Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

FEATURE

Five Steps to Resolving


Construction Disputes--
Without Litigation
Richard H. Steen

Disputes are a reality in every construction to shift risk to the other party, so that the basis
project. Without a means to address them, minor for claims and disputes is eliminated. For ex-
issues can fester and grow, with crippling conse- ample, making a contractor responsible for the
quences for proiect participants. The rising cost, impact of unanticipated site conditions may ef-
delay and risk of litigating construction disputes fectively preclude recovery of additional costs
has prompted the construction industry to look caused by such conditions. Similarly, contract- THE ARRAYOF
for new and more efficient ways to resolve these
disputes outside of the courtroom.
dispute clauses can be drafted so that submit-
ring a valid claim is nearly impossible, which
i TECHN
QUESFOR
Within the past decade, the industry has tak- actually encourages litgafion. I ALTERNATIVE
en steps to avoid litigation and control disputes
by developing and employing various mecha-
Such contract provisions, however, do not pre-
vent disputes from occurring. Often, they only
DISPUTERESOLUTION
nisms for alternative dispute resolution (ADR)
that can be used during nearly any stage of a
create fractious relationships among the parties
involved in the project. Constrnction-project own-
INCLUDESEVERYTHING
construction project. These mechanisms range ers generally have two concerns when they shift FROMSIMPLE
from simple negotiation to binding arbitration. unanticipated risks to a contractor: The first is
Experience has shown that when resolution that the contractor will build a contingency into
NEGOTIATIOTO
N
occurs sooner rather than later, and when reso-
lution is relatively unconfrontational, there is a
the price to cover the risks; the second is that the
contractor will not have a contingency and will
BINDINGARBITRATION,
much better chance that litigation can be avoid- get into financial trouble. Unfair shifting of risk
ed. Waiting until the end of a project to address can result in a party having to spend time and ef-
a dispute inevitably makes it harder and more fort looking for ways to stay alive on the project,
expensive to resolve. Parties involved in a con- usually to the detriment of the project itself.
strncfion dispute, or indeed any commercial dis- As the costs and risks of construction con-
pute, generally prefer to retain control over the tinue to rise, more construction-industry pro-
outcome and maintain business relationships. fessionals are turning to a fair allocation of risk
There are five key steps to take to resolve among all parties involved--the planner, archi-
construction disputes without litigation. Two tect/engineer, owner, contractor and subcon-
deal with contract provisions: equitable alloca- tractors. Fairness is an elusive concept, but the
tion of responsibilities and risks, and proce- objective is to have the party who is best able
dures for dealing with contract disputes. The to control a risk be responsible for that risk.
third step involves building teams and estab- The federal government has recognized the in-
lishing objectives. These first three should be equity in requiring competitive bids while sad-
taken before a dispute even occurs. Step 4 pro- dling contractors with unquantifiable risks, and
vides for a neutral forum to resolve disputes has long included equitable adjustment provi-
throughout the life of a project. Step 5, the "last sions in government contracts.
resort," is binding ADR,such as arbitration. An equitable contract serves as the first step
in building cooperation and close coordination Richard H. Steen is vice
president of Hill Interna-
Step 1: allocating fair contract risk among the project participants, providing a tional, Willingboro, N.J.,
It comes as no surprise that parties to a con- strong foundation for working out the in- where he concentrates on
the resolufion of complex
tract often include contract language designed evitable disputes before they lead to divisive construction disputes.
JOURNALOF MANAGEMENTIN ENGINI~ERING/JULY/AUGUST 1994 / 19

Downloaded 17 Feb 2011 to 129.128.253.36. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelibrary.org
change orders as explicit provisions for resolv-
ing disputes as they arise during the course of
the project. For example, provisions for binding
resolution can include dispute resolution by ar-
bitration under the American Arbitration Asso-
ciation (AAA) construction-industry arbitration
rules.
Contractual provisions should at a minimum
require before resorting to arbitration, parties
will first try to settle all disputes by some non-
binding technique, such as mediation.
The American Institute of Architects, the As-
sociated General Contractors of America and
AAAhas each published suggested guidelines
and model contract terms for such provisions.
The guidelines can be helpful in tailoring the
dispute-resolution provisions of a contract to
your specific needs.
Establishing procedures for dispute resolu-
tion at the start of a project can save consider-
able time and cost later. Like fair allocation of
risk, including dispute-resolution provisions in
a contract can help retain focus on the success
of the project, and not the success of litigation.

Step 3: building teams


Team building is another dispute-resolution
technique that can be instituted at the begin-
ning of a construction project to help allow for
better cooperation and coordination among all
parties.
One such process, partnering, has gained in-
creasing popularity in recent years. It involves
an extracontractual understanding among all
parties to form a partnership of sorts to achieve
mutually determined goals and objectives as
well as minimize disputes and claims.
This agreement is often reached through a
partnering workshop, wherein all parties agree
to take specific steps to work together, fairly al-
locate risk and responsibilities, and recognize
their common goal--a successful project.
Although partnering may require more
manpower and effort up front, its payoff can be
invaluable, creating a more harmonious, less
confrontational process--and at completion, a
successful project without litigation and claims.
Other team-building concepts such as total
quality management are also popular methods
of preventing disputes.
claims that can negatively impact the schedule
and cost of construction. Step 4: providing for a "neutral'
Even the most careful planning can't always
Step 2: drafting dispute clauses prevent disputes and this step is the last
In addition to identifying responsibilities and chance to resolve a dispute before resorting to
allocating risk, a contract also should contain a binding settlement. Providing for a neutral
language for addressing disputes and claims at party to analyze issues and facilitate dispute
the earliest possible stage in a project. This in- resolution should negotiations fail is an impor-
cludes provisions for handling and processing tant step to minimizing the problems caused by
20 /JOURNAL OF MANAGEMENTIN ENGINEERING/JULY/AUGUST 1994

Downloaded 17 Feb 2011 to 129.128.253.36. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelibrary.org
disputes. This technique involves a preselected tion and minitrials--a structured settlement
independent "neutral" to serve the parties as an procedure in which each side presents its case
observer, fact finder and dispute resolver before neutrals or senior executives of each
ONTRACT.DISPUTE
throughout the construction process. Ideally, a
neutral is selected at the inception of the con-
struction phase of the project to act immediate-
party involved in the dispute.

Step 5: using binding ADR


C CLAUSESCAN
BEDRAFTEDSO
ly to resolve disputes that cannot be otherwise The construction industry, more than per-
settled. haps any other, has experience with using arbi-
THATSUBMITTING
Although procedures for establishing a neu- tration for resolving disputes. Serious contract A VALIDCLAIM
tral vary and can be tailored to meet the specific disputes involving huge cost overruns, long ISNEARLY
needs of a project, they involve a few basic ele- schedule delays and complicated technical
ments, including: specifications requirements are, in many cases,
IMPOSSIBLE,
* At the outset of the project, the parties select best decided by experienced arbitrators. The WHICHACTUALLY
one or more neutrals in whom they have trust construction industry's success in moving away ENCOURAGES
and confidence to serve throughout the course from litigation is a valuable lesson to those who
of the project. The neutral can be a firm with today are considering ADR as a substitute for
LITIGATION.
experienced dispute-resolution professionals, facing litigation, given the current "crisis" in
or a technical expert who will participate in the civil courts.
fact-finding and issue analysis. The neutral usu- Even having taken the four preceding steps,
ally must be acceptable to and compensated by some disputes won't be resolved. Turning the
both parties, and must be both independent decision over to an arbitration panel comprised
and impartial. of knowledgeable and experienced industry
* Depending on the wishes of the parties, the professionals has many advantages over a
role of the neutral will be to manage the dis- judge and/or jury.
pute process, to mediate the dispute, or to ren- Although once seen as the only option, bind-
der either a nonbinding or a binding decision. ing arbitration is now considered a last resort,
9 The neutral is initially given an introduction after equitable contracting, ongoing dispute
to the nature, scope and purpose of the project resolution and nonbinding ADRtechniques have
and is furnished contract documents. The neu- failed.
tral often is then required to visit the project As in litigation, the parties in arbitration give
site and meet with key project personnel on up control over the decision and have to pro-
project progress, even if there are not existing ceed in an adversarial forum, endangering fu-
disputes. The neutral may attend project meet- ture relationships. The perception, if not the re-
ings and be kept appraised of project progress. ality in every case, is that arbitration has advan-
9 Whenever the parties are unable to resolve a tages over litigation of lower cost, more prompt
dispute, it may be immediately referred to the resolution and finality.
neutral for a prompt, nonbinding recommenda- In New Jersey, the finality of arbitration is
tion or binding decision. being questioned as a result of the state
9 If the neutral is empowered to make only supreme court's opinion in Perini Corp., 129
nonbinding recommendations and its recom- N.J. 479 (1992). In that case, the court held that
mendation is challenged by either party, the arbitrators are required to follow applicable law
r e c o m m e n d a t i o n can be admissible as evi- and that arbitration proceedings awards are
dence in a subsequent ADR proceeding or in a subject to judicial review to determine whether
court of law. the arbitrator(s) made gross errors of law.
Because the neutral is readily available and Many practitioners agree with a recent New Jer-
knowledgeable about the project, he or she of- sey Law Journal editorial, which commented on
ten can help mediate or encourage prompt res- the potential for increased postarbitration litiga-
olution of disputes. In addition, the time and tion as a result of the Perini decision.
cost saved by immediately addressing disputes
can help preserve the relationships among the Conclusion
parties and project focused on mutual goals. ADR is rapidly entering the mainstream of
Neutrals can be used in a variety of ADRtech- business relationships and the arsenal of options
niques. One of the most commonly used is the for practicing lawyers. The bar can benefit from
three-person dispute-review board in which the the successful experience of the construction in-
contractor and owner each select an expert to dustry in this area. Lawyers are assisting clients
sit on the board and those two then select the in fashioning comprehensive ADRprograms dur-
third member. Other innovative ADR schemes ing initial contract formation, and counseling
include "rent-a-judge," in which a magistrate and advising throughout many unique and excit-
(usually retired) presides over a private litiga- ing ADRproceedings. 9
JOURNALOF MANAGEMENTIN ENGINEERING/ JULY/AUGUST 1994 / 21

Downloaded 17 Feb 2011 to 129.128.253.36. Redistribution subject to ASCE license or copyright. Visithttp://www.ascelibrary.org

You might also like