TOWER MONITORING SUTT 70KV Ropa Mei 2018
TOWER MONITORING SUTT 70KV Ropa Mei 2018
TOWER MONITORING SUTT 70KV Ropa Mei 2018
ERECTION 21/7/'12 22/10/'12 07/7/'12 05/7/'12 21/6/'13 10/7/'12 30/8/'12 29/8/'13 22/8/'12 22/10/'12 06/9/'12 10/10/'112 20/10/'12 24/10/'12 15/7/'12
Final Cek Erection 21/8/'13 21/8/'13 21/8/'13 21/8/'13 28/8/'13 22/8/'13 22/8/'13 10/10/'13 22/8/'13 22/8/'13 22/8/'13 22/8/'13 23/8/'13 23/8/'13 23/8/'13
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Jenis Pondasi
Kelas Pondasi 2 1 1 2 5 6 6 5 7 5 6 2 7 5 6
Nomer Tower 01 01A 02 03 04 05 06 07 08 09 10 11 12 13 14
Type tower DDr1+3 Aa1s+3 Aa1s+3 Aa1s+6 Aa1s+6 Aa1s+6 Aa1s+6 Cc1+3 Aa1s+6 Aa1s+6 Bb1+3 Aa1s+6 Aa1s+6 Aa1s+3 Aa1s+3
Span 70.0 251.100 236.300 267.200 301.000 301.000 276.400 299.400 274.300 288.500 278.800 274.500 275.100 262.800 242.900
Lokasi KABUPATEN ENDE
STRINGING
ERECTION 15/7/'12 30/10/'12 20/8/'12 10/08/'12 26/11/'12 19/10/'12 19/10/'13 27/8/'13 27/8/'13 28/11/'13 26/8/'12 24/12/'12 23/7/'12 28/8/'12 7/8/2012
Final Cek Erection 23/8/'13 23/8/'13 23/8/'13 24/8/'13 28/8/'13 24/8/'13 24/8/'13 28/8/'13 28/8/'13 12/12/'13 16/9/'13 15/9/'13 15/9/'13 15/9/'13 15/9/'13
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Jenis Pondasi
Kelas Pondasi 6 5 1 7 3 3 1 5 1 1 1 3 3 3 2
Nomer Tower 14 15 15A 16 17 18 19 20 21 21A 22 23 24 25 26
Type tower Aa1s+3 Aa1s+3 Aa1s+6 Aa1s+6 Bb1s+0 Aa1s+3 Aa1s+6 Bb1s+0 Bb1 -3 Bb1+0 Bb1s+3 Bb1s+12 Aa1s+6 Aa1s+6 Cc1+9
Span 238.900 235.100 279.400 198.600 220.700 274.800 180.000 440.600 ......... ........ 352.300 274.300 274.400 328.100
Lokasi
PT PLN ( Persero ) PUSAT MANAJEMEN KONSTRUKSI
UNIT MANAJEMEN KONSTRUKSI II
TEAM SUPERVISI KONSTRUKSI JARINGAN WILAYAH NTT
ERECTION 07/8/'12 18/8/'12 21/10/'13 29/8/'13 29/8/'12 26/8/'12 26/8/'12 09/8/'12 15/8/'12 24/10/'13 01/9/'13 30/10/'12 20/10/'12 20/11/'12 01/09/'13
Final Cek Erection 15/9/'13 15/9/'13 23/9/'13 15/10/'13 15/10/'13 24/9/'13 24/9/'13 24/9/'13 24/9/'13 23/9/'13 23/9/'13 23/9/'13 23/9/'13 23/9/'13 23/9/'13
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Jenis Pondasi
Kelas Pondasi 2 5 1 7 3 3 1 5 1 5 3 3 7 3 5
Nomer Tower 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
Type tower Cc1+9 Aa1s+15 Aa1s+6 Bb1s+6 Bb1s+6 Bb1+6 Aa1s+6 Aa1s+3 Aa1s+6 Aa1s+3 Aa1s+6 Aa1s+3 Aa1s+6 Aa1s+3 Bb1+6
Span 283.300 280.300 277.900 159.700 369.000 306.600 269.400 274.600 262.300 275.300 275.300 274.300 274.800 267.500
Lokasi
STRINGING
ERECTION 01/9/'13 10/11/'12 09/11/'12 11/11/'12 14/11/'12 20/11/'12 12/11/'12 17/9/'13 24/11/'12 04/12/'12 29/11/'12 30/11/'12 21/11/'12 28/11/'12 02/9/'13
Final Cek Erection 23/9/'13 21/9/'13 21/9/'13 21/9/'13 21/9/'13 21/9/'13 25/9/'13 25/9/'13 02/10/'13 02/10/'13 02/10/'13 01/10/'13 01/10/'13 01/10/'13 26/9/'13
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Jenis Pondasi
Kelas Pondasi 5 3 7 7 1 7 7 7 1 1 1 1 1 7 7
Nomer Tower 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54
Type tower Bb1+6 Aa1s+6 Aa1s+3 Aa1s+6 Aa1s+3 Aa1s+6 Aa1s+6 Aa1s+9 Aa1s+6 Aa1s+3 Aa1s+6 Aa1s+3 Aa1s+6 Bb1+3 Aa1s+6
Span 308.100 249.900 275.000 274.500 274.000 275.000 278.800 334.500 274.100 244.400 280.700 269.300 273.300 251.800
Lokasi
PT PLN ( Persero ) PUSAT MANAJEMEN KONSTRUKSI
UNIT MANAJEMEN KONSTRUKSI II
TEAM SUPERVISI KONSTRUKSI JARINGAN WILAYAH NTT
ERECTION 02/9/'13 07/5/'12 30/11/'12 15/9/'13 03/3/'13 05/3/'13 17/12/'12 04/1/'13 30/1/'13 20/1/'13 03/2/'13 05/6/'13 20/2/'13 25/1/'13 11/5/'13
Final Cek Erection 26/9/'13 26/9/'13 01/1/'13 26/10/'13 28/10/'13 06/4/'13 23/10/'13 23/10/'13 23/10/'13 28/10/'13 23/10/'13 07/6/'13 22/2/'13 22/2/'13 28/10/'13
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Jenis Pondasi
Kelas Pondasi 7 1 1 1 1 1 1 1 1 1 1 1 1 1 7
Nomer Tower 54 55 56 57 58 59 60 62 63 64 65 65A 66 67 68
Type tower Aa1s+6 Dd1s+9 Bb1+9 Bb1+6 Bb1+3 Bb1+3 Bb1+0 Bb1s+6 Bb1+12 Aa1s+12 Bb1+9 Bb1+9 Bb1+9 Aa1s+12 Aa1s+15
Span 225.500 236.000 315.800 270.600 466.700 178.000 455.200 269.700 281.800 263.200 228.900 123.600 245.600 246.400
Lokasi
STRINGING
ERECTION 11/5/'13 28/4/'13 26/3/'13 08/9/'13 09/9/'13 07/9/'13 06/9/'13 04/12/'12 10/9/'13 16/2/'13 21/11/'12 19/2/'13 19/4/'13 18/4/'13 05/3/'13
Final Cek Erection 28/10/'13 31/10/'13 31/10/'13 31/10/'13 31/10/'13 30/10/'13 30/10/'13 30/11/'13 02/11/'13 02/11/'13 02/11/'13 02/11/'13 31/12/'13 29/12/'13 29/12/'13
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Jenis Pondasi
Kelas Pondasi 7 1 1 1 1 1 1 2 1 1 3 1 1 1 2
Nomer Tower 68 69 70 71 72 73 74 75 77 78 79 80 82 84 85
Type tower Aa1s+15 Bb1+6 Bb1+6 Bb1+3 Aa1s+3 Aa1s+12 Bb1s+6 Bb1+9 Aa1s+12 Bb1+0 Bb1+9 Bb1+15 Aa1s+6 Aa1s+6 Bb1+9
Span 284.300 227.000 263.600 149.600 399.600 185.200 255.000 549.900 347.900 354.400 235.700 511.100 457.300 356.900
Lokasi
PT PLN ( Persero ) PUSAT MANAJEMEN KONSTRUKSI
UNIT MANAJEMEN KONSTRUKSI II
TEAM SUPERVISI KONSTRUKSI JARINGAN WILAYAH NTT
ERECTION 05/3/'13 30/5/'13 05/7/'13 22/10/'13 17/5/'13 05/11/'13 18/10/'13 06/10/'13 20/11/'12 27/9/'13 31/12/'12 05/10/'13 11/9/'13 05/2/'13 10/12/'13
Final Cek Erection 29/12/'13 29/12/'13 29/12/'13 29/12/'13 30/12/'13 30/12/'13 02/01/'14 02/01/'14 02/1/'14 31/12/'13 02/1/'14 28/12/'13 28/12/'13 28/12/'13 02/1/'14
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Jenis Pondasi
Kelas Pondasi 2 1 1 1 1 2 1 5 5 3 3 1 1 1 3
Nomer Tower 85 86 87 88 90 91 93 94 95 96 97 99 100 101 104
Type tower Bb1+9 Aa1s+6 Bb1s+9 Bb1s+6 Aa1s+9 Bb1s+9 Ee1-3 Bb1+9 Bb1+6 Aa1s+15 Bb1+12 Aa1s+3 Bb1+6 Bb1s+9 Bb1s+12
Span 274.800 329.100 142.300 764.700 199.200 657.200 281.500 261.100 281.400 293.800 678.300 139.400 236.300 846.800
Lokasi
STRINGING
ERECTION 10/2/'13 11/9/'13 15/9/'13 20/09/'13 19/01/'13 05/2/'13 15/9/'13 15/09/'13 15/09/'13 12/12/'13 06/1/'13 13/9/'13 12/9/'13 17/12/'12 13/9/'13
Final Cek Erection 02/1/'14 03/11/'13 03/11/'13 03/11/'13 03/11/'13 03/11/'13 04/11/'13 04/11/'13 04/11/'13 15/01/'14 04/11/'13 06/11/'13 06/11/'13 07/11/'13 07/11/'13
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Jenis Pondasi
Kelas Pondasi 3 2 2 1 3 3 1 3 1 3 3 1 7 7 1
Nomer Tower 104 105 106 107 108 109 110 111 112 113 114 115 117 118 121
Type tower Bb1s+12 Bb1+12 Aa1s+15 Aa1s+15 Aa1s+9 Aa1s+0 Aa1s+9 Aa1s+12 Bb1s+6 Aa1s+0 Aa1s+6 Aa1s+6 Aa1s+9 Bb1+6 Bb1s-3
Span 316.700 237.600 212.400 337.700 211.000 401.600 207.600 214.600 400.600 158.400 305.000 507.400 247.300 639.300
Lokasi
PT PLN ( Persero ) PUSAT MANAJEMEN KONSTRUKSI
UNIT MANAJEMEN KONSTRUKSI II
TEAM SUPERVISI KONSTRUKSI JARINGAN WILAYAH NTT
ERECTION 13/9/'13 13/9/'13 02/10/'12 06/11/'12 04/10/'13 07/1/'13 06/10/'13 05/01/'13 07/9/'12 10/11/'12 04/3/'13 17/9/'123 25/12/'12 17/09/'13 16/11/'13
Final Cek Erection 07/11/'13 07/11/'13 26/11/'13 26/11/'13 26/11/'13 28/11/'13 28/11/'13 28/11/'13 28/11/'13 28/11/'13 30/11/'13 02/12/'13 03/12/'13 03/12/'13 30/11/'13
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Jenis Pondasi
Kelas Pondasi 1 2 1 7 1 2 2 2 2 3 1 1 3 5 1
Nomer Tower 121 123 124 125 126 127 128 129 130 131 132 133 134 135 136
Type tower Bb1s-3 Bb1s+6 Bb1s+6 Aa1s+12 Aa1s+15 Aa1s+0 Bb1+9 Bb1s+9 Bb1+0 Aa1s+15 Cc1+6 Aa1s+6 Dd1s+3 Dd1s+3 Bb1s+9
Span 741.400 325.500 230.400 164.500 472.700 260.300 200.500 214.700 354.800 361.300 273.700 286.100 249.500 351.600
Lokasi
STRINGING
ERECTION 16/11/'13 14/11/'13 07/11/'13 11/10/'13 10/1/'14 11/10/'13 11/10/'13 10/10/'13 05/1/'13 04/9/'13 03/9/'13 03/9/'13 25/10/'12 08/04/'13 15/1/'13
Final Cek Erection 30/11/'13 03/12/'13 03/12/'13 30/11/'13 26/02/'14 01/12/'13 01/12/'13 01/12/'13 10/2/'14 25/11/'13 03/10/'13 03/10/'13 05/10/'13 12/10/'13 05/10/'13
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Jenis Pondasi
Kelas Pondasi 1 4 4 5 2 2 1 1 1 3 3 1 1 1 3
Nomer Tower 136 137 138 139 140 142 142A 142B 143 144 145 146 147 148 149
Type tower Bb1s+9 Bb1+9 Bb1+9 Bb1s+6 Dd1s+6 Bb1s+3 Dd1s+6 Aa1s+9 Bb1s+3 Bb1+6 Bb1+6 Dd1s+0 Cc1+3 Dd1s+12 Cc1s+12
Span 253.300 287.400 421.200 312.200 593.200 230.000 310.100 377.500 174.600 246.900 173.400 233.100 370.800 233.000
Lokasi
PT PLN ( Persero ) PUSAT MANAJEMEN KONSTRUKSI
UNIT MANAJEMEN KONSTRUKSI II
TEAM SUPERVISI KONSTRUKSI JARINGAN WILAYAH NTT
ERECTION 15/1/'13 17/5/'13 26/10/'12 18/10/'12 30/8/'12 21/8/'12 30/8/'12 03/9/'12 14/8/'12 26/1/'13 26/7/'12
Final Cek Erection 05/10/'13 05/10/'13 06/10/'13 06/10/'13 06/10/'13 07/10/'13 07/10/'13 07/10/'13 07/10/'13 07/10/'13 07/10/'13
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test 1 1 1 1 1 1 1 1 1 1 1
Jenis Pondasi
Kelas Pondasi 3 1 1 1 2 2 2 1 1 7 5
Nomer Tower 149 149A 150 151 152 153 154 155 156 157 158
Type tower Cc1s+12 Bb1+9 Bb1+6 Bb1+9 Bb1+0 Bb1+6 Bb1+12 Aa1s+6 Aa1s+3 Bb1+12 Ddr1+6
Span 173.900 140<8 315.800 227.000 214.300 342.700 290.900 265.000 289.400 283.900
Lokasi
Keterangan
Tanggal Final Check Tower Telah Selesai Pondasi Selesai Cor Erection Tower Telah Selesai
Jumlah
ERECTION 24/4/14 3/6/2014 1/7/2014 3/7/2014 23/9/2016 5/7/2014 5/9/2014 8/4/2014 23/2/'14 26/2/'14 03/3/'14 07/3/'14 08/3/'14 11/3/'14 10/9/'14
Final Cek Erection 7/5/2018 7/5/2018 7/5/2018 7/5/2018 7/5/2018 8/5/2018 8/5/2018 8/5/2018 8/5/2018 9/5/2018 9/5/2018 9/5/2018 9/5/2018 9/5/2018 11/5/'18
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test
Jenis Pondasi Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal
Kelas Pondasi 7 7 7 1 1 1 1 1 1 1 1 2 1 1 1
Nomer Tower 01 01A 02 03 03A 04 05 06 09 10 11 12 13 14 15
Type tower DDr1+3 Ee1+6 Aa1s+3 Aa1s+0 Aa1s+3 Aa1s+6 Aa1s+6 Bb1-3 Cc1+3 Bb1+9 Bb1+3 Bb1+3 Bb1+9 Bb1 +12 Aa1s-3
Span 70.0 301.000 240.800 213.900 188.200 243.300 274.100 250.500 318.700 307.500 236.200 273.800 283.200 276.800 335.700
Lokasi KABUPATEN ENDE
STRINGING
ERECTION 10/9/'14 21/10/'14 28/5/'14 11/3/'14 15/3/'14 6/4/14 15/3/'14 16/5/'18 15/5/'18 14/5/'18
Final Cek Erection 11/5/'18 19/5/'18 19/5/'18 10/5/2018 10/5/'18 10/5/2018 10/5/2018 19/5/'18 19/5/'18 19/5/'18
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test
Jenis Pondasi Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal
Kelas Pondasi 1 1 1 2 2 1 1 1 1 1 1 1 1 1 1
Nomer Tower 15 17 18 19 20 20A 21 23 24 27 28 29 30 31 33
Type tower Bb1-3 Bb1s+9 Bb1+9 Bb1s+3 Bb1+3 Bb1+6 Bb1+0 Bb1s-3 Bb1s+3 Bb1s+9 Cc1s+6 Bb1+12 Bb1s+3 Bb1s+0 Bb1s+0
Span 519.400 237.800 397.700 253.700 197.700 277.300 517.900 260.200 753.300 178.000 123.600 154.900 299.000 549.900
Lokasi
PT PLN ( Persero ) PUSAT MANAJEMEN KONSTRUKSI UNIT
MANAJEMEN KONSTRUKSI II
TEAM SUPERVISI KONSTRUKSI JARINGAN WILAYAH NTT
ERECTION 27/9/'14 04/7/'14 13/6/'14 12/6/'14 10/6/'14 04/10/'14 04/10/'14 18/10/'14 08/10/'14 08/10/'14 30/6/'14 06/6/'14
Final Cek Erection 05/10/'18 10/5/'18 10/5/2018 10/5/2018 10/5/2018 10/5/'18 11/5/'18 11/5/'18 11/5/'18 11/5/'18 11/5/'18 11/5/'18
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test
Jenis Pondasi Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal
Kelas Pondasi 1 1 1 7 7 7 7 3 7 7 7 1 2
Nomer Tower 33 36 37 39 40 41 42 42A 43 44 45 46 47 48 49
Type tower Bb1s+0 Bb1+0 Bb1s+0 Bb1+0 Aa1s+6 Aa1s+6 Aa1s+6 Aa1s+9 Cc1+6 Aa1s+3 Aa1s+9 Aa1s+9 Aa1s-3 Aa1s+6 Aa1s+9
Span 676.500 247.400 626.400 285.700 243.300 255.600 192.900 231.400 265.400 284.000 267.700 334.600 296.400 324.000
Lokasi
STRINGING
ERECTION 26/4/'18 28/4/'18 22/4/'18 23/4/'18 25/4/'18 10/10/'16 05/10/'16 07/9/'16 10/9/'16 19/10'16 14/9/'16 04/9/'16 22/10'16 26/10'16
Final Cek Erection 18/5/'18 18/5/'18 18/5/'18 18/5/'18 18/5/'18 18/5/'18 16/5/'18 16/5/'18 16/5/'18 16/5/'18 16/5/'18 16/5/'18 16/5/'18 16/5/'18
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test
Jenis Pondasi Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal
Kelas Pondasi 1 1 1 1 1 1 7 2 1 1 2 3 1 1 1
Nomer Tower 65 66 67 68 69 70 71 72 73 74 75 76 78 79 80
Type tower Cc1s-3 Bb1-3 Bb1+3 Bb1+6 Bb1s+9 Bb1+9 Bb1s+3 Bb1+6 Bb1s+0 Bb1s+0 Bb1s+9 Bb1s+9 Bb1s+3 Bb1s+0 Bb1s+3
Span 239.600 314.500 174.300 220.200 276.800 192.000 274.800 229.900 322.400 263.100 299.700 401.600 234.700 237.200
Lokasi
STRINGING
ERECTION 12/9/'14 18/9/'14 16/9/'14 12/6/'14 06/6/'14 13/6/'14 16/6/'14 28/9/'16 22/6/'14 22/9/'14
Final Cek Erection 16/5/'18 16/5/'18 16/5/'18 16/5/'18 16/5/'18 16/5/'18 16/5/'18 16/5/'18 16/5/'18 16/5/'18
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test
Jenis Pondasi Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal
Kelas Pondasi 3 1 1 1 1 4 4 1 1 1 1 1 1 1 1
Nomer Tower 97 98 100 101 102 103 104 105 105A 106 108 109 111 112 116
Type tower Bb1+3 Bb1+0 Bb1+3 Bb1+3 Aa1s+6 Aa1s+6 Aa1s+3 Aa1s+3 Aa1s+6 Bb1s+3 Aa1s+6 Bb1+9 Cc1+6 Bb1+3 Bb1s+3
Span 228.500 304.400 229.700 235.600 296.600 246.000 248.400 230.500 298.800 409.100 168.900 265.100 261.300 512.200
Lokasi
STRINGING
STRINGING
ERECTION 27/8/'16 21/6/'14 20/3/'14 28/3/'14 20/3/'14 1/4/14 10/5/14 17/6/14 16/6/14
Final Cek Erection 15/5/'18 15/5/'18 15/5/'18 15/5/'18 15/5/'18 15/5/'18 15/5/'18 15/5/'18 15/5/'18
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test
Jenis Pondasi Normal Normal Normal Normal Normal Normal Normal Bor pile Bor pile Bor pile Normal Normal Normal Normal Normal
Kelas Pondasi 1 1 5 2 2 3 5 6 6 6 2 1 1 1 1
Nomer Tower 151 152 154 155 156 157 158 159 160 161 162 165 166 167 168
Type tower Bb1+3 Bb1s+3 Bb1+9 Aa1s+9 Bb1+6 Aa1s+12 Bb1+12 Aa1s+6 Aa1s+9 Aa1s+6 Bb1+3 Bb1+12 Cc1s+6 Bb1+6 Aa1s+3
Span 594.100 450.400 353.900 332.500 269.000 274.700 274.700 319.000 300.000 298.800 632.900 134.600 278.200 239.100
Lokasi
PT PLN ( Persero ) PUSAT MANAJEMEN KONSTRUKSI UNIT
MANAJEMEN KONSTRUKSI II
TEAM SUPERVISI KONSTRUKSI JARINGAN WILAYAH NTT
ERECTION 28/10/'14 08/7/'14 24/01/'15 06/7/'14 02/9/'14 30/9/'14 05/12/'14 23/11/'14 01/12/'14 27/7/'14 16/11/'14 01/10/'16 28/8/'14
Final Cek Erection 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test
Jenis Pondasi Normal Normal Normal Normal Normal Normal Normal Normal Normal Bor pile Normal Normal Normal Normal Normal
Kelas Pondasi 1 4 1 1 1 7 7 7 7 6 7 1 4 1 4
Nomer Tower 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182
Type tower Aa1s+3 Bb1+3 Bb1s-3 Aa1s+9 Aa1s+9 Aa1s+3 Aa1s+6 Aa1s+6 Aa1s+6 Aa1s+6 Bb1s+3 Cc1+6 Aa1s+6 Bb1+3 Aa1s+6
Span 286.400 184.300 280.600 331.100 276.300 289.800 289.400 269.100 283.100 284.000 230.500 296.800 290.200 288.400
Lokasi
STRINGING
ERECTION 28/8/'14 23/10/'14 13/6/'14 23/10/'14 22/10/'14 09/6/'14 29/10/'14 24/10/'14 09/6/'14 30/10/'14 06/6/'14 07/11/'14 11/12/'14 13/12/'14 19/11/'14
Final Cek Erection 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 14/5/'18 12/5/'18 12/5/'18 12/5/'18
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test
Jenis Pondasi Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal
Kelas Pondasi 1 1 1 4 1 4 4 1 4 4 4 4 1 1 4
Nomer Tower 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196
Type tower Aa1s+6 Aa1s+6 Bb1+6 Bb1+9 Aa1s+0 Aa1s+0 Bb1+6 Aa1s+3 Aa1s+6 Bb1+3 Bb1+6 Aa1s+12 Aa1s+0 Aa1s+3 Cc1+0
Span 260.000 297.100 258.200 317.800 265.600 315.400 230.000 282.500 444.800 339.900 189.700 495.300 167.900 445.100
Lokasi
PT PLN ( Persero ) PUSAT MANAJEMEN KONSTRUKSI UNIT
MANAJEMEN KONSTRUKSI II
TEAM SUPERVISI KONSTRUKSI JARINGAN WILAYAH NTT
ERECTION 19/11/'14 09/12/'14 09/12/'14 21/12/'14 23/11/'14 07/06/'15 12/01/'15 30/05/'15 18/12/'14 03/01/'15 26/12/'14 19/01/'15 28/01/'15 30/05/'15 08/4/'14
Final Cek Erection 12/5/'18 12/5/'18 12/5/'18 12/5/'18 12/5/'18 12/5/'18 12/5/'18 12/5/'18 12/5/'18 12/5/'18 12/5/'18 12/5/'18 12/5/'18 11/5/'18 11/5/'18
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test
Jenis Pondasi Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal
Kelas Pondasi 4 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Nomer Tower 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210
Type tower Cc1+0 Aa1s+6 Bb1+3 Aa1s+3 Aa1s+3 Aa1s+6 Aa1s+6 Bb1+3 Aa1s+3 Aa1s+6 Bb1+9 Aa1s+9 Aa1s+3 Aa1s+9 Aa1s+6
Span 251.700 289.800 271.900 280.100 239.300 285.400 267.500 201.000 204.700 262.800 291.300 272.200 277.600 273.100
Lokasi
STRINGING
ERECTION 08/4/'14 02/4/'14 04/4/'14 01/4/'14 26/3/'14 17/5/'14 10/3/14 11/3/14 01/3/14 25/3/14 10/7/14 10/5/14 04/11/14 10/4/14
Final Cek Erection 11/5/'18 11/5/'18 11/5/'18 11/5/'18 11/5/'18 11/5/'18 11/5/'18 11/5/'18 11/5/'18 11/5/'18 11/5/'18 11/5/'18 11/5/'18 11/5/'18
Re-survey
Pemb. Lahan
Soil Investigation
Galian tanah
D C D C D C D C D C D C D C D C D C D C D C D C D C D C
Cor pondasi
A B A B A B A B A B A B A B A B A B A B A B A B A B A B
Urugan tanah
Grounding Test
Jenis Pondasi Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal Normal
Kelas Pondasi 1 1 1 1 4 1 1 1 1 1 1 1 1 1
Nomer Tower 210 211 212 213 214 215 216 217 218 219 220 221 223 224
Type tower Aa1s+6 Aa1s+6 Aa1s+9 Bb1+3 Aa1s+6 Aa1s+3 Bb1+0 Aa1s+3 Aa1s+3 Bb1+0 Cc1+3 Aa1s+6 Aa1s+12 Ddr1+6
Span 230.300 380.300 276.500 233.800 269.500 300.000 165.500 258.000 454.500 188.000 230.800 335.000 349.500 70.0
Lokasi
Keterangan Tanggal Final Check Tower Telah Selesai Pondasi Selesai Cor Erection Tower Telah Selesai