PROJECT SUMMARY

1. LV LINE

Installation of line 150-PL-3108-151430X


• Refer isometric drawing P5-HCP-PL-B3108 SHT 2/2
• Remove existing line and control valve that going to be replace
• Pre-lay new fabricated spool at worksite
• Erect habitat at pipe support location
• Fit up and weld pipe supports PS-12.
• Remove existing pipe support PS-81508-012 at line 150-PL-3110-151430X
• Modify to add angle bar as guide at existing PS-81608-002
• Pipe support PS-81608-009 will be reused.
• Install 1 pc new gate valve
• Install 1 pc new control valve LV-2113
• Perform hydraulic bolt torqueing by vendor
• Conduct MPI test on pipe support joint
• Touch up painting at the weldment area
• Remove habitat
• Conduct reinstatement leak test
• Conduct housekeeping

Condensate Evacuation Project Phase 2 Piping Summary

Total Total Total Total Total PS STATUS


Line Number
Joint Pre-fab FFW Spool New Share Exist
EVACUATION LINE 25 17 8 10 4 - -
100-PL-3304-91430X 8 4 4 4 2 - -
100-PL-3305-91430X 9 8 1 2 2 - - COMPLETE
100-PL-3306-93833X 8 5 3 4 2 - -
LV LINE 33 34 - 4 - - -

150-PL-3008-151430X 17 17 - 2 1 - 1 COMPLETE

150-PL-3108-151430X 17 17 - 2 1 - 1 PENDING

TOTAL 59 51 8 14 8 - 2

FT3301 & PT-3301 SUPPORT

• Disconnect & ungland cable at FT-3301 & PT-3301


• Disconnect existing impulse tubing FT-3301 & PT-3301
• Erect habitat at FT-3301 support location
• Weld/ install C channel for FT-3301 & PT-3301 support
• Install FT-3301 & PT-3301 support
• MPI after installation
• Remove habitat
• Gland & terminate existing cable at FT-3301 & PT-3301
• Reconnect existing impulse tubing
PAINTING REPORT

1. To prepare the following report:


• DE-F-52, Daily Painting Report
• Painting Summary
• ITR P11-A Pipe Painting Coating & Marking

2. To take photo of the completed scope (softcopy only)

SUPPORTING DOCUMENTS

1. Isometric drawings
2. Pipe support drawings
3. Instrument
4. ITP Painting
5. Paint Matrix
6. Paint batch certs
7. Condy phase 2 – QAQC Closeout Report (Onshore Prefab)
8. Condy train B schedule

EQUIPMENT

1. QAQC/ST/06/14
2. QAQC/WF/02/13
3. QAQC/MM/02/18
4. QAQC/WH/03/18
5. QAQC/DFT/03/14