Professional Documents
Culture Documents
Project Managemnt - Delhi-5
Project Managemnt - Delhi-5
Project Managemnt - Delhi-5
EF of A =
ES ES of A + 2
of A
A
Start 0 2
0 0
2
ES/EF Network
A
0 2
2 EF of B =
ES ES of B + 3
0
Start
0 of B
B
0 0 3
3
ES/EF Network
A C
0 2 2 4
2 2
Start
0 0
B
0 3
3
ES/EF Network
A C
0 2 2 4
2 2
Start
0 0
= Max (2, 3) D
0
3 7
B
0 3
3
4
ES/EF Network
A C
0 2 2 4
2 2
Start
0 0
B D
0 3 3 7
3 4
ES/EF Network
A C F
0 2 2 4 4 7
2 2 3
Start E H
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
3 4 5
Backward Pass
Begin with the last event and work backwards
Latest Finish Time Rule:
► If an activity is an immediate predecessor for just a
single activity, its LF equals the LS of the activity that
immediately follows it
► If an activity is an immediate predecessor to more than
one activity, its LF is the minimum of all LS values of all
activities that immediately follow it