MATERIAL TAKE-OFF LIST

ARAMCO 6228(03/06)
SAMS TEMP. SAP PER DWG.
REV. CODE DESCRIPTION QTY I/U STATUS REMARKS
STOCK NUMBER NUMBER REQ. CODE
SEPTIC HOLDING TANK (QUANTITY = 1 UNIT)
EXCAVATION 1164 M3

BACKFILLING: GENERAL FILL 299 M3


CONCRETE: READY MIX, 4000PSI (28
MPA)COMPRESSIVE STRENGTH, TYPE-
309 M3
V; PER SAES-Q-001 AND 09-SAMSS-
097.
LEAN CONCRETE: READY MIX,
2000PSI (14 MPA) COMPRESSIVE
9 M3
STRENGTH, TYPE-V; PER SAES-Q-001
AND 09-SAMSS-097.
FILM, PLASTIC SHEETING: 0.15 MM
(0.006 IN) THK, 6.1 M (20 FT) WD,
CLEAR, POLYETHYLENE, 185.8 M2 1 RO
(2000 SQ FT)/ROLL (SAP#
1000216009). SAES-Q-005
BAR, REINFORCING, COATED:
CONCRETE, 20 MM DIA, STEEL, HOT
ROLLED, DEFORMED, FUSION BOND
EPOXY COATED, 500 N/MM2
TENSILE, 350 N/MM2 YIELD, 3.14 SQ 490 M
CM, 2.495 KG/M, 11.5-12 M LG, SSA
2/1399H, 09-SAMSS-106, ROUND,
MEDIUM TENSILE
GRADE
BAR, REINFORCING, COATED:
CONCRETE, 16 MM DIA, STEEL, HOT
ROLLED, DEFORMED, FUSION BOND
EPOXY COATED, 500 N/MM2
9830 M
TENSILE, 350 N/MM2 YIELD, 2.01 SQ
CM, 1.596 KG/M, 11.5-12 M LG, SSA
2/1399H, 09-SAMSS-106, ROUND,
MEDIUM TENSILE GRADE
BAR, REINFORCING, COATED:
CONCRETE, 12 MM DIA, STEEL, HOT
ROLLED, DEFORMED, FUSION BOND
EPOXY COATED, 500 N/MM2
3500 M
TENSILE, 350 N/MM2 YIELD, 1.13 SQ
CM, 0.897 KG/M, 11.5-12 M LG, SSA
2/1399H, 09-SAMSS-106, ROUND,
MEDIUM TENSILE GRADE
ANGLE, STRUCTURAL: 76.2 MM (3 IN)
X 76.2 MM (3 IN) X 9.5 MM (3/8 IN)
TH, 10.7 KG/M (7.2 LB/FT), CS, 10.7-
400 M
12.2 M (35-40 FT) LG, BLACK, HOT
ROLLED, ASTM A36, L-SHAPE,
DESIGNATION L 3X3X3/8
20MM DIA STAINLESS STEEL LIFTING
40 M
HOOK

PVC WATERSTOP 150MM WIDE 38 M

MEMBRANE WATERPROOFING WITH


292 M2
PROTECTION BOARD

JOINT FILLER 22 M2

PRECAST: CONCRETE COVER


30 PC
3328 x 991 x 200 THK
NOTES: 1. CONSTRUCTION CONTRACTOR SHALL VERIFY AND PROVIDE ALL QUANTITIES OF CONTRACTOR SUPPLIED MATERIAL
REQUIRED TO PERFORM THE WORK, AS DETAILED, ON THE CONSTRUCTION DRAWINGS.

APPROVAL
COMPILED BY REV. REFERENCE DRAWING
CHECKED DATE PROJECT ENGR DATE
SASEC 00 FOM 8/12/2015 FDB 8/12/2015 SK-5B-Q-003 & SK-5B-Q-004

CONTRACT NO. PHASE ENG. ITEM AREA START-UP DATE PRELIMINARY REVISION
STRUCTURAL FINAL X REVISION 00
INDEX Material Take-Off for BGCS-5 SEPCO & LABOR CAMP SHEET 2 OF 2
Q
STRUCTURAL WORKS ON BGCS-5
PLANT SK-5B-Q-002
K53 YANBU SAUDI ARABIA