Standard Costing and Variance Analysis Problems

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

JOANN R.

SALOMON COST ACCOUNTING


BSA IVX

Standard Costing and Variance Analysis Problems & Solution:

The scenario of STD costing and variance analysis.


http://www.accountingformanagement.com/standard_costing_system_solved_problems.htm

Problem 1:
Materials Variance Analysis:
The Schlosser Lawn Furniture Company uses 12 meters of aluminum pipe at ₱0.80 per
meter as standard for the production of its Type A lawn chair. During one month's
operations, 100,000 meters of the pipe were purchased at ₱0.78 a meter, and 7,200 chairs
were produced using 87,300 meters of pipe. The materials price variance is recognized
when materials are purchased.

Required: Materials price and quantity variances.

Solution:
Meters of pipe Unit Cost Amount
Actual quantity purchased 100,000 ₱0.78 actual ₱78,000
actual quantity purchased 100,000 ₱0.80 standard ₱80,000
----------- ----------- -----------
Materials purchase price variance 100,000 ₱ (0.02) ₱ (2,000) fav.
======= ======= =======
Actual quantity used 87,300 0.80 standard ₱69,840
Standard quantity allowed 86,400 0.80 standard ₱69,120
------------- ------------- -------------
Materials quantity variance 900 0.80 ₱720 Unfav.
======= ======= =======

1|Page
JOANN R. SALOMON COST ACCOUNTING
BSA IVX

Problem 2:
Labor Variance Analysis:
The processing of a product requires a standard of 0.8 direct labor hours per unit for Operation 4-802 at
a standard wage rate of ₱6.75 per hour. The 2,000 units actually required 1,580 direct labor hours at a
cost of ₱6.90 per hour.
Required: Calculate:

 labor rate variance or Labor price variance.


 Labor efficiency or usage or quantity variance.

Solution:
Time Rate Amount

Actual hours worked 1,580 ₱6.90 actual ₱10,902


Actual hours worked 1.580 ₱6.75 standard 10,665

-------- -------- --------

Labor rate variance 1,580 ₱0.15 ₱237 unfav.


===== ===== =====

Actual hours worked 1,580 ₱6.75 standard ₱10,665


Standard hours allowed 1,600 ₱6.75 standard ₱10,800
---------- ------------ -----------

Labor efficiency variance (20) 6.75 standard ₱ (135) fav.


====== ====== ======

2|Page
JOANN R. SALOMON COST ACCOUNTING
BSA IVX

Problem 5:
Variance Analysis:
On May 1, Bovar Company began the manufacture of a new mechanical device known a "Dandy." The
company installed a standard cost system in accounting for manufacturing costs. The standard costs
for a unit of Dandy are:

Materials: 6 lbs. at ₱1 per lb. ₱6.00

Direct labor: 1 hour at ₱4 per hour ₱4.00


Factory overhead: 75% of direct labor cost ₱3.00
-----------

Total ₱13.00
======

The following data were obtained from Bovar's record for may:

Actual production of Dandy 4,000 units

Units sold of Dandy 2,500

Sales ₱50,000
Purchases (26,000 pounds) 27,300

Materials price variance (applicable to May purchase) ₱1,300 unfavorable


Materials quantity variance 1,000 unfavorable

Direct labor rate variance 760 unfavorable.

Direct labor efficiency variance 800 favorable

Factory overhead total variance 500 unfavorable

Required:
1. Standard quantity of materials allowed (in pounds).
2. Actual quantity of materials used (in pounds).
3. Standards hours allowed.
4. Actual hours allowed.
5. Actual direct labor rate.
6. Actual total factory overhead.

Solution:
3|Page
JOANN R. SALOMON COST ACCOUNTING
BSA IVX
Actual production 4,000 units

Standard materials per unit 6 pounds

------------

Standard quantity of materials allowed 24,000 pounds

=======

Standard quantity of materials allowed 24,000 pounds

Unfavorable materials quantity variance (₱1,000 variance / ₱1 standard price per pound) 1,000 pounds

-------------

Actual quantity of materials used 25,000 pounds

========

Actual production 4,000 units

Standard hours per unit 1 hour

------------

Standard hours allowed 4,000 hours

========

Standard hours allowed 4,000 hours

4|Page

You might also like