Professional Documents
Culture Documents
Effect of Open-Ended PHC Pile Installation During Embankment Widening On The Surrounding Soil
Effect of Open-Ended PHC Pile Installation During Embankment Widening On The Surrounding Soil
Abstract: This paper investigates the effect of jacking two groups of open-ended prestressed high-strength concrete (PHC) piles on an
Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.
existing highway embankment based on field measurements of excess pore pressure and lateral soil displacement. Excess pore pressure
due to pile jacking increased with depth and decreased with increasing distance from the pile; the influence reached a distance of 43 pile
diameters from the pile axis. For pile groups, the amount of excess pore pressure dissipated decreased with increasing depth and varied from
54% to 100% in 20 days. Lateral soil displacement and excess pore pressure continued to increase for a period of time after the end of pile
jacking, and this could have resulted in significant inclination of piles if pile installation was too quick and pile spacing was too small. Lateral
soil displacement due to pile group decreased with decreasing distance to the existing embankment as a result of higher soil stiffness
and strength produced by the embankment loading. The effect of pile group installation on the existing embankment was negligible.
DOI: 10.1061/(ASCE)GT.1943-5606.0002016. © 2018 American Society of Civil Engineers.
Author keywords: Existing embankment widening; Prestressed high-strength concrete pile; Pile jacking; Excess pore pressure; Lateral
displacement.
Introduction strength, pore pressure, and soil displacement during and after pile
installation.
Many existing highway embankments in China have been under- The installation of piles in clay causes an initial reduction in
going expansion works, and some of these highways are located in undrained shear strength in the clay around the piles. Orrje and
soft ground terrain, which requires improvement with piled foun- Broms (1967) observed that the undrained shear strength around
dations. Proper evaluation of the effects of pile installation on the a single pile in a sensitive clay was reduced up to a distance of
existing road is therefore important in these projects. five pile radii from the pile axis. The largest decrease was observed
Pile jacking allows for piles to be installed without the noise near the surface of the pile, where the reduction was about 40%. An
and ground vibrations associated with conventional driven piles. increase in shear strength was observed 9 months after pile driving,
However, ground disturbance associated with pile installation is but the full initial strength was not regained. Tomlinson (1969) con-
inevitable. Soil deformation and excess pore pressure resulting cluded from a review of some case studies that at least 75% of the
from pile installation may exert lateral pressures and vertical ultimate bearing capacity was achieved within 30 days after pile
forces on the piles and therefore have a negative impact on the driving. In contrast, numerical studies by Randolph et al. (1979)
project and existing structures. Soil disturbances due to pile instal- have shown that in any clay, when consolidation is complete, the
lation have been a subject of many investigations over the years. new strength is 60% higher than the initial in situ value.
These investigations have usually involved the assessment of shear The dissipation of pore pressures induced by pile installation is
related to the regaining of shear strength after pile installation. Data
1
Professor, Key Laboratory of Ministry of Education for Geotechnique presented by Soderberg (1962) showed that the increase in the
and Embankment Engineering, Hohai Univ., Nanjing, Jiangsu 210098, ultimate bearing capacity of a pile was very similar in character to
China; Professor, Highway and Railway Research Institute, Hohai Univ., the rate of dissipation of excess pore pressure with time. A review
Nanjing, Jiangsu 210098, China. Email: lgwnj@163.com of some case histories of pore pressures developed due to pile driv-
2
Ph.D. Student, Geotechnical Research Institute, Hohai Univ., Nanjing,
ing by Poulos and Davis (1980) showed that very high excess pore
Jiangsu 210098, China (corresponding author). ORCID: https://orcid.org
/0000-0002-3022-9645. Email: ac.amenuvor@gmail.com; 2257917007@
pressures developed in the vicinity of the pile. Some of these pore
qq.com pressures were as high as 1.5–2.0 times the in situ vertical effective
3
Ph.D. Student, Geotechnical Research Institute, Hohai Univ., Nanjing, stress. There is, however, considerable scatter in the data reported,
Jiangsu 210098, China. Email: 291190849@qq.com which has mainly been attributed to differences in soil type. Higher
4
Ph.D. Student, Geotechnical Research Institute, Hohai Univ., Nanjing, pore pressures have been associated with sensitive clays. Field ex-
Jiangsu 210098, China. Email: luxiaocen@hhu.edu.cn periments performed by Seed and Reese (1957) in San Francisco
5
Associate Professor, Highway and Railway Research Institute, Hohai Bay mud with piles instrumented with load, total pressure, and pore
Univ., Nanjing, Jiangsu 210098, China. Email: jiantao.wu@hhu.edu.cn pressure gauges at locations along their length showed that the pile
6
Lecturer, Faculty of Civil Engineering, Water Resources Univ., Hanoi installation generated large pore water pressures at the pile surface,
100000, Vietnam; Ph.D. Student, Geotechnical Research Institute, Hohai
with only a slight increase at a distance of 15 pile diameters away.
Univ., Nanjing, Jiangsu 210098, China. Email: thangnn@tlu.edu.vn
Note. This manuscript was submitted on January 17, 2018; approved on Field measurements indicated that the increase in pore pressures
August 24, 2018; published online on December 10, 2018. Discussion per- resulted from the transfer of pressures generated from pile instal-
iod open until May 10, 2019; separate discussions must be submitted for lation to the soil. Bozozuk et al. (1978) reported on soil disturbance
individual papers. This paper is part of the Journal of Geotechnical and due to driving of 116 concrete piles in sensitive marine clays in a
Geoenvironmental Engineering, © ASCE, ISSN 1090-0241. construction project in eastern Canada. Maximum pore pressures
distances of more than one pile diameter from the pile wall, excess Fig. 2 shows the pile setup of sections K55+630 to K55+660
pore pressure dissipated upto 80% between 50 and 80 days. and K55+670 to K55+720. The pile identity is expressed as #
Fellenius et al. (2003) conducted static loading tests on a 45-m-long (row number)-(column number); for example, #4-8 indicates the
pile and showed that pore pressures induced by pile driving dissi- pile in the fourth row and the eighth column. The arrows show
pated 48 days after pile driving. Bogard and Matlock (1990a, b) and the sequence of pile installation. For the purpose of investigating
Bogard et al. (1991) presented results of open- and closed-ended the effect of jacking a single pile on the surrounding ground, piles
model pile tests performed in normally consolidated clays. Pore #4-8 and #4-4 in sections K55+630 to K55+660 and K55+670 to
pressures and total lateral stresses were highest for closed-ended K55+720, respectively, were jacked and their effects investigated
penetration, with relatively small influences from pile diameter. two days before the installation of the entire pile group began
Cooke and Price (1973) studied a 168-mm-diameter instru- in each section. A total of 52 piles, arranged in a square pattern
mented pile jacked into overconsolidated London clay. Outward with center-to-center spacing of 2.6 m, were installed in section
lateral displacements ranging from 10 to 20 mm were observed, K55+630 to K55+660. Pile installation started with row 4 (pile
depending on initial distance from the pile. Data from Hwang et al. #4-0), followed by rows 5, 3, and 2. The piles in this section had
(2001) showed that lateral displacement of soil due to pile driving a length, diameter, and wall thickness of 11 m, 0.3 m, and 0.07 m,
decreased with increasing distance from the pile. The lateral dis- respectively. A total of 66 piles, arranged in a square pattern
placements at distances of 3 and 1.5 pile diameters from the pile with center-to-center spacing of 3.0 m, were installed in section
were 29 and 36 mm, respectively. Massarsch and Wersäll (2013) K55+670 to K55+720. In this section, pile installation started from
concluded from model tests of pile group installation that ground row 2 (pile #2-18), followed by rows 3, 4, and 5. The piles in this
and pile movements do not occur in straight lines but follow an section had a length, diameter, and wall thickness of 13 m, 0.3, and
incremental path in a direction that depends on the order of pile 0.07 m, respectively. In both sections, the piles were jacked into the
installation. However, the displacement of a given element of soil slightly weathered limestone.
depends on the cumulative effect of all installed piles, regardless of
their order of installation. Inclinometer Instrumentation
Results of ground heave measurements by Gue (1984) of open- and
In-place inclinometers with an automatic data collection system
closed-ended piles from model tests showed that the amount of heave
were used to record changes in lateral soil displacement during pile
resulting from driving closed-ended piles was about four times that
installation. The inclinometers used (model JMQJ-74XX, Chang-
of similar open-ended piles (with an area ratio of 34%). In contrast,
sha Kingmach Measurement & Monitoring Technology, Changsha,
Steenfelt et al. (1981) conducted model tests to observe soil deforma-
China) have micro-electro-mechanical systems (MEMS) dual axis
tion patterns around open- and closed-ended piles jacked into
tilt sensors. They have a measurement range, resolution, and accu-
clay. The results showed no measurable ground heave. Pestana et al.
racy of 30°, 0.008°, and 0.1%, respectively, for temperature ranges
(2002) drove a 610-mm-diameter, 36.6-m-long closed-ended pile
between −20°C and þ60°C. The coordinates were set with the x-axis
into young bay mud. No soil heave was noticed at the site, and this
parallel to the existing embankment and the y-axis perpendicular to
was attributed to the confining effect of the stiff fill layer at the site.
the existing embankment, with its positive direction pointing away
The literature review shows a significant number of studies con-
from it. Four inclinometer casings were installed to different depths
ducted on pile installation and its influence on ground movement
within the limestone in each section. The inclinometers were in-
and pore water pressure generation in the ground. However, a vast
stalled to different depths because of slight variations in the grade
majority of these studies focused on the effects of driving a single
of the limestone at different locations. Details of the inclinometer
pile, with only a few focusing on pile groups. Also, there is gen-
instrumentation are summarized in Fig. 2 and Table 2.
erally a lack of information on the effects of jacking pile groups
on existing structures. Therefore, this study seeks to investigate the
influence of jacking open-ended prestressed high-strength concrete Piezometer Instrumentation
(PHC) piles on an existing highway foundation based on field Excess pore pressure measurements were obtained with vibrating
measurements of pore pressure and lateral soil displacement in wire (VW) piezometers installed in four different boreholes in each
the Guangqing Highway Expansion Project in China. of the sections. The boreholes were grouted with cement-bentonite
grout in order to increase the response time of the piezometers; VW
Test Site Description piezometers respond rapidly to pore pressure changes when in-
stalled in material similar to bentonite (Penman 1961; Mckenna
The Guangqing highway lies mainly in Quaternary flood plains 1995). The piezometers used (model JTM-V3000B, Changzhou
made up of organic clay, silt, and other organic soils, which are Jintumu Engineering Instrument, Changzhou, China) have a meas-
widely spread in plains and valleys. The geology of the test site, urement range of up to 200 kPa and a measurement accuracy
(a)
K55+660
4
K55+680
Depth (m)
(b)
Fig. 1. (a) Geological profile of test site; and (b) undrained shear strength for section K55+660 to K55+680.
2011-12-18
Starting point
0.8m
#4-4 4
3.6m 3.4m 8.6m
I4 X
13.6m I3 I2 I1
13.0m 13.0m 14.5m
3.0m
5
4.6m 3.0m 7.9m
P4 P3 P2 P1
6
17 0.16m
Downloaded from ascelibrary.org by Columbia University on 12/10/18. Copyright ASCE. For personal use only; all rights reserved.
2011-12-22
10
0.4m 3.6m 3.0m 9.0m
K4 K3 K2 K1
9
1.0m 4.8m 3.5m 7.4m
2011-12-9
C4 C3 C2 C1
11.2m 12.0m 15.0m 19.0m
8
2.6 m
7
Piezometer
2011-12-11
Inclinometer
#4-0 0
C-1
6.0m
Existing
Embankment
9.5m
Pile Driving
Area C-4 C-3 C-2
0.0m
6.5m
Fill Fill Silty
3.5m
5.0m
Organic K2-5.5
K3-7 Organic
Clay
Clay
K1-14.5
Organic
Clay
10.0m
Slightly weathered 16.5m
Limestone
Slightly weathered
Pile
Limestone
2.6m 2.6m 2.6m 12.5m
19.0m
Slightly weathered
Limestone
15.0m
brate before readings were taken. Fig. 3 shows a plot of excess pore
pressures generated at various depths during pile jacking as a func-
tion of time and pile tip depth. The pile tip depth is plotted against
Table 3. Piezometer instrumentation pile jacking time, and excess pore water pressure is plotted against
Distance from pile jacking time. A point on the pile tip depth curve is projected
shoulder of vertically onto the pore pressure curves for pore pressure values to
Piezometer Location Depth embankment be read. Excess pore pressures are generated and increased simul-
Section Borehole number description (m) (m) taneously at all depths with increasing depth of pile tip penetration
K55+630 K1 K1-9.5 Shoulder of 9.5 0 and time. It can also be observed that excess pore pressure is gen-
to K55+660 K1-14.5 embankment 14.5 0 erated at a particular depth before the pile tip reaches that depth. For
K2 K2-3.5 Within pile 3.5 9 instance, for the data for section K55+630 to K55+660 presented in
K2-5.5 group 5.5 9 Fig. 3(a), excess pore pressures of 0.2 and 0.8 kPa were generated
K3 K3-3.5 Within pile 3.5 12 at the piezometers located at depths of 5.5 and 7.0 m, respectively,
K3-5.5 group 5.5 12 when the pile tip reached a depth of 3.0 m. Although the piles
K3-7 7.0 12 in this section had a design length of 11 m, pile #4-8 was driven
K4 K4-3.5 Edge of 3.5 16
only 10 m because bedrock was encountered at that depth. A sim-
K4-5.5 pile group 5.5 16
ilar trend can be observed for section K55+670 to K55+720 in
K55+670 P1 P1-9.5 Shoulder of 9.5 0 Fig. 3(b), in which excess pore pressures of 0.2 and 0.2 kPa were
to K55+720 P1-11.5 embankment 11.5 0 generated at piezometers located at depths of 4.0 and 8.5 m, respec-
P2 P2-4.0 Within pile 4.0 7.9 tively, when the pile tip reached a depth of 3.0 m. Therefore, excess
P2-6.0 group 6.0 7.9 pore pressure generation is not limited to areas along the pile length
P3 P3-4.0 Within pile 4.0 10.9
but also reaches beyond the pile tip. From the general trend of
P3-6.0 group 6.0 10.9
P3-8.5 8.5 10.9 excess pore pressure increment with pile tip depth in both
P4 P4-4.0 Edge of 4.0 15.5 Figs. 3(a and b), pore pressure at a depth of 7 m is expected to
P4-6.0 pile group 6.0 15.5 be lower than that at a depth of 5.5 m, but the piezometer at a depth
of 5.5 m recorded a relatively low pore pressure. In addition, when
Fig. 3. Excess pore pressure at different depths as a function of time and pile tip depth: (a) section K55+630 to K55+660; and (b) section K55+670 to
K55+720.
Fig. 4. Excess pore pressure histories at specific depths: (a) section K55+630 to K55+660; and (b) section K55+670 to K55+720.
the pile tip reached or passed the depth of the piezometers, a sharp after pile jacking was completed. Increased pore pressure at the pile
increase in pore pressure was recorded for all piezometers except surface due to pile installation induced a pore pressure gradient in
the one at a depth of 5.5 m. This relatively low initial increment of the soil and a transient flow occurred in the soil with pore pressure
pore pressure at a depth of 5.5 m may have been due to the occur- migrating radially outward from the pile to the location of the
rence of relatively high permeability around that depth, leading to piezometers. This was responsible for the observed excess pore
rapid drainage and low pore pressure. pressure delay and the longer time needed for the piezometers far-
Fig. 4 shows excess pore pressure histories at various lateral dis- ther from the pile to reach peak excess pore pressures. Also, at the
tances and depths from the pile. In both Figs. 4(a and b), excess same distance of 4.0 m from the pile, peak excess pore pressures
pore pressures continued to increase, and then reached peak values were reached in 74, 332, and 1,352 min at depths of 3.5, 5.5, and
after pile jacking ceased, and the time at which peak values were 7.0 m, respectively. This may have been due to decreasing hydraulic
reached was later for deeper zones than for shallower zones. Table 4 conductivity with depth, as void ratio is expected to decrease with
presents a summary of excess pore pressure generation at vari- depth within the same material (note that the piezometers were in-
ous piezometer locations. In Fig. 4(a), as summarized in Table 4, stalled in the same material) due to increasing overburden stress,
the jacking of pile #4-8 in section K55+630 to K55+660 was causing reduced flow velocity with depth and increasing the time
completed in 26 min, but peak excess pore pressure was reached needed for pore pressures to migrate in the lateral direction. The
in 214 and 1,352 min at distances of 4.89 and 13.3 m, respec- data in Table 4 also show that peak excess pore pressure was reached
tively, for a constant depth of 3.5 m. A similar trend can be seen as long as 24 h after the completion of pile jacking. It can also be
in Fig. 4(b), also summarized in Table 4; the jacking of pile #4-4 in observed from Table 4 that pile jacking pore pressures influenced
section K55+670 to K55+720 was completed in 35 min, but peak a range not less than 13.0 m from the pile, which corresponds to
pore pressures were reached after a considerable length of time. 43 pile diameters. However, the ratio of maximum pore pressure to
The results strongly show a delay in excess pore pressure after the effective overburden stress varied from 0.6% at a distance of 13 m
end of pile jacking. In fact, data from a subsequent section on lat- to 26.7% at a distance of 3.8 m, which corresponds to 13.3 pile
eral displacement indicates that soil displacement increased after diameters. This value falls within the 10–20 pile diameters, reported
pile jacking, with maximum displacement attained several minutes by Seed and Reese (1957), Bjerrum and Johannessen (1960), Lo and
Stermac (1965), and Hwang et al. (2001), at which driving pore
Table 4. Summary of excess pore pressure generation pressures become negligible in clays.
Location End of Figs. 4(a and b) and Table 4 also show that excess pore pressure
jacking Peak Peak increased with increasing depth. The resistance of the soil to pile
Pile number/pile 0
Distance Depth EPWP EPWP time Dumax :σvo penetration increases with depth due to increasing confining stress
length/jacking time (m) (m) (kPa) (kPa) (min) (%) with depth, resulting in the pile exerting a higher radial stress (Ds
#4-8/10.0 m/26 min 4.0 3.5 2.5 4.6 74 16. or sr ) on the soil. According to Terzaghi’s effective stress principle,
4.0 5.5 1.3 9.6 332 23.4 the change in total stress (in this case sr ) must be equal to the
4.0 7.0 2.5 13.9 1,352 26.7 change in pore pressure (Du) under undrained conditions. There-
4.89 3.5 1.65 3.9 214 13.8 fore, as the change in total stress (sr ) increases with depth, there
13.3 3.5 0.1 1.6 1,352 2.2 should be a corresponding increase in the excess pore pressure
#4-4/13.0 m/35 min 4.69 4.0 1.7 5.1 175 14.9 (Du). This explains the increase in excess pore pressure with depth.
4.69 8.5 2.0 7.2 263 11.2 Fig. 5 shows excess pore pressure as a function of pile jacking
5.51 4.0 0.2 3.7 233 10.8 time and pile tip depth at constant depths and various lateral dis-
13.0 4.0 0.3 0.5 383 0.6 tances from pile. In the same way as in Fig. 3, a point on the pile
0 =
Note: EPWP = excess pore pressure; Dumax = peak pore pressure; and σvo tip depth curve is projected vertically onto the pore pressure curves
initial effective overburden stress. for pore pressure values to be read. Excess pore pressure at all
Fig. 5. Excess pore pressure at various lateral distances as a function time and pile tip depth: (a) section K55+630 to K55+660; and (b) section
K55+670 to K55+720.
distances increased simultaneously with pile tip penetration in ap- and section K55+670 to K55+720 [Fig. 5(b)] that the trend of ex-
proximately linear fashion. The trend of the curves is identical at all cess pore pressure as time progressed was similar at all distances
distances, and this indicates that soil disturbance due to pile jacking from the pile. It is also apparent that excess pore pressure decreased
may occur at different distances from the pile at almost the same with increasing distance from the pile. In Fig. 7, the ratios of maxi-
time. The relationship between excess pore pressure and distance mum excess pore pressure Dumax due to the jacking of piles #4-4
0
is well defined, such that excess pore pressure increased with de- and #4-8 to initial effective overburden stress svo at depths of 5.5
creasing distance to the pile. In section K55+620 to K55+660, as and 6.0 m, respectively, are plotted as a function of the ratio of
shown in Fig. 5(a), excess pore pressures at the end of pile jacking radial distance from pile r to pile radius a and then compared to
(26 min) were 2.5, 1.6, 1.2 and 0.1 kPa at 4.0, 4.89, 5.6, and 13.3 m, some previous published results, such as Bjerrum and Johannessen
respectively. Similarly, in section K55+670 to K55+720, as shown (1960), Soderman and Milligan (1961), Lo and Stermac (1965),
in Fig. 5(b), excess pore pressures increased with decreasing dis- Airhart et al. (1969), D’Appolonia and Lambe (1971), and Hwang
tance to the pile, from 0.3 kPa at 6.24 m to 1.7 kPa at 4.69 m at the et al. (1994, 2001). The excess pore pressure values in this study
end of pile jacking (35 min). were measured beyond r:a values of 25 and are in good agreement
Fig. 6 shows excess pore pressure histories at constant depths with the results of previous studies. Fig. 8 illustrates the process of
and various lateral distances from the pile during and after pile excess pore pressure generation and dissipation at various distances
jacking. It can be seen in section K55+620 to K55+660 [Fig. 6(a)] from the pile over time.
Fig. 6. Excess pore pressure histories at constant depths and various lateral distances from the pile: (a) section K55+630 to K55+660; and (b) section
K55+670 to K55+720.
Fig. 8. Excess pore pressure generation and dissipation over time: (a) field data; and (b) schematic representation.
Fig. 11. Excess pore pressure histories for (a) K2 and K3; and (b) K1 and K4.
located on the opposite side, 1.0 m away from the outer edge of the
pile installation area, under natural soil conditions. C1, C2, and C3 result of the long distance of C1 from the pile installation area and
recorded maximum displacements of 7, 20, and 75 mm, respec- the high stiffness and strength of the soil due to the stress of the
tively. This shows that lateral displacement decreased with decreas- embankment. Therefore, the influence of pile group installation on
ing distance to the existing embankment, which was due to higher the existing embankment was negligible.
stiffness and strength of the soil closer to the existing embankment.
Although C2 was closer to the pile installation area than C4, its
measured lateral displacement was much smaller than that of C4. Volume Displacement
The reason for the relatively small displacement at C2 was that The volume of displaced soil should be equal to the volume of
the load of the existing embankment increased the stress on the the piles installed. Given that the piles in this study were open-
foundation soil, thereby increasing its stiffness and strength and ended, the volume displaced should be less than closed-ended piles
consequently decreasing its displacement. The small cumulative dis- of similar diameter and length if no soil plug occurs. The volume of
placement of 7 mm at C1, which was 7.5 m from the edge of the pile soil displaced or ground heave induced by open-ended piles de-
installation area at the shoulder of the existing embankment, was a pends on the volume of soil plug. The amount of ground heave
Fig. 17. Lateral displacement along the y-axis at C1, C2, and C4 after
pile group installation.
2
Length of pile penetration (m)
10
12
Fig. 16. Lateral displacement along the y-axis due to row 2 and 3 piles
at C1.
Fig. 18. Degree of soil plugging.
was not measured in this study. Soil plug was, however, measured
ground heave within the pile group. From the driving of 116 con-
for some of the piles and is presented here. Fig. 18 shows a plot of
crete piles with diameters and average lengths of 0.3 and 26 m,
the length of pile that penetrated the soil versus the length of the soil respectively, Bozozuk et al. (1978) showed that average heave of
plug. Fig. 18 indicates various degrees of soil plug formation, rang- 450 mm occurred within the pile group. A heave value of 110 mm
ing from almost unplugging to almost fully coring behavior. The was measured 3 m outside the pile group, which decreased rapidly
ratio of the total volume of soil plugs to the total volume of all the to zero at a distance of 12 m from the group. Because the piles used
piles considered was 12%. The total volume of the piles was cal- in this study were open-ended piles driven to a maximum depth
culated by considering only the total length that penetrated the soil of 13 m and considering the volume of the soil plugs, it can be
and the solid section of the piles (i.e., the annulus of the pile was concluded that ground heave would have had an insignificant effect
deducted from the total volume). This implies that closed-ended on the existing embankment, which was 7.8 m away from the edge
piles would have displaced 12% more volume than open-ended of the pile group.
piles of similar size (the additional displacement could occur in
the form of ground heave), and the volume of ground heave caused
by the open-ended piles would be 88% of the total volume of the Conclusions
piles. As stated earlier, heave measurements were not made during
pile installation. However, previous studies (e.g., Cummings et al. Pore water pressure and lateral soil displacement measurements
1950; Hagerty and Peck 1971; Bozozuk et al. 1978) have indicated were made during and after jacking of two large groups of open-
that about 50% of the volume of piles inserted in the soil appears as ended PHC pipe piles during expansion of an existing highway
excess pore pressure did not fully dissipate at every location, the
pile driving.” J. Soil Mech. Found. Div. 97 (11): 1513–1532.
bearing capacity is not expected to reach its maximum within Hwang, J.-H., C.-C. Lee, J.-S. Fang, and J.-Z. Chang. 1994. “Behavior of
20 days after pile group installation. The ratio of maximum excess frictional driven pile in underconsolidated clay.” In Proc., 1st Int. Symp.
pore pressure to initial effective overburden pressure varied from on Structural and Foundation, Hangchow.
7% to 134%. Hwang, J.-H., N. Liang, and C.-H. Chen. 2001. “Ground response during
Lateral soil displacement resulting from single pile and pile pile driving.” J. Geotech. Geoenviron. Eng. 127 (11): 939–949. https://
group installation, which continued to increase for a period of time doi.org/10.1061/(ASCE)1090-0241(2001)127:11(939).
after the end of pile driving in response to the excess pore pressure, Lo, K. Y., and A. G., Stermac. 1965. “Induced pore pressures during pile
decreased with increasing distance from the pile, and the range of driving operations.” In Vol. 2 of Proc., 6th Int. Conf. on Soil Mechanics
and Foundation Engineering, 285–289. Montreal: University of
influence was less than a distance of 26 pile diameters. The lateral
Toronto Press.
displacement decreased with decreasing distance to the existing em- Massarsch, K., and C. Wersäll. 2013. “Cumulative lateral soil displacement
bankment. The small displacement at the shoulder of the existing due to pile driving in soft clay.” In Sound geotechnical research to prac-
embankment was a result of the high stiffness and strength of the tice, 462–479. Reston, VA: ASCE.
soil produced by the embankment loading and a result of the em- McKenna, G. T. 1995. “Grouted-in installation of piezometers in bore-
bankment lying outside the range of influence of the pile installation. holes.” Can. Geotech. J. 32 (2): 355–363. https://doi.org/10.1139/t95
-035.
Orrje, O., and B. B. Broms. 1967. “Effects of pile driving on soil proper-
ties.” J. Soil Mech. Found. Div. 93 (SM5): 59–73.
Acknowledgments
Penman, A. D. M. 1961. “A study of the response time of various types of
piezometer.” In Proc., Pore Pressure and Suction in Soils, 53–58.
The authors wish to express their gratitude and sincere appreciation
London: Butterworths.
for the financial support received from the National Natural Science Pestana, J. M., C. E. Hunt, and J. D. Bray. 2002. “Soil deformation and
Foundation of China (Grant No. 41272327) and the Department of excess pore pressure field around a closed-ended pile.” J. Geotech. Geo-
Communications of Guangdong Province, China [Grant No. 2011 environ. Eng. 128 (1): 1–12. https://doi.org/10.1061/(ASCE)1090-0241
(794)-02-021]. (2002)128:1(1).
Poulos, H. G., and E. H. Davis. 1980. Pile foundation analysis and design.
New York: Wiley.
References Randolph, M. F., J. P. Carter, and C. P. Wroth. 1979. “Driven piles in clay—
The effects of installation and subsequent consolidation.” Geotechnique
Airhart, T. P., H. M. Coyle, T. J. Hirsch, and S. J. Buchanan. 1969. Pile-soil 29 (4): 361–393. https://doi.org/10.1680/geot.1979.29.4.361.
system response in cohesive soil. STP 444. West Conshohocken, PA: Seed, H. B., and L. C. Reese. 1957. “The action of soft clay along friction
ASTM. piles.” Trans. Am. Soc. Civ. Eng. 122 (1): 731–754.
Soderberg, L. O. 1962. “Consolidation theory applied to foundation pile
Bjerrum, L., and I. Johannessen. 1960. “Pore pressures resulting from
time effects.” Geotechnique 12 (3): 217–225. https://doi.org/10.1680
driving piles in soft clay.” In Proc., Conf. on Pore Pressure and Suction
/geot.1962.12.3.217.
in Soil, 108–111. London: Butterworths.
Soderman, L. G., and V. Milligan. 1961. “Capacity of friction piles in
Bogard, J. D., and H. Matlock. 1990a. “In-situ pile segment model experi- carved clay increased by electro-osmosis.” In Vol. 1 of Proc., 5th
ments at Empire, Louisiana.” In Proc., 22nd Offshore Technology Int. Conf. on Soil Mechanics and Foundation Engineering, 319–326.
Conf., 459–467. Houston: Offshore Technology Conference. Paris: Dunod.
Bogard, J. D., and H. Matlock. 1990b. “In-situ pile segment model experi- Steenfelt, J. S., M. F. Randolph, and C. P. Wroth. 1981. “Instrumented
ments at Harvey, Louisiana.” In Proc., 22nd Offshore Technology model piles jacked into clay.” In Vol. 2 of Proc., 10th Int. Conf. on Soil
Conf., 469–477. Houston: Offshore Technology Conference. Mechanics and Foundations in Engineering, 857–864. Stockholm,
Bogard, J. D., H. Matlock, and J. H. C. Chan. 1991. “In-situ model pile Sweden: A.A. Balkema.
experiments at West Delta 58A.” In Proc., 23rd Offshore Technology Tomlinson, M. J. 1969. Foundation design and construction. 2nd ed.
Conf., 133–143. Houston: Offshore Technology Conference. London: Pitman.