RENCANA ANGGARAN BIAYA ( RAB )

PEKERJAAN PEMINDAHAN TIANG LISTRIK KM 2 - KM 7 PENAJAM


LOKASI KECAMATAN PENAJAM
NO URAIAN PEKERJAAN Harga Jumlah
Satuan Volume
Satuan (Rp) Harga (Rp)
A. PEMINDAHAN TIANG LISTRIK

I MATERIAL UTAMA
1 Tiang Beton 13 m Batang 85.00 10,470,000.00 889,950,000.00
2 Tiang Beton 11 m Batang 3.00 8,350,000.00 25,050,000.00
3 Tiang Beton 9 m Batang 57.00 6,972,467.00 397,430,619.00
4 Kawat AAACS 70 mm Meter 13,032.00 23,700.00 308,858,400.00
5 Kabel NYY 120 mm Meter 88.00 195,900.00 17,239,200.00
6 Kabel NYY 90 mm Meter 132.00 118,980.00 15,705,360.00
7 Kabel Twisteed AL 3x70 + 1x50 mm Meter 7,763.00 46,904.00 364,115,752.00

JUMLAH A 2,018,349,331.00

II MATERIAL NON UTAMA

1 Trafers UNP 8x2x200 cm Lengkap Buah 22.00 682,800.00 15,021,600.00


2 Trafers UNP 8x185 cm Buah 79.00 204,000.00 16,116,000.00
3 Pin Post Isolator 20 KV Buah 270.00 273,000.00 73,710,000.00
4 Strain Isolator Set 33.00 510,000.00 16,830,000.00
5 Arm Tie Buah 101.00 81,120.00 8,193,120.00
6 Material Trec Score Set 22.00 582,000.00 12,804,000.00
7 Material Druc Score Set 3.00 490,485.00 1,471,455.00
8 CCO 5T5 Buah 73.00 70,320.00 5,133,360.00
9 Fix And Dead Assy Buah 30.00 80,419.00 2,412,570.00
10 Suspension Assy Buah 125.00 50,578.00 6,322,250.00
11 Stainless Steel Strip Meter 84.00 12,898.00 1,083,432.00
12 Kabel Twisteed AL 2x10 mm Meter 2,300.00 3,654.00 8,404,200.00
13 CCO 1T1 Buah 312.00 12,100.00 3,775,200.00
14 Service Wadge Clamp Buah 312.00 3,850.00 1,201,200.00
15 Pole Breacket 7 In untuk Tiang Beton Set 69.00 16,830.00 1,161,270.00
16 Transport Material Ls 1.00 25,000,000.00 25,000,000.00

198,639,657.00

III UPAH KERJA

1 Mendirikan Tiang 13 mtr / Pembongkaran Batang 85.00 616,860.00 52,433,100.00


2 Mendirikan Tiang 11 mtr / Pembongkaran Batang 3.00 565,000.00
3 Mendirikan Tiang 9 mtr / Pembongkaran Batang 57.00 495,000.00 28,215,000.00
4 Pasang Trafers UNP / Pembongkaran Buah 101.00 47,790.00 4,826,790.00
5 Pasang Pin Post Isolator / Pembongkaran Buah 270.00 31,625.00 8,538,750.00
6 Pasang Strain Isolator / Pembongkaran Buah 33.00 35,625.00 1,175,625.00
7 Pasang Arm Tie / Pembongkaran Buah 101.00 21,000.00 2,121,000.00
8 Pasang Material Trec Scoer / Pembongkaran Buah 22.00 152,310.00 3,350,820.00
9 Pasang Material Druc Scoer / Pembongkaran Buah 3.00 158,860.00 476,580.00
10 Pasang Kontramask / Pembongkaran Buah 1.00 211,309.00 211,309.00
11 Pasang SUTM AAACS 150 mm / Pembongkaran Gawang 86.00 173,505.00 14,921,430.00
12 Pasang Twisteed AL 2x70 + 1x50 mm / Pembongkar Gawang 142.00 114,359.00 16,238,978.00
13 Pengepresan Buah 385.00 30,000.00 11,550,000.00
14 Pemasangan Accessorir SUTR Buah 112.00 75,600.00
15 Pemasangan / Pembongkaran SR Buah 156.00 85,608.00 13,354,848.00
16 Biaya Serah Terima Operasi (Commisioning Test) Ls 1.00 25,000,000.00 25,000,000.00

182,414,230.00
SUB JUMLAH A 2,399,403,218.00

B. PEMINDAHAN GARDU DISTRIBUSI


I MATERIAL UTAMA
1 Lighting Arrester 24 KV 10 A Buah 9.00 3,067,920.00 27,611,280.00
2 Open Disk Cut Out 3-6 A Buah 9.00 3,573,900.00 32,165,100.00
3 Kabel NYFGBY 4 x 95 mm Meter Batang 200.00 686,400.00 137,280,000.00
4 Tiang Beton 11 meter 3.00 8,350,000.00 25,050,000.00

JUMLAH A 222,106,380.00
MATERIAL NON UTAMA
II 1 Fuse Link 6 A - 20 KV
2 Bordesk Trafo Tiang Tunggal 3 Bordesk Trafo Tiang Ganda
4 Trafers UNP 6,5x240 cm untuk Cut Out 5 LV Bord 2 Jurusan 400 Amper Buah 9.00 44,580.00 401,220.00
6 LV Bord 4 Jurusan 630 Amper Set 1.00 2,975,000.00 2,975,000.00
7 Trafers UNP 6,5x240 cm untuk LV Bord 8 Kabel NYY 120 mm Set 2.00 4,380,000.00 8,760,000.00
9 Kabel NYY 95 mm
10 Pipa Galvanize 3 inchi lengkap inporing 11 Pipa Galvanize 2,5 inchi Buah 8.00 281,700.00 2,253,600.00
lengkap inporing 12 Arm Tie PPI lengkap Klam / Bolt Set 1.00 7,260,000.00 7,260,000.00
13 Material Grounding / Arde 2,75 mtr 14 Material Grounding / Arde 5,50 Set 2.00 12,632,400.00 25,264,800.00
mtr 15 Perlengkapan LV Bord
16 Pondasi Trafo Tiang Tunggal 17 Pondasi Trafo Tiang Ganda Buah 6.00 281,700.00 1,690,200.00
18 Comp Conector AL 70 mm / (CCO 5T5) 19 Sambungan AL / CU 5T5 Meter 132.00 195,900.00 25,858,800.00
70/95 mm Meter 220.00 118,980.00 26,175,600.00
20 Plat Tanda Bahaya
Batang 3.00 789,900.00 2,369,700.00
21 Sepatu Kabel 120 mm
22 Sepatu Kabel 95 mm 23 Papan Ulin 3/4 inchi 24 Stainless Steel Strip Batang 5.00 604,930.00 3,024,650.00
25 Kabel Twisteed AL 2x10 mm 26 CCO 1T1 Set 6.00 81,120.00 486,720.00
27 Service Wadge Clamp Set 3.00 905,880.00 2,717,640.00
28 Pole Breacket 7 inchi untuk Tiang Beton 29 Transport Material
Set 3.00 1,305,000.00 3,915,000.00
Set 2.00 635,000.00
Buah 1.00 514,800.00 514,800.00
Buah 2.00 574,560.00 1,149,120.00
Buah 12.00 70,319.00 843,828.00
Buah 28.00 52,710.00 1,475,880.00
Buah 3.00 78,000.00 234,000.00
Buah 12.00 54,340.00 652,080.00
Buah 32.00 51,700.00 1,654,400.00
Lembar 30.00 66,000.00 1,980,000.00
Meter 30.00 13,700.00 411,000.00
Meter 2,300.00 3,654.00 8,404,200.00
Buah 216.00 12,100.00 2,613,600.00
Buah 108.00 3,850.00 415,800.00
Set 42.00 16,830.00 706,860.00
Ls 1.00 20,000,000.00 20,000,000.00

154,208,498.00
UPAH KERJA
III 1 Pasang Sepatu Kabel / Pembongkaran
2 Pasang Bordesk Trafo Tiang Tunggal / Bongkar 3 Pasang Bordesk Trafo
Tiang Ganda / Bongkar 4 Pasang Cut Out / Pembongkaran Buah 308.00 17,500.00 5,390,000.00
5 Pasang Lighting Arrester / Pembongkaran 6 Pasang Arde Buah 1.00 274,755.00 274,755.00
7 Pasang Perlengkapan LV Bord / Bongkar 8 Pengepresan Buah 2.00 461,585.00 923,170.00
9 Pemasangan Kabel Ponding 10 Bongkar Pasang Pondasi Trafo 11
Bongkar Pasang Trafo Buah 9.00 227,700.00 2,049,300.00
12 Upah Pemasangan Kabel Tanah 13 Transport Material Buah 9.00 227,700.00 2,049,300.00
14 Biaya Serah Terima Operasi (Commisining Test) Buah 6.00 50,310.00 301,860.00
Buah 3.00 498,185.00 1,494,555.00
Buah 115.00 30,000.00 3,450,000.00
Buah 10.00 414,170.00 4,141,700.00
Buah 3.00 50,310.00 150,930.00
Buah 3.00 976,040.00 2,928,120.00
Meter 216.00 48,000.00 10,368,000.00
Ls 1.00 17,500,000.00 17,500,000.00
Ls 1.00 20,000,000.00 20,000,000.00

71,021,690.00
S 447,336,568.00
U
B
JUMLAH A + B JU 2,846,739,786.00
PPN 10% M 284,673,978.60
TOTAL JUMLAH L 3,131,413,764.60
A
3,131,413,000.00
H
B

OE
Harga
Satuan (Rp)
8,950,000.00

7,600,000.00

623,400.00

593,100.00

JUMLAH A

JUMLAH A
OE
HARGA PERKIRAAN SENDIRI (HPS)
PEKERJAAN PEMINDAHAN TIANG LISTRIK KM 2 - KM 7 PENAJAM
LOKASI KECAMATAN PENAJAM
NO URAIAN PEKERJAAN Harga Jumlah
Satuan Volume
Satuan (Rp) Harga (Rp)
A. PEMASANGAN DAN PENGADAAN TIANG LISTRIK

I MATERIAL UTAMA
1 Tiang Beton 13 m Batang 85.00
2 Tiang Beton 9 m Batang 57.00
3 Kawat AAACS 70 mm Meter 13,032.00
4 Kabel Twisteed AL 3x70 + 1x50 mm Meter 7,763.00

JUMLAH A -

II MATERIAL NON UTAMA

1 Trafers UNP 8x2x200 cm Lengkap Buah 22.00


2 Trafers UNP 8x185 cm Buah 79.00
3 Pin Post Isolator 20 KV Buah 270.00
4 Strain Isolator Set 33.00
5 Arm Tie Buah 101.00
6 Material Trec Score Set 22.00
7 Material Druc Score Set 3.00
8 CCO 5T5 Buah 73.00
9 Fix And Dead Assy Buah 30.00
10 Suspension Assy Buah 125.00
11 Stainless Steel Strip Meter 84.00
12 Kabel Twisteed AL 2x10 mm Meter 2,300.00
13 CCO 1T1 Buah 312.00
14 Service Wadge Clamp Buah 312.00
15 Pole Breacket 7 In untuk Tiang Beton Set 69.00
16 Transport Material Ls 1.00

III UPAH KERJA

1 Mendirikan Tiang 13 mtr / Pembongkaran Batang 85.00


2 Mendirikan Tiang 9 mtr / Pembongkaran Batang 57.00
3 Pasang Trafers UNP / Pembongkaran Buah 101.00
4 Pasang Pin Post Isolator / Pembongkaran Buah 270.00
5 Pasang Strain Isolator / Pembongkaran Buah 33.00
6 Pasang Arm Tie / Pembongkaran Buah 101.00
7 Pasang Material Trec Scoer / Pembongkaran Buah 22.00
8 Pasang Material Druc Scoer / Pembongkaran Buah 3.00
9 Pasang Kontramask / Pembongkaran Buah 1.00
10 Pasang SUTM AAACS 150 mm / Pembongkaran Gawang 86.00
11 Pasang Twisteed AL 2x70 + 1x50 mm / Pembongkar Gawang 142.00
12 Pengepresan Buah 385.00
13 Pemasangan / Pembongkaran SR Buah 156.00

-
SUB JUMLAH A -

B. PEMASANGAN DAN PENGADAAN GARDU DISTRIBUSI


I MATERIAL UTAMA
1 Lighting Arrester 24 KV 10 A Buah 9.00
2 Open Disk Cut Out 3-6 A Buah 9.00
3 Kabel NYFGBY 4 x 95 mm Meter 200.00
4 Tiang Beton 11 meter Batang 3.00

JUMLAH A -

II MATERIAL NON UTAMA


1 Fuse Link 6 A - 20 KV Buah 9.00
2 Bordesk Trafo Tiang Tunggal Set 1.00
3 Bordesk Trafo Tiang Ganda Set 2.00
4 Trafers UNP 6,5x240 cm untuk Cut Out Buah 8.00
5 LV Bord 2 Jurusan 400 Amper Set 1.00
6 LV Bord 4 Jurusan 630 Amper Set 2.00
7 Trafers UNP 6,5x240 cm untuk LV Bord Buah 6.00
8 Kabel NYY 120 mm Meter 132.00
9 Kabel NYY 95 mm Meter 220.00
10 Pipa Galvanize 3 inchi lengkap inporing Batang 3.00
11 Pipa Galvanize 2,5 inchi lengkap inporing Batang 5.00
12 Arm Tie PPI lengkap Klam / Bolt Set 6.00
13 Material Grounding / Arde 2,75 mtr Set 3.00
14 Material Grounding / Arde 5,50 mtr Set 3.00
15 Pondasi Trafo Tiang Tunggal Buah 1.00
16 Pondasi Trafo Tiang Ganda Buah 2.00
17 Comp Conector AL 70 mm / (CCO 5T5) Buah 12.00
18 Sambungan AL / CU 5T5 70/95 mm Buah 28.00
19 Plat Tanda Bahaya Buah 3.00
20 Sepatu Kabel 120 mm Buah 12.00
21 Sepatu Kabel 95 mm Buah 32.00
22 Papan Ulin 3/4 inchi Lembar 30.00
23 Stainless Steel Strip Meter 30.00

III UPAH KERJA

1 Pasang Sepatu Kabel / Pembongkaran Buah 308.00


2 Pasang Bordesk Trafo Tiang Tunggal / Bongkar Buah 1.00
3 Pasang Bordesk Trafo Tiang Ganda / Bongkar Buah 2.00
4 Pasang Cut Out / Pembongkaran Buah 9.00
5 Pasang Lighting Arrester / Pembongkaran Buah 9.00
6 Pasang Arde Buah 6.00
7 Pasang Perlengkapan LV Bord / Bongkar Buah 3.00
8 Pengepresan Buah 115.00
9 Pemasangan Kabel Ponding Buah 10.00
10 Bongkar Pasang Pondasi Trafo Buah 3.00
11 Bongkar Pasang Trafo Buah 3.00
12 Upah Pemasangan Kabel Tanah Meter 216.00
13 Biaya Serah Terima Operasi (Commisining Test) Ls 1.00

-
S -
U
B
Harga J
Satuan (Rp) U
M
L
10,470,000.00 A
H
B
6,972,467.00
23,700.00
46,904.00

JUMLAH A

682,800.00
204,000.00
273,000.00
510,000.00
81,120.00
582,000.00
490,485.00
70,320.00
80,419.00
50,578.00
12,898.00
3,654.00
12,100.00
3,850.00
16,830.00
25,000,000.00

616,860.00
495,000.00
47,790.00
31,625.00
35,625.00
21,000.00
152,310.00
158,860.00
211,309.00
173,505.00
114,359.00
30,000.00
85,608.00
25,000,000.00

3,067,920.00
3,573,900.00
686,400.00
8,350,000.00

JUMLAH A

44,580.00

2,975,000.00
4,380,000.00
281,700.00
7,260,000.00
12,632,400.00
281,700.00
195,900.00
118,980.00
789,900.00
604,930.00
81,120.00
905,880.00
1,305,000.00
514,800.00
574,560.00
70,319.00
52,710.00
78,000.00
54,340.00
51,700.00
66,000.00
13,700.00

17,500.00
274,755.00
461,585.00
227,700.00
227,700.00
50,310.00
498,185.00
30,000.00
414,170.00
50,310.00
976,040.00
48,000.00
20,000,000.00
REKAPITULASI
HARGA PERKIRAAN SENDIRI (HPS)
PEKERJAAN PEMINDAHAN TIANG LISTRIK KM 2 - KM 7 PENAJAM
LOKASI KECAMATAN PENAJAM

NO URAIAN JUMLAH HARGA (RP)

A PEMASANGAN DAN PENGADAAN

1 Material Utama
2 Material Non Utama
3 Upah Kerja

B PEMASANGAN DAN PEMASANGAN GARDU DISTRIBUSI


1 Material Utama
2 Material Non Utama
3 Upah Kerja

TOTAL -
PPN 10% -
JUMLAH TOTAL -
TOTAL DIBULATKAN -
Terbilang :

Dibuat oleh:

Derektur/dekekt
ris
PT/CV.................
..........
Derektur/dekekt
ris
PT/CV.................
..........