P.O.

Box 5971
Jeddah, Saudi Arabia
TEL: + 966 12 648 2146
FAX: +971-4-883-1240

DAILY ACTIVITES

Sheet : 1

Date : 1-Nov-19
To : Daniel Kim Soon TR. No :
Ref. No :
Cc: Ahmad Thameem

S/N Time Combi Wall Underwater Anode Installation Purpose


0600H Started work Activities
0700H First trailor carrying Rocks dispatched to site from doosan yard. For Approval
0730H Dump Trucks dumping soil to build the access road For Information

Offloaded rock trailer at site Doosan excavator 300LC is loading dump trucks and 800LC excavator is
0800H For Review
being used for the preparation of access ramp.

1000H Excavators excavating the sand and making access road


1100H Stopped the work for Jumma Prayer

1340H offloading rocks at site from trailor.

Excavator shifted to new location for soil loading..800 LC reached in the arra where sand is available so
1400H
Operator is digging and using this sand to move the access road forward.
Dump tricks dumping the dry sand on access road .Today excavators increased the length of access
1600H
road 40 meters .Visited doosan yard to calculate the remainind rocks

1800H Finished work activities .Trailer made 4 trips of rocks from doosan yard to coast guard berth.

Manpower

No. Title Name No. Title Name


1 Project Engineer Hafiz Muhammad 9 Forklidt Operator Muhammad
2 Site Supervisor Souriya 10 High bed trailer driver Sumith
3 Driver Fateh 11
4 Excavator Operator Zafar Parvej 12
5 Excavator Operator Muhammad Naeem 13
6 DT Driver Vantakestan 14
7 DT Driver Murgessan 15
8 DT Driver Thomas 16
Equipment Used / Transport Vehicle
No. No. No.

1 Excavator 30 Ton 6 Tower lights 11


2 Excavator 80 Ton 7 Acccent car for transportation 12
3 Excavator 80 Ton maintenance no work 8 Forklift for loading rocks 13
4 Wheel loader under maintenance no work 9 Breaker under maintenance 14
5 Dump Truck 3 Nos working 10 Highbed Trailer working. 15

Hafiz Muhammad Sherdil Khan


Prepared/Reported Project Engineer

Receipt required(Please acknowledge the



receipt in the duplicate and return)
The above document received by
Date

Form No. QP-11-001 (3)

You might also like