Professional Documents
Culture Documents
Appendix Iio - Template For Breakdown of Project Cost
Appendix Iio - Template For Breakdown of Project Cost
Appendix Iio - Template For Breakdown of Project Cost
(THE ITEMS ON THE TEMPLATE ARE FOR REFERENCE ONLY. THE CONTRACTOR SHALL DEVELOP BASE ON SCOPE OF WORKS)
I DIRECT COST
I.1.1 AREA 21
I.1.1.B ELECTRICAL
SWITCHGEAR
PANEL LIGHTING
LCS (LOCAL SWITCH CONTROL)
CABLE TRAY
LIGHTING & RECEPTACLE
CABLE
BULK MATERIAL
I.1.1.C INSTRUMENT
CONTROL SYSTEM
FIELD INSTRUMENT
VALVE
ANALYZERS
BULK MATERIAL
I.1.1.D PIPING
Pipe
Valve
Fittting
Special Item
I.1.2.B ELECTRICAL
SWITCHGEAR
PANEL LIGHTING
LCS (LOCAL SWITCH CONTROL)
CABLE TRAY
LIGHTING & RECEPTACLE
CABLE
BULK MATERIAL
I.1.2.C INSTRUMENT
1 of 5
APPENDIX IIO - TEMPLATE FOR BREAKDOWN OF PROJECT COST
(THE ITEMS ON THE TEMPLATE ARE FOR REFERENCE ONLY. THE CONTRACTOR SHALL DEVELOP BASE ON SCOPE OF WORKS)
CONTROL SYSTEM
FIELD INSTRUMENT
VALVE
ANALYZERS
PROPYLENE METERING SYSTEM
BULK MATERIAL
I.1.2.D PIPING
Pipe
Valve
Fittting
Special Item
TOTAL MATERIAL
2 of 5
APPENDIX IIO - TEMPLATE FOR BREAKDOWN OF PROJECT COST
(THE ITEMS ON THE TEMPLATE ARE FOR REFERENCE ONLY. THE CONTRACTOR SHALL DEVELOP BASE ON SCOPE OF WORKS)
CONTENT (USD)
No. ITEM DESCRIPTION REMARKS
INDONESIA FOREIGN
I.2 CONSTRUCTION
I.2.5.2 Piping
I.2.5.2.1 Prefabrication
I.2.5.2.2 Above Ground Installation
I.2.5.2.3 Underground Installation
I.2.5.2.4 Pipe Support Fabrication & Installation
I.2.5.2.5 Post Heat Treatment
I.2.5.2.6 Inspection
I.2.5.2.7 Pressure Test Flushing and Drying
3 of 5
APPENDIX IIO - TEMPLATE FOR BREAKDOWN OF PROJECT COST
(THE ITEMS ON THE TEMPLATE ARE FOR REFERENCE ONLY. THE CONTRACTOR SHALL DEVELOP BASE ON SCOPE OF WORKS)
CONTENT (USD)
No. ITEM DESCRIPTION REMARKS
INDONESIA FOREIGN
I.2.5.3.1 Electrical
I.2.5.3.2 Demolish Electrical Works
I.2.5.4.1 Instrument
I.2.5.4.2 Demolish Instrument Works
4 of 5
APPENDIX IIO - TEMPLATE FOR BREAKDOWN OF PROJECT COST
(THE ITEMS ON THE TEMPLATE ARE FOR REFERENCE ONLY. THE CONTRACTOR SHALL DEVELOP BASE ON SCOPE OF WORKS)
CONTENT (USD)
No. ITEM DESCRIPTION REMARKS
INDONESIA FOREIGN
II.1.2 ENGINEERING
II.1.2.1 Man Hours Cost
II.1.2.2 Expenses
II.1.3 PROCUREMENT
II.1.3.1 Man Hours Cost
II.1.3.2 Inland & Overseas Transportation Cost
II.1.3.3 Inspection Cost
II.1.3.4 Vendor Supervision
II.1.3.5 Other
5 of 5