1 Project planning
Define the volunteer-rider dynamics for the
1.1 Lagon 2/25/20 2/28/20 3 40%
carpool system
1.2 Promote the idea to potential pilot volunteers Pascua 3/2/20 3/6/20 4 20%
1.3 Screen list of volunteers Buhion 3/7/20 3/8/2020 1 15%
1.4 Orient volunteers regarding program Pascua 3/9/20 3/11/20 2 0%
1.5 Gather data of drivers and cars Lagon 3/9/20 3/11/20 2 0%
Create weekly schedule based on car
1.6 Legaspi 3/12/20 3/13/20 1 0%
availability
2 Project execution
2.1 Promote idea to potential volunteer riders Pascua 3/9/20 3/15/20 6 0%
Buhion, Lagon,
ISKO RIDE
Project Name Project Members Legazpi, Pascua
Subject BA 106 Start Date February 25
GROUP Group 3 End Date April 12
ISKO RIDE
Estimated Hours Resource Rate Total Cost
Phase
1 Project Planning 14 ₱750.00
2.1 Setting up carpool dynamics and rules 3 Marvin ₱0.00 ₱0.00
1.1 Setting up facebook group 2 Louie ₱0.00 ₱0.00
1.2 Social Media Promotions 12 K.C. ₱0.00 ₱250.00
1.3 Room reservation for volunteer orientation 3 Louie ₱0.00 ₱500.00
2 Project Execution 2.5 ₱3,500.00
2.1 Driver incentives 1 Marvin ₱0.00 ₱500.00
2.2 Gas reimbursements 0.5 Aldrick ₱0.00 ₱1,000.00
2.3 Emergency fund for accidents 1 K.C. ₱2,000.00 ₱2,000.00
2.4 System for tracking user activity 1 Louie ₱0.00 ₱0.00
3 Post-Execution Data Analysis 4 ₱250.00
3.1 Collection of feedback through google forms 5 K.C. ₱0.00 ₱0.00
3.2 FGD with users 1 K.C. ₱250.00 ₱250.00
3.3 Post-project documentation 2 Marvin ₱0.00 ₱0.00
3.4 Data and Feedback analysis 1 Louie ₱0.00 ₱0.00
4 Product Launch: Beta Version 18 ₱0.00
4.1 User Interface and UX Design 5 Aldrick ₱0.00 ₱0.00
4.2 Beta Version Website Launch 1 Aldrick ₱0.00 ₱0.00
4.3 Final report 12 Marvin ₱0.00 ₱0.00
Total 20.5 ₱4,500.00