principles: Options for support of plant
an abutment 235
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.10.9.2 Renewable energy capture equipment • The upstand of the waterproof membrane at 7.10.10.2 Structural deck
Renewable energy capture equipment includes risers should be arranged to enable a separate
photovoltaic panels and multi-panel arrays, solar downstand or weathering flashing to be formed General
thermal panels and multi-panel arrays and wind in ductwork. At the earliest practical stage, the likely deflection
turbines. All such equipment should be secured • Cladding to insulation placed around ductwork in the deck, and the tolerance in the level of its
to a frame and/or posts that transfer their load should not be sealed to the waterproof finish, should be confirmed, because this informs
directly to the structure. The roof system and membrane. the design for drainage. If the deck is intended to
waterproof membrane should be designed to • Sufficient clearance should be provided to receive mechanical fasteners for the attachment
enable equipment to be demounted without horizontal ductwork to ensure it does not rest of roof system components such as insulation,
loss of the roof’s waterproofing integrity and upon the waterproof membrane or roof finish. or equipment such as fall-arrest line posts, its
without the involvement of the roofing specialist. resistance to pull-out should also be confirmed to
Support systems based on ‘top-fixed’ plate and 7.10.10 Materials enable design for resistance to wind load.
post components should be accompanied by
documentation to demonstrate their compatibility 7.10.10.1 Requirement Concrete
with the waterproof membrane. Precast concrete construction should be designed
General in accordance with BS 8110. Information on span
7.10.9.3 Handrails and balustrades Materials for use in flat roofing systems are suitable capability and the installation requirements
See chapter 7.6 – Balconies. only if the manufacturer has declared compliance of precast panels can be obtained from
with the relevant harmonised European Product manufacturers. Information on the location of
7.10.9.4 Mechanical and electrical services Specification (hEN or European Technical Approval required movement joints should be obtained early
Detailed design should take account of the Guideline (ETAG) and has affixed the CE Mark to in the design process as they have implications
Technical Manual V8: TS-11A-8.00-010117
installation of such equipment by other (usually the product. All waterproof membrane products for drainage layout and detailing. Precast panels
following) trades, as follows: shall also have a certificate of fitness for purpose installed to a fall can provide a simple layout but
issued by a member of the European Union of without cross falls.
• Services entry/exit points should be suitably Agrément (UEAtc). This may comprise a British
weathered to enable connection without loss of Board of Agrément certificate or an equivalent
integrity of the waterproof membrane and
© LABC Warranty
In-situ concrete construction should be designed In precast panel decks the locations of any Profiled metal decks should conform to the
in accordance with BS 8110. It is more difficult to anticipated differential movement (e.g. at following standards:
lay to a fall, and it is more common to create falls perimeter or abutment interfaces or between
in the insulation (warm roofs only) or by using an adjacent panels that are subject to differential • Galvanised steel: minimum recommended
additional screed. Information on compressive loading) must be identified in order that stress is thickness 0.7mm to BS EN 10346 Fe E280G Z275.
strength, resistance to point load and drying not transferred to the waterproof membrane. Typical gauge range 0.7mm–1.2mm.
periods of wet screeds can be obtained from • Plain aluminium: minimum recommended
suppliers and relevant trade associations. Profiled metal (steel or aluminium) thickness 0.9mm to BS EN 485-2 AA3004 H34.
Profiled metal decks should have a crown width at Reference should also be made to BS EN 1396
Where structural movement joints are required in least 50% of the profile width. To provide a sound as appropriate.
large concrete decks, a clearly defined movement base for the insulation and waterproofing system,
joint detail should be constructed to a design and and to avoid reduced drainage performance, Timber panels
with the materials that afford durability equivalent the mid-span deflection of the metal deck should Roofing grade OSB should be manufactured
to that of the roof system. not exceed 1/200 of the span under uniformly to BS EN 300 grade OSB/3 and be certificated
distributed design loads. When considering the by the British Board of Agrément. The minimum
deck profile and the necessity for side lap stitching recommended thickness is 18mm.
and metal deck closures, reference should be
made to the manufacturers of the deck, insulation Plywood should be minimum 18mm thickness and
and waterproof membrane. certificated to conform to BS EN 1995-1-1 Eurocode
5. Design of timber structures, and to BS EN 636
Plywood, specifications minimum service class 2 –
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
a supporting deck. It may be used to clad an on the level of vapour resistance required, based Fully bonded
High density to prepared
abutment or parapet but is not suitable for use on calculation, and the type of deck. polyethylene As per substrate
Proprietary
with mechanically fastened single ply membrane. and metal certification all as per
foil laminate manufacturer’s
instructions
Fully bonded
Coated
to prepared
metal foil
As per substrate
Technical Manual V8: TS-11A-8.00-010117
laminate Proprietary
certification all as per
– self-
manufacturer’s
adhesive
instructions
Notes:
239
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Products suitable for roofing should have current certification by one of the following:
In addition, specifications for systems of multi-layer reinforced bitumen membranes for flat roofing should comply with BS 8747.
Roof system type Deck type Insulation type(1) Venting layer(2) Underlayer(3) Cap sheet(4)
Thermoplastic
3G S2P3(5) S4P4(5)
Profiled metal foam
Mineral fibre - S2P3 S4P5
Thermoplastic
- S2P3 S4P4
Warm deck Concrete foam
Mineral fibre - S2P3 S4P4
Thermoplastic
3G S2P3 S4P5
Timber panel foam
Mineral fibre - S2P3 S4P4
Technical Manual V8: TS-11A-8.00-010117
Notes:
(1) Insulation type: Thermoplastic foam: PIR, EPS, PF. Mineral fibre: (4) Cap sheet: as defined in BS 8747. SBS-modified
© LABC Warranty
Bitumen membranes should be protected from • Part 4: Flexible unsaturated polyesters European Standard for these products.
solar radiation. This should be by integral protection • Part 5: Hot applied polymer modified Products suitable for roofing should have current
provided in the product in the form of: bitumen certification by one of the following:
• Part 6: Polyurethanes
• Mineral granules • Part 7: Bitumen emulsions and solutions • British Board of Agrément
• Metal foil • Part 8: Water dispersible polymers • Another member of the UEAtc
• Another notified body
The use of solar reflective paint is not permitted. The manufacturer of a product for use in flat
The use of stone chippings is not recommended roofing should declare compliance with the The separating membrane should be one of the
unless required to achieve enhanced external fire relevant parts of ETAG 005. In the absence of this following, and should be laid directly under the
performance. If used, chippings should be washed, declaration, the product should have a current mastic asphalt:
crushed rock, normally 10mm–14mm nominal size certificate of fitness for purpose issued by one of
aggregate, bedded in a proprietary gritting solution. the following: • Sheathing felt, comprising a base of flax or jute,
or other suitable fibres, impregnated with bitumen.
7.10.12.4 Liquid-applied membranes • British Board of Agrément • Glass fibre tissue.
There is no harmonised European Product • Another member of the UEAtc
Specification for liquid applied membranes • Another notified body Bitumen-coated plain expanded metal lathing
for roofing. The European Technical Approval should be in accordance with BS EN 13658-2.
Guideline ETAG 005 Part 1 – General gives overall Such certification should be accompanied by full
guidance on assessment of fitness for use, instructions for installation. Stone chippings (bedded) for use as a protective
including methods of verification and attestation topping should be washed, crushed rock, normally
Technical Manual V8: TS-11A-8.00-010117
of conformity. The remaining seven parts, known 7.10.12.5 Mastic asphalt 10mm–14mm nominal size aggregate, bedded in a
as the Complementary Parts or the ETA Parts, deal There is no harmonised European Product proprietary gritting solution over the mastic asphalt
with specific requirements for particular families Specification for mastic asphalt for roofing. Products membrane.
of products, and are the generic types covered used for flat roofing should comply with BS 6925:
primarily by this Guidance Note, shown as follows: 1988 Specification for mastic asphalt for buildings
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.10.12.6 Site-applied hot-melt coverings 7.10.13.2 Access areas: concrete paving slabs • Integral insulation to avoid condensation.
There is no harmonised European Product Concrete paving slabs for use as walkways or • Method of attachment.
Specification for site-applied hot-melt waterproofing as paving on terrace decks should conform to
systems. BS EN 1340, and be laid in accordance with the Rainwater outlets for inverted roofs should be of the
manufacturer’s instructions. dual height type, designed to maximise removal of
Products suitable for roofing should have current rainwater at WCM level.
certification by one of the following: 7.10.13.3 Access areas: porous concrete tiles
(for use on reinforced bitumen sheets 7.10.13.6 Fall-arrest and edge protection
• British Board of Agrément and mastic asphalt only) equipment
• Another member of the UEAtc Tiles for walkways or terrace deck paving should be The following should be confirmed by reference
• Another notified body designed for this application, bedded in a bonding to the manufacturer’s information or independent
compound compatible with the water proof certification, as appropriate:
As these systems comprise a multi-layer application membrane and fixed in accordance with the tile
(usually a base coat, reinforcement and top coat), manufacturer’s recommendations. • Compliance with BS EN 795.
a detailed specification for the system should be • Method of attachment.
available prior to commencement of the works to 7.10.13.4 Access areas: flexible walkway tiles • Compatibility with the waterproof membrane.
enable its suitability for the project to be confirmed. Evidence of the compatibility of the tile with the • Means of forming a water tight seal to the
waterproof membrane is required. Tiles for walkways waterproof membrane.
7.10.13 Ancillary components or terrace deck paving should be bedded in
a bonding compound compatible with the 7.10.13.7 Lightning protection
7.10.13.1 Non-access areas: stone ballast waterproof membrane and fixed in accordance The following should be confirmed by reference
Technical Manual V8: TS-11A-8.00-010117
Stone ballast for inverted warm deck roofs and with the tile manufacturer’s recommendations. to the manufacturer’s information or independent
ballasted warm deck roofs should be clean, certification, as appropriate:
rounded aggregate graded 20mm–40mm and 7.10.13.5 Rain water outlets
as free from fines as practicable. Ballast should be The following should be confirmed by reference • Design in compliance with BS EN 62305.
applied over a protection layer on warm ballasted to the manufacturer’s information or independent • Method of attachment to the waterproof
systems and over a filter layer or WCM on inverted
© LABC Warranty
7.10.13.8 Support for renewable energy 7.10.15 Installation It is recommended that concrete paving is laid
capture equipment on support pads, as this allows adjustment, thus
Renewable energy equipment includes 7.10.15.1 Protection of the roof reducing the risk of a trip hazard:
photovoltaic panels and multi-panel arrays,
solar thermal panels and multi-panel arrays and Temporary protection (during construction) • The height of support pads should not exceed
wind turbines. All such equipment should be Responsibility for temporary protection and a the maximum recommended by the
secured to a frame and/or posts that transfer method statement for its use should be agreed manufacturer.
their load directly to the structure. Support systems prior to commencement of works. Suitable • Paving should not be cut.
based on ‘top-fixed’ plate and post components materials should be selected in consultation with • Paving should be firmly butted up against
are acceptable only if accompanied by membrane manufacturers as appropriate, for support pad separating pegs.
documentation to demonstrate their dead and example:
live loading capacity and compatibility with the 7.10.15.2 Vapour control layer (VCL)
waterproof membrane. • Linked recycled thermoplastic sheets. The attachment of the VCL should be designed to
• Rolled recycled thermoplastic or elastomeric resist calculated wind load by a declared margin
7.10.14 Compatibility of components sheets. of safety. All laps should be sealed and the VCL
The selection of components within the roofing should be sealed to the adjoining element, which
system should be discussed in detail with the Particular consideration should be given to forms the continuation of the resistance to air
membrane manufacturer or appropriate trade locations of concentrated access, such as step-out permeability. The VCL should be extended behind
association to ensure chemical and mechanical areas onto the roof or where wheeled equipment all thermal insulation, including insulation placed
compatibility between components, since the may be used. on vertical surfaces such as parapet walls. Where
incorrect specification may lead to reduced the roof system is penetrated by a detail such as
Technical Manual V8: TS-11A-8.00-010117
performance or premature failure of the roofing A clear plan of type, location, sequencing and a pipe or duct, a suitable method for providing
system. The correct choice of insulation is also removal of temporary protection should be continuous vapour control should be provided,
important when it is to be adhered to the substrate. available before the roof system installation starts. and this method should be followed in practice.
In case of doubt, the insulation manufacturer or Where a reinforced bitumen membrane VCL is
relevant trade association should be consulted. Permanent protection (during service) used, its installation should be in accordance with
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.10.15.3 Thermal insulation Where the method of attachment is outside 7.10.15.4 Waterproof membrane
The attachment of the thermal insulation should the scope of BS 8217, the manufacturer should
be designed to resist calculated wind load by a demonstrate that the method provides sufficient Polymeric single ply membranes
declared margin of safety. This includes consideration resistance to wind load. There is no British Standard for the installation of
of dead loads required in all roof zones in ballasted single ply membranes. Installation should be in
warm roofs and inverted warm roofs. Warm roof systems with mastic asphalt accordance with the Single Ply Roofing Association’s
waterproofing Design Guide to Single Ply Roofing and with the
Except in tapered insulation schemes, thermal Generally, mastic asphalt on sheathing felt provides specific instructions of the membrane manufacturer.
insulation should always be laid in a broken bond sufficient dead load to resist wind load, but this should
pattern. Where two or more layers are laid, the be demonstrated by calculations in all situations. The attachment of the single ply membrane should
joints in each layer should be offset. On substrates be designed to resist calculated wind load by a
of profiled metal, the short dimension should be Warm roof systems with polymeric declared safety factor of two times (200%). This
parallel to the deck crowns and supported across single ply waterproofing design will normally be provided by the membrane
half the crown width. Where the insulation is mechanically fixed, the manufacturer.
number and arrangement of fasteners required
Insulation should be lightly butted so as to avoid to resist wind load will be prescribed by the Whatever the means of attachment, specific
thermal bridging caused by gaps. If large gaps are manufacturer, applying a safety factor of two to the restraint is always required at the roof perimeter, at
created by damaged or undersized boards, any design load on each fastener. This arrangement changes of slope and around details. This ensures
infill sections should be attached in accordance may vary across the roof according to wind load, that any tension in the membrane in the roof field
with the manufacturer’s instructions. but should be followed in all areas. Thermal break or upstand is not transferred to the other as a
fasteners shall be used wherever feasible. peeling action.
Technical Manual V8: TS-11A-8.00-010117
If restraint relies upon adhesive alone, the Irrespective of the wind uplift considerations • Provision of consistent electrical power supply.
membrane manufacturer shall provide evidence or distribution requirements for securing the • Production and retention of test weld samples
of satisfactory testing for resistance to wind load membrane, the fixing of the insulation boards at the start of each day.
using a method defined by the Single Ply Roofing should always be considered separately, unless • Declared procedures for repair of weak welds or
Association. specifically sanctioned by the membrane damage.
manufacturer. The number and distribution
of mechanical fasteners required to fix the Reinforced bitumen membranes
insulation boards may vary with the insulation Installation should be in accordance with BS
type, geographical location of the building, 8217. In case of doubt, or where the waterproof
topographical data and the height of the roof membrane is beyond the scope of the Standard,
concerned. the advice of the Flat Roofing Alliance (National
Federation of Roofing Contractors) should prevail.
The upper termination of the single ply membrane
at linear details such as plinths, parapets, The safe use of gas torches, and the positioning,
abutments and door openings should be secured monitoring and transferring hot bitumen to the
by one of the following mechanical means: work face, should be adopted, all in accordance
with the Health & Safety Executive/Flat Roofing
• Clamping beneath a metal rail, e.g. a parapet Alliance Code of Practice for Safe Handling of
capping or roof light frame. Bitumen.
• Welding to a membrane-metal laminate trim
(itself mechanically fixed). The practice of applying reinforced bitumen
Technical Manual V8: TS-11A-8.00-010117
• Mechanical fixing using individual fasteners or membranes by torching onto thermoplastic foam
a mechanically fixed termination bar. insulation is not permitted, unless the boards
are manufactured with a covering of reinforced
The welding of single ply membranes is a critical bitumen membrane.
Figure 10: Methods of restraint of single ply membrane at
perimeters process. The following should be considered;
© LABC Warranty
If the remainder of the roof system is to be bonded, • Supply of a card for each installer indicating
it is essential that the design resistance to wind successful completion of the manufacturer’s
load is also achieved for the attachment of these product–specific training.
components. 245
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
successful completion of the manufacturer’s proprietary hot-melt waterproof membrane systems. circumstances of the project.
product–specific training Reference should be made to independent • Experience and training of operator.
• The coverage rate in kg/m2 must be declared certification and the manufacturer’s detailed • Membership of an appropriate trade
before work starts instructions. association that sets a Code of Conduct for the
• During installation assessment of wet film service.
thickness by one of the following methods as
© LABC Warranty
appropriate:
- gauge pin
- ‘comb’ type measurer
- visual inspection
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Flood testing
Flood testing is not recommended as a method of
demonstrating the integrity of flat roofs. It may be
used to test balconies (see chapter 7.6 – Balconies). 247
CHAPTER 7
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in a ii. Roof coverings must prevent any external moisture passing into the
workmanlike manner. internal environment of the dwelling.
iii. Certification is required for any work completed by an approved iii. Structural elements outside the parameters of regional Approved
installer. Documents must be supported by structural calculations provided by
a suitably qualified expert.
Materials iv. The materials, design and construction must meet the relevant
i. All materials should be stored correctly in a manner that will not cause regional Building Regulations.
damage or deterioration of the product.
ii. All materials, products and building systems shall be appropriate and Limitations of Functional Requirements
suitable for their intended purpose. i. The Functional Requirements are limited by the recommendations
iii. Whilst there is and can be no Policy responsibility and/ or liability for applied to the specific areas covered in this chapter.
a roof covering performance life of 60 years or less, roof coverings shall ii. These Functional Requirements do not and will not apply to create
be designed and constructed so they have an intended life of not less any policy liability for any remedial works carried out by the contractor
Technical Manual V6: TS-011a-6.00-010413
than 15 years.
Technical Manual V8: TS-11A-8.00-010117
7.11.1 Scope Cold deck roof systems (not recommended): Extensive green roof: a lightweight, low
This part of the Manual should be read in maintenance roof system, typically with succulents
conjunction with chapter 7.10 – Roof Coverings. • Waterproof membrane or other hardy plant species (often sedum)
Where appropriate, cross reference will be provided • Continuously supporting deck planted into a shallow substrate (typically less than
to the relevant section. • Ventilation externally 100 mm) that is low in nutrients. Irrigation is not
• Principal thermal insulation normally required.
This chapter provides specific advice and • Vapour control layer
requirements in respect of membrane roof systems Filter fleece/fines layer: geotextile of low resistance
over which a finish of living vegetation or materials 7.11.2 Definitions to water penetration, which prevents fines and
that will support vegetation is to be applied. For the purposes of this standard, the following sediments from being washed out of the green roof
The membrane roof systems may comprise one of definitions shall apply: into the drainage system.
the following, but the advice of chapter 7.10 – Roof
Coverings applies: Biodiverse roof: a roof that is designed to create a FLL: Forschungsgesellschaft
desired habitat that will attract a particular flora and Landschaftsentwicklung Landschaftbau (German
Warm deck, comprising: fauna, whether replicating the original footprint of Landscape Research, Development and
the building or enhancing the previous habitat. Construction Society).
• Waterproof membrane
• Principal thermal insulation Brown roof: a biodiverse roof where the growing Green roof: a roof or deck onto which vegetation
• Vapour control layer medium is purposely selected to allow local plant is intentionally grown or habitats for wildlife are
• Continuously supporting deck (Structural deck) species to inhabit the roof over time. established, including extensive, intensive and
semi-intensive roofs, roof gardens, biodiverse roofs,
Technical Manual V8: TS-11A-8.00-010117
Inverted warm deck roof systems: Drainage layer/reservoir board: available in brown roofs and public and private amenity
a variety of materials, including hard plastic, spaces.
• Ballast polystyrene, foam, coarse gravel and crushed
• Water control membrane recycled brick, depending on the Functional Green roof system: the component layers of a
• Principal thermal insulation Requirements. This allows excess water to drain green roof build-up.
• Waterproof membrane
© LABC Warranty
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Growing medium/substrate: an engineered Moisture/protection layer: geotextile blanket, Wildlife roof: a version of a biodiverse roof
soil replacement that contains a specified ratio available in varying thicknesses (typically between designed to provide a specific habitat to attract a
of organic and inorganic material, specifically 2mm–12mm), which performs a dual function. wildlife species.
designed to provide green roof plants with the air, Firstly, protecting the waterproof membrane during
water and nutrient levels they need to survive, whilst the installation of the green roof system, and
facilitating the release of excess water. secondly, increasing the water holding capacity of
the green roof system.
GRO: Green Roof Organisation, the industry forum for
green roof development and promotion in the UK. Root barrier: a waterproof membrane designed to
prevent roots from penetrating the waterproofing layer
Hydro seeding: spraying a specially designed and building fabric.This function may be incorporated
blend of seeds and growing medium. in a single membrane waterproofing product.
Inspection chamber: a chamber situated over an Sedum: genus of about 400 species of low-growing,
internal rain water outlet designed to constrain the leafy succulents that are wind, frost and drought
surrounding landscaping but allowing easy access tolerant and found throughout the northern
for maintenance. Allows water entry, but helps hemisphere. Not all species are suitable for roofs.
prevent unwanted silt, debris or vegetation from
entering and obstructing free drainage. Semi-intensive green roof: intermediate green
roof type with characteristics of both extensive
Intensive green roof: a version of a green roof and intensive green roofs. Typically with a 100mm–
Technical Manual V8: TS-11A-8.00-010117
often referred to as a roof garden that provides 200mm substrate depth, sometimes irrigated,
benefits akin to a small urban park or domestic occasionally managed and usually planted with
garden. Designed primarily for recreational a range of species.
use, intensive roofs are typically configured with
200mm+ of substrate, and often require regular SuDS: Sustainable (Urban) Drainage Systems
maintenance and irrigation.
© LABC Warranty
7.11.3 Design and system types The roof system may be of warm deck, inverted 7.11.4 Loading
A green roof essentially comprises an organic warm deck or cold deck configuration (see
vegetation layer and those components necessary chapter 7.10 – Continuous Membrane Roofing). 7.11.4.1 Statutory requirement
to support its growth, which is placed over a Generally, the warm deck configuration is Design for loading should comply with current
membrane roof system. For convenience, green recommended unless there are specific design Building Regulations.
roofs are divided into the following types: circumstances for which inverted and cold roofs
are better suited. A technical justification for any 7.11.4.2 Resistance to wind load
• Biodiverse roof departure from warm deck will be required. In all situations, including ballasted and inverted
• Brown roof roofs, a calculation of wind load to BS EN 1991-1-4
• Extensive green roof should be undertaken by a suitably competent
• Semi-intensive green roof person. Wind load acting on a green roof will be
• Intensive green roof affected significantly by the design of the perimeter
and by the geometry and finishes on the elevations
of the building. Any changes to these elements will
necessitate a review of the calculation output.
Figure 2: Intensive green roof - inverted warm roof (section)
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
• Standing water will inevitably result from design RWO • Brown, biodiverse and extensive green roof
without falls, due to tolerances and deflection. systems: no allowance for rain water
Separate gutter
RWO
Standing water, which may become stagnant, is to fall attenuation.
not conducive to plant growth and should not • Intensive green roof systems: attenuation as
be confused with the temporary retention of 1:80 Finished advised by the horticultural supplier. If no data
Fall
The UK’s National Annex to BS EN 12056 does components and waterproof membranes, and it is 7.11.7 Design for irrigation
permit the use of a coefficient to factor down the recommended that they be used wherever possible. Rainfall is the typical source of water. However,
drainage infrastructure to account for factors such complementary irrigation options may be required
as the additional retention performance of green Rain water goods from higher roof areas or for semi-intensive and intensive systems or those
roofs. However the coefficient that is used to reflect adjacent roof areas should not be designed to where, for example, the appearance of a grass
this reduction should be based on average annual discharge onto the green roof. The downpipe finish may be important.
retention and not on responses to dynamic storm should be connected directly to the downpipe
events. serving the green roof. Provision may include hoses, sprinklers, overhead
irrigation and automated systems that pump from
Any drainage infrastructure designed to Green roofs are compatible with siphonic roof some reservoir storage. The establishment of a
accommodate this reduced flow rate may not drainage systems. In the right circumstances, these need for an irrigation system, and the design of
accurately account for seasonal differences or can offer the advantages of: an irrigation scheme, should be in accordance
individual storm events. Any reductions in drainage with the principles of BS 7562-3. Where irrigation is
capacity should therefore need to be countered • Very high capacity, enabling fewer outlets and required, a frost-protected water supply, rain water
by alternative measures, e.g. appropriate detailing therefore less detailing work on site. or grey water storage facility should be provided at
to ensure that any attenuation of water at the • Smaller bore horizontal collector pipework, roof level.
roof level will not be detrimental to the building enabling reduced roof void depth.
structure or fabric. • Self-cleaning in many situations. 7.11.8 Thermal performance
Rain water outlets should be readily accessible However, siphonic drainage should be designed Statutory requirement
without disruption to the green roof or pedestrian specifically for the green roof system because it Design for thermal performance must comply with
Technical Manual V8: TS-11A-8.00-010117
finish. On finishes raised above the waterproof must operate siphonically with sufficient regularity current Building Regulations, as appropriate.
membrane (warm deck roofs) or Water control to avoid silting-up small-bore pipework.
membrane (inverted roofs), this may be achieved 7.11.9 External fire performance
by a suitably marked paving slab or demountable For further information, see
section of decking. Within the area of the green www.siphonic-roof-drainage.co.uk. 7.11.9.1 Statutory requirement
roof, a specific vegetation-free inspection chamber
© LABC Warranty
253
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.11.9.2 Design for resistance to external fire 7.11.10 Provision for access
The design of green roof systems can influence
the fire performance of the overall roof system. 7.11.10.1 Statutory requirement
The rate of growth and moisture content of natural The design should comply with current Building
vegetation is unpredictable and determined by Regulations.
irregular weather conditions. The substitution of
planted species with others is also unpredictable. 7.11.10.2 Temporary provision during
Design to minimise fire risk cannot be based on an construction
assumption of regular maintenance or of irrigation At the earliest possible stage, the anticipated
during drought. The latter is not relevant with loading of the roof system (prior to application of
sedum species, which die back, but is important for the green roof components) should be assessed in
intensive roof gardens or extensive systems planted terms of:
with grasses.
Figure 4: Green roofs: vegetation-free zones plan and zone width • Load, e.G. Foot traffic, equipment
(not to scale of building)
The design should not allow the vegetation to grow • Frequency
or propagate towards adjoining elements, such as • Risk of impact
abutments, eaves or pitched roofs. It should also be
kept away from openings, such as roof lights and If such usage is intense or long-lasting during the
smoke vents. construction phase, consideration should be given
to temporary works only, with completion occurring
This is achieved in two ways: after all non-roofing usage has ceased, as follows:
Technical Manual V8: TS-11A-8.00-010117
• A vegetation-free zone of minimum 0.5m width • Warm deck roof system: installation of
at all perimeters, abutments and openings. This temporary vapour control layer to be overlaid
zone should be extended to 1m to separate when remainder of system is installed.
large roof zones in excess of 40m in length. • Inverted warm deck roof system: overlay of
• Design of flexible walkways, hard paving and
© LABC Warranty
7.11.10.3 Permanent pedestrian access finishes • Downstands (of separate metal or other 7.11.14 Installation
Pedestrian finishes should be designed to suit the flashings) should lap the upstand by a
purpose and frequency of access in the context minimum of 75mm. 7.11.14.1 Protection of the roof
of the intended planned maintenance regime. • Reliance on sealant as the sole means of
For example, paving on paving supports may be protection should be avoided. Temporary protection (during construction)
desirable to allow drainage and to level up the • Consideration of the effect of vegetation growth Responsibility for temporary protection and a
finish, but may be unsuitable if plants could spread on the integrity of the weather proofing. method statement for its use should be agreed
beneath the paving. Generally, for amenity access, a prior to commencement of works. Suitable
finish of porous or hard concrete paving laid directly The total roof zone depth should be measured from materials should be selected in consultation with
on a suitable protection fleece may be most suitable. the surface of the growing medium and assessed membrane manufacturers as appropriate, for
at critical points, such as the top of drainage example:
For service and maintenance access only, a flexible slopes, to ensure that there is enough free upstand
walkway tile may be sufficient (depending on the available to create the minimum required 150mm • Linked recycled thermoplastic sheets
waterproof membrane and roof system type). of waterproofing protection above finished roof • Rolled recycled thermoplastic or elastomeric
level. It is important that this minimum 150mm sheets
7.11.11 Detailing upstand is maintained at all points around the
area of the green roof, except at continuous water Particular consideration should be given to
General principles checks and at verges. locations of concentrated access, such as step-out
At an early stage in the design process, an audit areas onto the roof or where wheeled equipment
of roof geometry should be carried out to establish 7.11.12 Design for sustainability may be used.
what types of details will be required and whether As per chapter 7.10 – Continuous Membrane
Technical Manual V8: TS-11A-8.00-010117
they are to be weather proof (incorporating Roofing. Permanent protection (during service)
an upstand/cover flashing arrangement) or See 7.11.14.1 (above).
waterproof (providing continuous waterproofing 7.11.13 Materials
across the detail). As per chapter 7.10 – Continuous Membrane 7.11.14.2 Vapour control layer (VCL)
Roofing. As per chapter 7.10 – Continuous Membrane
The following key principles should be followed in
© LABC Warranty
Roofing.
design of all details: Note: If the waterproof membrane is also intended
to provide root resistance, suitable certification of 7.11.14.3 Thermal insulation
• Upstands to extend 150mm above the finished testing in accordance with BS EN 13948 should be As per chapter 7.10 – Continuous Membrane
roof level, i.e. top of growing medium. available. Roofing. 255
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.11.14.4 Waterproof membrane 7.11.15.2 Procurement of testing services High voltage electrical discharge
As per chapter 7.10 – Continuous Membrane The waterproof membrane should be tested The high voltage electrical discharge method is
Roofing. for integrity before the application of any best suited to the testing of continuous thin films,
other components above it. Testing should be such as liquid-applied coatings. Its use is not
Note: Warm roof systems – restraint against wind undertaken by a third-party that is independent of recommended with polymeric single ply, reinforced
load. It is unusual for the installation of ballast and the roofing contract. The testing service provider bitumen membranes and mastic asphalt.
green roof components to follow immediately after should provide evidence of the following:
installation of the roof system. This may be because • Efficacy of the method proposed in the Vacuum
the roof system and green roof overlay are to be circumstances of the project. Vacuum testing of seams of membranes
installed by different contractors, or because of • Experience and training of operator. manufactured off-site is an effective means of
site factors, such as limited storage. Unless it is • Membership of an appropriate trade quality assessment, but is not recommended as a
sequenced to do so, the roof system should be association that sets a Code of Conduct for method of demonstrating the integrity of flat roofs.
installed with restraint against wind load based the service.
on an assumption of an exposed waterproof Flood testing
membrane. 7.11.15.3 Methods of test Flood testing is a suitable method of demonstrating
the integrity of small areas of roof to which a green
7.11.15 Testing Low voltage earth leakage roof system is to be applied. However, consideration
Low voltage earth leakage is a safe and effective should be given to the effect of ingress on
7.11.15.1 Final inspection method for the testing of waterproofing integrity programme and the risk of entrapped water in
A thorough, recorded, visual inspection of all in roofs where the waterproof membrane is an insulation (warm deck roofs) and decks (all types).
areas, including details, should be carried out, with electrical insulator and the deck provides an The area under any one test should not exceed
Technical Manual V8: TS-11A-8.00-010117
representation from the General Contractor and electrical earth. It is not suitable for testing flat 50m2.
Roofing Contractor in attendance. roofs where the waterproof membrane has been
overlaid with insulation and ballast (inverted roofs)
or ballast only (ballasted warm roofs); therefore,
testing should be carried out prior to completion of
© LABC Warranty
257
CHAPTER 7
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Roof coverings must prevent any external moisture passing into the
a workmanlike manner. internal environment of the dwelling.
iii. Certification is required for any work completed by an approved iii. Structural elements outside the parameters of regional Approved
installer. Documents must be supported by structural calculations provided by
a suitably qualified expert.
Materials iv. The materials, design and construction must meet the relevant
i. All materials should be stored correctly in a manner that will not cause regional Building Regulations.
damage or deterioration of the product.
ii. All materials, products and building systems shall be appropriate and Limitations of Functional Requirements
suitable for their intended purpose. i. The Functional Requirements are limited by the recommendations
iii. Whilst there is and can be no Policy responsibility and / or liability for a applied to the specific areas covered in this chapter.
roof covering performance life of 60 years or less, roof coverings shall ii. These Functional Requirements do not and will not apply to create
be designed and constructed so they have an intended life of not less any policy liability for any remedial works carried out by the contractor
Technical Manual V6: TS-011a-6.00-010413
than 15 years.
Technical Manual V8: TS-11A-8.00-010117
7.12.1 Introduction Top weathering sheets are generally secret fixed Check that end and side lap tape sizes conform to
Metal roofing is usually built to a decent standard, onto clips or standing seam sheets onto halters, the manufacturer’s requirements.
but occasionally there are problems, especially these being machine seamed once fixed. Pierce
where site workmanship has not been up to fixed sheets are still widely used, which are fixed For pierce fixed trapezoidal sheets, check for tell
standard. Any roof cladding details proposed directly to the spacer system with external visible tales to end laps and side laps for the correct
outside of the following guidance will require a fixings. number of rows of tape.
specialist consultants design using third party
accredited solutions where appropriate Liner sheets can be solid or perforated to give Liner sheets
an acoustic, sound-deadening roof. They are Where the liner sheet is solid and used as a vapour
fixed directly to purlins, and can act as a VCL if a check, note the following:
separate vapour barrier is not specified. If the liner
is not used as a VCL, a reinforced vapour control • Frequency of main fixings to purlins and
sheet should be incorporated within the roof. frequency of side lap stitchers.
• End laps to be sealed with mastic tape; check
Insulation must be installed between the VCL the size and that this is continuous. Side laps
and the top weathering sheet; some systems have a wider 50mm Polyband tape placed from
may require ventilation above the insulation and the inside so this is visible from above.
others may not; it varies from manufacturer to • Check for cuts or splits in this metal liner.
Figure 1: Typical metal double skin insulated roof manufacturer. Where there is no requirement to • Ensure that to eaves and ridge the correct
ventilate, the insulation should be compressed filler blocks have been used, bedded in mastic;
slightly to ensure that there are no air voids where if necessary, a closure flashing must be used
7.12.2 Double skin insulated roofs condensation may occur. from the crown of the sheet to the wall junction
Technical Manual V8: TS-11A-8.00-010117
system, insulation, breather membrane and in accordance with the manufacturer’s instructions.
finished externally with top weathering sheets.
These must be long enough to discharge into the
gutter correctly and allow for an eaves angle if
required by the system. 259
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Separate vapour control layer (VCL) Ensure that no packaging or debris is left in the Roof penetrations
This should be a reinforced sheet, and is used roof void prior to or during the installation of the These must be sealed to maintain the VCL.
to ensure a more positive air seal around the insulation. The insulation should fill the void or be Where the liner is used as a VCL, the metal-to-
perimeter of the building. The vapour check compressed into the void; there should be no metal junction must be sealed with fire-retardant
should be sealed in the field area with the correct slumping or gaps and it should be packed into foam. With a separate VCL, this must be sealed
tape, with the number of rows dependant on the voids at the junctions of the ridge and verge. to the upstand or pipes with the appropriate
application. Check the integrity of these tapes tape. Externally with aluminium roof sheets, the
and that they are continuous and correctly With standing seam roofs, a rigid mineral slab junctions with penetrations should be site welded
joined. Where the vapour check abuts the walls insulation should be placed at eaves, ridge and or weathered using glass reinforced plastic (GRP)
to the verge or eaves, it must be properly sealed around all penetrations and walkways to support in-situ weathering.
in accordance with the Designer’s detail. Around the vulnerable areas of the roof, which will give a
penetrations, the vapour check must be cut and solid support to the roof sheet pans. This is easy Roof lights
sealed to any pipes or upstands. to see during construction and easily felt on Standing seam roof sheets are usually on separate
completion. The supported pan of the sheet feels insulated upstands. With pierce fixed trapezoidal
The spacer system is fixed through the vapour solid to walk on. roof sheets, roof lights are in line, either factory or
check and liner into the purlins. The spacer system site assembled. Ensure that the correct size of tape
will have a soft sealing pad to ensure the vapour Support system is used, check the number of rows of tape that are
check is maintained around the fixing. Check the frequency of brackets against the required and that side lap tapes are not twisted by
specification and the number of fixings per bracket, fasteners.
Check for punctures of the vapour check by foot and that they are the correct type of fixing.
traffic or damage, and patch as required. General
Technical Manual V8: TS-11A-8.00-010117
With standing seam roofs, the halter may be fixed Check surface finishes for abrasions, dents and
Insulation with a stainless steel fixing; check the type and cuts, and that the roof has not been used as a
Check the packaging to ensure that the correct frequency of fixing. Check the orientation of the cutting surface for flashings or other metal. Hot
thickness is being used if one layer is used, or a halter in relation to the lay of the sheet, i.e. will they swarf from angle grinders burns into the plastisol
combination of thicknesses to give the correct pick up the seam, as there is a right and wrong coating of steel sheets, marks aluminium and
specified thickness. For two thicknesses or more,
© LABC Warranty
way round for halters. rapidly turns to rust. Flashings should have sufficient
check that all joints are staggered and check the overlap or butt straps, 150mm wide, and be sealed
Lambda value against the specification. Manufacturers provide halter templates to set out and supported. Check the frequency of fixings and
halters, and there must be one on-site to obtain the that they are of the correct type.
correct gauging of the halters.
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
7.12.3 Composite panel metal roofing Check that the right number of fixings has been panels needs to be filled with foam to maintain the
used for the panel and the frequency of side lap insulation and prevent condensation forming. There
7.12.3.1 What is a composite panel roof? stitchers; ensure that they are side lap stitchers and also needs to be a suitably sealed inner ridge.
A simple sheet roof system with ensured insulation not main fixings.
thickness that is delivered with the top weathering Verge details are difficult and it may be necessary
sheet, insulation and white liner all in one sheet. Sealant tapes for an internal verge to be cut and sealed around
With the increase in insulation, thickness panels Check the number of rows required by the purlins. Check sealant tapes and the use of gun
are being made shorter in length so they can be manufacturer of the panel for end laps. Tell tales foam to maintain insulation. The manufacturer’s
handled into position. This means that there are should be visible at side laps of each sheet. Tell details may not be achievable, but an alternative
more end laps to be checked. tales are the ends of the mastic tape run that can must be devised to maintain air tightness. A degree
be seen or must be felt for at the side of each of confidence in this requirement should be shown
The standard manufacturer’s details are to be sheet. The same applies to side laps; there should on-site as an indication of the importance of air
adhered to, but the following need to be checked. be a tell tale at the end of the sheet. Use the end of tightness and how this can be achieved.
a hacksaw blade to locate the rows of mastic tape.
7.12.3.2 Workmanship and installation On roof lights, mastic tape is visible; check Gutter junctions
its location, that its size complies with the If parapet or valley gutters are being used, check
Fixings manufacturer’s requirements and that there are the the air seal at the junction of the two. Gutter joints
There may be a requirement for stainless steel correct number of rows. Tape should not be twisted are not always level, and any gaps have to be
fixings to be used. Check by inspecting boxes and by the fixings. filled. This will not only prevent wind-driven rain from
use a magnet; drill points will be magnetic only. entering the building, but will also maintain an air
Air tightness seal.
Technical Manual V8: TS-11A-8.00-010117
Check fixings are suitable for the purlin type – steel, There must be a supply of gun foam, fire rated,
light gauge cold rolled, heavy gauge or timber – at roof level for filling in voids before flashings Check that roof sheets are oversailing into the
as all fixings are different. are fixed. If there is not one on site, air tightness gutter correctly.
and maintaining the insulation cannot be fully
Check the bearing area of the purlin; if the building achieved.
is not square, the sheets will run out and the
© LABC Warranty
end lap detail will not be supported. This can be The use of foam needs to be inspected during
overcome by using a galvanised support that is the course of construction, and internal tapes to
fixed to the purlin and which supports the end lap. eaves and ridge purlins need to be inspected for
size and position. At the ridge, the gap between 261
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Roof penetrations
Penetrations such as flues, vents, upstand-type roof
lights and sun tubes need to be sealed internally,
the insulation being maintained with site-applied
foam. Externally, upstands must be weathered
correctly and, with steel composite sheets, this is
best achieved using GRP in-situ weathering.
General
Check surface finish for cuts and abrasions.
© LABC Warranty
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Rectification
Component / Inspection needed Comments
Yes No
Check bearing width of purlin
Check minimum overlap of linear decking sheets:
1. Light gauge steel;
2. Hot rolled steel;
3. Timber - check for minimum penetration.
Check that side laps are stitched at the correct centres
Vapour control checks using the liner:
1. Check tape to side laps, minimum width 50mm air and moisture barrier tape;
2. Check tape to end laps;
3. Check inner fillers to ridge, eaves and verge;
4. Check for sealing around the perimeter with fire resisting foam.
Vapour control checks using a separate Vapour Control Layer:
1. Check the minimum overlap is correct;
2. Check for the correct sealant tape;
3. Check for the correct number of rows of sealant tape;
4. Check junctions between Vapour Control Layer and building elements, e.g., upstands, eaves, verge, etc.;
5. Check for puncture and repair where necessary.
Spacer systems: Use a magnet
1. Check for correct height of bracket or halter;
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Rectification
Component / Inspection needed Comments
Yes No
Roof sheets - standing seam and secret fixed:
1. Check that sheets are long enough so that water effectively drains into the gutter;
2. Check the direction of lay of sheets in relation to the direction of prevailing wind;
3. Check eaves detail, in accordance with manufacturer’s details including eaves drips and fixing;
4. Check ridge detail including turn up fillers and ridge dams, in accordance with manufacturers details;
5. Check verge detail and adequacy of support for cut sheets;
6. Check flashing supports, sheet / verge flashing seals and frequency of fixings.
Roof sheets - pierced fixed:
1. Check overlap dimension;
2. Check end lap tape and correct number of rows of tape;
3. Check for side lap tape;
4. Check quantity of fixings per sheet per purlin;
5. Check washer size of main fixings and side lap stitchers;
6. Check frequency of side lap stitchers;
7. Inspect for correct tightening of main fixings and side lap stitchers.
Penetrations for vents, sun pipes, etc.
A - Aluminium sheets:
1. Check sheets are site welded and area post coated where colour sheets are used;
2. Check that Vapour Control Layer and breather membrane is maintained around the welded area;
3. Check upstands to be at least 150mm.
B - Steel sheets: Ideally use GRP in-situ weathering flashings; however, if folded flashings are used, check:
1. Overlap;
2. Sealing and fixing of overlaps;
3. If a flat sheet back to the ridge is used, check for insulation under the sheet;
4. Check frequency of fixings;
Technical Manual V8: TS-11A-8.00-010117
Rectification
Component / Inspection needed Comments
Yes No
Panel laps to be tight when viewed from inside the building
Constant straight line on side laps to be achieved
Fasteners correct for the purlin:
1. Light gauge steel;
2. Heavy gauge steel;
3. Timber.
Fastener material: Check with a magnet
1. Coated carbon steel;
2. Stainless steel.
Fastener frequency main roof:
1. Main fixings;
2. Side lap stichers.
Fastener frequency roof lights:
1. Main fixings;
2. Side lap stichers.
Bearing area of purlin at end lap is a supporting bearing plate required Is the building square?
End laps:
1. Correct number of rows of joining tape;
2. Correct size of end lap tape;
3. Correct position of end lap tape in relation to fixing.
Technical Manual V8: TS-11A-8.00-010117
2. Verges;
3. Gutters;
4. Internal verge positions;
5. Foam insulation at ridge.
265
CHAPTER 7
CHAPTER 7: SUPERSTRUCTURE
CHAPTER 7: SUPERSTRUCTURE
Rectification
Component / Inspection needed Comments
Yes No
Gutter junctions:
1. Adequacy of seals at gutter junctions;
2. Correct provision of weir overflows to gutter runs;
3. Correct junction detail between gutters and verge flashings;
4. Gaps sealed to prevent vermin infestation;
5. Correct discharge of water from roof sheets into gutter.
Roof penetrations:
1. Check seals around cut foam insulation internally;
2. Check internal flashing closures;
3. Check weather penetrations externally.
Flashings:
1. Check end overlaps;
2. Check frequency of fixings.
General:
1. Check roof covering for cuts and abrasions;
2. Check for hot swarf damage.
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
CONTENTS
8.1 INTERNAL WALLS
8.2 UPPER FLOORS
8.3 STAIRS
8.4 FIRE STOPPING AND FIRE PROTECTION TO FLATS AND APARTMENTS
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
267
CHAPTER 8
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
a suitably qualified expert.
Materials iii. Party walls between dwellings must achieve satisfactory levels of
i. All materials should be stored correctly in a manner that will not cause sound insulation to meet the relevant requirements of the Building
damage or deterioration of the product. Regulations.
ii. All materials, products and building systems shall be appropriate and iv. The materials, design and construction must meet the relevant
suitable for their intended purpose. regional Building Regulations
iii. The structure shall, unless specifically agreed otherwise with the
Warranty provider, have a life of not less than 60 years. Individual Limitations of Functional Requirements
components and assemblies, not integral to the structure, may have i. The Functional Requirements are limited by the recommendations
a lesser durability, but not in any circumstances less than 15 years. applied to the specific areas covered in this chapter.
ii. These Functional Requirements do not and will not apply to create
Technical Manual V6: TS-011a-6.00-010413
Technical Manual V8: TS-11A-8.00-010117
any policy liability for any remedial works carried out by the contractor
or otherwise, nor to any materials used in those remedial works.
© LABC Warranty
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
Lowest storey of a
To provide structural stability, the two leaves of a
Blocks - 7.5N/mm2
three Storey wall, masonry cavity separating wall should normally be
or where individual
Bricks - 13N/mm2 tied together. Sound transmission across the cavity
storeys exceed 2.7m
should be limited by the type of tie and spacing.
Blocks - 2.8N/mm2 Figure 1: Bonded walls
Upper storeys of three Ties should be specified in accordance with the
© LABC Warranty
CHAPTER 8
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
To limit sound transmission, metal tie straps should be: 8.1.2.2 Lintels and studs Lintels should extend beyond each end of
A lintel and cripple studs are to be provided to any openings in masonry as follows:
• No more than 3mm thick opening other than where the stud spacing is not
• Fixed below ceiling level affected. Traditionally, multiple studs will be used to Span (m) Minimum length of bearing (mm)
• Spaced at least 1.2m apart horizontally support multiple joists. Up to 1.2 100
Over 1.2 150
Thicker ties, fixed at ceiling level or more closely Where internal walls are made up of panels,
Table 2: Minimum bearing lengths of lintels
spaced, will increase sound transmission through structural continuity is to be maintained, for example
the cavity. through the use of a continuous top binder. Where structurally necessary, provide padstones
under the bearings of lintels and beams.
8.1.2 Load-bearing timber walls and partitions Framing joints need to be secured with a minimum Non-load-bearing partitions shall have acceptable
Load-bearing timber internal walls are to be of two nails per joint. strength and be adequately supported.
designed to provide support and transfer loads to
foundations safely and without undue movement. 8.1.3 Beams and lintels 8.1.3.2 Partition construction
Beams and lintels shall be satisfactory for their The following partition constructions are
The structural design of load-bearing timber walls purpose. satisfactory:
should be in accordance with BS 5268.
Items to be taken into account include: • Partitions of brick or block construction.
Structural timber should be specified according to • Timber stud partitions using studs, sills and head
the strength classes, e.g. C16 or C24. • Loads and spans are in accordance with plates nominally 63mm x 38mm. Studs should
the manufacturer’s recommendations. be spaced to suit the thickness of plasterboard
Technical Manual V8: TS-11A-8.00-010117
8.1.4 Non-load-bearing timber partitions • Timbers supporting plasterboard should be maximum partition height of 3m. However, in order
Partitions should be robust and form a smooth, regularised and have a moisture content not to accommodate tolerances for plasterboard fixing,
stable, plane surface to receive decoration: greater than 20% at the time of erection (lower a minimum width of 44mm is recommended.
moisture contents can reduce incidents of nail Head and sole plates should consist of single
• Supporting members should be accurately popping and other effects of shrinkage). length members fixed to the building structure at
spaced, aligned and levelled. no less than 600mm centres.
• The tolerance of horizontal straightness of a Stud partitions should be no less than 38mm wide
partition should be +/-10mm over a 5m length. and no less than 63mm thick (up to a maximum Partitions should be located on double joists when
• The deviation in vertical alignment of a partition partition height of 2.4m), and 89mm thick up to a parallel to floor joist span and nailed to 50mm
in any storey height should be +/-10mm. x 50mm noggins fixed between ceiling joists at
600mm centres when parallel to ceiling joist span.
For short lengths of partitions (1.2m maximum),
blocking between joists at 600mm centres may be
used. Intersecting head and sole plates should be
skew nailed together.
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
Figure 3: Timber stud partition Figure 4: Typical timber stud plan 271
CHAPTER 8
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
Timber members should be fixed together with a 8.1.5 Method of supporting partitions Allowance for the probable deflection of floors at
minimum of 2No. 75mm long x 2.65mm diameter nails. Walls and partitions are to be supported by the the head of partitions is required to prevent the
Proprietary partitions of plasterboard, strawboard or structural floor only if the material is specifically partition becoming load-bearing.
other material must be detailed and constructed manufactured for that purpose; it is not to be
in accordance with the manufacturer’s supported by a floating floor that incorporates a 8.1.6 Proprietary systems
recommendations. compressible layer. Proprietary systems are to be specified
in accordance with the manufacturer’s
Where partitions are to support heavy items such Masonry partitions should be supported on: recommendations.
as radiators or kitchen cupboards, additional
noggins should be provided within the stud • Other masonry partitions or walls (wherever 8.1.6.1 Metal stud system
partition to accommodate fixings. conceivable, the design of dwellings should be There are a number of proprietary systems on the
such that the first floor masonry partitions are market.
an extension of those on the ground floor).
• Concrete floors. This traditionally consists of U-shaped channels that
• Steel or concrete beams. act as ceiling (head), base plates (tracks) and the
vertical studs. The advantage of this system is that it
It may be necessary to use padstones at bearings is lightweight, versatile and quick to erect.
where steel or concrete beams are to be used.
Installation should always be carried out in
Masonry partitions should not be supported by accordance with the manufacturer’s instructions.
timber joists or beams. Allowance should be given Plasterboard coverings are screw-fixed to the metal
Technical Manual V8: TS-11A-8.00-010117
in the design for the relatively flexible nature of the studs, with the perimeter studs/tracks generally
timber and the rigid nature of masonry. being mechanically fixed to the surrounding walls,
ceilings and floors.
Extra noggins or joists should be specified where
stud partitions or proprietary plasterboard It may be necessary to provide earth-bonding to
partitions are supported by a timber floor, unless it
© LABC Warranty
Plasterboard
laminated 12.5mm laminated on both sides of 19mm board Refer to manufacturer’s recommendations
wall
CHAPTER 8
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Party floors between dwellings must achieve satisfactory levels of
a workmanlike manner. sound insulation to meet the relevant requirements of the Building
Regulations.
Materials iii. Structural elements outside the parameters of regional Approved
i. All materials should be stored correctly in a manner that will not cause Documents must be supported by structural calculations provided by
damage or deterioration of the product. a suitably qualified expert.
ii. All materials, products and building systems shall be appropriate and iv. The materials, design and construction must meet the relevant
suitable for their intended purpose. regional Building Regulations
Technical Manual V6: TS-011a-6.00-010413
iii. The structure shall, unless specifically agreed otherwise with the
Warranty provider, have a life of not less than 60 years. Individual Limitations of Functional Requirements
components and assemblies, not integral to the structure, may have i. The Functional Requirements are limited by the recommendations
a lesser durability, but not in any circumstances less than 15 years. applied to the specific areas covered in this chapter.
ii. These Functional Requirements do not and will not apply to create
Technical Manual V8: TS-11A-8.00-010117
any policy liability for any remedial works carried out by the contractor
or otherwise, nor to any materials used in those remedial works.
© LABC Warranty
275
CHAPTER 8
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
8.2.1 Floor boarding or decking Particle boards should be either screwed or nailed • BS 8103-3, Structure design of low rise buildings,
Suitable floor boards and decking include: to the joists at 250mm centres. Nails should be Code of Practice for timber floors and roofs for
Tongue and grooved softwood flooring with a annular ring shanks that are at least three times dwellings.
minimum moisture content at the time of fixing the depth of the board. • BS EN 1995-1: 2004+A1, Eurocode 5 design of
of between 16%–20% and in accordance with BS timber structures. General. Common rules and
1297. All boards must be double nailed or secret A 10mm expansion gap should be provided around rules for buildings.
nailed to each joist using nails that are at least the perimeter of the floor against a wall abutment.
three times the depth of the board. Boards must To prevent the distortion of finishes, joists should be
have a minimum thickness, as indicated in Table 4. Thickness Thickness
Maximum Typical nail
stopped from twisting over supports and provision
(mm) (mm)
span (mm) fixing (mm) provided to accommodate up to 10mm of drying
(chipboard) (OSB)
Finished board
Maximum
Typical nail 60mm shrinkage in floor joists supported by steel beams.
centres of joists 18 and 19 15 450 annular ring
thickness (mm) fixing (mm)
(mm) shank
45mm lost It is essential that joists are not overloaded during
15 Max 450 65mm
head nail
22 18 and 19 600 annular ring construction. Joints in joists, rafters and purlins
60mm lost shank should only be in place over a load-bearing
18 Max 600
head nail
support, or the joint be designed by a qualified
Table 5: Particle floor boarding: minimum thickness and centres of
Table 4: Softwood floor boarding: minimum thickness and centres support Structural Engineer.
of support
8.2.2 Floor joists Joists should be restrained at supports using tightly
8.2.1.1 Particle boarding
For advice on ‘sizing of certain timber members in fitted strutting.
Acceptable particle boards consist of oriented
floors and roofs for dwellings’, the Designer should
strand board (OSB) or chipboard. Chipboard
refer to the following sources:
Technical Manual V8: TS-11A-8.00-010117
Suitably sized trimmer joists shall be provided 8.2.2.2 Strutting or bridging of solid timber 8.2.3 I-joists
around floor openings. floor joists I-joists and metal web trimmed joists should be
Where the span of a floor joist or flat roof joist is supported using joist hangers. If an I-joist is used as
Trimmed openings may be needed around more than 2.5m, strutting is necessary. This should a trimmer to support another I-joist, backer blocks
staircase openings and chimneys. Solid trimmed be provided either by timber bridging or strutting in should be provided on both sides of the web of the
joists may be supported using either joist hangers accordance with Figure 3 of BS 8103-3: 2009 or by trimmer.
or a structurally designed connection; timber a proprietary system.
trimmers around openings should consist of Engineered timber I-joists include a timber flange
at least two members and be designed by a Timber strutting can be in the form of solid bridging (usually solid timber or laminated veneer lumber
Structural Engineer. of at least 38mm basic thickness and with a depth (LVL) and a panel product web (usually OSB). They
equal to at least three-quarters of the depth of are manufactured in an assortment of depths and
the joists; or it can consist of herringbone strutting flange widths under controlled factory conditions
with members of at least 38mm by 38mm basic to low and uniform moisture contents.
size. Herringbone strutting should not be used
where the distance between the joists is more than Strutting or bridging of I-joists should be in
approximately three times the depth of the joists. accordance with the manufacturers requirements.
CHAPTER 8
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
8.2.3.3 Bracing 8.2.3.5 Precast concrete floor units 8.2.3.6 Precast beam and block floors
Large areas of floor joists can be assembled Precast concrete units and infill blocks are to be Ensure that precast concrete beam and block
with these products due to their light weight and carefully stored and handled on-site, preventing floors are fully supported by load-bearing walls.
availability in long lengths. It is of great importance damage occurring before, during and after Similar beams of the same size may have differing
that adequate safety bracing is provided to incorporation into the structure. Units should be strength properties because of their varying
ensure that the joists remain stable through the lifted as near as possible to their ends. reinforcement size, so it is important to check
construction phase. Joist manufacturers provide beam reference numbers and their layout. It is also
simple guide recommendations that allow an The bearing surface of walls, beams and other essential sometimes to provide two or more beams
installer to facilitate this process with ease and supports to receive precast units are to be smooth adjacent to each other where spans are excessive
speed. and level. or in heavily loaded areas. Suitable infill bricks or
blocks are to be properly bedded on mortar and
Unbraced joist layouts are not to be walked on by Infill blocks and slabs should fully bear onto provided between pre cast (PC) beams where
workers. supporting beams and walls. bearing onto supporting walls.
Figure 10: Lateral restraint to walls at floors and roofs (beam and block)
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
Beams and blocks are to be grouted together with 8.2.4 Fire resistance
a 1:6 cement to sand mix in accordance with the All floors should have the fire resistance required by
manufacturer’s instructions. the relevant Building Regulations.
Load-bearing walls are to continue through the To achieve the same fire resistance, I-joists
beam and block floor. and metal web joists may require a different
specification for the ceiling than that for solid
Holes for service pipes are properly filled by laying timber joists. Holes should not be made in the
non-timber formwork between PC joists and filling ceilings, e.g. for down lighters, unless it can be
with good quality concrete (ST2 mix) prior to proven that the floor construction achieves the
screeding. required fire resistance.
279
CHAPTER 8
FUNCTIONAL REQUIREMENTS
8.3 STAIRS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Stairs and landings must have appropriate guarding to meet the
a workmanlike manner. relevant Building Regulations
iii. Structural elements outside the parameters of regional Approved
Materials Documents must be supported by structural calculations provided by
i. All materials should be stored correctly in a manner that will not cause a suitably qualified expert.
damage or deterioration of the product. iv. The material, design and construction must meet the relevant
ii. All materials, products and building systems shall be appropriate and regional Building Regulations.
suitable for their intended purpose.
iii. The structure shall, unless specifically agreed otherwise with the Limitations of Functional Requirements
Warranty provider, have a life of not less than 60 years. Individual i. The Functional Requirements are limited by the recommendations
components and assemblies, not integral to the structure, may have a applied to the specific areas covered in this chapter.
lesser durability, but not in any circumstances less than 15 years. ii. These Functional Requirements do not and will not apply to create
any policy liability for any remedial works carried out by the contractor
Technical Manual V6: TS-011a-6.00-010413
CHAPTER 8
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
iii. Fire stopping is to be completed by a third-party approved contractor. a suitably qualified expert.
iii. The materials, design and construction must meet the relevant
Materials regional Building Regulations.
i. All materials should be stored correctly in a manner that will not cause
damage or deterioration of the product. Layouts indicating the positions of compartment walls/floors and other
ii. All materials, products and building systems shall be appropriate and lines of fire resistance must be available to the Builder and Warranty
Technical Manual V6: TS-011a-6.00-010413
ii. chapter 8.4 applies to any building that contains flats or apartments
party certification confirming suitability in its application. with a floor, four or more storeys above the ground.
iii. These Functional Requirements do not and will not apply to create
any policy liability for any remedial works carried out by the contractor
or otherwise, nor to any materials used in those remedial works.
© LABC Warranty
283
CHAPTER 8
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
CHAPTER 8: SUPERSTRUCTURE (INTERNAL)
and concealed spaces will also meet the The fire stopping material or cavity barriers competent to install such products.
requirements of this Technical Manual. should be installed by a person who is deemed
competent to install such products. A competent Where intumescent paints are used to provide
This section applies to buildings with four or more person is deemed to be a third-party approved the required level of fire protection, certification
storeys that contain flats or apartments; however, it contractor specialising in fire stopping and passive confirming that the paint applied will achieve the
is recommended that the guidance is followed for
© LABC Warranty
CONTENTS
9.1 DRAINAGE (BELOW GROUND)
9.2 DRAINAGE (ABOVE GROUND)
9.3 ELECTRICAL INSTALLATIONS
9.4 HEATING AND MECHANICAL SERVICES
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
285
CHAPTER 9
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. The materials, design and construction must meet the relevant
a workmanlike manner. regional Building Regulations
Impervious surfaces can drain to a permeable recommendations of the relevant Building Control Drain materials should comply with either:
area within the garden providing it is free draining. body and the Pipe Manufacturer. Requirements are
as follows: • BS 1194 – Concrete porous pipes
The drainage system, including manholes, gullies, • BS 65 or BS 1196 – Clayware pipes
pipe connections, etc., should be protected from • Pipes should be laid to an even gradient, • BS 4962 – Plastic pipes
damage throughout the course of the construction
© LABC Warranty
CHAPTER 9
CHAPTER 9: BUILDING SERVICES
CHAPTER 9: BUILDING SERVICES
trenches are located near to foundations, Walls should accommodate movement where
9.1.7 Foul water drainage system
foundation depths should be increased or the drains pass through substructure by:
Foul water drainage systems only take foul waste
drain re-routed further from the foundations. from a property or properties. Foul waste is the
• 50mm clearance all round. waste water from sinks, toilets, showers, baths,
The trench should be filled with concrete to an • A sleeve with a 50mm clearance. dishwashers and washing machines. These systems
appropriate level where the bottom of a trench is • (If built in) a connection on both sides of the
© LABC Warranty
9.1.8 Surface water In areas where snow lies on roofs, the front edge of Max
Gutter RWP outlet Flow
Surface water drainage is allowable through the the gutter should not be higher than the projected effective
size (mm size (mm capacity
roof area
use of one of the following systems: line of the roof, unless snow guards or other diameter) diameter) (litres / sec)
(m²)
precautions are used. 6 - - -
• An adequate soakaway, or some other adequate
18 75 50 0.38
infiltration system; or where this is not realistic. Discharge of gutters into downpipes can be 37 100 63 0.78
• A watercourse; or where this is not realistic. substantially improved by the careful location of 53 115 63 1.11
• A sewer (this helps minimise surface water downpipes: 65 125 75 1.37
arriving into the foul water drainage system, 103 150 89 2.16
which can often overload the capacity of the • Locating downpipes at end quarter positions
sewer and cause flooding). will double the flow capacity if more than one Table 2: Gutter sizes and outlet sizes
downpipe is required.
9.1.10 Layout of land drains
9.1.9 Provision of gutters and downpipes • The downpipe should be located within 200mm
Drain runs on sloping sites need to be positioned
If the roof area is greater than 6m2, it needs to be of the change in direction in order to maintain
perpendicular to the fall of the site.
provided with rain water gutters and rainwater the flow capacity of the gutter where changes
downpipes (RWP) that meet the minimum size in the line of the gutter occur.
Land drains should be positioned adjacent to
requirements shown in Table 2. Thought should also
paths, drives and outbuildings. The pipe soffit
be provided to the provision of rain water drainage Type of surface area Effective design area
should be positioned at least 400mm below the
to roof areas less than 6m2, such as dormer roofs. Paved areas plan area
finished ground level, and the backfill consolidated
Flat roof plan area of roof
to the same degree of compaction as the
Gutters should be laid to a nominal gradient 30° roof pitch plan area x 1.29
adjacent soil.
Technical Manual V8: TS-11A-8.00-010117
of between 1 mm/m and 3 mm/m where 45° roof pitch plan area x 1.5
practicable. The gradient of an eaves gutter 60° roof pitch plan area x 1.87
shall not be so steep that the gutter drops below 70° roof pitch plan area x 0.5
the level of the roof to such an extent that water
Table 1: Calculation of roof area
discharging from the roof will pass over the front
edge of the gutter.
© LABC Warranty
289
CHAPTER 9
CHAPTER 9: BUILDING SERVICES
CHAPTER 9: BUILDING SERVICES
9.1.11 Soakaways • Situated so that it will not saturate the For sites where chalk is prevalent, the CIRIA C574
Soakaways are a simple way of dispersing foundations of any structure. Engineering in Chalk 2002 publication gives the
surface and storm water in circumstances where • Situated so that the base of any soakaway/ following recommendations:
connection to the storm water sewer system is not infiltration system is permanently above the
feasible or unnecessary. A soakaway is basically a water table. Concentrated ingress of water into the chalk can
system that loses water rather than collects water. • Situated far enough away from other initiate new dissolution features, particularly in
Soakaways are part of the Sustainable Urban soakaways/infiltration systems to ensure that the low-density chalk, and destabilise the loose backfill
Drainage Systems (SuDS) technologies that handle capacity of those other systems and the ground of existing ones. For this reason, any soakaways
storm water at the source rather than leading it into itself is not impaired. should be sited well away from foundations for
the public sewer systems. • Situated so that there is no risk of contamination structures or roads, as indicated below:
from pollutants.
Developments proposing to use other types of • In areas where dissolution features are known
Sustainable Urban Drainage Systems (SuDS) should to be prevalent, soakaways should be avoided
follow the guidance found in ‘SuDS Manual’ (a if at all possible but, if unavoidable, should be
design manual published by CIRIA). The developer sited at least 20m away from any foundations.
should also confirm if the Planning consent for the • Where the chalk is of low density, or its density is
project imposes any additional requirements which not known, soakaways should be sited at least
may impact on the design of the sustainable 10m away from any foundations.
drainage systems (SuDS). • For drainage systems, flexible jointed pipes
should be used wherever possible; particular
Any surface water drain, soakaway or other care should be taken for the avoidance of leaks
Figure 2: Chamber type soakaway
Technical Manual V8: TS-11A-8.00-010117
infiltration system (including a SuDS system) which in both water supply and drainage pipe work.
is intended to discharge to a water course should • As the chalk is a vitally important aquifer, the
have Environment Agency consent to discharge. Environment Agency and Local Authority
must be consulted when planning soakaway
Soakaways can only be considered in permeable installations where chalk lies below the site,
conditions. A suitable site must be:
© LABC Warranty
Any septic tank or other sewerage treatment Figure 4: Typical package sewerage plant
291
CHAPTER 9
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. The materials, design and construction must meet the relevant
a workmanlike manner. regional Building Regulations.
9.2.1 Above ground drainage 9.2.2 Soil and waste systems 9.2.3 Air admittance valves
All above ground plumbing systems need to be In all above ground plumbing systems, the Air admittance valves provide a means of
designed to allow the unobstructed flow of waste unobstructed flow of waste from an appliance to ventilation to the drainage system to prevent the
water from an appliance to the underground the underground drainage will be allowed. This will loss of water seals in traps.
drainage system. To achieve this, the points below be achieved by following the notes below at the
should be noted at the design and installation design and installation stages: They are suitable for use in domestic buildings, e.g.
stages: bungalows, houses, multi-storey flats, and they only
• Rodding access is to be provided at all allow air to enter the drainage system. Their use
• Provide rodding access facilities at all changes direction changes. does not avoid the need to ventilate the drainage
of direction. • Pipe and gutter sizes are adequate to take the system adequately.
• Avoid bends and changes of direction in the expected rate of discharge, and are laid at
wet part of the above ground drainage system. suitable gradients with the minimum of direction Where air admittance valves are used to terminate
• 75mm-deep seal traps should always be used, changes. soil pipes they should comply with Building
except on a WC or where an appliance on the • 75mm deep seal traps should always be used, Standards. Valves within the building should be:
ground floor discharges directly into a trapped except on a WC where a 50mm depth of water
gully. seal can be used on the above ground • Positioned in areas that are not liable to freezing.
• Pipe sizes should not exceed the dimensions for drainage system. • Positioned in areas with adequate ventilation.
diameter against pipe length. • Pipe sizes should not exceed the dimensions for • Accessible for maintenance.
• Pipes should be laid at gradient 1:80 or better. diameter against pipe length.
• Any admittance valve fitted to the system • Pipes should be laid at a gradient of 1:80 or If the discharge stack provides the only ventilation
should be located above the highest flood level better. to septic tanks or cesspits, the connecting drain
Technical Manual V8: TS-11A-8.00-010117
of any appliance connected to that stack pipe. • Venting to the external air will be required at the is subject to periodic surcharging or is fitted with
• Enclosures to air admittance valves should be highest point of a drainage system (head of run). intercepting traps, air admittance valves are not
adequately ventilated. • At the head of underground drains, ventilation suitable for providing ventilation.
• The highest point of a drainage system (head is to be provided, either by a soil pipe or a
of run) should always be vented to the external separate ventilation pipe.
© LABC Warranty
CHAPTER 9
CHAPTER 9: BUILDING SERVICES
CHAPTER 9: BUILDING SERVICES
Figure 6: Single stack system: air admittance valves Figure 7: Sealing of service entry points
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. The materials, design and installation must meet the relevant
a workmanlike manner. regional Building Regulations
iii. Certification is required for any work completed by an approved
installer. Limitations of Functional Requirements
i. The Functional Requirements are limited by the recommendations
Materials applied to the specific areas covered in this chapter.
i. All materials should be stored correctly in a manner that will not cause ii. These Functional Requirements do not and will not apply to create
damage or deterioration of the product. any policy liability for any remedial works carried out by the contractor
Technical Manual V6: TS-011a-6.00-010413
ii. All materials, products and building systems shall be appropriate and or otherwise, nor to any materials used in those remedial works
suitable for their intended purpose.
iii. The structure shall, unless specifically agreed otherwise with the
Warranty provider, have a life of not less than 60 years. Individual
components and assemblies, not integral to the structure, may have a
lesser durability, but not in any circumstances less than 15 years.
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
295
CHAPTER 9
CHAPTER 9: BUILDING SERVICES
CHAPTER 9: BUILDING SERVICES
9.3.1 General
A suitable electrical service of the appropriate size
for normal domestic use shall be provided.
Figure 9: Supplementary bonding in a bathroom plastic pipe installation Figure 10: Supplementary bonding in bathroom metal pipes 297
CHAPTER 9
CHAPTER 9: BUILDING SERVICES
CHAPTER 9: BUILDING SERVICES
9.3.3 Socket outlets Halls, landings and staircases are to be provided Passive infrared (PIR) sensors are to be used in
Socket outlets are to be conveniently positioned with lighting outlets and two-way switches. common and external areas.
in close proximity to the TV aerial and telephone
outlets, thus allowing for electrical equipment Down lighters and other flush-fitting attachments 9.3.6 Positioning of sockets and switches
including TVs and DVD players. Rooms should be should not be installed through a ceiling if the Sockets and switches should be positioned in
provided with the following 13a outlets: ceiling is providing part of the required acoustic accordance with Figure 11.
insulation or fire resistance to the property.
• Kitchen/Utility – 8 outlets Consumer units should be between 1350mm and
• Dining Room – 4 outlets If down lighters are provided to ceilings below roof 1450mm above floor level.
• Living or Family room – 8 outlets voids (excluding thatched roofs), precautions are
• Bedroom (main) – 6 outlets to be taken to ensure that no fire risk is caused by
• Bedroom (other) – 4 outlets the proximity of other materials.
• Landing – 2 outlets
• Hall – 2 outlets
9.3.4 Cooking
Cooking appliances provided to the cooker
space in a dwelling must be suitably switched and
terminated with a minimum 30a electricity supply.
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. The materials, design and installation must meet the relevant
a workmanlike manner. regional Building Regulations.
iii. Certification is required for any work completed by an approved
installer. Limitations of Functional Requirements
i. The Functional Requirements are limited by the recommendations
Materials applied to the specific areas covered in this chapter.
i. All materials should be stored correctly in a manner that will not cause ii. These Functional Requirements do not and will not apply to create
damage or deterioration of the product. any policy liability for any remedial works carried out by the contractor
Technical Manual V6: TS-011a-6.00-010413
ii. All materials, products and building systems shall be appropriate and or otherwise, nor to any materials used in those remedial works.
suitable for their intended purpose.
iii. The structure shall, unless specifically agreed otherwise with the
Warranty provider, have a life of not less than 60 years. Individual
components and assemblies, not integral to the structure, may have a
lesser durability, but not in any circumstances less than 15 years.
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
299
CHAPTER 9
CHAPTER 9: BUILDING SERVICES
CHAPTER 9: BUILDING SERVICES
CHAPTER 9
CHAPTER 9: BUILDING SERVICES
CHAPTER 9: BUILDING SERVICES
Cold water systems may have provision for storage Holes should be formed with a cutter in the it can benefit from heat from beneath. Tanks that
or be directly connected to the main supply. positions shown in the design. are raised need to be insulated on all sides in an
Drinking water needs to be supplied directly from unheated roof space.
the main supply. Overflows in warning pipes should be no less than
19mm diameter and situated 25mm from the shut Fully insulated bends and junctions are required,
Cold water pipes and storage cisterns located in off water level in the cistern. The pipe may dip especially near openings to the outside air, such
roof spaces and other unheated areas should be below the water level in accordance with water as the eaves. If possible, water pipes should not be
appropriately insulated to the relevant standards. regulations. Alternatively, the pipe should terminate located within a loft space where they could be
vertically downwards, or a tee should be fitted affected by cold ventilation air.
Cold water storage cisterns will require the horizontally at the discharge end.
capacity specified in the design. Suitable support 9.4.3.1 Provision for expansion
should be given for the cistern filled with water. 9.4.3 Hot water services An expansion pipe is to be provided on vented
Hot water systems may have provision for storage or systems for hot water.
To stop the cistern bottom being deformed, may be of the instantaneous type, e.g. combi boilers.
permanent support is to be given where necessary. 9.4.3.2 Unvented hot water systems
Adequate materials for support platforms are: Vertical installation of cylinders is required with Third-party accreditation is required where an
access, and cylinders are to be insulated as unvented hot water system with a storage capacity
• Softwood boarding specified in the design. greater than 15 litres is required by the design.
• Marine Plywood Installation is to be completed by a competent
• Chipboard Type P5 Where an immersion heater is fitted, it should be: person.
• Oriented Strand Board Type OSB3 to British
Standards • Appropriate for the type of water supplied to the 9.4.3.3 Draining down facility
Technical Manual V8: TS-11A-8.00-010117
periods a day. In the case of electrically heated indicated in the table below.
storage systems (Electricaire), there will normally
be a further time switch to control the electrical Central heating system fuel PCDF% (2009)
‘charging’ periods to conform within the chosen Mains natural gas 88
tariff. LPG 88
© LABC Warranty
CHAPTER 9
CHAPTER 9: BUILDING SERVICES
CHAPTER 9: BUILDING SERVICES
9.4.6 Ventilation 9.4.8 Extract ducts Where a gas appliance requires an electrical
Adequate support is required for extract ducts, supply, a suitably fixed spur or socket outlet should
Intermittent Continuous and they also need to have sealed joints where be provided.
Room
extract extract
required. Insulation needs to be provided where
30 l/s adjacent
Kitchen to hob 13 l/s ducts pass through unheated spaces, such as roof A concealed co-axial cable should be provided
Or 60 l/s elsewhere voids, to the outside air, or a condensation drain from the roof void to a terminal outlet within the
Utility (access via should be provided in accordance with the design. main living room. Where the co-axial cable is
30 l/s 8 l/s
dwelling)
not provided, a conduit and draw wire, or an
Bath/shower room 15 l/s 8 l/s
Where ducting is part of a mechanical ventilation alternative, should be provided. The provision of
Sanitary
6 l/s 6 l/s and heat recovery system, it should be insulated an aerial is not required.
accommodation
in accordance with the manufacturer’s
Table 5: Extract ventilation rates
recommendations.
9.4.9 Whole-building ventilation To ensure good transfer of air throughout the • Services must be sleeved or ducted through
The whole-building ventilation rate for the supply of dwelling, there should be an undercut of minimum structural elements (and not solidly embedded)
air to the habitable rooms in a dwelling should be area 7600mm2 in all internal doors above the floor to prevent damage. Fire stopping may also
no less than the rates stated in Table 6 below. finish (equivalent to an undercut of 10mm for a be required.Services should not to be located in
standard 760mm wide door). the cavity of an external wall, except for
Number of bedrooms in dwelling electricity meter tails.
Ventilation
1 2 3 4 5 • Only to be buried in screeds where permitted by
Whole building relevant Codes of Practice.
ventilation rates 13 17 21 25 29
(l/s)
Where copper pipes are permitted in floor screeds,
Table 6: Whole building ventilation rates they should be:
9.4.10 Passive stack ventilation (PSV) • Sleeved or wrapped so that they can move
The system is to meet the relevant third-party freely along the length and at joints and bends.
accreditation. • Jointed with capillary joints.
The PSV layout should be designed to: A metallic tape should be applied to the pipework
where plastic pipework is hidden within or behind
• Avoid cross flow between the kitchen and wall surfaces, which would otherwise not be
bathroom/WCs. located by a metal detector.
• Prevent, as far as possible, air flow in the ducts Figure 16: Passive stack ventilation
being adversely affected by the prevailing wind
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 9
CHAPTER 9: BUILDING SERVICES
CHAPTER 9: BUILDING SERVICES
Suitable clips or brackets are to be used to secure. 9.4.14 Concealed services 9.4.16 Services within or beneath floors
Fixings should be installed adequately, and spaced If the services are hidden in walls or floors, they Protection through wrapping or ducting is
to stop sagging but not restrict thermal movement. need to be positioned so that any significant necessary when pipes are situated under floor
Where needed, pipes should have adequate falls. cracking of the surface cannot occur. screeds. Thermal expansion allowances are to be
made, especially at changes of direction.
Sufficient room should be allowed for thermal 9.4.15 Wall chasing
expansion and contraction to avoid damage and If chases in walls are necessary, their depth should The insulating material around the pipework needs
noise from pipe movement. not exceed: to be a minimum of 25mm in thickness. The screed
thickness should still be at least 25mm where pipes
Holes should be at least three times their diameter • One-sixth the thickness of the single leaf for cross over.
apart. horizontal chases.
• One-third the thickness for vertical chases. 9.4.17 Fire stopping
9.4.13 Notches and drillings Fire stopping is required around services
Floor joists should not be excessively notched or Hollow blocks should not be chased unless that penetrate fire-resisting floors, walls or
drilled. Further guidance can be found in chapter specifically permitted by the manufacturer. partitions. If proprietary systems are used, they
8 of this manual.
should be installed using the manufacturer’s
recommendations.
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
Figure 17: Staggered services on party walls Figure 18: Recommended positioning of pipes in screeds
CHAPTER 10: FINISHES
CONTENTS
10.1 PLASTERWORK
10.2 SECOND AND THIRD FIX FINISHES
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
307
CHAPTER 10
FUNCTIONAL REQUIREMENTS
10.1 PLASTERWORK
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Surfaces that will be subjected to water from the use of a showerhead
a workmanlike manner. over a bath should be tiled or have an appropriate alternative water-
resistant finish.
Materials iii. The materials and construction must meet the relevant regional
i. All materials should be stored correctly in a manner that will not cause Building Regulations
damage or deterioration of the product.
ii. All materials, products and building systems shall be appropriate and Limitations of Functional Requirements
suitable for their intended purpose. i. The Functional Requirements are limited by the recommendations
iii. The structure shall, unless specifically agreed otherwise with the applied to the specific areas covered in this chapter.
Warranty provider, have a life of not less than 60 years. Individual ii. These Functional Requirements do not and will not apply to create
components and assemblies, not integral to the structure, may have any policy liability for any remedial works carried out by the contractor
a lesser durability, but not in any circumstances less than 15 years. or otherwise, nor to any materials used in those remedial works.
Technical Manual V6: TS-011a-6.00-010413
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
CHAPTER 10: FINISHES
CHAPTER 10: FINISHES
10.1.1 Introduction 10.1.3 Plaster mixes 10.1.5 Plasterboard and dry lining
This chapter covers all plastered finishes to walls Plaster mix ratios should be in accordance
and ceilings. Plastered finishes should be applied with manufacturer’s recommendations and be Support of plasterboard
to a certain standard to receive a suitable appropriate for the intended use. Supports for plasterboard should be designed so
decorative finish. It should be durable enough to that the following span limits are not exceeded:
prevent surface cracking and, if applicable as part 10.1.4 Minimum plaster thickness
of the whole element, meet the required levels The thickness of plaster will vary depending on the Board
Timber
Intermediate Perimeter
support
of fire and sound insulation in accordance with evenness of the substrate. The finished element thickness noggins noggins
centres
(mm) required required
current Building Regulations. must meet the tolerances identified in chapter (mm)
1 of this Manual, and be of a suitable quality so 400 No Yes
9.5
10.1.2 Substrate and background that a decorative finish can be applied. Minimum 450 Yes Yes
Plasterwork should be applied to suitable thickness should be in accordance with Table 1. 400 No Yes
manufacturer’s instructions. 1 provide suitable and 10mm from bound edges. Position cut edges
concrete
and durable
finish to internal angles whenever possible, removing
Where the background has a mix of varying Skim to provide paper burrs with fine sandpaper. Stagger horizontal
Ceiling -
materials, e.g. blockwork and brickwork, expanded plasterboard
1 suitable and and vertical board joints between layers by a
durable finish
metal should be provided to prevent differential minimum of 600mm. Locate boards to the centre
Ceiling -
movement in the plaster finish. 2 10mm maximum
© LABC Warranty
CHAPTER 10
CHAPTER 10: FINISHES
CHAPTER 10: FINISHES
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. The materials, design and construction must meet the relevant
a workmanlike manner. regional Building Regulations.
iii. The structure shall, unless specifically agreed otherwise with the or otherwise, nor to any materials used in those remedial works.
Warranty provider, have a life of not less than 60 years. Individual
components and assemblies, not integral to the structure, may have
a lesser durability, but not in any circumstances less than 15 years.
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
311
CHAPTER 10
CHAPTER 10: FINISHES
CHAPTER 10: FINISHES
10.2.1 Ceramic tiling • Where forming part of a framed wall to a Ensure that design and specification information
shower enclosure, walk in shower or wet is issued to Site Supervisors and relevant specialist
10.2.1.1 Ceramic wall tiling room; moisture resisting plasterboard (or a third subcontractors and/or suppliers.
Tiles should be fit for purpose, have a suitable finish party product approved water resistant backer
and be of an appropriate size and thickness. board) should be used for the area of the 10.2.1.5 Ceramic floor tiling
‘shower enclosure’ wall that is to be tiled (up Tile floorings shall provide a suitable surface and
The installation of the tiling should follow the to a height of 1800mm above the floor level). In be fit for purpose.
guidance contained in BS 5385 – 3: 2014 Wall and addition where the enclosure wall forms part
floor tiling. of a walk in shower or wet room, the The installation of the tiling should follow the
‘surrounding’ walls to the enclosure are required guidance contained in BS 5385 – 3: 2014 Wall and
10.2.1.2 Background surfaces to be water proof for a height of 150mm above floor tiling.
Background surfaces should be adequate to the floor junction.
support ceramic tiles, and as a minimum should: Note the guidance below is for ceramic tiling only
10.2.1.3 Fixing and does not apply to other heavier tiles such
• Be even, to adequately support the whole tile. Depending on the background, tiles should be as Marble, Travertine or stone which would be
• Be strong and durable enough to support fixed using cement mortar or a suitable adhesive considered too heavy for a traditional suspended
the tile. purposely designed for ceramic tiling. Tiles to timber floor construction.
• Have sufficient absorbency to ensure that shower enclosures and other areas that will be
adhesives will stick effectively or a suitable exposed to water should be fixed with waterproof
bonding agent applied. adhesive.
• Be of the same construction type; where two
Technical Manual V8: TS-11A-8.00-010117
10.2.1.6 Background surfaces 10.2.1.7 Tiles on wood-based substrate • Additional solid timber strutting between the
Background surfaces should be adequate to The floor must be fit for purpose and should joists will be required to assist in stiffening the
support ceramic tiles, and as a minimum should have adequate stiffness to support the tiles and floor construction for the entire span of the
be: adhesive. joists between supports, this may include
strutting beyond the area of the tiled room e.g.
• Level and even enough to provide a plane For floors supported by joists up to 600mm if the joist span continues over a landing area.
surface; falls should be specified where maximum centres, the floor decking should be: • Tiles should be suitable for laying over a
required. timber base and deformable (flexible) tile
• Resistant to ground moisture; a damp proof • 18mm exterior grade plywood screwed to the adhesive (e.g. C2S1), and grout should be used
membrane (DPM) should be provided to a joists at 300mm centres with all square edges in accordance with the adhesive
ground bearing slab. supported on joists or noggins. Plywood should manufacturer’s recommendations.
• Adequately dry, i.e. at least six weeks drying out be laid with a 1.5mm–2mm movement gap • Tiles must be laid to a level finish except where
time for concrete base, three weeks for screed. between boards and at abutments or. required in a walk in shower / wet room, see
• Movement joints will be required in the tile • Moisture resistant floor decking overlaid with a 10.2.1.7
finishes where they continue over changes minimum 10mm exterior grade plywood fixed to
in the subfloor construction below For example; joists at 300mm centres or 10.2.1.8 Walk in showers and wet rooms floors
below a door opening in an internal wall, where • A combination of one of the above with a The floor areas to a walk in shower or wet room
end bearings of beam and block joists may proprietary separating/de-coupling layer, tile (where the floor area is part of the shower floor) is
be found. If the tiled floor finish continues backer board or tile bedding reinforcement required to be water proof and drained, a timber
through into another room, a movement joint sheet used in accordance with third floor deck substrate is not recommended. The floor
at the door threshold will be required to prevent party product approved manufacturer’s deck must be a water stable component with a
Technical Manual V8: TS-11A-8.00-010117
cracking in the tiles occurring. recommendations. third party product approval confirming its use for
• For internal floors, which might be subjected • The length of screw fixings should be at least this situation.
to significant thermal changes, i.e. direct 2.5 times the thickness of the combined
sunlight in sunrooms, atria or underfloor heating, decking material to ensure adequate • The fall to the wet room area floor must prevent
etc., the floor area should be divided up by penetration into the timber sub-floor or joist / ponding and should be between 1:80 to 1:100
© LABC Warranty
intermediate movement joints into bays of size strut supports. to a drainage point.
not greater than 40m with an edge length not
2
• The floor drainage point must be maintainable
greater than 8m. and adequate in size to take the intended
water flow from the shower head without
flooding occurring. 313
CHAPTER 10
CHAPTER 10: FINISHES
CHAPTER 10: FINISHES
• Due to the need for a fall in the finished tiled Proprietary additives should have been assessed 10.2.2.3 Finishing of screeds
surface to an outfall a suitable threshold and have third-party certification. Screed should provide an even surface as
may be necessary at the wet room door appropriate, as defined in chapter 1 of this Manual.
opening (which gives access to the rest of Minimum thickness of screeds are as follows: Concrete floor slabs may be suitably finished to
the accommodation) serve directly as a wearing surface without the
Surface
Minimum thickness need for an additional topping, in accordance
at any point (mm)
10.2.2 Floor finishes with the recommendations of BS 8204. If required,
Laid monolithically with base 12
surface sealers or hardeners should only be used
Laid and bonded to a set and
Screeding 20 in accordance with the manufacturer’s instructions.
hardened base
Screeds should be fit for purpose, have a suitable Laid on a separating membrane
50
finish and be of an appropriate thickness. (e.g. 1000g polyethylene) 10.2.2.4 Insulation
Laid on resilient slabs or Insulation below screeds should have enough
quilts (screed reinforced with 65
Background surfaces galvanised wire mesh) compressive strength to support the screed.
Background surfaces where screeds are being Damp proof membranes should be installed in the
Table 3: Screed thickness requirements
supported should meet the following requirements: correct positions, as indicated by the insulation
manufacturer’s instructions. Sound insulation
Where service pipes are bedded in the screed, the
• Bond should be installed in accordance with the
screed should be deep enough to provide at least
Background surfaces for bonded screeds manufacturer’s instructions.
25mm of screed cover over service pipes, insulation
should provide an adequate mechanical key.
and reinforcing.
If necessary, cement grouting or a bonding 10.2.2.5 Building services
agent should be specified to provide adequate Where building services pass through the screed
10.2.2.1 Maximum areas of screed
Technical Manual V8: TS-11A-8.00-010117
10.2.2.2 Curing
• Screed mix
Screeds should be cured naturally and should not
Cement and sand screeds should have a mix
be covered for at least three weeks.
ratio of between 1:3 and 1:4.5.
CHAPTER 10: FINISHES
CHAPTER 10: FINISHES
manufacturer’s recommendations.
10.2.3.4 Plaster and plasterboard
Painting Plaster and plasterboard surfaces should be
Painting of timber should consist of at least prepared and made ready for decorating in
one primer coat, one undercoat and one finish accordance with the manufacturer’s instructions.
coat, or alternatively in accordance with the
© LABC Warranty
manufacturer’s instructions.
315
CHAPTER 10
Technical Manual V8: TS-11A-8.00-010117
Technical Manual V6: TS-011a-6.00-010413
© LABC Warranty
CHAPTER 11: EXTERNAL WORKS
CONTENTS
11.1 PAVING AND DRIVEWAYS
11.2 (THIS SECTION HAS BEEN REMOVED)
11.3 OUTBUILDINGS
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
317
CHAPTER 11
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Structural elements outside the parameters of regional Approved
a workmanlike manner. Documents must be supported by structural calculations provided by
a suitably qualified expert.
Materials iii. The materials, design and construction must meet the relevant
i. All materials should be stored correctly in a manner that will not cause regional Building Regulations.
damage or deterioration of the product.
ii. All materials, products and building systems shall be appropriate and Limitations of Functional Requirements
suitable for their intended purpose. i. The Functional Requirements for external pathways and drives in this
iii. The structure shall, unless specifically agreed otherwise with the chapter apply only to the drive and pathway leading to the principle
Warranty provider, have a life of not less than 60 years. Individual entrance to the dwelling.
components and assemblies, not integral to the structure, may have a ii. These Functional Requirements do not and will not apply to create
lesser durability, but not in any circumstances less than 15 years. any policy liability for any remedial works carried out by the contractor
or otherwise, nor to any materials used in those remedial works.
Technical Manual V6: TS-011a-6.00-010413
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
CHAPTER 11: EXTERNAL WORKS
CHAPTER 11: EXTERNAL WORKS
11.1.1 Preparation of ground • Paths and driveways should be effectively 1. Where access requirements are required under
The area to be surfaced should be prepared by drained to prevent ponding of water adjacent Building Regulations to the principal entrance
stripping away all vegetation and organic material. to the building. of the visitable dwelling the ground surface of
Land drainage should be considered for ground • Paths and drives should be laid to fall away the defined approach route must be firm, even,
that is saturated. from the building. smooth enough to be wheeled over, not
• Rain water should either discharge into a covered by loose laid materials such as gravel
Excavation trenches (e.g. service trenches) should trapped gulley or drain to garden land that is and shingle and have a minimum cross-fall
be backfilled with granular type material to the well drained. of 1:40.
required level. The backfill should be compacted in • Gullies should be trapped when discharging 2. Where a driveway is required by relevant
layers no greater than 300mm, and the fill material to a soakaway or combined drainage system Building Regulations, to provide access for fire
should at least have the same bearing capacity as (the approval of the statutory sewerage fighting vehicles to allow a “pump” appliance to
the adjacent ground. undertaker may be required). be able to get to within 45m of the entire
• Where slotted surface water drainage channels dwelling house, the construction of the
are proposed to be used near the building (e.g. driveway must be suitable and durable to take
in front of garage door openings) and the the additional loadings (at least a minimum of
ground levels would otherwise cause water 12.5 tonnes). The access width of the drive must
to concentrate towards the building wall and be adequate (at least 3.7m) and if the
potentially flood the building; a gradient should driveway length is in excess of 20m a turning
be created for at least 500mm away from the circle or hammer head should be provided.
Technical Manual V8: TS-11A-8.00-010117
319
CHAPTER 11
CHAPTER 11: EXTERNAL WORKS
CHAPTER 11: EXTERNAL WORKS
principle level access into the dwelling, should be Table 1: Minimum thickness of sub-base
Table 2: Suitable compaction of sub-bases
laid at least 150mm below the damp proof course
(DPC) of the dwelling.
© LABC Warranty
CHAPTER 11: EXTERNAL WORKS
CHAPTER 11: EXTERNAL WORKS
11.1.4 Edgings 11.1.5 Surfacing of paths and drives Minimum thickness of surfaces
Edgings are to be provided to paths and driveways Differences in the surface should not exceed +/- The minimum thicknesses of surfaces are indicated
to prevent movement or displacement. Edgings are 10mm from a 2m straight edge with equal offsets. in Table 3.
not necessary if the driveway is in-situ concrete or Some fracturing or weathering may also appear if
for any pathway made of precast concrete paving the material is natural stone because of the natural Minimum
Surface Material thickness (1) British
slabs laid on a mortar bed. make-up of the material. This tolerance applies to type specifications Standard
Path Drive
principle pathways and driveways to the dwelling
Macadam
Edgings should be laid to ensure that there are no that are required to meet the standards of Part M 40mm coated
single 75 75 BS 4987
macadam
excessive gaps, and laid with smooth alignment (Access to dwellings). course
along the top of the edging. Concrete edgings Coarse
Rolled
asphalt 10mm 60 60 BS 594
should be bedded on a 200mm wide x 100mm Suitable surfaces for paths and driveways asphalt
nominal size
deep ST1 mix concrete base. The concrete should Suitable surfaces are considered as:
Nominal
be haunched up the side of the edging to give 20mm coated 60 60 BS 4987
adequate support. • Block paving Macadam macadam
two course Nominal
• Precast concrete paving slabs
6mm wearing 20 20 BS 4987
• Timber decking course
• Cast in-situ concrete Clay or
Block
• Rolled asphalt calcium 50 50 BS 6677
paving
silicate
• Macadam
Block Pre-cast
60 60 BS 6717
paving concrete
Note: Where access requirements are required Designated
Concrete 75 100 (2)
Technical Manual V8: TS-11A-8.00-010117
and shingle (1) Drive minimum thickness assumes standard loadings for a
typical family car, additional thicknesses are required where
increased loads are applied e.g. LGV vehicles.
(2) Drives increased to 150mm on poor ground or clay.
CHAPTER 11
CHAPTER 11: EXTERNAL WORKS
CHAPTER 11: EXTERNAL WORKS
11.1.5.1 Paving slabs 11.1.5.4 In-situ concrete Hardwoods: Only use species rated as durable or
Paving slabs should be placed on a 25mm bed In-situ concrete should be laid in areas of 20m 2
moderately durable.
of sharp sand or a semi-dry mortar mix (sand/ maximum to allow for movement. Where abutting
cement mix ratio 3:1). Joints between slabs should an adjacent structure, the concrete should be Softwoods: Only use species/components with
be no greater than 4mm for straight edge paving isolated using a flexible jointing material. Where natural durability or which have been treated
slabs, and should be filled with kiln-dried sand. A the sub-base is well drained, it is recommended in accordance with BS EN 335 to a ‘Use Class’
neat consistent joint should be provided to rustic that the concrete is cast onto a damp proof standard appropriate to their use, i.e. ‘Use Class
slabs. Slabs should be cut with a diamond blade membrane. 4’ treatment for posts and other structural
cutter or similar to give a neat finish. components in direct ground or freshwater
contact, or ‘Use Class 3’ treatment for all
11.1.5.2 Block paving components out of direct ground contact subject
Block paving should be laid on a minimum of to frequent wetting.
50mm sharp sand, and gaps between blocks
should not exceed 5mm. All joints should be filled Note:
with kiln-dried sand or similar. Blocks should be
cut using a block splitter and the finished path • Whitewood should not be used for posts
or driveway should be compacted with a plate embedded in the ground or for other elements
vibrator. Care should be taken to ensure that the (joists) in the ground or other non-permeable
surface of the paving is not damaged or scuffed. surface, e.g. concrete slab.
Figure 4: typical cast in-situ drive or path abutting the dwelling • All crosscuts, notches or large boreholes shall
11.1.5.3 Porous block paving joints be treated on site with a suitable preservative.
11.1.5.5 Macadam and asphalt
Technical Manual V8: TS-11A-8.00-010117
Where paving is designed to allow ground water to For full guidance on wood preservation
drain through the joints, the gaps between blocks Ensure that sub-bases are dried and primed and specification, contact the Wood Protection
and the material within the joints should meet the that the surface is appropriately rolled with a Association.
initial design specification. The joint material should vibratory roller to the required finish.
be sufficient to prevent blocking and prevent moss
growth. 11.1.5.6 Timber decking
© LABC Warranty
life, the surface mounting of posts on precast piers nail guns as they can damage timber.
or metal shoes is recommended. Board spacing
When laying timber decking boards: Fall
To aid drainage, build a gentle fall of 1:100 into the
• Allow for a 5mm minimum to 8mm maximum deck, away from any adjacent property. Grooved
© LABC Warranty
gap between board lengths. deck boards are designed to assist the drainage of
• where the board abuts a post, allow a 5mm surface water, so lay them in the direction of the fall.
gap.
• where board ends meet, allow a 3mm gap.
323
CHAPTER 11
CHAPTER 11: EXTERNAL WORKS
CHAPTER 11: EXTERNAL WORKS
against biological attack – Part 2: Guide to the wood Loading for buildings. Code of Practice for dead
application of use classes to solid wood and imposed loads
CHAPTER 11: EXTERNAL WORKS
CHAPTER 11: EXTERNAL WORKS
BS 7359: 1991 The following diagrams present acceptable provisions to meet Warranty standards:
Nomenclature of commercial timbers, including
sources of supply
BS 5268-2: 2002
Structural use of timber. Code of Practice
for permissible stress design, materials and
workmanship
BS 6180: 1999
Barriers in and about buildings – Code of Practice
BS 6399-1: 1996
Loading for buildings. Code of Practice for dead
and imposed loads
325
CHAPTER 11
CHAPTER 11: EXTERNAL WORKS
CHAPTER 11: EXTERNAL WORKS
External
wall Perimeter Non-deformable suitable
insulation cavity closer (insulated)
Landing area
Floor finish
Figure 6: Typical level threshold cast in-situ concrete slab Figure 7: Level threshold: with canopy protection (block and beam floor)
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
FUNCTIONAL REQUIREMENTS
SECTION 11.2
327
CHAPTER 11
FUNCTIONAL REQUIREMENTS
11.3 OUTBUILDINGS
Workmanship Design
i. All workmanship must be within the tolerances defined in chapter 1 i. The design and specifications shall provide a clear indication of the
of this Manual. design intent and demonstrate a satisfactory level of performance.
ii. All work is to be carried out by a technically competent person in ii. Outbuildings should be constructed to resist lateral and vertical loads
a workmanlike manner. adequately.
iii. Foundations should be designed and constructed to suit local ground
Materials conditions and adequately support the weight of the structure and
i. All materials should be stored correctly in a manner that will not cause imposed loads.
damage or deterioration of the product. iv. The materials and construction shouldmeet the relevant regional
ii. All materials, products and building systems shall be appropriate and Building Regulations.
suitable for their intended purpose.
iii. The structure shall, unless specifically agreed otherwise with the Limitations of Functional Requirements
Warranty provider, have a life of not less than 60 years. Individual i. The Functional Requirements are limited by the recommendations
components and assemblies, not integral to the structure, may have applied to the specific areas covered in this chapter.
a lesser durability, but not in any circumstances less than 15 years. ii. These Functional Requirements do not and will not apply to create
any policy liability for any remedial works carried out by the contractor
Technical Manual V6: TS-011a-6.00-010413
Technical Manual V8: TS-11A-8.00-010117
the appearance, value and serviceability of the by meeting the relevant parts of the Approved
building or the housing unit. Documents.
• They provide an acceptable and durable
external surface and are not adversely affected
by harmful or toxic materials in the atmosphere
or from the ground.
© LABC Warranty
329
CHAPTER 11
CHAPTER 11: EXTERNAL WORKS
CHAPTER 11: EXTERNAL WORKS
CONTENTS
12.1 EXISTING ELEMENTS
12.2 NEW ELEMENTS CONNECTING TO EXISTING STRUCTURE
12.3 HISTORIC BUILDINGS
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
331
CHAPTER 12
FUNCTIONAL REQUIREMENTS
Workmanship Design
i. All workmanship is to be completed by a technically competent i. The design and specifications should give clear indication of the
person in a workmanlike manner. design intent and demonstrate a satisfactory level of performance
ii. Any new work must meet the tolerances defined in chapter 1 of this with regards the renovation of components and the interaction of new
Manual. Tolerances will not apply to existing finishes that have not elements.
been upgraded or altered, or where the supporting elements will not ii. Specialist reports are required to confirm that existing elements will
allow for the tolerances to be met. have an adequate level of structural stability, as defined in the materials
section above, the reports must confirm the adequacy of the existing
Materials ‘waterproof envelope’.
i. All new materials should be stored correctly in a manner that will not
cause damage or deterioration of the product. Limitations of Functional Requirements
ii. Materials, products and building systems shall be appropriate and i. The Functional Requirements are limited by the recommendations
suitable for their intended purpose. applied to the specific areas covered in this chapter.
iii. The structure, regardless of whether it is a new or existing element, ii. These Functional Requirements do not and will not apply to create
shall, unless specifically agreed otherwise with the Warranty provider, any policy liability for any remedial works carried out by the contractor
have a life of not less than 60 years. Individual components and or otherwise, nor to any materials used in those remedial works.
Technical Manual V6: TS-011a-6.00-010413
12.1.1 Introduction The Warranty includes cover for the retained an unnecessary early expense, the savings in
This section relates to buildings that do not have structural elements and waterproof envelope of reconstruction costs can greatly outweigh the cost
any Historic or Conservation Planning restrictions. It any existing building for the duration of the policy. of the preparatory work.
is expected that the building can be appropriately The Warranty Surveyor will always undertake an
upgraded in accordance with current Building initial assessment of the existing fabric to ascertain Elements of the retained structure and proposed
Regulations with respect to structure, fire, resistance in general terms if the proposal is capable of works should not be considered in isolation, as
to moisture, sound, ventilation, drainage, heat representing a standard risk to the Underwriter. If a solution for one problem may cause issues
producing appliance, conservation of fuel and deemed acceptable, the development is then elsewhere. Past performance is no guarantee of
power, access and security. subject to a technical audit process during ongoing adequate performance because different
construction, and the following guidance is expectations and changing living conditions can
Buildings not suitable for warranty cover intended to assist all parties in ensuring the all impact on both the actual and perceived
The following building types will not be considered relevant requirements are met, as well as providing performance of a converted/refurbished structure.
an element of consistency in approach.
• Cob Construction It is not possible to cover every building type within
• Through Wall oak / timber frame Depending on the condition of the original this chapter; therefore, the guidance is general,
• Wattle & Daub building; an expert survey may be required for the and certainly will not apply in every scenario. It
different elements of the building as described in is strongly recommended that early discussions
The following guidance has been formulated to the following sections of this chapter. If the survey are held to determine exact requirements and to
assist both Warranty Surveyors and Developers concludes that any of these elements are unable enable a full review of the proposed strategy and
on projects involving either the conversion or to meet the life expectancy of 60 years for structure development.
refurbishment of existing buildings. and 15 years for non-structural elements, they
Technical Manual V8: TS-11A-8.00-010117
should be systematically replaced or repaired. Where new work is proposed, it should follow the
Conversions and refurbishments are projects that guidance for those elements in this Technical
involve work to existing buildings or parts of existing Existing buildings and structures can present Manual. Where new work is applied to, or meets,
buildings. This could include the conversion of particular problems both initially and on an existing elements, consideration on how these
industrial or commercial buildings into housing; the ongoing basis. Therefore, it is essential that areas will interact must be made; for example, new
conversion of an existing residential building into
© LABC Warranty
thorough and comprehensive survey work is cavity masonry that abuts an existing solid wall
flats; an additional storey to an existing building; undertaken prior to new works commencing to construction.
the refurbishment of an existing residential building; understand both the current condition of any
or a façade retention project. structure and the impact any proposed works may
have. Although initially this may be considered 333
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
Please note that the requirements of the Damp proof courses (DPC) and membranes Roof coverings
technical audit are quite different from those All walls, floors and basements should include Coverings and support systems should be
undertaken for the purposes of compliance a DPC. Ground levels and ventilation should be replaced unless a specialist report compiled by
with Building Control and planning legislation. checked before any remedial DPC treatments an independent, competent and appropriately
If any such bodies have imposed restrictions on are considered. However, where remedial experienced Chartered Building Surveyor
the areas above, we suggest that you contact DPC treatments are required, these need to concludes that the system can provide a life
the Technical Services Department before be appropriate to the type of construction, span of at least 15 years. This should include the
undertaking any works. independently tested/approved and provided with covering, battens, felt, flat roof decking, fascias,
a 10 year insurance-backed guarantee. Installed soffits, flashings, nails and clips, etc.
12.1.2 Retained elements, foundations and by a member of the Property Care Association,
load-bearing structures (including the guarantees must cover workmanship and Weather resistance of walls, including claddings,
floors, walls and roofs) materials. The construction of any existing ground render, re-pointing, etc.
Any areas of cracking or suspected movement are floor will need to be assessed, and details provided The remedial works for the external walls must have
to be assessed and remedial measures provided to the Warranty Surveyor for consideration. regard for the exposure rating provided in BS 5628.
by an appropriately qualified and experienced Any retained cladding system must be surveyed
Structural Engineer. Any additional loads must Timber treatment against insect and fungal attack to determine a minimum 15 year life expectancy.
be catered for. Consideration of the impact of All retained timbers will need to be assessed, Provision of additional thermal insulation must also
any landscaping and drainage works is required. logged and the remedial treatment noted. be considered.
Spalling masonry can be locally repaired, with units Timbers that are embedded should be exposed
cut out and replaced, or re-used with sound face or removed and replaced with masonry. Where External doors and windows
showing. Larger areas will require a schedule of this is not possible, core samples should be taken A condition survey should be provided by an
Technical Manual V8: TS-11A-8.00-010117
repair to be submitted and agreed. to assess the moisture content, and remedial independent, competent and appropriately
works considered. Any remedial treatment must qualified Surveyor or Specialist to confirm life
be provided with a 10 year insurance-backed expectancy of 15 years. Consideration must be
guarantee and undertaken by a member of the given to improving the thermal characteristics.
Property Care Association, where guarantees must Any services to be retained should be suitably
© LABC Warranty
Sound testing Where some of the elements are new and Where the existing foundations are inadequate
Party walls and party floors should be sound tested replaced as part of the conversion/refurbishment, and the building has moved/cracked, and/
in accordance with National Building Regulations no report is necessary. or the proposals are to increase the load on
to determine compliance, access maybe required the foundations, a Structural Engineer should
into adjacent buildings in order that sound testing 12.1.3 Substructure design a suitable solution, which should then be
is completed. discussed with your Warranty Surveyor prior to
12.1.3.1 Foundations implementation.
External and internal services An appraisal of the existing building and its
Any services to be retained should be suitably foundations should be carried out by a Structural Proposals for underpinning should be prepared by
tested and reported by a Specialist. Engineer. an expert and be in accordance with BS 8004.
Drainage This appraisal should address: Where trees are within close proximity of the
Drainage systems should be replaced unless it existing structure, the potential risk of movement
can be demonstrated that the existing drainage • Settlement must be fully assessed, However as chapter 6.1 of
system is fit for purpose, have suitable falls and the • Heave this manual relates to new building works, more
required rodding facilities. • Foundation depth and type detailed analysis supported by comprehensive
• Soil type structural designs and calculations should be
Where private drains are retained, a CCTV survey • Basement walls and floors provided supported by soil samples to determine
should be undertaken to ensure the integrity and • Trees adjacent to buildings the plasticity of the ground and the extent of the
design of any retained system. Where the lengths • Undermining due to new floor structures root intrusion beneath or around the building.
of existing retained drainage do not have rodding or building services
Technical Manual V8: TS-11A-8.00-010117
and any alterations to the existing stability of the joints should be provided between existing and
treatment system. building. underpinned/new foundations.
335
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
12.1.3.2 Tanking of basements Some types of wall are not suitable for treatment by
Where it is intended that there will be any useable a remedial DPC system. These include:
space below ground level, then the design should
be such that adequate resistance to the passage • Walls of exceptional thickness, i.e. greater than
of water/moisture to the inside is achieved, following 600mm
the guidance in BS 8102: 2009. Please refer to • Rubble-filled walls
chapter 6, Section 6.1. in this Technical Manual for • Random flint/granite walls, or those of other
our requirements for basement provision. similar impermeable materials
• Mud walls (cob), wattle and daub
Where there is not a requirement under • Rat trap bond
Building Regulations to upgrade a basement
from a waterproofing perspective (i.e. certain Where it is not suitable to provide a remedial DPC,
storage areas and car parking) there will be no the wall should be assessed to demonstrate that
requirement to upgrade the basement and an it prevents rising dampness from entering into
endorsement will be placed on the policy to the building. The assessment should include the
Figure 1: Typical traditional underpinning detail
exclude seepage below ground to non habitable following:
spaces.
• Damp Proof Survey from a member of the
Walls Property Care Association or RICS Chartered
Surveyor to confirm that there is no evidence of
12.1.3.3 Damp proofing rising damp and;
Technical Manual V8: TS-11A-8.00-010117
Where an existing DPC cannot be identified or is • Suitable detail of the ground floor construction
found to be defective, a remedial DPC should be and independent internal lining system that
provided; it should have an insurance-backed keeps the internal environment of the dwelling
guarantee and be installed by a Property Care dry.
Association Member. A suitable DPC should be
provided to existing walls, placed at least 150mm
© LABC Warranty
337
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
An alternative method of detecting any dry rot is The cause of fungal attack is dampness, which Primary measures
by seeking the expertise of: may be caused by the following: These consist of locating and eliminating
sources of dampness and promoting the rapid
Hutton & Rostron: • Rain penetration drying out of the structure. Where the timber
Tel No. 01483 203221 • Condensation becomes wet and remains wet, e.g. the moisture
Fax No. 01483 20291 • Hygroscopic salts content exceeds 20%, then it is likely to decay;
www.handr.co.uk • Defective rain water goods and roofs by eliminating the source of dampness and the
• Bridging of existing DPCs, or no DPC drying of timbers to below 20%, the fungus will
or • Defective renders normally stop growing and will eventually die.
• Direct penetration of rain water through solid
Ridout Associates: walls, particularly those facing prevailing winds Secondary measures
Tel No. 01562 885135 • Leaking drains and internal plumbing These consist of determining the full extent of the
Fax No. 01562 885312 • Incorrect external levels outbreak and a combination of:
www.ridoutassociates.co.uk
Fungal attack is controlled by two sets of measures, • Removing all decayed timbers.
primary and secondary. • Treating of walls to contain fungi within the wall
Fungal attack covers wet rot and dry rot. Wood (only applicable to dry rot).
rotting fungi can be divided into two categories Areas that have not been inspected should • Treating of sound timbers with preservative on a
according to their effects on the wood. These are: be clearly identified to enable a subsequent localised basis where required.
inspection to be carried out when the structure has • Using preservative-treated replacement timbers
• Brown rot – causes the wood to become darker been fully exposed. This could include rafter feet (pre-treated).
Technical Manual V8: TS-11A-8.00-010117
in colour and crack along and across the and wall plates that are particularly prone to rot. • Introducing support measures, such as isolating
grain when dry. Badly decayed wood will timbers from walls and the provision of
crumble to dust, and the majority of wet rot and ventilation between timbers and the walls.
dry rot instances fall within this group.
• White rot – the wood becomes lighter in colour, Dry rot commonly occurs when timber is in contact
and cracks along the grain. All white rots are
© LABC Warranty
339
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
Existing concrete floors will be required to meet the 12.1.4.2 External walls An independent lining system should also be
following requirements provided where party walls between buildings,
Solid walls project above adjacent roof coverings (thus
• That the floor has a suitable damp proof To provide an acceptable level of protection becoming external walls)
membrane, where this cannot be confirmed against the ingress of rain water, any retained solid
a new DPM should be installed. A liquid masonry external walls should either: Where damage has occurred to walls, the cause
applied membrane to the surface of the needs to be investigated.
concrete would be suitable in most cases • Be fully lined internally with an independent
subject to the liquid membrane having timber or metal stud wall. Likely reasons for the damage include:
appropriate third party certification. • Be clad externally with a rain screen or other
• That the floor is free of any structural distress or protective measure. • Ground movement – foundation failure,
movement. Where there are signs of movement, • Comply with the requirements of BS 5628 settlement, subsidence, chemical attack.
the floor should be replaced unless it can be (as outlined below). • Thermal movement – thermal expansion of wall
proved by a Chartered Structural Engineer that due to temperature changes.
the floor is suitable for carrying imposed loads • Roof spread – pitched roofs not properly tied,
and supporting its own weight without any spreading at eaves.
further movement or cracking • External and internal walls not bonded together.
• Wall tie corrosion.
12.1.4 Superstructure • Lintels inadequate over openings.
• Sulphate attack – water-soluble sulphates
12.1.4.1 Structural repairs attack cement-based mortar, normally in a wet
Technical Manual V8: TS-11A-8.00-010117
Prior to undertaking structural repairs, it is essential environment, i.e. below ground level and
that the root cause of the structural defect parapet walls.
has been remedied by underpinning, addition • Frost attack.
of adequate lateral restraint, buttressing, etc. • Bonding timbers present and subject to rot
Strengthening works to the structure may also be and shrinkage.
necessary to accommodate increased or modified
© LABC Warranty
Claddings If the above situations cannot be satisfied, a new Thermal insulation of walls and claddings
external cladding or render system will need to be Various methods exist to upgrade the thermal
Weather resistance of walls and cladding installed. insulation of existing walls and floors. Regardless
Existing solid brick or stone walls are unlikely to of the methods adopted, it is essential that risks
be acceptable as weather-resisting, although Internal treatments associated with increased thermal insulation are
consideration of the exposure category of the An alternative to preventing moisture penetration minimised, including:
building and porosity of the masonry will be given, by using externally applied claddings and renders
i.e. do existing non-gypsum-based internal linings is to adopt internally applied methods. • Surface condensation caused by improvements
allow for greater insulation and evaporation than to draught proofing of the building.
gypsum plasters alone? It is anticipated that in all Systems are available that are installed on • Interstitial condensation caused by moisture-
buildings, at least one of the additional treatments the inside of existing walls to prevent moisture laden air passing from the dwelling to within the
noted below will be required, and this must include penetration reaching the internal accommodation. fabric of the structure and condensing on
appropriate insulation. These include: cooler surfaces.
• Increased risk of damp penetration caused by
However, all solid masonry wall situations will • Independent metal or timber framed systems: the filling of cavities with insulation
require a Specialist’s report to identify the extent of these should not be fixed to the existing • Maintaining the robustness of the external and
any necessary remedial treatment. masonry walls, but fixed at the ‘head and internal wall surfaces by the provision of
base’ to avoid direct contact. Ventilation should adequate mechanical protection over
External treatments be provided to avoid a build-up of insulation materials, e.g. externally applied
Existing claddings can be retained if it can be condensation between the masonry and the insulation systems with render coat mechanical
shown that: inner lining system. protection.
Technical Manual V8: TS-11A-8.00-010117
• New internal walls: these would normally be • Avoidance of cold bridges around openings
• The system is maintaining the integrity of formed in blockwork, must be adequately and where structural elements extend through
the building. founded and, where necessary, tied to the the thickness of the building envelope.
• It is adequately fixed and the expected life span retained and new elements of structure. • Repeating thermal bridging must be
of the fixings, where appropriate, is in excess of considered, e.g. internal metal-framed walls
15 years. Control of damp penetration
© LABC Warranty
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
Render application finishes plasters usually incorporate adhesives to increase Cracking in masonry walls
resistance to the passage of hygroscopic salts from Minor cracking can be defined as cracking
Plaster for conversions / refurbishment the wall into the plaster. They should not, however, that occurs in the mortar joints and which does
Where the condition and bond of the existing act as a vapour barrier. Gypsum plaster should not not extend through the masonry components.
plaster can be shown to be adequate, it can be used in conjunction with chemically injected Providing that the crack is no wider than 4mm, and
remain, with the exception of the following: DPC. there has been no lateral displacement of the wall,
the wall can be re-pointed.
• Where rising damp is present. The plaster should not bridge the DPC or be in
• Where a chemical DPC is installed. contact with the ground floor slab. Major cracking affects the structural integrity of the
• At the junction of external walls and party walls wall, and investigation should be undertaken to
to see if they are properly bonded. Final redecoration should not be carried out until find the cause of the problem.
• Above openings to examine the make-up and residual moisture has disappeared. Matt emulsion
condition of lintels. paint is recommended for use during this period. Walls out of plumb/bulging
• Where there is a possibility that bond timbers Where walls are more than 25mm out of plumb
may have decayed. Internally drilled holes concealed by skirting or bulge more than 10mm within a storey height,
• Where the wall is solid and the plaster is boards, etc. should not be plugged. Other visible a Structural Engineer should comment on the
gypsum-based. holes and external holes should be plugged. stability. The wall may need to be rebuilt or
strengthening works undertaken.
Where a chemically injected DPC is installed, it is Rendering for conversion/refurbishment
necessary to remove the plaster one meter above Where the condition and bond of the existing Where it is intended to provide buttressing walls to
the DPC level or 600mm above any apparent salt render can be shown to be adequate, it can support out of plumb and/or bulging walls, they
Technical Manual V8: TS-11A-8.00-010117
line/dampness, whichever is higher. remain, subject to the following exceptions: should be designed by an Engineer.
Re-plastering work should be delayed as long as • If the render bridges the DPC. In raised tie roofs (where no ceiling ties are
possible in order to encourage rapid evaporation • Above door and window openings where it is provided at eaves level), lateral spread of the
of residual moisture, and the building should be necessary to examine the type and condition of brickwork just below eaves level may have
well ventilated during the drying period.
© LABC Warranty
exposed when undertaking a conversion and if Where movement has occurred and the timber Bulging of the external leaf could also indicate that
the bond is inadequate, a suitable stitching detail lintel is inadequate, the lintel should be replaced the ties have failed.
incorporated. Design by a Chartered Structural with either a concrete or steel lintel.
Engineer may be required. Where there is wall tie corrosion or inadequate
Where cracking has occurred in masonry ties, a specialist company should be employed
to provide a report that includes measures to
© LABC Warranty
343
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
Where wall ties have corroded to an extent The fire performance of the façade, particularly Existing studwork
serious enough to threaten the stability of the with respect to external firespread and ensuring Many properties built before 1880 have trussed
wall or building, a Structural Engineer should be cavity barriers are correctly installed in line with internal partitions, usually located approximately
appointed to determine the necessary remedial current Building Regulations. halfway back in the depth of the property. Often,
works. these walls are load-bearing, continue up through
No fines construction and the building and carry floor and roof loads onto
Insulation to cavity walls other non traditional methods the foundations.
Most cavity walls constructed after 1985 should It is essential that any “no fines” construction is
already be insulated, however where a cavity wall correctly assessed and tested to determine the If a timber partition is load-bearing, providing it is
is required to be thermally upgraded, it should be durability and integrity of the structure. adequate, the loads are not being increased and
lined internally. The injection of cavity wall insulation the timber is free from rot and insect infestation,
is not acceptable as the overall condition of the 12.1.4.3 Internal walls it can remain. Where there are defects, i.e. the
cavity is not known. floor sags on the line of the partition and there
Existing masonry is distortion of door heads, then additional
Timber Framed walls Where a wall is adequately founded or supported strengthening works should be undertaken.
Timber framed elements must be structurally on a beam that shows no signs of distress, it can
durable and free from rot. remain providing there is no increase in load onto New door openings cut into an existing trussed
the wall. Any increase in load should be justified partition should be overseen by a qualified
The timber frame must be assessed as part of any by calculation. However, masonry supported on Structural Engineer, as this can adversely affect the
timber survey as described in section 12.1.3.4 of timber beams should be avoided. triangulation of the truss.
this chapter. Particular attention should be given to
Technical Manual V8: TS-11A-8.00-010117
sole plates and timber framed elements that are In older properties, it is possible that flitch beams
close to the ground. and Bessemer’s may be supporting masonry walls,
and these should be examined by an appropriate
Curtain Walling expert to ascertain their capability to carry the
Curtain walling must be assessed by a cladding load.
and façade specialist to determine the following:
© LABC Warranty
12.1.4.4 Timber floors above ground level 12.1.4.5 Other framed buildings Where the intention is to increase the load on the
Existing timber floor joists can be retained within Where the scheme involves converting a concrete existing structure, e.g. by the introduction of an
the building, providing they are adequate for their or steel-framed building into dwellings, the following additional floor, then structural calculations should
purpose. guidance is given. be provided to prove the adequacy of the building
and foundations.
The following points should be considered: An appraisal of the existing building should be
carried out by an experienced and qualified Concrete-framed buildings
• Joists are of sufficient size for the span. Structural Engineer, taking into account the Where the building is of concrete construction,
• Load on the floor is not being increased. proposals for the change of use. additional reports are needed for:
• Joists have not been weakened by excessive
notching and/or drilling. This will include: • Carbonation
• Ends of joists are free from rot. • Chlorination
• All timbers to be treated for insect infestation • Condition of the structural frame, including joints.
and wood rot. • Proposals to increase loadings on the structure The two major causes of corrosion in concrete
• No masonry walls are built off timber joists. and foundations. are carbonation, in association with inadequate
• Appropriate strutting is provided. • Alterations to existing load paths. depth of cover to the reinforcement, and chlorine
• Alterations to stability systems. penetration, due to the de-icing salts and
Alterations to existing openings • Changes in environmental exposure. admixtures used to accelerate the setting and
Where existing openings are to be filled with • Recommendations to cover additional reports hardening of concrete in temperatures at or below
masonry, the new work should be adequately and testing by Specialists. freezing point.
bonded to the existing and the weather resistance
Technical Manual V8: TS-11A-8.00-010117
of the wall maintained. However, if a party wall it The floor loads on the building may decrease, Carbonation involves a reaction of carbon dioxide
should comply with the requirements for sound as they will now be for domestic use only where in the air with the free lime present in the concrete.
insulation. previously they were, for example, offices. Over a period of time, this reduces the pH level of
the concrete.
A statement from a qualified Structural Engineer
© LABC Warranty
confirming, where appropriate, that the existing With a reduction in the alkalinity, and the presence
foundation design is acceptable for the new loads of both water and oxygen, corrosion of the
subject to the building showing no signs of distress, embedded steel will occur.
i.e. movement, cracking, etc., will be acceptable in
such circumstances. 345
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
Visual surveys on concrete structures are a starting High alumina cement concrete (HACC) If any one of these factors is absent then the ASR
point to gather information. However, care should Where HACC has been used in a building, and cannot take place. Once cracking occurs, the
be taken, as although the concrete structure the intentions are to keep the existing structure, structure can deteriorate further as water entering
may not show any obvious signs, corrosion of the consideration should be given to: the cracks generates reinforcement corrosion and
reinforcement may be occurring. this, in conjunction with the freeze/thaw cycle, can
• The structure being free from obvious signs result in additional cracking and so on.
It is important that a second-stage survey of deterioration.
incorporates the following: • The building being weather tight. Affected concrete often exhibits surface cracking
• Structural calculations being provided to show in the pattern of a star, and heavily loaded sections
• Chemical tests on the concrete structure to that the floors and roof can solely carry the may exhibit cracks along the line of the main
ascertain if corrosion of the steelwork is loads imposed on them. reinforcement.
occurring or likely to occur.
• Depth of carbonation can be assessed either Alkali silica reaction (ASR) Defects in structures attributable to the
on-site or in the laboratory, and the depth of the The ASR occurs when the strongly alkaline cement performance of concrete are relatively rare in
reinforcement measured. This allows areas of risk begins to dissolve susceptible sand and aggregate the UK. Increased awareness of ASR, and the
to be identified. within the concrete itself. The chemical reaction publication of guidance on avoidance, has
• Chloride ion content can be determined by creates a gel material that absorbs water, expands reduced the risk of problems in new buildings to
analysis of a drilled dust sample taken from the and in turn creates tremendous pressures in the very small proportions.
concrete. pores of the concrete surface and subsequent
cracking. For a damaging reaction to occur, the Consequently, on any refurbishment project
Where concrete repairs are necessary, they should following need to be present in sufficient quantities: where the existing structure is concrete-frame,
Technical Manual V8: TS-11A-8.00-010117
be carried out by a Specialist Contractor. the Warranty Surveyor will request copies of the
• High alkali cement or a high cement content; following to identify the presence or otherwise
it may also arise from salt contamination during of ASR:
batching/mixing.
• Reactive aggregate – siliceous materials such • Desk studies undertaken to identify materials
© LABC Warranty
If ASR is identified, the following possible remedial ascertain if the structural frame is adequate for the Bimetallic corrosion
works will need to be assessed by the project’s proposed loads. This should be considered in the existing and
Design Engineer, and the details put to Warranty proposed structure.
Surveyors for consideration: Where steelwork has corroded, further analysis
must be sought to determine if any expansion of Bimetallic corrosion occurs where two different
• Critical examination of the robustness of the the frame will/has occurred. In such scenarios metals are in electrical contact and are bridged
reinforcement. cathodic protection may need to be considered. by water or water containing other chemicals to
• Measures to the amount of water available to form an electrolyte. A current passes through the
the structure – any weather proofing or Exterior steelwork: should be inspected; where solution from the base metal to the noble metal
cladding should not impair the ability of the corrosion is visible, the steel can be grit blasted, and, as a consequence, the noble metal remains
structure to dry naturally. cleaned and recoated. protected and the base metal suffers increased
• Limited strengthening of the structure. corrosion.
• Partial or full demolition, followed by rebuilding. Perimeter steelwork: in direct contact with
the outer leaf of the building can be prone Where there is a possibility of this occurring, or if it
Furthermore, any alterations to the waterproof to corrosion, particularly in older properties. A has already occurred, advice should be taken from
envelope will need to be considered to ensure sign indicating that this has happened is the a Specialist on how to deal with it.
that the concrete elements are not exposed to displacement of the external masonry due to the
additional sources of moisture. expansion of the steelwork caused by corrosion.
During the conversion process, the appropriate
Steel-framed buildings repairs/replacement should be carried out.
In addition to any structural reports, a visual
Technical Manual V8: TS-11A-8.00-010117
inspection of the steel frame should be carried Interior steelwork: normally, corrosion of
out to assess the extent of any corrosion of the unprotected steelwork within the interior of
framework. a building is low, with only superficial rusting.
Providing that a visual inspection confirms this,
Where corrosion is present, accurate and the environment intends to remain dry, no
measurements can be made using an ultrasonic
© LABC Warranty
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
Cast iron, wrought iron and mild steel structures 12.1.4.6 Filler joist floors 12.1.5 Timber roofs
Many older buildings that are converted into Many buildings of the late Victorian and Edwardian
dwellings, e.g. warehouses, cotton mills, etc., were periods were built with floors constructed of Surveying roof timbers
built using cast iron, wrought iron or mild steel. clinker concrete supported by embedded iron All roof timbers should be surveyed by a Specialist,
or steel joists. The concrete produced with clinker and any necessary treatment carried out.
When the intention is to keep the existing structural aggregate was porous, and therefore provided Particular attention should be given to rafter feet,
elements, an appraisal of the existing building is poor corrosive protection to the metal. wall plates and valley timbers, as these often show
necessary. signs of rot.
The clinker also contains particles of un-burnt
In addition to this, the Engineer should comment or partially burnt coke or coal, which contain Roof structure
on the following: substantial proportions of sulphur. As the concrete It is essential that the roof structure has adequate
is porous, the sulphur oxidises to form sulphur strength, stiffness and dimensional accuracy
• Determine the age of the building and the dioxide (SO2), and if moisture is present, this then appropriate for the new roof covering. All
materials used. forms sulphuric acid (H2SO4). Where floors have strengthening work should be designed by a
• Assess how its construction has fared. been subject to the weather for any length of time, Structural Engineer.
• Justify the loadings by calculation. severe corrosion of the embedded iron or steelwork
• Identify areas where additional testing is likely to have occurred. Common problems encountered include:
and/or opening up is necessary.
When considering a conversion in a building with • Excessive spans of rafters, purlins, binder and
If the proposed loads remain unchanged or filler joist floors, it is important to first investigate ceiling joists.
are reduced, as will probably be the case, and whether the floors have been subject to damp • Inadequate ties between rafters and ceiling ties.
Technical Manual V8: TS-11A-8.00-010117
it can be shown that the existing structure has conditions and whether any significant corrosion • Insufficient number of collar ties at purlin level.
not suffered any deterioration due to corrosion or has taken place. • Decay of rafter feet and valley beams.
deflection of structural members, etc., the building • Settlement of purlin supports.
may only require localised structural alterations. Particular attention should also be paid to ensuring • Lateral spread of raised-tie roofs.
Where the intention is to increase loads, carry out that the floor remains dry during the conversion,
major structural alterations or the existing building
© LABC Warranty
Roof coverings Continuous membrane roofs and balconies 12.1.6 Windows and Doors
Membrane roofs and balconies should be r Where windows and doors are replaced they
Traditional slate and tiled roofs e-covered in accordance with chapters 7.6, 7.10 should be replaced in accordance with 7.4 of this
Roofs should generally be re-covered in and 7.11 of this manual unless the following manual.
accordance with chapter 7.9 of this manual, where provisions can be met.
roofs are to be re-covered it is required that existing Any retained windows and doors must meet the
gable walls are appropriately supported during the • That the existing membrane is less than five following provisions
construction works and lateral restraint straps are years old and is tested for leaks (testing
fitted to any gable walls. guidance can be found in chapter 7.10) • Should be no more than 15 years old
• There are no signs of excessive ponding • Be in good condition and free from any
There may be exceptional circumstances where an • The roof has a fall, adequate upstands and damage rot or decay
existing tiled roof covering can be retained; however suitable drainage outlets • Be able to perform as part of the waterproof
the following requirements would apply namely; • That balconies are fitted with overflows envelope
• That any thermal upgrade via inverted • Provide adequate ventilation where the building
• That the tiled roof shows no sign of deterioration insulation does not compromise roof drainage ventilation system relies on purge ventilation
that suggests that the roof covering has past its or upstands. • That window mechanisms and catches operate
useful life. correctly.
• That the roof has felt beneath the tiles which is
functioning correctly and not damaged
• That ridges and hips are well bedded and
mortar has not eroded, (please note it maybe
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 12
FUNCTIONAL REQUIREMENTS
12.2 NEW ELEMENTS CONNECTING TO EXISTING STRUCTURES ii. There should be a Party Wall Agreement in accordance with the Party
Wall Etc… Act (please note that this requirement will be relevant where
Workmanship the applicant is not the owner of the adjoining property).
i. All workmanship must be within the tolerances defined in chapter 1 iii. The separating wall between the new and existing building must meet
of this Manual. the relevant requirements of the Building Regulations.
ii. All work is to be carried out by a technically competent person in iv. The existing foundations and wall structure must be suitable to support
a workmanlike manner. any proposed increased loading resulting from the construction of the
new dwelling.
Materials v. The junction of the new walls to the existing walls must ensure that
i. All materials should be stored correctly in a manner that will not cause dampness cannot track back into the new home or the existing home.
damage or deterioration of the product. vi. An effective damp proof course should be present in the existing wall,
ii. All materials, products and building systems shall be appropriate and linked to the new damp proof course and damp proof membrane of
suitable for their intended purpose. the new home.
iii. The structure shall, unless specifically agreed otherwise with the vii. At the junction of the existing and new structures, detailing should
Warranty provider, have a life of not less than 60 years. Individual allow for differential movement without cracking. Any settlement
components and assemblies, not integral to the structure, may have a should be limited to 2mm–3mm, which would not normally adversely
lesser durability, but not in any circumstances less than 15 years. affect the roof covering.
iv. Whilst there is and can be no Policy responsibility and/ or liability viii. The materials used for construction must meet the relevant regional
Technical Manual V6: TS-011a-6.00-010413
for a roof covering, window and/ or door performance life of 60 years Building Regulations
Technical Manual V8: TS-11A-8.00-010117
design intent and demonstrate a satisfactory level of performance. any policy liability for any remedial works carried out by the contractor
or otherwise, nor to any materials used in those remedial works.
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
12.2.1 Introduction 12.2.3 Separating walls The existing wall should also be appraised to
A number of residential developments are The separating wall between the new and existing determine whether it is structurally stable and
attached to existing buildings, and the existing building must meet the relevant requirements of suitable to support additional loadings.
elements that form part of the new structure must the Building Regulations.
meet the Functional Requirements of the Warranty. 12.2.5 New wall junctions
The details below give some guidance on the Confirmation should be provided where the The junction of the new walls to the existing walls
minimum information and standards required to existing wall is to be upgraded to meet current must ensure that dampness cannot track back into
meet the Functional Requirements. Building Regulations, particularly in meeting the the new home or the existing home.
relevant sound insulation and fire separation
12.2.2 Party Wall Agreement requirements. The structural integrity of the existing The detailing of this junction is critical to ensure
There should be a Party Wall Agreement in wall and its resistance to ground moisture should that moisture ingress does not occur between the
accordance with the Party Wall Act (please also meet current standards. new and existing walls. Typical acceptable details
note that this requirement will be relevant where are indicated in Figure 8 and Figure 9.
the applicant is not the owner of the adjoining 12.2.4 Existing foundations
property). The existing foundations and wall structure must
be suitable to support any proposed increased
It is highly likely that improvements to an existing loading resulting from the construction of the new
wall are necessary to meet the requirements of dwelling.
the Warranty. This may include underpinning,
injected DPC and internal linings. A signed Party Foundations to the existing wall should be exposed
Wall Agreement provides evidence that the and assessed for suitability to support additional
Technical Manual V8: TS-11A-8.00-010117
adjacent building owner consents to any potential loadings. It is important to protect existing
alterations. foundations at all times, and care must be taken
not to ‘undermine’ existing foundations when
Further guidance on the Party Wall Act can be clearing the site or reducing levels.
found on the Planning Portal website
www.planningportal.gov.uk
© LABC Warranty
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
12.2.6 Damp proof course (DPC) In order to prevent excessive differential movement,
An effective DPC should be present in the existing the new dwelling should have the same
wall, linked to the new DPC and Damp Proof foundation type as the existing dwelling. Where the
Membrane (DPM) of the new home. foundation types are different, e.g. new dwelling
pile and beam, existing dwelling traditional strip
Acceptable existing DPCs are considered as: foundation, the new dwelling should be completely
independent of the existing dwelling.
• A continuous felt or proprietary DPC material.
• A chemically injected DPC supported by an
insurance-backed guarantee.
• A slate DPC is considered acceptable if the
existing wall incorporates an independent wall
lining system to the inner face of the new
dwelling.
Workmanship Design
i. All workmanship is to be completed by a technically competent i. The design and specifications should give clear indication of the
person in a workmanlike manner. design intent and demonstrate a satisfactory level of performance
ii. Any new work must meet the tolerances defined in chapter 1 of this with regards the renovation of components and the interaction of new
Manual. Tolerances will not apply to existing finishes that have not elements.
been upgraded or altered, or where the supporting elements will not ii. Specialist reports are required to confirm that existing elements will
allow for the tolerances to be met. have an adequate level of structural stability, as defined in the
materials section above, the reports must confirm the adequacy of the
Materials existing ‘waterproof envelope’.
i All new materials should be stored correctly in a manner that will not
cause damage or deterioration of the product. Limitations of Functional Requirements
Technical Manual V6: TS-011a-6.00-010413
ii. Materials, products and building systems shall be appropriate and i. The Functional Requirements are limited by the recommendations
suitable for their intended purpose. applied to the specific areas covered in this chapter.
iii. The structure, regardless of whether it is a new or existing element, iv. These Functional Requirements do not and will not apply to create
shall, unless specifically agreed otherwise with the Warranty provider, any policy liability for any remedial works carried out by the contractor
have a life of not less than 60 years. Individual components and or otherwise, nor to any materials used in those remedial works.
assemblies, not integral to the structure, may have a lesser durability,
Technical Manual V8: TS-11A-8.00-010117
353
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
12.3.1 Introduction The Warranty Surveyor will always undertake an Elements of the retained structure and proposed
This section relates to buildings that have Historic initial assessment of the existing fabric to ascertain works should not be considered in isolation, as
or Conservation Planning restrictions, where due in general terms if the proposal is capable of a solution for one problem may cause issues
to such restrictions it is not possible or feasible to representing a standard risk to the Underwriter. If elsewhere. Past performance is no guarantee of
upgrade the building. The guidance in this section deemed acceptable, the development is then ongoing adequate performance because different
is applicable to those elements that cannot be subject to a technical audit process during expectations and changing living conditions can
improved are altered, In all cases there are some construction, and the following guidance is all impact on both the actual and perceived
types of construction that will not be suitable for intended to assist all parties in ensuring the performance of a converted/refurbished structure.
warranty cover these are as follows; relevant requirements are met, as well as providing
an element of consistency in approach. It is not possible to cover every building type within
• Cob Construction this chapter; therefore, the guidance is general, and
• Through Wall oak / timber frame Depending on the condition of the original certainly will not apply in every scenario. It is strongly
• Wattle & Daub building; an expert survey may be required for the recommended that early discussions are held to
different elements of the building as described in determine exact requirements and to enable a full
The following guidance has been formulated to the following sections of this chapter. If the survey review of the proposed strategy and development.
assist both Warranty Surveyors and Developers concludes that any of these elements are unable
on projects involving either the conversion or to meet the life expectancy of 60 years for structure Where new work is proposed, it should follow the
refurbishment of existing buildings. and 15 years for non-structural elements, they guidance for those elements in this Technical
should be systematically replaced or repaired. Manual. Where new work is applied to, or meets,
Conversions and refurbishments are projects that existing elements, consideration on how these
involve work to existing buildings or parts of existing Existing buildings and structures can present areas will interact must be made; for example, new
Technical Manual V8: TS-11A-8.00-010117
buildings. This could include the conversion of particular problems both initially and on an cavity masonry that abuts an existing solid wall
industrial or commercial buildings into housing; the ongoing basis. Therefore, it is essential that construction.
conversion of an existing residential building into thorough and comprehensive survey work is
flats; an additional storey to an existing building; undertaken prior to new works commencing to Please note that the requirements of the technical
the refurbishment of an existing residential building; understand both the current condition of any audit are quite different from those undertaken for
or a façade retention project. the purposes of compliance with Building Control
© LABC Warranty
12.3.2 Retained elements, foundations by a member of the Property Care Association, Weather resistance of walls, including claddings,
and load-bearing structures the guarantees must cover workmanship and render, re-pointing, etc.
(including floors, walls and roofs) materials. The construction of any existing ground The remedial works for the external walls must have
floor will need to be assessed, and details provided regard for the exposure rating provided in BS 5628.
Planning Restrictions to the Warranty Surveyor for consideration. Any retained cladding system must be surveyed
Where building renovation or thermal upgrade to determine a minimum 15 year life expectancy.
is limited by planning restrictions, a copy of the Timber treatment against insect Provision of additional thermal insulation must also
planning permission and supporting conditions and fungal attack be considered.
must be provided. All retained timbers will need to be assessed,
logged and the remedial treatment noted. External doors and windows
The Structure Timbers that are embedded should be exposed A condition survey should be provided by an
Any areas of cracking or suspected movement are or removed and replaced with masonry. Where independent, competent and appropriately
to be assessed and remedial measures provided this is not possible, core samples should be taken qualified Surveyor or Specialist to confirm life
by an appropriately qualified and experienced to assess the moisture content, and remedial expectancy of 15 years.
Structural Engineer. Any additional loads must works considered. Any remedial treatment must
be catered for. Consideration of the impact of be provided with a 10 year insurance-backed Sound testing
any landscaping and drainage works is required. guarantee and undertaken by a member of the Party walls and party floors should be sound tested
Spalling masonry can be locally repaired, with units Property Care Association, where guarantees must in accordance with National Building Regulations
cut out and replaced, or re-used with sound face cover workmanship and materials. to determine compliance, access maybe required
showing. Larger areas will require a schedule of into adjacent buildings in order that sound testing
repair to be submitted and agreed. Roof coverings is completed. Where Planning restrictions do
Technical Manual V8: TS-11A-8.00-010117
Coverings and support systems should be not permit upgrading of internal walls for sound
Damp proof course’s (DPC) and membranes replaced unless a specialist report compiled by purposes, the declaration of sound test results in
All walls, floors and basements should include an independent, competent and appropriately accordance with current Building Regulations must
a DPC. Ground levels and ventilation should be experienced Chartered Building Surveyor be provided at completion.
checked before any remedial DPC treatments concludes that the system can provide a life
are considered. However, where remedial
© LABC Warranty
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
no report is necessary. of this manual for further guidance. The guidance in chapter 12.1.3.5 applies to this
section.
Where there is not a requirement under
Building Regulations to upgrade a basement 12.3.4 Superstructure
from a waterproofing perspective (i.e. certain
12.3.4.1 Structural repairs
© LABC Warranty
Strengthening works to the structure may also be - Parapets 12.3.4.3 Internal walls
necessary to accommodate increased or modified - Roof/wall abutments The requirements to chapter 12.1.4.3 apply to this
loads. - Penetrations and openings section
- Stone feature-work
12.3.4.2 External walls - Window and door reveals 12.3.4.4 Timber floors above ground level
- Rain water outlets and rain water pipes. The requirements in chapter 12.1.4.4 apply to this
Solid walls section.
Where walls cannot be upgraded in accordance The following information should accompany the
with chapter 12.1.4.2 and where the existing building survey 12.3.4.5 Other framed buildings
thickness of the external wall does not meet the The requirements in chapter 12.1.4.5 apply to this
required exposure rating in BS 5628, a full survey of • A scope of works clearly identifying any section.
the wall will be required by a Chartered Building remedial measures
Surveyor with proven experience in historic • Details of any ongoing maintenance 12.3.4.6 Filler joist floors
and listed buildings (RICS Accredited Building requirements for the walls The requirements in chapter 12.1.4.6 apply to this
Conservation Surveyor or equivalent). The report • Confirmation of the level of supervision during section.
should not only identify the potential issues or the remediation process
defects but also provide solutions to ensure that 12.3.5 Timber roofs
the external walls remain durable. It should be noted that although the external
walls may be proven as acceptable without Surveying roof timbers
The report should include the following information; independent internal lining systems, particular All roof timbers should be surveyed by a Specialist,
attention should be given to window and and any necessary treatment carried out.
Technical Manual V8: TS-11A-8.00-010117
• Overall condition of the exiting external walls door reveals and it is likely that in all cases an Particular attention should be given to rafter feet,
• The quality of existing mortar independent lining will be necessary to window wall plates and valley timbers, as these often show
• The quality of existing masonry with respect to heads, cills and reveals. Consideration can be signs of rot.
the durability of bricks/stone/render. given where the reveals are already lined such as
• Potential high risk areas or areas of concern oak panelling adjacent to existing sash windows
where there is potential for future water ingress
© LABC Warranty
357
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
Roof structure There may be exceptional circumstances where an • There are no signs of excessive ponding
It is essential that the roof structure has adequate existing tiled roof covering can be retained; however • The roof has a fall, adequate upstands and
strength, stiffness and dimensional accuracy the following requirements would apply namely; suitable drainage outlets
appropriate for the new roof covering. All • That balconies are fitted with overflows
strengthening work should be designed by a • That the tiled roof shows no sign of deterioration • That any thermal upgrade via inverted
Structural Engineer. that suggests that the roof covering has past its insulation does not compromise roof drainage
useful life. or upstands.
Common problems encountered include: • That the roof has felt beneath the tiles which is
functioning correctly and not damaged 12.3.6 Windows and doors
• Excessive spans of rafters, purlins, binder and • That ridges and hips are well bedded and Where windows and doors do not meet the
ceiling joists. mortar has not eroded, (please note it maybe guidance in chapter 12.1.6 the following
• Inadequate ties between rafters and ceiling ties. reasonable in some circumstances that ridges information must be provided to determine
• Insufficient number of collar ties at purlin level. and hips are re-fitted, mechanical fixing should adequacy of performance.
• Decay of rafter feet and valley beams. also be provided in such circumstances).
• Settlement of purlin supports. • That timber laths and nails are in good • A full survey of the windows and doors by
• Lateral spread of raised-tie roofs. condition and fit for purpose. a suitable specialist to determine the current
• That existing flashings and weathering’s are condition and the windows and door ability to
Roof coverings assessed, particular attention should be given be resistant against water ingress for 15 years
to valleys and parapets, if there is any doubt of • Where windows are to be repaired, a full repair
Traditional slate and tiled roofs the condition of any weathering’s, they should schedule must be provided detailing the extent
Where roofs cannot be recovered or meet the be replaced. of the repairs.
Technical Manual V8: TS-11A-8.00-010117
requirements of chapter 12.1.5, a specialist survey • Full details if the window repair specialist to be
is required to determine durability against future Continuous membrane roofs and balconies provided, the repair specialist must demonstrate
water ingress and failure of components. Roofs Membrane roofs and balconies should be that they have suitable experience for the
should generally be re-covered in accordance re-covered in accordance with chapters 7.6, specialist repairs of windows and doors.
with chapter 7.9 of this manual. Where roofs are 7.10 and 7.11 of this manual unless the following • Where the window and door system includes
to be re-covered, it is required that existing gable
© LABC Warranty
CONTENTS
13.1 DEVELOPMENTS WITHIN COASTAL LOCATIONS
Technical Manual V8: TS-11A-8.00-010117
© LABC Warranty
359
CHAPTER 13
FUNCTIONAL REQUIREMENTS
ii. For developments that are between 500m to 5km from the coastal
shoreline; structures and protective coatings/claddings and detailing
should be scrutinised for the potential enhanced risk of the effects
of corrosion and reduced durability. The design team must provide a
detailed assessment of the protection and maintenance
arrangements required for a project that falls within these locations
and identify suitably approved materials which are appropriate for use
in the construction.
iii. Structural elements outside the parameters of Regional Approved
Documents must be supported by structural calculations provided by
a suitably qualified expert.
iv. The design and construction must meet the relevant regional Building
Regulations.
Technical Manual V6: TS-011a-6.00-010413
361
CHAPTER 13
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
13.1.1 Coastal location definition 13.1.3 Key risks to construction 13.1.3.3 Durability of materials
For the purposes of this Technical Manual, we are in coastal locations The durability of construction materials used in
considering any building works on; coastal locations must be suitable for the site
13.1.3.1 Wind speed location environment. The effects of corrosion from
• The shoreline and sites within 500m of the Coastal regions particularly in the South West, West wind blown salt spray and higher UV exposure can
shoreline and North Western areas of the UK are at greater significantly reduce the normal expected durability
• Other sites up to 5km Inland from the shoreline risk of exposure to higher wind speeds than inland of a component, in a coastal location, to below
• Sites located in ‘tidal’ estuarine areas where areas. Gust wind speeds in combination with rain the life expectancy required by the Functional
they are within 5km of the general UK coastal can create particular design issues for buildings Requirements within this Technical Manual.
shoreline sited in shoreline locations, particularly for cladding
and roof coverings and their associated fixtures 13.1.3.4 Workmanship
Shoreline means: and fittings. A high number of failures of the building envelope
in coastal environments are directly due to poor
• The foreshore 13.1.3.2 Rain penetration workmanship rather than the failure of the actual
• Land adjacent to the foreshore including in Walls, claddings, external openings including material. Examples of this are;
particular any cliff, bank, barrier, dune beach or windows and doors, construction junctions and
flat which is adjacent to the foreshore roofs exposed to the prevailing wind driven rain • Poor installation of roof tiles or slates due to lack
are vulnerable to rain penetration unless correctly of correct fixings required for the location.
13.1.2 Developments within coastal locations designed and constructed for the conditions of the • Poor fixing of timber claddings resulting in
A coastal location is considered as having an site and orientation of the elevations. The level of splitting and warping of boards leading to wind
aggressive environment particularly with regard to exposure to rain penetration in coastal locations is and water ingress to the inner components of
Technical Manual V8: TS-11A-8.00-010117
environmental corrosion conditions as well as other deemed to be ‘very severe’ (see chapter 7 section the wall construction.
risks (see 13.1.3). 7.1). • Lack of adequate preparation and protective
finishes to external windows.
There are numerous publications providing good • Inadequate provision of correct damp proofing
practice guidance on methods of preventing rain in walls around openings e.g. poorly fitted cavity
© LABC Warranty
Certain materials and particularly the finishes Any wall element exposed to precipitation or
may, due to the environment, require an on-going wind driven moisture, should prevent penetration
maintenance requirement in order to keep a of moisture to the inner surface of any part of a
satisfactory finish, e.g. balcony timber decking. dwelling so as to protect the occupants and to
In these circumstances it will be the building ensure that the building is not damaged.
owner’s responsibility to ensure that regular All external wall constructions in a coastal
maintenance of exposed components and finishes environment must be designed and constructed to
is undertaken to ensure they perform correctly. suit the degree of exposure to wind and rain that it
Maintenance plans will need to be in place during may be subject to BS EN ISO 15927-3: 2009 and BS
the lifetime of the building to ensure premature 8104: 1992 provide a range of methodologies for
failure of coatings or components is avoided. the assessment of wind driven rain on the walls of
Typically dark coloured finishes will fade much a building.
sooner.
An alternative simplified approach is provided
Technical Manual V8: TS-11A-8.00-010117
Debris build up (e.g. wind blown sand) must be within BR 262 ‘Thermal insulation: avoiding the risks’
managed, particularly to balconies. These can This document is based on BS 8104 and provides
lead to leaks and overflowing of blocked outlets a map (see Figure 1) which indicates exposure
which in turn cause damage to other parts of the zones.
structure and concentrate the potential for water
ingress. Bi fold and patio type doors are known
© LABC Warranty
363
CHAPTER 13
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
13.1.4.2 Masonry walls The following should be avoided in very severe • Detailing of all the window, door and roof
The guidance in BS EN 771 for masonry walls of exposures; junctions is provided as part of the design
bricks and/or blocks incorporating damp-proof specification by the render manufacturer.
courses and flashings in very severe exposure • Flush sills,
locations may be adopted. • Inadequate or non existent overhangs 13.1.4.3 Rendering
at verges, External rendering to external masonry walls should
Fair faced masonry cavity walls incorporating • Large expanses of glazing or impermeable conform to the relevant recommendations of BS EN
insulation material within the cavity should only cladding with no effective means to shed run 13914-1:2005.
be constructed as a partial cavity fill using an off water, clear of the masonry below.
insulation material which has a current third party • Areas of rendering abutting masonry with no Render angle beads should be appropriate for
product approval certificate confirming its use for effective seal at the junction to prevent water the environment and allow for any damage to
such conditions. Full fill cavity insulation is not penetration to the rear of the render. coatings when installed. Non corrosive render
permitted. beading e.g. PVC or marine grade stainless steel
Insulated concrete formwork (ICF) structures should be specified. Any other products used must
Masonry walls of natural stone or cast stone blocks ICF structures rely on a suitable external cladding have a current third party product approval stating
should be constructed in accordance with the to provide the water proof envelope. The external they are suitable for the environmental conditions
relevant recommendations of BS EN 771 and to suit cladding, if masonry, should be constructed as proposed.
the degree of exposure. described earlier in this guide. Direct render
applications in a very severe exposure location are Fixings to render angle beads must be suitable to
External masonry walls in severe and very severe not recommended unless the render system has a prevent corrosion occurring.
categories of exposure will benefit from having third party product approval for installation directly
Technical Manual V8: TS-11A-8.00-010117
additional protective features to avoid excessive applied to the ICF in these conditions and; The durability of the rendering will also be
wetting of the masonry. Features such as deep dependent upon the type of background, the type
overhanging eaves, verges and projecting sills • A full design specification for the render of rendering, mix proportions and the method of
should be incorporated into the design. system is provided by the render manufacturer application.
and installed by the manufacturers approved
© LABC Warranty
CHAPTER 13
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
manufacturer must provide a specification for the Whilst traditional renders are applied in several Note: adding additional water repellent which is
render application over these areas to avoid future layers and normally are 20 to 25mm thick to not within the render manufacturer’s specification
cracking. provide a ‘physical waterproofing’; in a very severe into the mix on the worksite should not be carried
location, a detailed specification from the render out, it may even be harmful to pre-prepared render
The choice of render and render carrier boards manufacturer will be required to justify it is suitable systems as it can lead to faults in the finish.
(if used) must be correctly specified and installed. for the proposed conditions and the overall
thickness. 13.1.4.4 External cladding systems including
Wherever possible, whatever the conditions rain screens
of exposure, advantage should be taken of Polymer modified, ready to use factory produced The materials used within the construction
architectural features which protect the rendering. renders contain high quality raw materials and should be capable of withstanding weathering,
Such protective features become more important a range of admixtures (notably water repellents) atmospheric pollution and potential chemical
as conditions become more severe, adequate which reinforce the waterproofing properties of attack for the intended design life.
overhangs and drips will reduce the risk of frost the renders. The thickness of these renders may
damage. vary depending upon the particular application The system must have a current third party product
and guidance should be sought from the render approval confirming the specification is suitable for
With traditional renders the quality of the sands manufacturer. a coastal environment.
used and design mix is critical as is the reliance
on good mixing techniques by the applicator. For these types of renders, a third party product The supplier and designer should provide evidence
Poor mixing ratios and low quality materials is approval certification will be required to identify to satisfy the following;
often the reason traditional renders fail, therefore, the scope of approved use. It should be noted
for projects located in a ‘coastal locations’; only that a number of third party product approval • Evidence of the minimum design life of the
Technical Manual V8: TS-11A-8.00-010117
a pre-blended bagged render system which has bodies have a limitation of 75litres/m² applied, enclosure as a whole for the particular
a third party accreditation such as a BBA or ETA which equates to a ‘severe’ rating only. Therefore in environment location (with maintenance
certification and backed up with a manufacturer’s ‘very severe’ locations any ‘polymer modified’ type considered to allow for components that may
specification, will be accepted. render intended to be used must be supported have a lessor design life but are expected to be
by the render manufacturer’s fully detailed periodically replaced)
© LABC Warranty
specification and should only be applied by the • Confirmation of what routine maintenance,
render manufacturer’s approved contractors. repair and replacement is likely during the
A 10 year insurance backed guarantee will also design life and who will be responsible for this.
be required.
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
• Details to confirm that the potential for Components which are likely to have a shorter External openings in solid wall / ICF structures will
electrolytic corrosion will be avoided within the design life of only a few years and will need to require specific DPC detailing with the use of a
system. be periodically replaced as part of a planned compriband or similar third party approved DPC
• The surfaces of the cladding system should be maintenance programme are; solutions linked to internal vapour control layers to
capable of resisting the action of chemicals prevent water ingress to the internal finishes.
with which it is likely to come into contact • Gun and knife-applied sealants
during its design life. • Site-applied external finishes
Components which should have a design life to The cavity behind a rain screen is deemed to be
meet the relevant Functional Requirements of a moist zone and materials selected must not
the Technical Manual (60 years for components corrode, deteriorate or affect the performance of
forming part of the structure, 15 years for the cavity barrier during its design life.
components not integral to the structure) are;
13.1.4.5 Window and door openings
• Secondary framing and its fixings Reliance on effective weather proofing around
• Panels and their fixings openings must not be placed on mastic
• Thermal-insulating components and materials sealants alone and agreement for solutions
• Vapour barriers should be sought from both Building Control
• Flashings and the Warranty provider prior to installation. A
Figure 2: Traditional cavity wall with a checked rebate detail
• Window sub frames combination of appropriate durable external (insulation value of wall construction to meet relevant standards)
• Door frames sealant and a continuous damp proof course will
Technical Manual V8: TS-11A-8.00-010117
CHAPTER 13
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
13.1.4.6 Window and doors Window and door furniture and fittings must be • The balcony roof waterproof covering must
The choice of windows and doors must be resistant to the effects of the saline environment. be designed to fall away from any external
supported by the manufacturer’s certification to doors opening into the building.
confirm they meet the design weather conditions Where back ground ventilators (trickle vents) are • Drainage outlets must be easily accessible
and be classified and tested in accordance with installed, they must be correctly specified for the and maintainable even if decking / balcony
the following weather performance standards location and should be installed so as not cause floor finishes are applied.
potential damage to render finishes or restrict the • Timber balcony guards require to be
BS 6375-1 Weather tightness ability to open the window / door. constructed from marine grade timbers.
• Fixings used in balcony decking or guarding
Air permeability - BS EN 12207 – Classification & BS 13.1. 5 Balconies must be appropriately specified to prevent
EN 1026 - Test method The following guidance is to be read in addition to the adverse reaction with certain timbers.
guidance found in chapter 7 of this Technical Manual. • Regular maintenance of balcony floors will
Water resistance - BS EN 12208–Classification & BS be required to avoid wind blown sand clogging
EN 1027 - Test method, An adequate step or raised threshold must be up drainage outlets and balcony door seals
provided to avoid the risk of penetrating moisture and tracks.
Wind resistance - BS EN 12210–- Classification & BS created by the high wind driven rain. A minimum of • Balcony steelwork must be adequately
EN 12211 – Test method 75mm difference between the highest point of the protected against the potential for corrosion
balcony roof waterproof surface and the underside (see structural steel 13.1.6)
Site testing for water penetration of the joints of the door sill should be provided, 150mm in all
to windows and doors in accordance with the other situations. See figures 3 & 4 below;
CWCT test methods is recommended to check
Technical Manual V8: TS-11A-8.00-010117
the site workmanship of the building envelope as In very severe exposure locations / elevations:
constructed. See CWCT Technical Note No. 41 for
guidance on site hose testing • A flush fitting balcony floor finish abutting any
door unit in the external wall of the dwelling
In addition to the above, workmanship should must not occur as this could lead to a
follow the recommendations of BS 1186: 2. The
© LABC Warranty
369
CHAPTER 13
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
13.1.6 Corrosion protection and There are several types of corrosion that must be 13.1.6.2 Protective coatings and finishes
protective coatings considered to ensure that the material(s) selected to metals
will not corrode and lead to functional impairment. All metals must have a suitable protective coating
13.1.6.1 Corrosion protection to steelwork to minimise or prevent corrosion during its life
All materials on buildings are subject to wear • Uniform surface corrosion and be selected to comply with the appropriate
during use, this is caused by mechanical, • Electrolytic corrosion standards and with the corrosion category
chemical, electrochemical, thermal, • Crevice corrosion described in the table below.
microbiological and radiation related impacts. • Pitting corrosion
Mechanical reactions lead to wear, chemical and • Stress corrosion The classification of environmental corrosion
electrochemical reactions cause corrosion. • Contact corrosion conditions below has been taken from BS EN ISO
9223 Table 4 and BS EN ISO 12944-4 Table 1. This
The following guidance is to be read in addition Standards provides a verbal description of the corrosion
to the guidance found in chapters 2 and 7 of this categories. Note: to determine the corrosion rates
Technical Manual. • ISO 8044 -Corrosion of metals and alloys — for aluminium, copper, steel and zinc, please refer
Basic terms and definitions to the standards listed above.
Corrosion is defined as the physical interaction • ISO 9223, Corrosion of metals and alloys —
between a metal and its environment which results Corrosivity of atmospheres — Classification
in changes to the metals properties, and which • ISO 9224, Corrosion of metals and alloys —
may lead to significant functional impairment of Corrosivity of atmospheres — Guiding values for
the metal, the environment, or the technical system the corrosivity categories
of which they form part of (BS EN ISO 8044) • ISO 12944-2:, Paints and varnishes — Corrosion
Technical Manual V8: TS-11A-8.00-010117
consider the building, its location, the surrounding Note: The CWCT Technical Note 24 provides
environment, the atmosphere and climatic guidance on corrosion and corrosion protection
conditions. to cladding.
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
Table 1: Reproduced from BS EN ISO 9223 Table 4 and BS EN ISO 12944-4 Table 1.
• Steel used on sites with an atmospheric corrosivity of C4 or C5 to BS EN ISO 12944, including sites within 500m from a coastal shoreline, should be galvanised to a rate of 710 g/m2.
• Decorative finishes must be compatible with the protective coat specification. Refer to BS EN 12944 ‘paints and varnishes: corrosion protection of steel structures by protective paint systems’ and the
manufacturers recommendations.
• Any section of previously galvanised or other protected steel which is then cut or drilled must be provided with appropriate remediation to the exposed parts of steel to ensure adequate corrosion
protection is maintained.
• The designer should specify the protective coating system where any steelwork is to be welded.
• Surface preparation should be to BS EN 12944-4.
© LABC Warranty
• Steel lintels used in both leaves of an external wall should be austenitic stainless steel, and in addition, protected by a separate damp proof system / cavity tray (as described in chapter 7).
• The use of Intumescent paint to achieve fire protection should be compatible with any corrosion protective coating applied. The manufacturer’s guidance should be followed.
371
CHAPTER 13
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
CHAPTER 13: DEVELOPMENTS WITHIN COASTAL LOCATIONS
then a minimum 15 year service life will be required. as well as the potential for wind uplift and
Otherwise, 60 years service life is required, if forming movement in a cladding system during
part of the structure. severe wind conditions, particularly over
party wall positions.
Due to the environment, certain materials and II) The designer should ensure capillary
particularly the finishes may require on-going
© LABC Warranty
MD Insurance Services Ltd. is the scheme administrator for LABC Warranty and is authorised and regulated by the Financial Conduct Authority. Registered in England No: 3642459.