MEDIUM VOLTAGE
SWITCHGEAR
Signature:
TABLE OF CONTENTS
2. PURPOSES 02
3. REFERENCES 02
4. RESOURCES 02
6. RESPONSIBILITIES ............................................................................... 03
7. PROCEDURE ......................................................................................... 04
8. QUALITY ASSURANCE/CONTROL 05
1. SCOPE OF WORK:
The work involves furnishing and installation of a complete operable Power MEDIUM
VOLTAGE SWITCHGEAR as shown on the drawings and that of the project technical
specifications.
2. PURPOSE:
3. REFERENCES:
4. RESOURCES:
4.1 Materials 4.2 Equipment 4.3 Personnel
Three-phase oil-immersed
- Drill Machine - Project Engineer
MEDIUM VOLTAGE SWITCHGEAR, - Crane - Electrical Engineer
h i ll filling,
with integral l d insulation - Hammer - QC Engineer
system with oil natural air natural - Lifting Jack - Rollers - Safety Officer
(ONAN) cooling for indoor or - Megger - Electrical Foreman
outdoor installation destined for - Crimping tools
use in three-phase MV/LV distribution - Torque wrench
systems. MEDIUM VOLTAGE SWITCHGEAR
shall comply with the requirements of
Saudi Electricity Company.
Magnetic Core
MV Connections
PE - Project Engineer
EE - Electrical Engineer
QCE - Quality Control Engineer
SO - Safety Officer
IN - Installer
RESPONSIBILITIES:
6.1 The Project Engineer
Shall direct when and where to start furnishing and installation of MEDIUM VOLTAGE
SWITCHGEAR
And establish deadlines for activity to be finished. He shall make sure that furnishing
and installation of MEDIUM VOLTAGE SWITCHGEAR shall be finished with-in the time
frame set
Shall confirm the materials delivered at site and prepare the MIR (Material's Inspection
request) for approval by the Engineer prior to utilization at site. Likewise, in charge of
the preparation of the RFI (Request for Inspection) for each stages of Activity.
Shall also monitor and periodically inspect all the installation of MEDIUM VOLTAGE
SWITCHGEAR
At all times to ensure compliance with approved shop drawings and that of the Project
Technical Specifications. Likewise, make sure that all the materials to be used for this
particular.
Scope of work are that of the approved type and must be complying with the
approved submittal
MS: Installation of Medium Voltage Switchgear
6
KAP2E2-MS-ELC-GEN-3765-0
Contract No.: 134/15/53/1 Doc. No.: KAP2E2-MS-ELC-GEN-3765-0
Shall make sure that Health and Safety of the Workers is taken into consideration at all
times.
7. PROCEDURE:
The following specified procedure for furnishing and installation of MEDIUM VOLTAGE
SWITCHGEAR for all the equipment and various metal components inside the building
connected to the outside grounding system shall serve as a guide or reference by the
EE along the course of their work in order to achieve an acceptable quality of
workmanship, and at the same time to control materials utilization but attaining the
optimum results with Less time and effort:
7.1 Installation:
The completed installation shall be tested for compliance with the specification
(specs + MTR) following completion of all site work. Testing shall be conducted
by the representatives of the manufacturer. The Engineer shall be notified in
advance and certified copies of test procedures and results shall be forwarded
to the Engineer. Field, inspection and testing will be performed under provisions
of contract preliminaries.
Check for damage and tight connections prior to energizing the Medium
Voltage Switchgear