Discharge Pressure Calculation

Client : Mcmai Cebu Trading Corp.


Project : 8" Ø Pipe line Calculation
Location: Calaca, Batangas

Design Data:

Density of Product, ρ (Kg/m3) 1841


Pipe diameter, D (m) NPS 8 0.20274
Dynamic Viscosity, μ (Ns/m2) 0.024
Estimated Equivalent Pipe Length, L ( m ) 1313
Product Sulfuric Acid

𝑄= 650𝑀𝑇/ℎ𝑟 𝑥 1ℎ𝑟/3600
1. Discharge Pressure at Pier = 7Bar.

Pressure Distance from Pier


6Bar 207.299
5Bar 414.599
4Bar 621.898
3Bar 829.198
2Bar 1036.5
0.664551Bar 1313

Prepared By : Mark kenneth A. Pacatang


Design Engineer

Reviewed By : Lynus Junio


Design and Technical Services Manager

Date: Jan. 01, 2016


Mechatrends Contractors Corporation
249 MANGGAHAN ST., BINAKAYAN, KAWIT, CAVITE
Tel No.: (046) 434-6643 * 434-9253 * 434-1503 * MECHANICAL ENGINEERS
Fax No.: (046) 434-1894 * FABRICATORS
E-mail add: mecha@info.com.ph * CONTRACTORS

Pipe Sizing Calculation

Client : Mcmai Cebu Trading Corp.


Project : 4" Ø Pipe line Calculation
Location:

Calculation of Required Pipe Diameter

Design Data:

Mass Flowrate, Q (MT/hr) 250


Density of Product, ρ (Kg/m3) 1840
Pipe diameter, D (m) 0.10226
Dynamic Viscosity, μ (Ns/m2) 0.024
Pipe Length, L ( m ) 980
Acceleration due to Gravity, G ( m/s2 ) 9.81
Pipe Roughness, e ( mm ) 0.045

𝑄= 250𝑀𝑇/ℎ𝑟 𝑥 1
Convert of Mass Flowrate to Volume Flowrate, Q (m3/s)

Q= 0.038 m3/s

Calculate for Velocity, V (m/s)

V = 4.5953461 m/s

Calculate for Reynold`s Number, Re

Re = 36027.21
Calculate for Friction Factor, f

f= 0.020
f= 0.0240
f= 0.0236
f= 0.0237

Calculate for Head Loss, HL (m)

HL = 244.45903 m

Calculate for Pressure Drop, P (Psi)

P = 347.34033 Psi

Prepared By : Mark kenneth A. Pacatang


Design Engineer

Reviewed By : Lynus Junio


Design and Technical Services Manager
Mechatrends Contractors Corporation
249 MANGGAHAN ST., BINAKAYAN, KAWIT, CAVITE
Tel No.: (046) 434-6643 * 434-9253 * 434-1503 * MECHANICAL ENGINEERS
Fax No.: (046) 434-1894 * FABRICATORS
E-mail add: mecha@info.com.ph * CONTRACTORS

Pipe Sizing Calculation

Client : Mcmai Cebu Trading Corp.


Project : 4" Ø Pipe line Calculation
Location: Calaca, Batangas

Calculation of Required Pipe Diameter

Design Data:

Mass Flowrate, Q (MT/hr) 300


Density of Product, ρ (Kg/m3) 1840
Pipe diameter, D (m) 0.10226
Dynamic Viscosity, μ (Ns/m2) 0.024
Pipe Length, L ( m ) 980
Acceleration due to Gravity, G ( m/s2 ) 9.81

𝑄= 300𝑀𝑇/ℎ𝑟 𝑥 1
Convert of Mass Flowrate to Volume Flowrate, Q (m3/s)

Q= 0.045 m3/s

Calculate for Velocity, V (m/s)

V= 5.514 m/s

Calculate for Reynold`s Number, Re

Re = 43232.65
Calculate for Friction Factor, f

f= 0.020
f= 0.0231
f= 0.0228
f= 0.0229

Calculate for Head Loss, HL (m)

HL = 340.13844 m

Calculate for Pressure Drop, P (Psi)

P = 483.28669 Psi

Prepared By : Mark kenneth A. Pacatang


Design Engineer

Reviewed By : Lynus Junio


Design and Technical Services Manager
Mechatrends Contractors Corporation
249 MANGGAHAN ST., BINAKAYAN, KAWIT, CAVITE
Tel No.: (046) 434-6643 * 434-9253 * 434-1503 * MECHANICAL ENGINEERS
Fax No.: (046) 434-1894 * FABRICATORS
E-mail add: mecha@info.com.ph * CONTRACTORS

Pipe Sizing Calculation

Client : Mcmai Cebu Trading Corp.


Project : 4" Ø Pipe line Calculation
Location: Calaca, Batangas

Calculation of Required Pipe Diameter

Design Data:

Mass Flowrate, Q (MT/hr) 400


Density of Product, ρ (Kg/m3) 1840
Pipe diameter, D (m) 0.10226
Dynamic Viscosity, μ (Ns/m2) 0.024
Pipe Length, L ( m ) 980
Acceleration due to Gravity, G ( m/s2 ) 9.81

𝑄= 400𝑀𝑇/ℎ𝑟 𝑥 1
Convert of Mass Flowrate to Volume Flowrate, Q (m3/s)

Q= 0.060 m3/s

Calculate for Velocity, V (m/s)

V= 7.353 m/s

Calculate for Reynold`s Number, Re

Re = 57643.53
Calculate for Friction Factor, f

f= 0.020
f= 0.0219
f= 0.0217
f= 0.0218

Calculate for Head Loss, HL (m)

HL = 576.6477 m

Calculate for Pressure Drop, P (Psi)

P = 819.33157 Psi

Prepared By : Mark kenneth A. Pacatang


Design Engineer

Reviewed By : Lynus Junio


Design and Technical Services Manager
Mechatrends Contractors Corporation
249 MANGGAHAN ST., BINAKAYAN, KAWIT, CAVITE
Tel No.: (046) 434-6643 * 434-9253 * 434-1503 * MECHANICAL ENGINEERS
Fax No.: (046) 434-1894 * FABRICATORS
E-mail add: mecha@info.com.ph * CONTRACTORS

Pipe Sizing Calculation

Client : Mcmai Cebu Trading Corp.


Project : 4" Ø Pipe line Calculation
Location: Calaca, Batangas

Calculation of Required Pipe Diameter

Design Data:

Mass Flowrate, Q (MT/hr) 600


Density of Product, ρ (Kg/m3) 1840
Pipe diameter, D (m) 0.10226
Dynamic Viscosity, μ (Ns/m2) 0.024
Pipe Length, L ( m ) 980
Acceleration due to Gravity, G ( m/s2 ) 9.81

𝑄= 600𝑀𝑇/ℎ𝑟 𝑥 1
Convert of Mass Flowrate to Volume Flowrate, Q (m3/s)

Q= 0.091 m3/s

Calculate for Velocity, V (m/s)

V= 11.029 m/s

Calculate for Reynold`s Number, Re

Re = 86465.30
Calculate for Friction Factor, f

f= 0.0200
f= 0.0205
f= 0.0205
f= 0.0205

Calculate for Head Loss, HL (m)

HL = 1217.6659 m

Calculate for Pressure Drop, P (Psi)

P= 1730.12 Psi

Prepared By : Mark kenneth A. Pacatang


Design Engineer

Reviewed By : Lynus Junio


Design and Technical Services Manager
Mechatrends Contractors Corporation
249 MANGGAHAN ST., BINAKAYAN, KAWIT, CAVITE
Tel No.: (046) 434-6643 * 434-9253 * 434-1503 * MECHANICAL ENGINEERS
Fax No.: (046) 434-1894 * FABRICATORS
E-mail add: mecha@info.com.ph * CONTRACTORS

Pipe Sizing Calculation

Client : Mcmai Cebu Trading Corp.


Project : 4" Ø Pipe line Calculation
Location: Calaca, Batangas

Calculation of Required Pipe Diameter

Design Data:

Mass Flowrate, Q (MT/hr) 750


Density of Product, ρ (Kg/m3) 1840
Pipe diameter, D (m) 0.10226
Dynamic Viscosity, μ (Ns/m2) 0.024
Pipe Length, L ( m ) 980
Acceleration due to Gravity, G ( m/s2 ) 9.81

𝑄= 750𝑀𝑇/ℎ𝑟 𝑥 1
Convert of Mass Flowrate to Volume Flowrate, Q (m3/s)

Q= 0.113 m3/s

Calculate for Velocity, V (m/s)

V= 13.786 m/s

Calculate for Reynold`s Number, Re

Re = 108081.62
Calculate for Friction Factor, f

f= 0.020
f= 0.0198
f= 0.0198
f= 0.0199

Calculate for Head Loss, HL (m)

HL = 1844.4898 m

Calculate for Pressure Drop, P (Psi)

P = 2620.7487 Psi

Prepared By : Mark kenneth A. Pacatang


Design Engineer

Reviewed By : Lynus Junio


Design and Technical Services Manager
Mechatrends Contractors Corporation
249 MANGGAHAN ST., BINAKAYAN, KAWIT, CAVITE
Tel No.: (046) 434-6643 * 434-9253 * 434-1503 * MECHANICAL ENGINEERS
Fax No.: (046) 434-1894 * FABRICATORS
E-mail add: mecha@info.com.ph * CONTRACTORS

Pipe Sizing Calculation

Client : Mcmai Cebu Trading Corp.


Project : 8" Ø Pipe line Calculation
Location: Calaca, Batangas

Calculation of Required Pipe Diameter

Design Data:

Mass Flowrate, Q (MT/hr) 650


Density of Product, ρ (Kg/m3) 1530
Pipe diameter, D (m) 0.20274
Dynamic Viscosity, μ (Ns/m2) 0.075
Pipe Length, L ( m ) 1418
Acceleration due to Gravity, G ( m/s2 ) 9.81

𝑄= 650𝑀𝑇/ℎ𝑟 𝑥 1ℎ
Convert of Mass Flowrate to Volume Flowrate, Q (m3/s)

Q= 0.12 m3/s

Calculate for Velocity, V (m/s)

V = 3.655533 m/s

Calculate for Reynold`s Number, Re

Re = 15118.90
Calculate for Friction Factor, f

f= 0.02775

Calculate for Head Loss, HL (m)

HL = 132.238 m

Calculate for Pressure Drop, P (Psi)

P = 187.8907 Psi

Prepared By : Mark kenneth A. Pacatang


Design Engineer

Reviewed By : Lynus Junio


Design and Technical Services Manager