GIS Module-Works (Inside PEB Building) : Description of Works Unit Qty October W1
GIS Module-Works (Inside PEB Building) : Description of Works Unit Qty October W1
GIS Module-Works (Inside PEB Building) : Description of Works Unit Qty October W1
October
SN Description of Works Unit Qty
W1
A 400KV GIS Bay Module Nos 15
GIS Module-Works (inside PEB Building)
Skilled Workers-GIS specilize 8
Support Workers-Skilled 7
Scaffolder 4
Cleaner 2
Tool Keeper 1
BUS DUCT-Works (Outside Works)
Skilled Workers-GIS specilize 8
Support Workers-Skilled 7
Cleaner 4
Logistic Suppot
Worker Skilled 4
Helpers 4
49
B Transformer & Reactor Unit Qty
315 MVA Transformer Nos 3
80 MVA Reactor Nos 1
60 KVA Transformer Nos 1
Skilled Worker for Transformer errection and goods Handling 4
Helpers for Transformer errection and goods Handling 4
Operator for Filter Plant
Helpers for Filter Plant
8
C Steel Structure, Equipments erection, Hardwares with Stringing Dropper, LT Switch gears, Batteries
Skilled Workers for equipments erection works, CRP Works, Cabling
and termination works, Hardware works, Earthing works, ACDB,
10
DCDB, Battery and Battery Charger and Electrification of GIS hall
and control Rooms etc
20
Man Powers for August and September
Supervisors 2 Nos each days (2*90)
Total
Other Expenditure Amount
Insurances 200000
Safety Item & Medical Test 200000
Kitchen Items 200000
Bedding Items 240000
Room Rents 100000
940000
Dhalkebar 400KV GIS Substation Manpower Plan and Costing
October November December
W2 W3 W4 W1 W2 W3 W4 W1 W2 W3
8 8 8 8 8 8 8 8 8 8
7 7 7 10 10 10 10 7 7 7
4 4 4 6 6 6 6 4 4 4
2 2 2 2 2 2 2 2 2 2
1 1 1 1 1 1 1 1 1 1
8 8 8 8 8 8 8 8 8 8
7 7 7 10 10 10 10 7 7 7
4 4 4 4 4 4 4 4 4 4
4 4 4 4 4 4 4 2 2 2
4 4 4 4 4 4 4 2 2 2
49 49 49 57 57 57 57 45 45 45
4 4 4 4 4 4 4 4 4
4 4 4 4 4 4 4 4 4
2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2
8 12 12 12 12 12 12 12 12 0
LT Switch gears, Batteries, Relay Panel, Power and control Cable, CCTV, Illuminationi and Substation Automation
10 10 10 10 10 10 10 5 5 5
10 10 10 10 10 10 10 5 5 5
20 20 20 20 20 20 20 10 10 10
10 -
600 1,500.00 900,000.00
270 1,440.00 388,800.00
10,125,600.00