ITP - 004 - Static Equipment - IFR
ITP - 004 - Static Equipment - IFR
Owner :
Consultant :
Sub Contractor :
Consortium PP-Wärtsilä
DOCUMENT NO :
BKN2-PP-ITP-004
PURPOSE :
DOCUMENT NO :
FIELD INSPECTION & TEST PLAN (F-ITP) QSHE/DVEPC/AE/P/005
DATE REVISION :
DESCRIPTION
: STATIC EQUIPMENTS INSTALLATION (Columns, Vessels, Heat Exchangers, Etc.)*
INSPECTION ACTIVITIES
REFERENCE
ITEM ACTIVITIES DOCUMENTS/ACCEPTANCE VERIFYING DOCUMENT PP/ PLNE/
Subcont
CRITERIA Wartsila PLN
5.4 Wetting area to be grout , normally 24 hours before grouting ( see vendor spec. ) Tech. Spec., Drawing, Proc.,
5.5 Mixing of grout mat'l ( equipment to be used, inveroment temperature, Manual Instruction. Grouting Report P SW & R R
Percented of mixing between water and cement )
5.6 Curing time , 48 haours after grouting ( see vendor spec. / proc. )
5.7 Tightening anchor bolt
6.0 INSTALLATION OF COLUM OR VESSEL INTERNALS
6.1. Material verification (Type, Identification, Qty and Dimensional Check) Inspection Report P SW & R R
6.2. During and After Installation
6.2.1 Levelness/Flatness of Outlet Wire & Tray Floor
6.2.2 Clearance between weir plate & Down comer
6.2.3 Check tightening bolts of Tray & Support
6.2.4 Check Welding of chimney Trays/Accumulator Inspection Report P W&R SW
6.2.5 Leakage Test for Draw-off Pans & chimney Tray / Accumulator
6.2.6 Cleaning , modification or change the gasket, etc. Tech. Spec., Drawing, Proc.,
6.2.7 Install catalyst before mechanical completion, or after mechanical compl. Manual Instruction.
due to safety consideration
6.3. Final Check and Cleaning
6.3.1 Visual Check
6.3.2 Cleaning Inspection Report P W&R W
6.3.3 Installation of Man way Deck
6.3.4 Closure of Vessel Manhole
7.0 PUNCH LIST / FINAL CHECK
7.1 Visual check completion installation all accessories and parts of Eqp as per drw
(Platform, Ladder, Grating, Handrail, Mainway, etc.)
Tech. Spec., Drawing, Proc.,
7.2 Check tigthening all bolt and connection Punch List P W&R W
Manual Instruction.
7.5 Loosening Side and anchor side (Setting bolt at sliding side and anchor side)
8.0 DOCUMENTATION
All documents dossier required as per contract shall be collected and submitted
All Quality Document as
to Client and copy for file
per Contract (Inspection
8.1 All Inspection as per this ITP has been done & the inspection P R R
Contract, Tech. Spec., Proc. Reports, RFI, NCR, MDR,
report has already been generated and signed
Punch List, As built
8.2 All NCR or any deviation of contract already closed and documented
Drawings, Etc.)
8.3 All drawing changes already updated in As built or mark up drawing
* General