Dod-Mst-E-023 (Rev-B) Dismantling & Reinstallation of Existing Electrical Pole
Dod-Mst-E-023 (Rev-B) Dismantling & Reinstallation of Existing Electrical Pole
Type of Job being analyzed: DISMANTLING AND REINSTALLATION OF EXISTING ELECTRICAL POLE
JHA Members: HSE DEPARTMENT, CONSTRUCTION MANAGER
Department/Section originating JHA
JOB Performers: Site Engineer, Site Supervisor, Rigging Foreman, Riggers, Operators, Helpers
Normal approvals: Name Signature DATE GENERAL JOB REQUIREMENTS
JHA By: John Vander Berg COMMON PPE
A. K. Rathore 3/13/2008
Jana V GENERAL JOB REQUIREMENTS
Additional Approvals (Determined by JOB Supervisor in correlation with CTJV EHSS Manager) 1 CTJV EHSS Inducted workforce
Name Signature Date 2 Dodsal HSE Inducted
3 Daily TBT
4 Adequate supervision
Discipline Superintendent (CTJV) 5 Third Party certified, colour coded lifting
EHSS Representative (CTJV) equipments and lifting tools & tackles.
EHSS Representative (Company) 6 Valid Qatari Licenses for drivers & operators
CTJV I.H. 7 Third Party certified, competent operators,
Other (List Below) welders
8 S.T.A.R.T Card
PPE
Notes: EHSS sign when required for hazardous NOMEX Coveralls, Safety shoes, Helmets
Work details as required by CTJV PTW. Safety Goggles , Appropriate Hand gloves
APPROVAL REQUIRED FOR HAZARDOUS WORK DETAILED IN THE CTJV WORK PERMIT PROCEDURE NOMEX Cover alls, H2S MONITORS
CHANGING CONDITIONS & EMERGENCY PROCEDURES: Stop Work, Switch Off Equipment, Supervisor Directs Personnel to Nearest and Safest
Muster point Considering Wind direction. Supervisor accounts for all Workers.
Missing persons are reported to CTJV EHSS Dept. When all clear is given check with CTJV EHSS before resuming to work.
EMERGENCY TELEPHONE NO: Ras Gas - 473 8999
Note: If any of the tasks involves biological, physical or chemical hazards, then CTJV Industrial Hygienist must also approve the work
Use additional sheets as necessary
Details on safety (PPE, Hazards etc) and environmental requirements can be found in CTJV and Ras Gas Safety and Environmental procedure.
Page 1 of 6
Doc. #: DOD-MST-E-023 DISMANTLING & REINSTALLATION OF EXISTING ELECTRICAL POLE (REV-B)
SEQUENCE OF BASIC RESPONSIBLE
POTENTIAL HAZARDS HAZARDS CONTROL
ACTIVITY STEPS PARTY
Type of Job being analyzed: Obtain PTW from OPCO prior to the commencement of the work and to
Necessary information not communicated to the Site Engineer,
2.0 DISMANTLING OF EXISTING 2.1 2.1.1 be made available at the work site during all the activities.
Plant Authority. Site Supervisor
ELECTRICAL POLE Site Mandatory PPE to be used by all employees.
Ensure all lifting equipments, tools & tackles are inspected and certified
by 3rd party.
Lifting equipment All lifting gears should be visually inspected prior to each rigging
Failure of lifting equipment preparations.
Uninspected lifting tools & tackles Competent rigger should be available at site.
Suspended load Ensure lifting area is barricaded and no unauthorized personnel entry.
Unauthorized crane operator Ensure only rigger is allowed inside the barricading during lifting in
Rigger,
10.0 Lifting Operation 10.1 Improper supervision 10.1.1 progress.
Site Supervisor
Wrong rigging preparations All rigging preparations should be done under the supervision of a
Improper guide lines qualified rigger.
Unauthorized personnel movement inside the lifting Proper guide lines should be provided.
area Always maintain good visual communication between rigger and crane
Lack of communication between rigger and operator operator.
Ensure rigger / site supervisor only give signals to the crane operator.
Ensure the supervisor well experienced for the lifting.
Prior to start the jobs ensure all team members are aware about the
evacuation procedures and nearby muster points.
Check the wind direction prior to start the job to find out a safe muster
point.
Panic
Ensure all crew members undergone H2S training. Site Supervisor,
14.0 Emergency Response 14.1 Wind direction 14.1.1
Ensure H2S monitor is available with the crew. OPCO Team
Unaware of muster point
In case of emergency, after evacuation head count should be done by
the site supervisor and report to the site engineer.
Do not re-enter the plant or start any jobs without re-validating the
permit / instructed by the area authority.
Ensure plenty of cool drinking water is available at site and all employees
Lack of drinking water are drinking water periodically
16.0 Heat stress Management 16.1 Unavailability of rest shelter 16.1.1 Ensure the availability of appropriate rest shelters and employees are Site Supervisor
Heat stress taking periodical rest as per the requirements
Ensure 'NO WATER - NO WORK'