Professional Documents
Culture Documents
Project Managemen1 Notes
Project Managemen1 Notes
Key Characteristics
As follows from the given definition, any project can be characterized by these
characteristics:
Temporary. This key characteristic means that every project has a finite
start and a finite end. The start is the time when the project is initiated and
its concept is developed. The end is reached when all objectives of the
project have been met (or unmet if it’s obvious that the project cannot be
completed – then it’s terminated).
Unique Deliverable(s). Any project aims to produce some deliverable(s)
which can be a product, service, or some another result. Deliverables
should address a problem or need analyzed before project start.
A project life cycle is the sequence of phases that a project goes through from its
initiation to its closure. The number and sequence of the cycle are determined by the
management and various other factors like needs of the organization involved in the
project, the nature of the project, and its area of application. The phases have a definite
start, end, and control point and are constrained by time. The project lifecycle can be
defined and modified as per the needs and aspects of the organization. Even though every
project has a definite start and end, the particular objectives, deliverables, and activities
vary widely. The lifecycle provides the basic foundation of the actions that has to be
performed in the project, irrespective of the specific work involved.
Project life cycles can range from predictive or plan-driven approaches to adaptive or
change-driven approaches. In a predictive life cycle, the specifics are defined at the start
of the project, and any alterations to scope are carefully addressed. In an adaptive life
cycle, the product is developed over multiple iterations, and detailed scope is defined for
iteration only as the iteration begins.
Concerned stakeholders
2. The Planning Phase: The purpose of this phase is to lay down a detailed strategy
of how the project has to be performed and how to make it a success.
Implementation Planning
3. The Execution Phase: In this phase, the decisions and activities defined during
the planning phase are implemented. During this phase, the project manager has to
supervise the project and prevent any errors from taking place. This process is also
termed as monitoring and controlling. After satisfaction from the customer,
sponsor, and stakeholder’s end, he takes the process to the next step.
4. The Termination Phase: This is the last phase of any project, and it marks the
official closure of the project.
This general lifecycle structure is used when dealing with upper management or other
people less familiar with the project. Some people might confuse it with the project
management process groups, but the latter contains activities specific to the project. The
project lifecycle, on the other hand, is independent of the life cycle of the particular
outcome of the project. However, it is beneficial to take the current life-cycle phase of the
product into account. It can provide a common frame of reference for comparing different
projects
The generic life cycle structure commonly exhibits the following characteristics:
At the start, cost and staffing levels are low and reach a peak when the work is in
progress. It again starts to drop rapidly as the project begins to halt.
The typical cost and staffing curve does not apply to all projects. Considerable
expenses are required to secure essential resources early in its life cycle.
Risk and uncertainty are at their peak at the beginning of the project. These factors
drop over the lifecycle of the project as decisions are reached, and deliverables are
accepted.
The ability to affect the final product of the project without impacting the cost
drastically is highest at the start of the project and decreases as the project advances
towards completion. It is clear from the figure 2 that the cost of making new changes and
rectifying errors increases as the project approaches completion.
These features are present almost in all kinds of project lifecycles but in different ways or
to different degrees. Adaptive life cycles are developed particularly with the intent of
keeping stakeholder influences higher and the costs of changes lower all through the life
cycle than in predictive life cycles.
Whatever project it is, a project manager usually spends most of the time at this
stage.
During the execution of the project, people perform their tasks and progress
information is exchanged through regular team meetings, so-called progress status
meetings .
The project manager uses this information to maintain control over the project
direction by comparing progress reports with the project plan, to measure the
performance of activities and take corrective actions if necessary.
The main strategy should always be to bring the project back to its original
course,that of the project plan drawn up in the previous phase. If this is not possible,
the changes from the original plan must be recorded and the modified plan must be
formalized.
Once the results of the various steps have been produced and the client has
accepted the final solution, the project is ready for closure.
Project Life Cycle: The closing phase
During this closing phase, the emphasis is placed on:
the final results;
the delivery of project documentation;
the termination of supplier contracts;
the release of project resources;
the communication of the closure of the project to all the stakeholders.
The last remaining step is to conduct an analysis of what went well and what did not.
Through this type of analysis you gain experience and knowledge, are gained,
factors that will help the project manager, and the team in general, for future
projects.
In reality, it isn’t only important to conclude a project successfully, but also to be able
to execute it in the way that was set in the original project plan.
There is no shortage of cases in which the objective has been achieved despite
having experienced a phase of execution full of changes, delays and problems.
The closure phase also serves to analyze this, in order to avoid making the same
mistakes in the future and not adequately assessing certain risks.
The four phases of this life cycle may vary according to the sector and the type of
project, but in general they are valid in any area.
When a project manager follows Project Life Cycle taking into account all the factors
of each individual phase, he will have already taken the first step towards success.
That’s a mouthful!
Let’s try another definition, this time from the Association of Project Management:
“A Work Breakdown Structure (WBS) is a hierarchical structure of things that the
project will make or outcomes that it will deliver”
Essentially, the WBS defines the “what” of the project. Everything you need to
accomplish in the project is displayed in a single, easy to understand chart. The
purpose of this chart is to break down complex activities into smaller, more
management constituents.
For example, here’s a WBS example for an aircraft system:
Developing an aircraft system is obviously a very complex endeavor. You need
an aircraft (which itself is an extremely complex undertaking), a system to train
staff and pilots, a way to manage infrastructure, etc.
As shown above, a WBS breaks down all these complex activities into smaller,
more management constituent parts.
Thus, you might have one group responsible for building an aircraft. Within this
group, you might have one team focused on building the airframe, another on
creating a propulsion system, and so on.
It’s common to have three levels of decomposition in the WBS. You might have a
fourth and even a fifth level in case of extremely complex projects. For most
projects, however, three levels will suffice.
Here’s another example of a bicycle construction broken down into three levels:
The numbers next to each item indicate the number of hours or resources
required to complete the work. The sum of all these must be 100 at each level.
This is the oft-quoted “100% rule” - that the sum of the work at each “child” level
must be 100% of the work at the “parent” level.
You’ll notice that the WBS doesn’t describe any actions. Instead, every item is a
noun describing an end product - a bicycle seat, fork, handlebar, etc.
This is one of the fundamental features of a WBS: it describes deliverables, not
the activities necessary to get there. Every item in the WBS must correspond to
an end product (real or virtual). If there are any verbs in your WBS, then you’re
doing something wrong.
For example, if you’re creating a work breakdown structure for manufacturing a
car, you’ll include items such as “car body” (a deliverable), not “welding steel” (an
activity).
Before we dive further into the benefits and impact of a WBS, there are a few
additional definitions you should know.
Additional Definitions
Throughout this article and others related to WBS, you’ll come across terms such
as “work”, “deliverable”, “work package”, etc.
In the context of project management, these terms often have very specific
definitions:
Work: According to PMBOK, work refers to “work products or deliverables
that are the result of effort and not the effort itself”. That is, “work” defines the end
result of any activity. The work remains constant even though the amount of
effort needed to get there might inflate/deflate.
This is a three-tier WBS with each level denoted with numerical notation (such as
“1.1.2”). For each subsequent level, you’d add another decimal to the notation
(such as “1.1.2.1”).
Also note how the WBS is organized into broad deliverables and sub-
deliverables, all of which are nouns, not activities. Further, if you were to add up
all the deliverables together, you’d get the first level in the WBS, i.e. the 100%
rule.
This is the key defining trait of a good WBS.
Note that the WBS lists activities (“cut lawn”) instead of deliverables. This
wouldn’t pass muster in a formal work breakdown structure, but if you’re using
something internally, it doesn’t really matter as long as each level makes sense
to you.
Computer program WBS example
In this third WBS example from VisualParadigm.com, we see one of the biggest
mistakes people make when creating the WBS: mistaking activities for
deliverables.
As you can see below, the third-level in the WBS identifies activities such as
“develop business case” or “perform primary planning”.
This is superfluous within the context of a WBS. If you remove the verb from
each of these WBS levels, you’d get a deliverable (i.e. a noun), not an activity.
That is, you don’t need “develop business case” - just “business case” is enough.
Keep this in mind when you create your work breakdown structures. Remove
verbs from each WBS level. You are, after all, describing things that need to be
delivered, not the tasks necessary to deliver them.
Work Breakdown Structure vs Project
Schedule vs Project Plan
Another common source of confusion for beginners is the difference between the
work breakdown structure, project schedule, and project plan.
While these three things often describe the same thing - what is to be achieved in
the project - they vary greatly in scope and details.
In terms of the level of detail, you can think of the project plan as the broadest,
followed by the project schedule, and finally, the work breakdown structure.
This might make you ask: why bother with the work breakdown structure at all?
Can’t you get all the same details in the project schedule?
As you’ll see below, the WBS has several advantages over the project schedule.
You can also use the map of deliverables (and the relationships between them)
in a WBS to figure out the resources to be used in their creation. This is called
a Resource Breakdown Structure (RBS).
A resource breakdown structure consists of both the material and human
resources required to complete a deliverable. For example, if you’re creating a
chair as part of a larger house remodeling project, you’ll need:
A carpenter
How to Create a Work Breakdown
Structure
The output of the WBS development process might seem simple: a short
document with a list of deliverables. To create it, however, you need a thorough
understanding of the project’s scope, your team’s capabilities, and your
stakeholders’ requirements.
Here’s a process for creating a WBS from scratch.
You’ll want to refer to your project charter to develop the scope statement and
scope management plan.
The output of the entire WBS development process is as follows:
WBS dictionary
Scope baseline
There are two heuristics you can follow for determining major deliverables at the
2nd level:
Definable: The work package should have a definite beginning and end,
and should be understood by all project participants.
In case the work can’t meet the above requirements, you can decompose the
WBS into another level.
There are a few heuristics you can follow for determining work packages:
8/80 rule: A common rule of the thumb is that each work package must be
no longer than 80 hours and no less than 8 hours in total length. If it is longer,
decompose it further. If it is shorter, think of going up by one level.
Department
Date of assignment
Due date
Estimated cost
Another option is to create a flowchart:
Once you’ve made the work breakdown structure, share it with your team. Use it
to get a high-level overview of the project’s progress.
All risk management processes follow the same basic steps, although
sometimes different jargon is used to describe these steps. Together these 5
risk management process steps combine to deliver a simple and effective risk
management process.
Step 1: Identify the Risk. You and your team uncover, recognize and
describe risks that might affect your project or its outcomes. There are a
number of techniques you can use to find project risks. During this step you
start to prepare your Project Risk Register.
Step 2: Analyze the risk. Once risks are identified you determine the
likelihood and consequence of each risk. You develop an understanding of the
nature of the risk and its potential to affect project goals and objectives. This
information is also input to your Project Risk Register.
Step 5: Monitor and Review the risk. This is the step where you take your
Project Risk Register and use it to monitor, track and review risks.
Risk is about uncertainty. If you put a framework around that uncertainty, then
you effectively de-risk your project. And that means you can move much more
confidently to achieve your project goals. By identifying and managing a
comprehensive list of project risks, unpleasant surprises and barriers can be
reduced and golden opportunities discovered. The risk management process
also helps to resolve problems when they occur, because those problems
have been envisaged, and plans to treat them have already been developed
and agreed. You avoid impulsive reactions and going into “fire-fighting” mode
to rectify problems that could have been anticipated. This makes for happier,
less stressed project teams and stakeholders. The end result is that you
minimize the impacts of project threats and capture the opportunities that
occur.
Each of these mitigation techniques can be an effective tool in reducing individual risks and the
risk profile of the project. The risk mitigation plan captures the risk mitigation approach for each
identified risk event and the actions the project management team will take to reduce or
eliminate the risk.
Risk avoidance usually involves developing an alternative strategy that has a higher probability
of success but usually at a higher cost associated with accomplishing a project task. A common
risk avoidance technique is to use proven and existing technologies rather than adopt new
techniques, even though the new techniques may show promise of better performance or lower
costs. A project team may choose a vendor with a proven track record over a new vendor that is
providing significant price incentives to avoid the risk of working with a new vendor. The
project team that requires drug testing for team members is practicing risk avoidance by avoiding
damage done by someone under the influence of drugs.
Risk sharing involves partnering with others to share responsibility for the risk activities. Many
organizations that work on international projects will reduce political, legal, labor, and others
risk types associated with international projects by developing a joint venture with a company
located in that country. Partnering with another company to share the risk associated with a
portion of the project is advantageous when the other company has expertise and experience the
project team does not have. If the risk event does occur, then the partnering company absorbs
some or all of the negative impact of the event. The company will also derive some of the profit
or benefit gained by a successful project.
Risk transfer is a risk reduction method that shifts the risk from the project to another party. The
purchase of insurance on certain items is a risk transfer method. The risk is transferred from the
project to the insurance company. A construction project in the Caribbean may purchase
hurricane insurance that would cover the cost of a hurricane damaging the construction site. The
purchase of insurance is usually in areas outside the control of the project team. Weather,
political unrest, and labor strikes are examples of events that can significantly impact the project
and that are outside the control of the project team.
Contingency Plan
The project risk plan balances the investment of the mitigation against the benefit for the project.
The project team often develops an alternative method for accomplishing a project goal when a
risk event has been identified that may frustrate the accomplishment of that goal. These plans are
called contingency plans. The risk of a truck drivers’ strike may be mitigated with a contingency
plan that uses a train to transport the needed equipment for the project. If a critical piece of
equipment is late, the impact on the schedule can be mitigated by making changes to the
schedule to accommodate a late equipment delivery.
Contingency funds are funds set aside by the project team to address unforeseen events that
cause the project costs to increase. Projects with a high-risk profile will typically have a large
contingency budget. Although the amount of contingency allocated in the project budget is a
function of the risks identified in the risk analysis process, contingency is typically managed as
one line item in the project budget.
Some project managers allocate the contingency budget to the items in the budget that have high
risk rather than developing one line item in the budget for contingencies. This approach allows
the project team to track the use of contingency against the risk plan. This approach also
allocates the responsibility to manage the risk budget to the managers responsible for those line
items. The availability of contingency funds in the line item budget may also increase the use of
contingency funds to solve problems rather than finding alternative, less costly solutions. Most
project managers, especially on more complex projects, will manage contingency funds at the
project level, with approval of the project manager required before contingency funds can be
used.