Professional Documents
Culture Documents
KTR Summary of Activities 3gi Week 10 2021
KTR Summary of Activities 3gi Week 10 2021
Reported Weld
DATE DAY TEAM Planned / Executed Activities Completed NOTES Accept/Reject
Analysis of LTCS 3X 16mm CW-M202A-M202B-025-02 M202A-M202B- No delays. 2 welds accept. One weld reject (CW-R602A-R603A-201-01)
Team 1 025-01, CW-R602A-R603A-201-01 yes Reject
No permit in place. Left site at 11 am with problem unresolved. Scanned weld in afternoon as requested.
Team 1
AM Calibration for 20'x33mm. No scanning due to permit issues. yes
10-Mar Wed Kenny
Partially scanned F22 CW-M253A-M253B-019-01C2 BPWHT Analysis Finish scanning weld tomorrow.
PM yes Accept
and report for 14X46 F22 FW-04C1 BPWHT
No Delays
Team 1
AM Finish scanning F22 CW-M253A-M253B-019-01C2 BPWHT yes
11-Mar Thu Kenny
Analysis and report forF22 CW-M253A-M253B-019-01C2 BPWHT
PM yes Accept
Analysis and report forLTCS 3'' CW-M201A-M201B-022-01
No delays. One weld reject CW-M201A-M201B-029-02
AM Calibration and scan of F22 16x52 FW-08 YES
Team 1
12-Mar Fri Kenny
Finish scanning of F22 16x52 FW-08. Supplementary MUT on 3"x16
PM YES Reject
welds. Report Sent for CW-M201A-M201B-029-02
No delays
Team 1
AM Scanning of 16x52 F22 CW-M253A-M253B-005-01C1. YES
13-Mar SAT Kenny
PM Scanning of 16x52 F22 CW-M253A-M253B-005-01C1. YES
2 Regular Water Deliveries. Coffee Lady is getting Angry at the local guys for taking 2 Monitor running of heater in Calibration workshop.
water
3 3 We are experiencing delays in the issue of NDT requests. We are unable to proceed with reporting and sign off
until these have been receved. Requests should be issued based on the planned week schedule.
4 4 It is critical to receive permit ASAP every morning. Delays in on site scanning results in lost productivity and
leaves no time to rectify any on site scanning issues, should they arise.