Professional Documents
Culture Documents
Rfi-00898 Welder Test
Rfi-00898 Welder Test
Rfi-00898 Welder Test
(RFI)
[IKAN] RDMP - Refinery Unit V
Project : Unit / Area : N/A
Balikpapan Project
Inspection Detail
Remark
Contractor
Subcontractor IPMT
Construction QA/QC
Signature
General notes:
comment from Package Audit shall be absorbed
1. Update transtition phase data as per PDS and MDS
2. Update nozzle and flange as per latest conditon
3. Update Flange Foam Chamber from WNFF --> SOFF
4. Vortex Breaker attached to elbow may be added to N2 and N14 after
study from Process
5. Supply gauge hatch that can be act as emergency vent
6. Add applicable major spec as per MDS to the GAD
7. Add Allowable Nozzle Table that has been calculated as per Latest
Strength Calculation.ed.
DESIGN DATA
change the sch as per purchased update value as per latest strength calc.
Month
Oct - March North
Apr - Sep South South West
Note 4. to be changed to
"Design Specification for Paint Schedule shall refer to
method statement 26071-203-V3A-MTF5-00006"
General notes:
comment from Package Audit shall be absorbed
1. Update transtition phase data as per PDS and MDS
2. Update nozzle and flange as per latest conditon
3. Update Flange Foam Chamber from WNFF --> SOFF
4. Vortex Breaker attached to elbow may be added to N2 and N14 after
study from Process
5. Supply gauge hatch that can be act as emergency vent
6. Add applicable major spec as per MDS to the GAD
7. Add Allowable Nozzle Table that has been calculated as per Latest
Strength Calculation.ed.
ELEVATION
put applicable project spec in reference
document as per MDS R.002
DESIGN DATA
nominal: 37,306
net work cap: 35,147
ESTIMATED WEIGHT & CAPACITY