Download as pdf or txt
Download as pdf or txt
You are on page 1of 13

Case Study

Effect of Open-Ended PHC Pile Installation during


Embankment Widening on the Surrounding Soil
Guowei Li 1; Andrew Cudzo Amenuvor 2; Yuzhou Hou 3; Xiaocen Lu 4;
Jiantao Wu 5; and Thang Ngoc Nguyen 6

Abstract: This paper investigates the effect of jacking two groups of open-ended prestressed high-strength concrete (PHC) piles on an
Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.

existing highway embankment based on field measurements of excess pore pressure and lateral soil displacement. Excess pore pressure
due to pile jacking increased with depth and decreased with increasing distance from the pile; the influence reached a distance of 43 pile
diameters from the pile axis. For pile groups, the amount of excess pore pressure dissipated decreased with increasing depth and varied from
54% to 100% in 20 days. Lateral soil displacement and excess pore pressure continued to increase for a period of time after the end of pile
jacking, and this could have resulted in significant inclination of piles if pile installation was too quick and pile spacing was too small. Lateral
soil displacement due to pile group decreased with decreasing distance to the existing embankment as a result of higher soil stiffness
and strength produced by the embankment loading. The effect of pile group installation on the existing embankment was negligible.
DOI: 10.1061/(ASCE)GT.1943-5606.0002016. © 2018 American Society of Civil Engineers.
Author keywords: Existing embankment widening; Prestressed high-strength concrete pile; Pile jacking; Excess pore pressure; Lateral
displacement.

Introduction strength, pore pressure, and soil displacement during and after pile
installation.
Many existing highway embankments in China have been under- The installation of piles in clay causes an initial reduction in
going expansion works, and some of these highways are located in undrained shear strength in the clay around the piles. Orrje and
soft ground terrain, which requires improvement with piled foun- Broms (1967) observed that the undrained shear strength around
dations. Proper evaluation of the effects of pile installation on the a single pile in a sensitive clay was reduced up to a distance of
existing road is therefore important in these projects. five pile radii from the pile axis. The largest decrease was observed
Pile jacking allows for piles to be installed without the noise near the surface of the pile, where the reduction was about 40%. An
and ground vibrations associated with conventional driven piles. increase in shear strength was observed 9 months after pile driving,
However, ground disturbance associated with pile installation is but the full initial strength was not regained. Tomlinson (1969) con-
inevitable. Soil deformation and excess pore pressure resulting cluded from a review of some case studies that at least 75% of the
from pile installation may exert lateral pressures and vertical ultimate bearing capacity was achieved within 30 days after pile
forces on the piles and therefore have a negative impact on the driving. In contrast, numerical studies by Randolph et al. (1979)
project and existing structures. Soil disturbances due to pile instal- have shown that in any clay, when consolidation is complete, the
lation have been a subject of many investigations over the years. new strength is 60% higher than the initial in situ value.
These investigations have usually involved the assessment of shear The dissipation of pore pressures induced by pile installation is
related to the regaining of shear strength after pile installation. Data
1
Professor, Key Laboratory of Ministry of Education for Geotechnique presented by Soderberg (1962) showed that the increase in the
and Embankment Engineering, Hohai Univ., Nanjing, Jiangsu 210098, ultimate bearing capacity of a pile was very similar in character to
China; Professor, Highway and Railway Research Institute, Hohai Univ., the rate of dissipation of excess pore pressure with time. A review
Nanjing, Jiangsu 210098, China. Email: lgwnj@163.com of some case histories of pore pressures developed due to pile driv-
2
Ph.D. Student, Geotechnical Research Institute, Hohai Univ., Nanjing,
ing by Poulos and Davis (1980) showed that very high excess pore
Jiangsu 210098, China (corresponding author). ORCID: https://orcid.org
/0000-0002-3022-9645. Email: ac.amenuvor@gmail.com; 2257917007@
pressures developed in the vicinity of the pile. Some of these pore
qq.com pressures were as high as 1.5–2.0 times the in situ vertical effective
3
Ph.D. Student, Geotechnical Research Institute, Hohai Univ., Nanjing, stress. There is, however, considerable scatter in the data reported,
Jiangsu 210098, China. Email: 291190849@qq.com which has mainly been attributed to differences in soil type. Higher
4
Ph.D. Student, Geotechnical Research Institute, Hohai Univ., Nanjing, pore pressures have been associated with sensitive clays. Field ex-
Jiangsu 210098, China. Email: luxiaocen@hhu.edu.cn periments performed by Seed and Reese (1957) in San Francisco
5
Associate Professor, Highway and Railway Research Institute, Hohai Bay mud with piles instrumented with load, total pressure, and pore
Univ., Nanjing, Jiangsu 210098, China. Email: jiantao.wu@hhu.edu.cn pressure gauges at locations along their length showed that the pile
6
Lecturer, Faculty of Civil Engineering, Water Resources Univ., Hanoi installation generated large pore water pressures at the pile surface,
100000, Vietnam; Ph.D. Student, Geotechnical Research Institute, Hohai
with only a slight increase at a distance of 15 pile diameters away.
Univ., Nanjing, Jiangsu 210098, China. Email: thangnn@tlu.edu.vn
Note. This manuscript was submitted on January 17, 2018; approved on Field measurements indicated that the increase in pore pressures
August 24, 2018; published online on December 10, 2018. Discussion per- resulted from the transfer of pressures generated from pile instal-
iod open until May 10, 2019; separate discussions must be submitted for lation to the soil. Bozozuk et al. (1978) reported on soil disturbance
individual papers. This paper is part of the Journal of Geotechnical and due to driving of 116 concrete piles in sensitive marine clays in a
Geoenvironmental Engineering, © ASCE, ISSN 1090-0241. construction project in eastern Canada. Maximum pore pressures

© ASCE 05018006-1 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2019, 145(2): 05018006


after pile driving within the group and 6 m (20 pile diameters) from which lies within the K55+630 to K55+660 and K55+670 to
the group were over 35%–40% of the total overburden stress, and K55+720 sections of the highway, consists of fill, silty clay, organic
the influence of pile driving on pore pressure 20 m away from the clay, and slightly weathered limestone. The geological profile of
group was very small. The excess pore pressures dissipated fully the site, developed from cone penetration test (CPT) test data, is
eight months after pile driving. Results of large-scale driving of piles presented in Fig. 1(a). Fig. 1(b) shows the undrained shear strength
in the Chiayi-Taipo area in Taiwan reported by Hwang et al. (2001) of the soil obtained from quick direct shear tests at K55+660 and
showed that the maximum excess pore pressure generated decreased K55+680. The properties of the soil at sections K55+630 to K55
with distance from the pile. The generated excess pore pressure be- +660 and K55+670 to K55+720 are presented in Table 1.
came negligible at a distance of 15 pile diameters from the piles.
Pestana et al. (2002) carried out full-scale closed-ended pile tests in
the young bay mud deposit of the San Francisco Peninsula. Higher Pile Setup and Instrumentation
excess pore pressures were observed for points close to the piles,
and decreased with increasing distance from the pile wall. Exponen- Pile Setup
tial decay of excess pore pressure with time was also observed. At
Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.

distances of more than one pile diameter from the pile wall, excess Fig. 2 shows the pile setup of sections K55+630 to K55+660
pore pressure dissipated upto 80% between 50 and 80 days. and K55+670 to K55+720. The pile identity is expressed as #
Fellenius et al. (2003) conducted static loading tests on a 45-m-long (row number)-(column number); for example, #4-8 indicates the
pile and showed that pore pressures induced by pile driving dissi- pile in the fourth row and the eighth column. The arrows show
pated 48 days after pile driving. Bogard and Matlock (1990a, b) and the sequence of pile installation. For the purpose of investigating
Bogard et al. (1991) presented results of open- and closed-ended the effect of jacking a single pile on the surrounding ground, piles
model pile tests performed in normally consolidated clays. Pore #4-8 and #4-4 in sections K55+630 to K55+660 and K55+670 to
pressures and total lateral stresses were highest for closed-ended K55+720, respectively, were jacked and their effects investigated
penetration, with relatively small influences from pile diameter. two days before the installation of the entire pile group began
Cooke and Price (1973) studied a 168-mm-diameter instru- in each section. A total of 52 piles, arranged in a square pattern
mented pile jacked into overconsolidated London clay. Outward with center-to-center spacing of 2.6 m, were installed in section
lateral displacements ranging from 10 to 20 mm were observed, K55+630 to K55+660. Pile installation started with row 4 (pile
depending on initial distance from the pile. Data from Hwang et al. #4-0), followed by rows 5, 3, and 2. The piles in this section had
(2001) showed that lateral displacement of soil due to pile driving a length, diameter, and wall thickness of 11 m, 0.3 m, and 0.07 m,
decreased with increasing distance from the pile. The lateral dis- respectively. A total of 66 piles, arranged in a square pattern
placements at distances of 3 and 1.5 pile diameters from the pile with center-to-center spacing of 3.0 m, were installed in section
were 29 and 36 mm, respectively. Massarsch and Wersäll (2013) K55+670 to K55+720. In this section, pile installation started from
concluded from model tests of pile group installation that ground row 2 (pile #2-18), followed by rows 3, 4, and 5. The piles in this
and pile movements do not occur in straight lines but follow an section had a length, diameter, and wall thickness of 13 m, 0.3, and
incremental path in a direction that depends on the order of pile 0.07 m, respectively. In both sections, the piles were jacked into the
installation. However, the displacement of a given element of soil slightly weathered limestone.
depends on the cumulative effect of all installed piles, regardless of
their order of installation. Inclinometer Instrumentation
Results of ground heave measurements by Gue (1984) of open- and
In-place inclinometers with an automatic data collection system
closed-ended piles from model tests showed that the amount of heave
were used to record changes in lateral soil displacement during pile
resulting from driving closed-ended piles was about four times that
installation. The inclinometers used (model JMQJ-74XX, Chang-
of similar open-ended piles (with an area ratio of 34%). In contrast,
sha Kingmach Measurement & Monitoring Technology, Changsha,
Steenfelt et al. (1981) conducted model tests to observe soil deforma-
China) have micro-electro-mechanical systems (MEMS) dual axis
tion patterns around open- and closed-ended piles jacked into
tilt sensors. They have a measurement range, resolution, and accu-
clay. The results showed no measurable ground heave. Pestana et al.
racy of 30°, 0.008°, and 0.1%, respectively, for temperature ranges
(2002) drove a 610-mm-diameter, 36.6-m-long closed-ended pile
between −20°C and þ60°C. The coordinates were set with the x-axis
into young bay mud. No soil heave was noticed at the site, and this
parallel to the existing embankment and the y-axis perpendicular to
was attributed to the confining effect of the stiff fill layer at the site.
the existing embankment, with its positive direction pointing away
The literature review shows a significant number of studies con-
from it. Four inclinometer casings were installed to different depths
ducted on pile installation and its influence on ground movement
within the limestone in each section. The inclinometers were in-
and pore water pressure generation in the ground. However, a vast
stalled to different depths because of slight variations in the grade
majority of these studies focused on the effects of driving a single
of the limestone at different locations. Details of the inclinometer
pile, with only a few focusing on pile groups. Also, there is gen-
instrumentation are summarized in Fig. 2 and Table 2.
erally a lack of information on the effects of jacking pile groups
on existing structures. Therefore, this study seeks to investigate the
influence of jacking open-ended prestressed high-strength concrete Piezometer Instrumentation
(PHC) piles on an existing highway foundation based on field Excess pore pressure measurements were obtained with vibrating
measurements of pore pressure and lateral soil displacement in wire (VW) piezometers installed in four different boreholes in each
the Guangqing Highway Expansion Project in China. of the sections. The boreholes were grouted with cement-bentonite
grout in order to increase the response time of the piezometers; VW
Test Site Description piezometers respond rapidly to pore pressure changes when in-
stalled in material similar to bentonite (Penman 1961; Mckenna
The Guangqing highway lies mainly in Quaternary flood plains 1995). The piezometers used (model JTM-V3000B, Changzhou
made up of organic clay, silt, and other organic soils, which are Jintumu Engineering Instrument, Changzhou, China) have a meas-
widely spread in plains and valleys. The geology of the test site, urement range of up to 200 kPa and a measurement accuracy

© ASCE 05018006-2 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2019, 145(2): 05018006


Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.

(a)

Undrained shear strength (kPa)


2 4 6 8 10 12 14 16

K55+660
4
K55+680
Depth (m)

(b)

Fig. 1. (a) Geological profile of test site; and (b) undrained shear strength for section K55+660 to K55+680.

Table 1. Soil properties


Section Soil category w (%) γ (kN=m3 ) e Cc PL (%) LL (%)
K55+630 to K55+660 Fill of existing embankment 20.3 17.9 0.78 0.15 — —
Silty clay 20.3 16.9 0.89 0.23 26.0 40.0
Organic clay 47.8 17.8 1.60 0.34 33.3 52.6
K55+670 to K55+720 Fill of existing embankment 27.6 17.8 0.88 0.21 — —
Silty clay 28.5 19.1 0.77 0.17 21.0 31.9
Organic clay 41.9 17.3 1.17 0.34 28.6 48.1
Note: w = moisture content; γ = unit weight; e = void ratio; Cc = compression index; PL = plastic limit; and LL = liquid limit.

© ASCE 05018006-3 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2019, 145(2): 05018006


Y

2011-12-18
Starting point

0.8m
#4-4 4
3.6m 3.4m 8.6m
I4 X
13.6m I3 I2 I1
13.0m 13.0m 14.5m

3.0m
5
4.6m 3.0m 7.9m

P4 P3 P2 P1
6

17 0.16m
Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.

2011-12-22

3.0m 2011-12-20 0.3m


18
3.0m
#2-18

10
0.4m 3.6m 3.0m 9.0m

K4 K3 K2 K1

9
1.0m 4.8m 3.5m 7.4m
2011-12-9

C4 C3 C2 C1
11.2m 12.0m 15.0m 19.0m

8
2.6 m

Starting point 2.6m LEGEND


#4-8
Pile

7
Piezometer
2011-12-11

Inclinometer

#4-0 0
C-1

6.0m

Existing
Embankment
9.5m

Pile Driving
Area C-4 C-3 C-2
0.0m
6.5m
Fill Fill Silty
3.5m

1.8m 2.0m Clay


8.5m
K4-3.5 K3-3.5 K2-3.5 Silty K1-9.5
Clay
2.0m

K4-5.5 K3-5.5 5.0m


11.0m
11.2m

5.0m

Organic K2-5.5
K3-7 Organic
Clay
Clay
K1-14.5
Organic
Clay
10.0m
Slightly weathered 16.5m
Limestone
Slightly weathered
Pile
Limestone
2.6m 2.6m 2.6m 12.5m
19.0m
Slightly weathered
Limestone
15.0m

Fig. 2. Setup of piles and instrumentation.

© ASCE 05018006-4 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2019, 145(2): 05018006


Table 2. Inclinometer instrumentation of 0.1 kPa for temperature ranges between −25°C and þ60°C. The
Distance from piezometer layout for the pile groups is shown in Fig. 2 and Table 3;
shoulder of the piezometers were installed in four borings (K1, K2, K3, and K4
Depth embankment in Fig. 2) located within and outside the pile installation area. The
Section Inclinometer Location description (m) (m) initial pore pressure readings were taken when the piezometers
K55+630 to C1 Shoulder of embankment 13.0 0 equilibrated after curing of the grout.
K55+660 C2 Within pile group 16.0 7.4
C3 Within pile group 11.5 10.9
C4 Edge of pile group 11.2 15.7 Test Results and Analysis
K55+670 to I1 Shoulder of embankment 9.0 0
K55+720 I2 Within pile group 13.0 8.6 Excess Pore Pressure due to a Single Pile
I3 Within pile group 13.0 12.0
I4 Edge of pile group 13.0 15.6 In order to obtain accurate measurement of pore pressure, pile jack-
ing was carried out intermittently to allow the piezometers to equili-
Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.

brate before readings were taken. Fig. 3 shows a plot of excess pore
pressures generated at various depths during pile jacking as a func-
tion of time and pile tip depth. The pile tip depth is plotted against
Table 3. Piezometer instrumentation pile jacking time, and excess pore water pressure is plotted against
Distance from pile jacking time. A point on the pile tip depth curve is projected
shoulder of vertically onto the pore pressure curves for pore pressure values to
Piezometer Location Depth embankment be read. Excess pore pressures are generated and increased simul-
Section Borehole number description (m) (m) taneously at all depths with increasing depth of pile tip penetration
K55+630 K1 K1-9.5 Shoulder of 9.5 0 and time. It can also be observed that excess pore pressure is gen-
to K55+660 K1-14.5 embankment 14.5 0 erated at a particular depth before the pile tip reaches that depth. For
K2 K2-3.5 Within pile 3.5 9 instance, for the data for section K55+630 to K55+660 presented in
K2-5.5 group 5.5 9 Fig. 3(a), excess pore pressures of 0.2 and 0.8 kPa were generated
K3 K3-3.5 Within pile 3.5 12 at the piezometers located at depths of 5.5 and 7.0 m, respectively,
K3-5.5 group 5.5 12 when the pile tip reached a depth of 3.0 m. Although the piles
K3-7 7.0 12 in this section had a design length of 11 m, pile #4-8 was driven
K4 K4-3.5 Edge of 3.5 16
only 10 m because bedrock was encountered at that depth. A sim-
K4-5.5 pile group 5.5 16
ilar trend can be observed for section K55+670 to K55+720 in
K55+670 P1 P1-9.5 Shoulder of 9.5 0 Fig. 3(b), in which excess pore pressures of 0.2 and 0.2 kPa were
to K55+720 P1-11.5 embankment 11.5 0 generated at piezometers located at depths of 4.0 and 8.5 m, respec-
P2 P2-4.0 Within pile 4.0 7.9 tively, when the pile tip reached a depth of 3.0 m. Therefore, excess
P2-6.0 group 6.0 7.9 pore pressure generation is not limited to areas along the pile length
P3 P3-4.0 Within pile 4.0 10.9
but also reaches beyond the pile tip. From the general trend of
P3-6.0 group 6.0 10.9
P3-8.5 8.5 10.9 excess pore pressure increment with pile tip depth in both
P4 P4-4.0 Edge of 4.0 15.5 Figs. 3(a and b), pore pressure at a depth of 7 m is expected to
P4-6.0 pile group 6.0 15.5 be lower than that at a depth of 5.5 m, but the piezometer at a depth
of 5.5 m recorded a relatively low pore pressure. In addition, when

Fig. 3. Excess pore pressure at different depths as a function of time and pile tip depth: (a) section K55+630 to K55+660; and (b) section K55+670 to
K55+720.

© ASCE 05018006-5 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2019, 145(2): 05018006


Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.

Fig. 4. Excess pore pressure histories at specific depths: (a) section K55+630 to K55+660; and (b) section K55+670 to K55+720.

the pile tip reached or passed the depth of the piezometers, a sharp after pile jacking was completed. Increased pore pressure at the pile
increase in pore pressure was recorded for all piezometers except surface due to pile installation induced a pore pressure gradient in
the one at a depth of 5.5 m. This relatively low initial increment of the soil and a transient flow occurred in the soil with pore pressure
pore pressure at a depth of 5.5 m may have been due to the occur- migrating radially outward from the pile to the location of the
rence of relatively high permeability around that depth, leading to piezometers. This was responsible for the observed excess pore
rapid drainage and low pore pressure. pressure delay and the longer time needed for the piezometers far-
Fig. 4 shows excess pore pressure histories at various lateral dis- ther from the pile to reach peak excess pore pressures. Also, at the
tances and depths from the pile. In both Figs. 4(a and b), excess same distance of 4.0 m from the pile, peak excess pore pressures
pore pressures continued to increase, and then reached peak values were reached in 74, 332, and 1,352 min at depths of 3.5, 5.5, and
after pile jacking ceased, and the time at which peak values were 7.0 m, respectively. This may have been due to decreasing hydraulic
reached was later for deeper zones than for shallower zones. Table 4 conductivity with depth, as void ratio is expected to decrease with
presents a summary of excess pore pressure generation at vari- depth within the same material (note that the piezometers were in-
ous piezometer locations. In Fig. 4(a), as summarized in Table 4, stalled in the same material) due to increasing overburden stress,
the jacking of pile #4-8 in section K55+630 to K55+660 was causing reduced flow velocity with depth and increasing the time
completed in 26 min, but peak excess pore pressure was reached needed for pore pressures to migrate in the lateral direction. The
in 214 and 1,352 min at distances of 4.89 and 13.3 m, respec- data in Table 4 also show that peak excess pore pressure was reached
tively, for a constant depth of 3.5 m. A similar trend can be seen as long as 24 h after the completion of pile jacking. It can also be
in Fig. 4(b), also summarized in Table 4; the jacking of pile #4-4 in observed from Table 4 that pile jacking pore pressures influenced
section K55+670 to K55+720 was completed in 35 min, but peak a range not less than 13.0 m from the pile, which corresponds to
pore pressures were reached after a considerable length of time. 43 pile diameters. However, the ratio of maximum pore pressure to
The results strongly show a delay in excess pore pressure after the effective overburden stress varied from 0.6% at a distance of 13 m
end of pile jacking. In fact, data from a subsequent section on lat- to 26.7% at a distance of 3.8 m, which corresponds to 13.3 pile
eral displacement indicates that soil displacement increased after diameters. This value falls within the 10–20 pile diameters, reported
pile jacking, with maximum displacement attained several minutes by Seed and Reese (1957), Bjerrum and Johannessen (1960), Lo and
Stermac (1965), and Hwang et al. (2001), at which driving pore
Table 4. Summary of excess pore pressure generation pressures become negligible in clays.
Location End of Figs. 4(a and b) and Table 4 also show that excess pore pressure
jacking Peak Peak increased with increasing depth. The resistance of the soil to pile
Pile number/pile 0
Distance Depth EPWP EPWP time Dumax :σvo penetration increases with depth due to increasing confining stress
length/jacking time (m) (m) (kPa) (kPa) (min) (%) with depth, resulting in the pile exerting a higher radial stress (Ds
#4-8/10.0 m/26 min 4.0 3.5 2.5 4.6 74 16. or sr ) on the soil. According to Terzaghi’s effective stress principle,
4.0 5.5 1.3 9.6 332 23.4 the change in total stress (in this case sr ) must be equal to the
4.0 7.0 2.5 13.9 1,352 26.7 change in pore pressure (Du) under undrained conditions. There-
4.89 3.5 1.65 3.9 214 13.8 fore, as the change in total stress (sr ) increases with depth, there
13.3 3.5 0.1 1.6 1,352 2.2 should be a corresponding increase in the excess pore pressure
#4-4/13.0 m/35 min 4.69 4.0 1.7 5.1 175 14.9 (Du). This explains the increase in excess pore pressure with depth.
4.69 8.5 2.0 7.2 263 11.2 Fig. 5 shows excess pore pressure as a function of pile jacking
5.51 4.0 0.2 3.7 233 10.8 time and pile tip depth at constant depths and various lateral dis-
13.0 4.0 0.3 0.5 383 0.6 tances from pile. In the same way as in Fig. 3, a point on the pile
0 =
Note: EPWP = excess pore pressure; Dumax = peak pore pressure; and σvo tip depth curve is projected vertically onto the pore pressure curves
initial effective overburden stress. for pore pressure values to be read. Excess pore pressure at all

© ASCE 05018006-6 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2019, 145(2): 05018006


Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.

Fig. 5. Excess pore pressure at various lateral distances as a function time and pile tip depth: (a) section K55+630 to K55+660; and (b) section
K55+670 to K55+720.

distances increased simultaneously with pile tip penetration in ap- and section K55+670 to K55+720 [Fig. 5(b)] that the trend of ex-
proximately linear fashion. The trend of the curves is identical at all cess pore pressure as time progressed was similar at all distances
distances, and this indicates that soil disturbance due to pile jacking from the pile. It is also apparent that excess pore pressure decreased
may occur at different distances from the pile at almost the same with increasing distance from the pile. In Fig. 7, the ratios of maxi-
time. The relationship between excess pore pressure and distance mum excess pore pressure Dumax due to the jacking of piles #4-4
0
is well defined, such that excess pore pressure increased with de- and #4-8 to initial effective overburden stress svo at depths of 5.5
creasing distance to the pile. In section K55+620 to K55+660, as and 6.0 m, respectively, are plotted as a function of the ratio of
shown in Fig. 5(a), excess pore pressures at the end of pile jacking radial distance from pile r to pile radius a and then compared to
(26 min) were 2.5, 1.6, 1.2 and 0.1 kPa at 4.0, 4.89, 5.6, and 13.3 m, some previous published results, such as Bjerrum and Johannessen
respectively. Similarly, in section K55+670 to K55+720, as shown (1960), Soderman and Milligan (1961), Lo and Stermac (1965),
in Fig. 5(b), excess pore pressures increased with decreasing dis- Airhart et al. (1969), D’Appolonia and Lambe (1971), and Hwang
tance to the pile, from 0.3 kPa at 6.24 m to 1.7 kPa at 4.69 m at the et al. (1994, 2001). The excess pore pressure values in this study
end of pile jacking (35 min). were measured beyond r:a values of 25 and are in good agreement
Fig. 6 shows excess pore pressure histories at constant depths with the results of previous studies. Fig. 8 illustrates the process of
and various lateral distances from the pile during and after pile excess pore pressure generation and dissipation at various distances
jacking. It can be seen in section K55+620 to K55+660 [Fig. 6(a)] from the pile over time.

Fig. 6. Excess pore pressure histories at constant depths and various lateral distances from the pile: (a) section K55+630 to K55+660; and (b) section
K55+670 to K55+720.

© ASCE 05018006-7 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2019, 145(2): 05018006


the pile experiences a reduction in excess pore pressure during the
dissipation time, whereas the farthest point experiences an increase
in excess pore pressure. At points far from the pile, say D2, excess
pore pressure increases from t1 through t2 to t3 , followed by a de-
crease to t4 . At t4 there is excess pore pressure dissipation at all
distances from the pile. The dissipation continues until equilibrium
is reached at some time, t∞ .

Lateral Displacement of Soil due to a Single Pile


Lateral soil displacement due to a single pile jacking was assessed
with inclinometers in four inclinometer casings installed in section
K55+670 to K55+720. Lateral displacement monitoring began
before the start of pile jacking and continued up to 3 h after the
Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.

end of pile jacking.


Fig. 9 shows the variation of resultant lateral displacement
with depth immediately after pile jacking for the four inclinometer
casings. Lateral displacement generally decreased with increasing
Fig. 7. Variation of normalized excess pore pressure with normalized depth, which is reasonable, because the inclinometer casings were
radial distance from pile. a = pile radius; r = radial distance from fixed into the competent stratum. This observation is in agreement
pile. with that of Massarsch and Wersäll (2013). It can also be observed
that lateral displacement decreased with increasing distance from
the pile, with I3 (1.6 m from the pile) showing the highest value
of 6 mm, whereas I1 (12.7 m from the pile) showed the lowest value
Fig. 8(a) shows excess pore pressures at various times and of about 1 mm. The highest displacement in I3 occurred around a
distances from the pile at a depth of 3.5 m in section K55+630 to depth of 5 m. This may have been due to the higher stiffness and
K55+660. It took a longer time to reach peak values at longer dis- strength of the surface fill, which restricted horizontal deformation
tances from the pile than at shorter distances from the pile. Thus, to some extent, or to the rebound of the ground after the pile pen-
the excess pressure at a distance of 13.3 m, 35 min after pile jack- etrated to a deeper level. The small lateral displacement recorded at
ing, is lower than that at the same distance 1,325 min after pile I1 is as expected, because it was far away from the pile and very
jacking, since the peak value was not reached in 35 min. However, close to the existing embankment, which had higher stiffness and
2,816 min is within the period of dissipation of excess pore pressure strength and restricted lateral deformation to some extent. However,
(i.e., after peak value is attained) for all distances from the pile, so the maximum displacement at a point was not attained immediately
the excess pore pressure is lowest at all distances. Excess pore pres- after the end of pile jacking.
sure decreased at distances closer to the pile while at the same time Fig. 10 shows the variation of resultant lateral displacement with
increasing at distances farther from the pile as time progressed until depth at different times after pile jacking at I3. The lateral displace-
equilibrium was reached; at equilibrium, excess pore pressure is the ment of 6 mm at I3 immediately after the end of pile jacking in-
same at all distances. Fig. 8(b) presents a schematic of excess pore creased to 8 mm after 10 min and then reached the maximum value
pressure distribution over distance from the pile at different times, of 13 mm 22 min after the end of pile jacking. Thus, the maximum
t1 < t2 < t2 < t3 < t4 < t∞ , after pile jacking. The closest point to lateral displacement was not reached instantly at the end of pile

Fig. 8. Excess pore pressure generation and dissipation over time: (a) field data; and (b) schematic representation.

© ASCE 05018006-8 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2019, 145(2): 05018006


due to pile group installation during pile group installation and up
to 20 days after pile group installation.
Fig. 11 shows excess pore pressure histories for the various
piezometers over a period of more than 86 h for the entire pile
group in section K55+630 to K55+660. Excess pore pressure gen-
erally increased with time during pile group installation, with occa-
sional oscillations—the troughs indicating periods of dissipation at
night after pile installation in the day. Pile installation was carried
out within three days during the daytime, and the excess pore pres-
sure dissipated only slightly at night. As seen in Figs. 11(a and b),
piezometers at depths of 3.5 and 5 m experienced rapid dissipation
of excess pore pressure during breaks in pile installation, while the
excess pore pressures of piezometers at depths of 7.0 and 8.0 m
stabilized. The rapid dissipation of excess pore pressures at shallow
Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.

depths was due to the higher hydraulic conductivity of the soil at


these depths. The higher hydraulic conductivity was likely caused
by the presence of cracks, because depths closer to the surface are
more likely to develop cracks. It is evident that piezometers within
the pile installation area experienced faster and higher excess pore
pressure increments than those outside the pile group. K2, K3
[Fig. 11(a)] and K4 [Fig. 11(b)], which were within the pile instal-
Fig. 9. Resultant lateral displacement immediately after pile driving. lation area, recorded maximum pore water pressure values exceed-
ing 35 kPa at a depth of 5.5 m. K3 experienced higher excess pore
pressures at the initial stage since pile rows closer to it were driven
first. K2, however, experienced higher excess pore pressures at later
stages because pile installation proceeded toward it and ended clos-
est to it. Therefore, the order of pile installation influenced the dis-
tribution of excess pore pressure and the trend of the curves at the
two different positions. A clear contrast in excess pore pressure in
the pile installation area and at the shoulder of the existing embank-
ment can be seen in Fig. 11(b); K4 recorded a maximum excess
pore pressure value of 46 kPa at a depth of 5.5 m, whereas K1,
which was at the shoulder of the existing embankment (7.5 m from
the edge of the pile installation area), attained a maximum excess
pore pressure of 15.7 kPa at a depth of 14.5 m (i.e., a depth of 9.5 m
relative to construction ground surface). The relatively low excess
pore pressure at K1 was a result of its greater distance from the
pile installation area and its different soil conditions from the pile
installation area.
During pile group installation, excess pore pressure at all
piezometer boreholes increased with depth; in particular, K4 in
Fig. 11(b) showed a significant difference in pore pressure values
in the piezometers at depths of 3.5 and 5.5 m, which attained maxi-
mum values of 20 and 46 kPa, respectively. Fig. 12 shows the re-
lationship between excess pore pressure and depth at various times
Fig. 10. Resultant lateral displacement at I3 at certain times after pile at K3 for piles driven on the first day (i.e., row 4 piles and half of
driving. the piles in row 5) in section K55+630 to K55+660. Pile installation
started with pile #4-1 at 10:55 in the morning and ended with pile
#5-5 at 5:03 in the evening.
The generation and dissipation of excess pore pressure at each
jacking, in response to a similar phenomenon in excess pore piezometer location in the two sections is summarized in Table 5.
pressure. The increasing lateral displacement after the end of pile The ratio, in percentage, of the maximum excess pore pressure
(Dumax ) to the effective overburden stress (σvo 0 ) of all the piezom-
jacking was in response to the continuous increase in excess pore
pressure after the end of pile jacking. It was mentioned in the pre- eters in section K55+630 to K55+660 varied from 13% to 134%. In
vious section that peak excess pore pressure was attained some time section K55+670 to K55+720, the values varied from 7% to 132%.
after pile jacking ceased, which implies that the effective stress of For the piezometers at K1 and P1, which were outside the pile in-
the soil kept decreasing until the time at which peak excess pore stallation area at the shoulder of the existing embankment, the ex-
pressure was attained. Reduced effective stress implies reduced cess pore pressures and the ratios of excess pore pressure to initial
confining stress and therefore higher lateral displacement. effective overburden stress were very low. This indicates that the
influence of pile installation on the shoulder of the existing em-
bankment, 7.5 and 6.5 m away from the pile installation area in
Pore Pressure due to Pile Group Installation
sections K55+630 to K55+660 and K55+670 to K55+720, re-
The piezometers in sections K55+630 to K55+660 and K55+670 to spectively, was small. Thus, the existing embankment was at a safe
K55+720 were used to monitor the excess pore pressure generated distance from the pile installation area. Excess pore pressure

© ASCE 05018006-9 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2019, 145(2): 05018006


Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.

Fig. 11. Excess pore pressure histories for (a) K2 and K3; and (b) K1 and K4.

increasing distance from the inclinometer, and piles more than 30


pile diameters from the inclinometer produced very small lateral
displacements.
Fig. 14 shows the cumulative lateral displacement perpendicular
to the existing embankment due to row 2 piles at C2. Pile #2-9 was
on one side of the inclinometer while the other three were on the
opposite side. The displacement curves of #2-6 and #2-7 almost
coincide with that of #2-8, which implies that jacking of #2-6
and #2-7 produced smaller displacements, because they were far-
ther away from the inclinometer than #2-8. However, the lateral
displacement due to #2-6 was higher than that due to #2-7, which
could not have been the case under normal circumstances, because
#2-6 was farther from the inclinometer than #2-7. Thus, there could
have been a contribution to the displacement measured after jack-
ing #2-6 from some previously driven piles, and this could be an
indication that the soil displacement produced by a pile continued
to increase for a period of time after the pile had been driven.
Fig. 15 shows the variation of y-axis lateral displacement at the
surface with distance from C2. The lateral displacement caused by
pile installation decreased with distance from the inclinometer and
Fig. 12. Relationship between excess pore pressure and depth at K3. became zero at a distance of 8.3 m, which is equivalent to 28 pile
diameters. It can be concluded from Figs. 13–15 that the measured
lateral displacement caused by pile driving decreased with distance
dissipation varied from 54% to 98% over a period of 20 days in to about 28 pile diameters, at which point the soil displacement
section K55+630 to K55+660. Within the same time period, the became insignificant. It is worth mentioning that the lateral dis-
amount of excess pore pressure dissipated in section K55+670 to placement and the range of influence will be higher if the pile is
K55+720 varied from 59% to 100%. In both sections, the amount closed-ended or has a larger thickness.
of excess pore pressure dissipated was higher for shallow zones Fig. 16 shows the variation of cumulative lateral displacement
than for deep zones. perpendicular to the existing embankment with depth at C1, which
was located on the shoulder of the existing embankment. The dis-
placements due to the installation of some piles in rows 2 and 3
Lateral Displacement of Soil due to Pile Group differed only slightly. The difference in displacement was less than
Lateral soil displacement due to pile group installation was as- 1 mm, and the displacement curves almost coincide. After instal-
sessed through inclinometer measurements in section K55+630 lation of all the piles in the section, the maximum cumulative dis-
to K55+660. Fig. 13 shows the y-axis cumulative lateral displace- placement measured at C1 was about 6 mm. This indicates that the
ment due to row 4 piles at C3. Pile installation began from #4-0 effect of the pile group installation on the existing embankment was
toward C3, and the cumulative displacement due to piles #4-0, negligible.
#4-1 , #4-2, #4-3, #4-4 and #4-5, which are at a distances not less Fig. 17 shows the cumulative lateral displacement perpendicular
than 30 pile diameters from C3, is 2 mm, whereas the displace- to the existing embankment at C1, C2, and C4 at the end of pile
ments produced solely by #4-6 and #4-7 were 2 and 3 mm, re- installation. C2 was located at the toe of the existing embankment,
spectively. This indicates that lateral displacement decreased with 0.5 m away from the edge of the pile installation area, while C4 was

© ASCE 05018006-10 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2019, 145(2): 05018006


Table 5. Excess pore pressure data
Piezometer Depth Dumax 0
Dumax :σvo EPWP
0
Section Borehole number (m) Soil layer σvo (kPa) (kPa) (%) (kPa) DR (%)
K55+630 to K55+660 K1 K1-9.5 9.5 Organic clay 73.4 15.7 21.3 — —
K1-14.5 14.5 Organic clay 107.7 14.4 13.3 — —
K2 K2-3.5 3.5 Organic clay 25.8 34.6 134.1 1.7 95.2
K2-5.5 5.5 Organic clay 36.3 36.8 101.4 7.4 79.8
K3 K3-3.5 3.5 Silty clay 27.9 35.9 128.7 2.5 93.1
K3-5.5 5.5 Organic clay 41.7 42.1 100.8 13.6 67.8
K3-7 7.0 Organic clay 51.9 45.5 87.6 21.0 53.8
K4 K4-3.5 3.5 Organic clay 27.9 20.1 72.1 0.4 97.9
K4-5.5 5.5 Organic clay 41.7 46.1 110.5 14.4 68.8
K55+670 to K55+720 P1 P1-9.5 9.5 Organic clay 80.9 7.1 8.8 — —
P1-11.5 11.5 Silty clay 96.9 6.5 6.7 — —
Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.

P2 P2-4.0 4.0 Organic clay 34.0 24.5 72.1 1.6 93.5


P2-6.0 6.0 Organic clay 49.1 45.9 93.5 1.4 97.0
P3 P3-4.0 4.0 Organic clay 34.0 34.2 99.4 0.6 98.7
P3-6.0 6.0 Organic clay 49.1 40.0 122.6 7.5 81.26
P3-8.5 8.5 Organic clay 64.6 48.5 132.1 12.9 73.4
P4 P4-4.0 4.0 Organic clay 34.0 18.3 53.9 0.0 100.0
P4-6.0 6.0 Organic clay 49.1 39.4 80.2 16.1 59.1
Note: Dumax = maximum excess pore pressure; σvo0 = initial effective overburden stress; EPWP = excess pore pressure 20 days after pile installation; and

DR = percentage reduction in pore pressure 20 days after pile installation.

Fig. 13. Cumulative lateral displacement along the y-axis at C3 due to


row 4 piles.
Fig. 14. Cumulative lateral displacement along the y-axis at C2 due to
row 2 piles.

located on the opposite side, 1.0 m away from the outer edge of the
pile installation area, under natural soil conditions. C1, C2, and C3 result of the long distance of C1 from the pile installation area and
recorded maximum displacements of 7, 20, and 75 mm, respec- the high stiffness and strength of the soil due to the stress of the
tively. This shows that lateral displacement decreased with decreas- embankment. Therefore, the influence of pile group installation on
ing distance to the existing embankment, which was due to higher the existing embankment was negligible.
stiffness and strength of the soil closer to the existing embankment.
Although C2 was closer to the pile installation area than C4, its
measured lateral displacement was much smaller than that of C4. Volume Displacement
The reason for the relatively small displacement at C2 was that The volume of displaced soil should be equal to the volume of
the load of the existing embankment increased the stress on the the piles installed. Given that the piles in this study were open-
foundation soil, thereby increasing its stiffness and strength and ended, the volume displaced should be less than closed-ended piles
consequently decreasing its displacement. The small cumulative dis- of similar diameter and length if no soil plug occurs. The volume of
placement of 7 mm at C1, which was 7.5 m from the edge of the pile soil displaced or ground heave induced by open-ended piles de-
installation area at the shoulder of the existing embankment, was a pends on the volume of soil plug. The amount of ground heave

© ASCE 05018006-11 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2019, 145(2): 05018006


Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.

Fig. 15. Variation of lateral displacement with distance from C2.

Fig. 17. Lateral displacement along the y-axis at C1, C2, and C4 after
pile group installation.

Length of soil plug (m)


0 2 4 6 8 10 12
0

2
Length of pile penetration (m)

10

12
Fig. 16. Lateral displacement along the y-axis due to row 2 and 3 piles
at C1.
Fig. 18. Degree of soil plugging.

was not measured in this study. Soil plug was, however, measured
ground heave within the pile group. From the driving of 116 con-
for some of the piles and is presented here. Fig. 18 shows a plot of
crete piles with diameters and average lengths of 0.3 and 26 m,
the length of pile that penetrated the soil versus the length of the soil respectively, Bozozuk et al. (1978) showed that average heave of
plug. Fig. 18 indicates various degrees of soil plug formation, rang- 450 mm occurred within the pile group. A heave value of 110 mm
ing from almost unplugging to almost fully coring behavior. The was measured 3 m outside the pile group, which decreased rapidly
ratio of the total volume of soil plugs to the total volume of all the to zero at a distance of 12 m from the group. Because the piles used
piles considered was 12%. The total volume of the piles was cal- in this study were open-ended piles driven to a maximum depth
culated by considering only the total length that penetrated the soil of 13 m and considering the volume of the soil plugs, it can be
and the solid section of the piles (i.e., the annulus of the pile was concluded that ground heave would have had an insignificant effect
deducted from the total volume). This implies that closed-ended on the existing embankment, which was 7.8 m away from the edge
piles would have displaced 12% more volume than open-ended of the pile group.
piles of similar size (the additional displacement could occur in
the form of ground heave), and the volume of ground heave caused
by the open-ended piles would be 88% of the total volume of the Conclusions
piles. As stated earlier, heave measurements were not made during
pile installation. However, previous studies (e.g., Cummings et al. Pore water pressure and lateral soil displacement measurements
1950; Hagerty and Peck 1971; Bozozuk et al. 1978) have indicated were made during and after jacking of two large groups of open-
that about 50% of the volume of piles inserted in the soil appears as ended PHC pipe piles during expansion of an existing highway

© ASCE 05018006-12 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2019, 145(2): 05018006


embankment in order to assess the extent of soil disturbance result- Bozozuk, M., B. H. Fellenius, and L. Samson. 1978. “Soil disturbance from
ing from pile installation and the influence of pile group installation pile driving in sensitive clay.” Can. Geotech. J. 15 (3): 346–361. https://
on the existing embankment. The results can be summarized as doi.org/10.1139/t78-032.
follows. Cooke, R. W., and G. Price. 1973. “Strains and displacements around fric-
tion piles.” In Vol. 3 of Proc., 8th Int. Conf. Soil Mechanics Foundation
Peak excess pore pressure due to jacking a single pile, which
Engineering, 53–60. Watford, UK: Building Research Establishment.
was attained some time after pile jacking, increased with increasing Cummings, A. E., G. O. Kerkhoff, and R. B. Peck. 1950. “Effect of driving
depth and decreased with increasing distance from the pile. It took a piles into soft clay.” Trans. ASCE 115 (1): 275–350.
longer time to attain peak values of excess pore pressure in deeper D’Appolonia, D. J., and T. W. Lambe. 1971. “Performance of four foun-
zones and at longer distances from the pile than in shallower zones dations on end-bearing piles.” J. Soil Mech. Found. Div. 97 (1): 77–93.
and at closer distances to the pile. For pile groups, significantly Fellenius, B. H., D. E. Harris, and D. G. Anderson. 2003. “Static loading
higher excess pore pressures were generated in the pile installation test on a 45 m long pipe pile in Sandpoint, Idaho.” Can. Geotech. J.
area as compared to outside the installation area. The amount of 41 (4): 613–628. https://doi.org/10.1139/t04-012.
excess pore pressure dissipated decreased with increasing depth Gue, S. S. 1984. “Ground heave around driven piles in clay.” Ph.D. thesis,
and ranged from 54% to 100% over a period of 20 days. Because Dept. of Engineering Science, Univ. of Oxford.
Hagerty, D. J., and R. B. Peck. 1971. “Heave and lateral movements due to
Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.

excess pore pressure did not fully dissipate at every location, the
pile driving.” J. Soil Mech. Found. Div. 97 (11): 1513–1532.
bearing capacity is not expected to reach its maximum within Hwang, J.-H., C.-C. Lee, J.-S. Fang, and J.-Z. Chang. 1994. “Behavior of
20 days after pile group installation. The ratio of maximum excess frictional driven pile in underconsolidated clay.” In Proc., 1st Int. Symp.
pore pressure to initial effective overburden pressure varied from on Structural and Foundation, Hangchow.
7% to 134%. Hwang, J.-H., N. Liang, and C.-H. Chen. 2001. “Ground response during
Lateral soil displacement resulting from single pile and pile pile driving.” J. Geotech. Geoenviron. Eng. 127 (11): 939–949. https://
group installation, which continued to increase for a period of time doi.org/10.1061/(ASCE)1090-0241(2001)127:11(939).
after the end of pile driving in response to the excess pore pressure, Lo, K. Y., and A. G., Stermac. 1965. “Induced pore pressures during pile
decreased with increasing distance from the pile, and the range of driving operations.” In Vol. 2 of Proc., 6th Int. Conf. on Soil Mechanics
and Foundation Engineering, 285–289. Montreal: University of
influence was less than a distance of 26 pile diameters. The lateral
Toronto Press.
displacement decreased with decreasing distance to the existing em- Massarsch, K., and C. Wersäll. 2013. “Cumulative lateral soil displacement
bankment. The small displacement at the shoulder of the existing due to pile driving in soft clay.” In Sound geotechnical research to prac-
embankment was a result of the high stiffness and strength of the tice, 462–479. Reston, VA: ASCE.
soil produced by the embankment loading and a result of the em- McKenna, G. T. 1995. “Grouted-in installation of piezometers in bore-
bankment lying outside the range of influence of the pile installation. holes.” Can. Geotech. J. 32 (2): 355–363. https://doi.org/10.1139/t95
-035.
Orrje, O., and B. B. Broms. 1967. “Effects of pile driving on soil proper-
ties.” J. Soil Mech. Found. Div. 93 (SM5): 59–73.
Acknowledgments
Penman, A. D. M. 1961. “A study of the response time of various types of
piezometer.” In Proc., Pore Pressure and Suction in Soils, 53–58.
The authors wish to express their gratitude and sincere appreciation
London: Butterworths.
for the financial support received from the National Natural Science Pestana, J. M., C. E. Hunt, and J. D. Bray. 2002. “Soil deformation and
Foundation of China (Grant No. 41272327) and the Department of excess pore pressure field around a closed-ended pile.” J. Geotech. Geo-
Communications of Guangdong Province, China [Grant No. 2011 environ. Eng. 128 (1): 1–12. https://doi.org/10.1061/(ASCE)1090-0241
(794)-02-021]. (2002)128:1(1).
Poulos, H. G., and E. H. Davis. 1980. Pile foundation analysis and design.
New York: Wiley.
References Randolph, M. F., J. P. Carter, and C. P. Wroth. 1979. “Driven piles in clay—
The effects of installation and subsequent consolidation.” Geotechnique
Airhart, T. P., H. M. Coyle, T. J. Hirsch, and S. J. Buchanan. 1969. Pile-soil 29 (4): 361–393. https://doi.org/10.1680/geot.1979.29.4.361.
system response in cohesive soil. STP 444. West Conshohocken, PA: Seed, H. B., and L. C. Reese. 1957. “The action of soft clay along friction
ASTM. piles.” Trans. Am. Soc. Civ. Eng. 122 (1): 731–754.
Soderberg, L. O. 1962. “Consolidation theory applied to foundation pile
Bjerrum, L., and I. Johannessen. 1960. “Pore pressures resulting from
time effects.” Geotechnique 12 (3): 217–225. https://doi.org/10.1680
driving piles in soft clay.” In Proc., Conf. on Pore Pressure and Suction
/geot.1962.12.3.217.
in Soil, 108–111. London: Butterworths.
Soderman, L. G., and V. Milligan. 1961. “Capacity of friction piles in
Bogard, J. D., and H. Matlock. 1990a. “In-situ pile segment model experi- carved clay increased by electro-osmosis.” In Vol. 1 of Proc., 5th
ments at Empire, Louisiana.” In Proc., 22nd Offshore Technology Int. Conf. on Soil Mechanics and Foundation Engineering, 319–326.
Conf., 459–467. Houston: Offshore Technology Conference. Paris: Dunod.
Bogard, J. D., and H. Matlock. 1990b. “In-situ pile segment model experi- Steenfelt, J. S., M. F. Randolph, and C. P. Wroth. 1981. “Instrumented
ments at Harvey, Louisiana.” In Proc., 22nd Offshore Technology model piles jacked into clay.” In Vol. 2 of Proc., 10th Int. Conf. on Soil
Conf., 469–477. Houston: Offshore Technology Conference. Mechanics and Foundations in Engineering, 857–864. Stockholm,
Bogard, J. D., H. Matlock, and J. H. C. Chan. 1991. “In-situ model pile Sweden: A.A. Balkema.
experiments at West Delta 58A.” In Proc., 23rd Offshore Technology Tomlinson, M. J. 1969. Foundation design and construction. 2nd ed.
Conf., 133–143. Houston: Offshore Technology Conference. London: Pitman.

© ASCE 05018006-13 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2019, 145(2): 05018006

You might also like