Itp - 002 - Duct Installation - Ifr
Itp - 002 - Duct Installation - Ifr
Owner :
Consultant :
Sub Contractor :
Consortium PP-Wärtsilä
DOCUMENT NO :
BKN2-PP-ITP-002
PURPOSE :
1.7 Welding Map & NDE Plan Review Engineering spec N/A H (R)H R
2 Material Reception
2.1 Material inspection Review Packing list VC & MT H (W)H R
Check Visual and
2.2 Review Drawing spec VC & MT H (W)H R
dimension
Check Material
2.3 Review Packing list VC & MT H (W)H R
identification
Check Material
2.4 Review Packing list VC & MT H (W)H R
mechanical ducting
Check duct
elevation,alignment for
3.6 duct flanges (release for Visual Eng drawing Checklist H (W)H R
installation of steel
bellows)
Check installation of
ruptur disc (check gasket
3.7 Visual Eng drawing Checklist H (W)H R
installation & bolts
tightening)
Insulation ring installation
3.8 Visual Eng drawing Checklist H (W)H R
(Release for insulation)
Check installation of steel
bellows (Check gasket
3.9 Visual Eng drawing Checklist H (W)H R
installation & bolts
tightening)
Check insulation - release
4 Visual Eng drawing WFG tool kit H (W)H R
for cladding
Check installation of steel
4.1 Visual Eng drawing VC & MT H (W)H W
bellows insulation box
4 Final Documentation
4.1 Punch List Review N/A Punch List Form H (H,R) H R
LEGENDS:
VC : Vernier caliper
MT : Measuring tape
DC : Depth caliper
WFG : Weld filler gage
H : Hold point (Hold Inspection)
R : Review (Review of Document or Report)
W : Witness (During normal Supervision of the installation; not a Hold Inspection )