Professional Documents
Culture Documents
Ewr Monitoring (Live) - 04072019
Ewr Monitoring (Live) - 04072019
Date of
Date ETR (estimate time
No EWR# Estate Requester Name Required Type of Asset Description Discipline Dwg RAB Doc Infra Name Est Hrs Est Numbner Actual Finsih Notes
Request ready)
(D0R) (C,M,E) Capex/Opex Dwg/Doc Week# Status (%) Date
1 EWR18-EBL-CXX EBL 01-Oct-18 Suroto Warehouse Repair dinding warehouse yg rusak C OPEX 1 Has Feb-19 100% DONE
Pembangunan RO Baru untuk menggantikan
2 EWR19-RO SMD - C01 HPM 01-Nov-18 P.Lefrand & P. JK Building 1 1 Has 16-Apr-19 15 100% DONE
RO Existing ( Sewa ) 15
TAP Pump n pipe
3 TAP 17-Dec-18 Has Pump & pipe Desain kapasitas pompa & ukuran pipa M CAPEX 1 1 Has TBD #VALUE! 0% HOLD
(due: Mon, 17 Dec '18)
4 EWR19-EBL-C01 EBL 11-Mar-19 P. Franky Road DED Jalan Aspal dan Beton C CAPEX 1 1 Has 5 4 13-Mar-19 11 100% 13-Mar-19 DONE
HOLD - no electrical eng to set
5 EWR19-TAP-C01 TAP 11-Mar-19 P. Toto Cable Single Line Diagram E CAPEX 1 Has 15-Mar-19 11 0%
the std
6 EWR19-EBL-C02 TAP 11-Mar-19 P. Tjandra Building Rumah G1 Manager A = 100 m2 C CAPEX 1 1 Has 16 22 15-Mar-19 11 100% 26-Mar-19 DONE
Rumah G1 Manager A = 85 m2 + 2 ruang bag
7 EWR19-YWA-C03 YWA 11-Mar-19 P. Sastri Building C CAPEX 1 1 Has 8 7 15-Mar-19 11 100% 29-Mar-19 DONE
belakang
- Jembtn Tio L = 12 M
Permanent
8 EWR19-NPN-C01 NPN 11-Mar-19 P. Edy WT - Jembtn S. Tambalang = 24 M C CAPEX 1 1 Has 8 15 13-Mar-19 11 100% 12-Mar-19 DONE
Bridge
- Jembtn S. Sepeti = 25 M
Sudah dibuatkan gambar
9 EWR19-MSL-C02 SLE 11-Mar-19 P. Jisamsu Water Gate Pintu Air M CAPEX 1 1 Has 18-Mar-19 11 100% oleh Mifta dan dikasihkan
8 6 ke P. Jisamsu
Kantor kebun permanen
10 EWR19-FLTI-C01 FLTI 11-Mar-19 P. George Office 2 C CAPEX 1 1 Has 16 22 30-Jul-19 30 90% kurang instalasi Listrik
A = 400 m
Permanent
11 EWR19-SAWA-C01 SAWA 11-Mar-19 Has Pekerjaan tambah kurang Jembatan 24 M C CAPEX 1 Has 8 3 12-Mar-19 10 100% 15-Mar-19 DONE
Bridge
12 EWR19-YWA-C02 YWA 11-Mar-19 P. Sastri Building Repair workshop C OPEX 1 1 Has 16 24-May-19 21 50% 26-May-19 DONE
13 EWR19-MSL-C01 SLE 11-Mar-19 P. Dian Retaining wall Stone crusher ramp C CAPEX 1 1 Has 16 27-May-19 21 5% CANCEL
Water storage Menampung air hujan dengan talang dan
14 EWR19-YWA-C01 YWA 12-Mar-19 P. Joko C CAPEX 1 1 Has 8 7 15-Mar-19 11 100% 26-Mar-19 DONE
& viaduct toren
Layout Master Layout perumahan staff AAPA gabung
15 EWR19-AAPA-C01 AAPA 15-Mar-19 P. Joko C CAPEX 1 1 Has 10-Jul-19 28 50%
Perumahan dng Mill 3
Sinkronisasi G2 Desain G2 ( Asisten)estate dan mill
16 EWR19-AAPA-C02 AAPA 15-Mar-19 P. Joko C CAPEX 1 1 Has 28-May-19 21 100% 31-May-19 DONE
Asisten disamakan dan dipercantik 5
Dinding
17 EWR19-YWA-C01 YWA 23-Mar-19 P. Sastri DPT tipe Stone Pitching/ Pasangan Batu C CAPEX 1 1 Has 03-Apr-19 14 100% 24-Apr-19 DONE
Penahan Tanah
2
Shelter BBM Gambar pondasi tangki solar dan tembok
18 EWR19-SLE-C02 SLE 26-Mar-19 P. Peter C CAPEX 1 1 Has 16 01-Jul-19 26 100% 01-Jul-19 DONE
20000 L keliling 5
19 EWR19-BBB-C01 BBB- 26-Mar-19 P. Bowie Gudang Non C CAPEX 1 1 Has 23-Jul-19 29 50%
Dinding Kayu + Kawat Ayam
SAWIT Permanen 5
Workshop Tambahan 4 bay untuk Arahan Pak Geogre 4 Bay Tambahan
20 EWR19-GBSM2-C01 GBSM 2 26-Mar-19 P. Oka C CAPEX 1 1 Has 31-Jul-19 31 50%
mekanisasi workshop existing Bangunan Non Permanen
10
21 EWR19-PTA- C01 PTA 01-Apr-19 P. Heri Faisal Building Kantor Kebun Semi Permanen C CAPEX 1 1 Has 24-Jul 30 15%
2
22 EWR19-TAP-C02 TAP 16-Apr-19 Peter Tanki Tanki timbun 5000 L C CAPEX 1 1 Has 11-Jul 28 0%
23 EWR19-GBSM-C02 GBSM 2 16-Apr-19 Edy Kurniawan Water Tower Pondasi water tower terletak di pasiran --> C CAPEX 1 1 Has 10-Mei 19 100% DONE
solusi?
28 EWR19-TAP-C06 TAP 27-Jun-19 P'Agung ( SHE ) Building WTP ( Reservoir di dalam tanah ) C CAPEX 1 1 Has 09-Jul 27 50%
28 EWR19-TAP-C07 TAP 01-Jul-19 P'Beres Building Instalasi Kompressor Workshop 8 Bay C CAPEX 1 1 Has 01-Jul 26 100% 01-Jul-19 DONE