Crashing Worksheet 7: Tmi / Dbe
Crashing Worksheet 7: Tmi / Dbe
Question 1:
The activities and completion times for a project are shown in the network diagram
below.
E,4 E’,0
E,4 E’,0
A,6
FINISH
START
F,6 I,2
G,2
B,5 C,2
The completion time of some of the remaining activities in the project can be
reduced at a cost.
The following table shows the reduced times (least possible time to complete an
activity after maximum reduction of time).
a. Determine the shortest completion time for the project, the critical path
and any float times for activities.
ii. Find the maximum time in hours that can be saved by this reduction.
1
TMI / DBE
Question 2:
The table below gives the activities involved in landscaping a garden. It is possible
to crash this project.
b. Find the:
c. Calculate the:
2
TMI / DBE
Question 3:
D, 1
A, 4 G, 3
Start Finish
B, 4 E, 4 H, 2 J, 6
C, 3 F, 4
The builders of the community centre are able to speed up the project.
Some of the activities can be reduced in time at an additional cost.
The activities that can be reduced in time are A, C, E, F and G.
The owner of the estate is prepared to pay the additional cost to achieve early
completion.
The cost of reducing the time of each activity is $5000 per week.
The maximum reduction in time for each one of the five activities, A, C. E, F, G, is
2 weeks.
d. Determine the minimum time, in weeks, for the project to be completed now
that certain activities can be reduced in time.
3
TMI / DBE
Question 3:
D, 1
A, 4 G, 3
Start Finish
B, 4 E, 4 H, 2 J, 6
C, 3 F, 4
The builders of the community centre are able to speed up the project.
Some of the activities can be reduced in time at an additional cost.
The activities that can be reduced in time are A, C, E, F and G.
The owner of the estate is prepared to pay the additional cost to achieve early
completion.
The cost of reducing the time of each activity is $5000 per week.
The maximum reduction in time for each one of the five activities, A, C. E, F, G, is
2 weeks.
d. Determine the minimum time, in weeks, for the project to be completed now
that certain activities can be reduced in time.
4
TMI / DBE