Professional Documents
Culture Documents
011 - RH340B - #340085 - Pressure Checking and Setting - 08 - 06-3720618en
011 - RH340B - #340085 - Pressure Checking and Setting - 08 - 06-3720618en
8.6.1.3 General
Before recommissioning, all pro-
tective devices must be refitted. The reference numbers used in the text and illus-
trations correspond to those used in the hydraulic
Catwalks on the boom are only to
circuit diagram.
be walked on when the excavator's
working attachment has been
Since the machine is equipped with the BCS-Board
brought into the position required
Control System, most pressures are available on
for checking/settings pressures.
the BCS display. If pressure must be reset, in any
Hydraulic cylinders must be case calibrated gauges have to be used, they have
brought into their end positions to be connected to the relevant test points.
before pressures are checked or
set to ensure that working attach-
ment does not move when pres- Numbering of main pumps
sure is applied.
The 8 main pumps (4 double pumps) are num-
The excavator operator must oper-
bered in travel direction from left to right and from
ate the relevant function gently
front to rear (Fig.1),
(gradual application of pressure)
thus P1/P2 and P3/P4 are driven by the LH en-
and then shift the joystick/pedals
gine, and P5/P6 and P7/P8 are driven by the RH
fully to their end position.
engine.
All Pressure test points on the ex-
cavator have Minimess connec-
tions. Pressure gauges used for Numbering of swing pumps
checking must therefore have cor-
responding fittings. Each drive unit is equipped with 2 swing pumps.
The swing pumps on the LH pump gearbox are
Always connect the Minimess-hose
named SP1 / SP2, the pumps on the RH pump
first to the gauge and then to the
gearbox are named SP3 / SP4 (Fig. 1).
test point on the machine to avoid
spillage of pressurized oil!
Auxiliary pumps (Fig. 1)
The springs in pressure relief
valves must never be tightened - Gear pump for the pilot pressure. (6)
fully to "block". The windings of - Charge pump (7)
the spring are then jammed so that - Hydraulic oil cooling pump (10)
the valve cannot open. - Variable displacement pump for the fan drive
of the engine radiator. (11)
Before setting/resetting a relief
valve (primary or secondary)
loosen the valve insert by approx.
2 turns:
Turning anti-clockwise (loosening)
= lower pressure setting
Turning clockwise (tightening)
= increase pressure setting
To set/reset a pressure relief valve
loosen the counter nut on the valve
insert, set the opening pressure
using the setting crew, and then
tighten the counter nut again.
When checking/setting pressures Fig. 1 642112
the hydraulic oil temperature must
be above 50°C.
PST bar 8 – 43
P bar 80
8.6.3 Tools
For pressure checking and setting the tools listed in table 2 are required.
Fig. 2 630640
Fig. 3 642113
Fig. 4 642114
Fig. 5 642115
Note:
Fig. 11 642119
Fig. 14 642122
3. Check pressure.
Both gauges must indicate approx. 8 bar
(225 mA).
Checking the load limit pressure for the LH 5. Check pressure (Stick cylinders are in end-
drive unit: position; pressure cut-off in function):
Both gauges must indicate approx. 43 bar
1. Connect gauges (range 60 bar) to the test (820 mA).
points (M, 23.1 & 23.2, Fig. 13).
2. Run LH engine with maximum speed. The RH In case the required pressures are not achieved
engine has to be shut off. the proportional valves must be checked.
Fig. 15 630782
Note:
It is also possible to check and read the current
values via the BCS
Note:
Fig. 16 642123
As a precondition for the following tests and set-
tings it is essential that all primary- and secondary
valves are correctly adjusted.
Fig. 18 642125
6. Shut of LH engine.
1. Connect a gauge (range: 400 bar) to test point 1. Connect a gauge (range: 400 bar) to test point
M 2/8. The test point is installed close to the M 3/5. The test point is installed close to the
high pressure filter block (Fig. 19). high pressure filter block (Fig. 19).
2. Start one engine. The other engine must be 2. Start one engine. The other engine must be
switched off. The shovel teeth must be pushed switched off. The shovel teeth must be pushed
into the ground and the travel parking brake into the ground and the travel parking brake
must be applied (remove plug connector of so- must be applied (remove plug connector of so-
lenoid valve Y12), so that travel movements lenoid valve Y12), so that travel movements
are avoided during the check. The undercar- are avoided during the check. The undercar-
riage has to be positioned with final drives at riage has to be positioned with final drives at
the rear. The parking brake "swing" must be the rear. The parking brake "swing" must be
activated to avoid turning of the superstructure. activated to avoid turning of the superstructure.
3. Set primary relief valve of main pumps (P2/8) 3. Set primary relief valve of main pumps (P3/5)
at the high pressure filter block (PRV 2/8 Fig. at the high pressure filter block (PRV 3/5 Fig.
20): 20):
When a new primary relief valve is installed When a new primary relief valve is installed
screw the adjuster 1 turn out, to avoid pressure screw the adjuster 1 turn out, to avoid pressure
peaks. peaks.
Screw the adjuster of the pressure cut-off Screw the adjuster of the pressure cut-off
valve A, at pump P2 & P8 completely in and valve A, at pump P3 & P5 completely in and
then ¼ turn back (Fig. 17 & 18). This is to raise then ¼ turn back (Fig. 17 & 18). This is to raise
the set value of this valve above 380 bar. the set value of this valve above 380 bar.
Screw the adjuster of the four secondary relief Screw the adjuster of the four secondary relief
valves “Bucket cylinder piston side” completely valves “Bucket cylinder piston side” completely
in and then ¼ turn back (Pos. 3 + 9 + 15 + 21, in and then ¼ turn back (Pos. 3 + 9 + 15 + 21,
Fig. 24 chapter 8.6.4.5). This is to raise the set Fig. 24 chapter 8.6.4.5). This is to raise the set
value of these valves above 380 bar. value of these valves above 380 bar.
Activate BCS Test mode. (see chapter Activate BCS Test mode. (see chapter
8.6.4.12) 8.6.4.12)
Start one engine (LH or RH) and bring it to Start one engine (LH or RH) and bring it to
maximum speed. maximum speed.
Activate function "bucket fill" until the cylinders Activate function "bucket fill" until the cylinders
are completely extended. are completely extended.
Check pressure (rated 380 bar). Check pressure (rated 380 bar).
If necessary reset primary relief valve PRV 2/8 If necessary reset primary relief valve PRV 3/5
Reset the four secondary relief valves “Bucket Reset the four secondary relief valves “Bucket
cylinder piston side” back to 360 bar. cylinder piston side” back to 360 bar.
After setting all secondary relief valves reduce After setting all secondary relief valves reduce
pressure cut-off valve back to 320 bar. pressure cut-off valve back to 320 bar.
After the settings are finished, stop the engine After the settings are finished, stop the engine
and interrupt the power supply with the key and interrupt the power supply with the key
switch, to deactivate the BCS Test mode. switch, to deactivate the BCS Test mode.
Test points to check the individual pump pressure Checking the pressure difference:
at the inlet and outlet of the HP-filters and to check
the function of the internal check valves. Pump Test point Fig. Test point Fig.
filter inlet filter outlet
1 MP1 21 MP1/1 21
2 MP2 21 MP2/1 22
3 MP3 22 MP3/1 22
4 MP4 22 MP4/1 22
5 MP5 23 MP5/1 23
6 MP6 23 MP6/1 23
7 MP7 21 MP7/1 23
8 MP8 21 MP8/1 23
Table 5
Engine 1 Engine 2
ON OFF
MP1 & MP1/1 MP7 & MP7/1
1 0
MP2 & MP2/1 MP8 & MP8/1
1 0
MP3 & MP3/1 MP5 & MP5/1
1 0
MP4 & MP4/1 MP6 & MP6/1
1 0
Table 6
Fig. 22 642128
1 = pressure
0 = no pressure
Engine 1 Engine 2
OFF ON
MP1 & MP1/1 MP7 & MP7/1
0 1
MP2 & MP2/1 MP8 & MP8/1
0 1
MP3 & MP3/1 MP5 & MP5/1
0 1
MP4 & MP4/1 MP6 & MP6/1
0 1
8.6.4.5 Secondary relief system for attachment two valves installed per section i.e. 12 at the A-
side and 12 at the B-side. The 3-spool control
The secondary relief valves (SRV) for the attach-
blocks are located on the boom.
ment are screwed into the 3-spool control blocks
(160, 161,162 & 163, Fig. 24). There are always
Fig. 24 642131
This pressure check has to be done with only one Example – stick cylinder rod side:
engine running. The pressure cut-off function
should be adjusted over 360 bar on one main Carefully apply pressure to rod side of stick
pump only. The smaller flow rate of one pump cylinders by shifting the joystick smoothly to
only allows a more accurate pressure setting. the end position “Stick OUT”.
Check pressure (rated: 360 bar), when cylin-
Check pressures with LH engine running and main ders are in end-position.
pump (P2) or with RH engine and main pump (P8),
because these pumps supply oil to all cylinders of 6. Because the pair of cylinders is connected via
the attachment. compensating lines and secured by 4 relief
valves, the gauge on the test point always in-
dicates the lowest pressure setting of the 4
valves. Therefore it is possible that, even with
an indicated pressure of 360 bar, one valve is
still set too high.
To check the valves for 9. After the checks and settings are finished, stop
the engine and interrupt the power supply with
Rod side: retract cylinders fully the key switch, to deactivate the BCS Test
Piston side: extend cylinders fully mode.
Location of the secondary relief valves is shown in
Fig. 24. Valves are also installed on the opposite
side (bottom) of the main control blocks.
Check pressures with LH engine running and main 5. Start LH engine and bring to maximum speed.
pumps (P3 & P4) or with RH engine and main The bucket teeth must be pushed into the
pumps (P5 & P6) ground to brake the machine and to prevent
travel of the machine during the test. The park-
ing brake "swing" must be activated to avoid
turning of the superstructure.
2. Activate BCS Test mode. (see chapter 9. After checking all secondary relief valves re-
8.6.4.12) duce pressure cut-off valve back to 320 bar.
3. Connect four 400 bar pressure gauges to the 10. After the checks and settings are finished, stop
check points (M1 to M4, Fig. 27) for the pres- the engine and interrupt the power supply with
sure relief valves. the key switch, to deactivate the BCS Test
mode.
4. Screw the adjuster of the pressure cut-off
valve AP3 & AP4 (Fig. 28) of pumps (P3 & P4)
completely in and then ¼ turn back. This is to
raise the pressure above 380 bar (secondary
relief setting).
Fig. 29 642132
Overview:
S31 M-A2 M-B1
OFF 60 bar 0 bar
ON 80 bar 80 bar
Table 9
Note:
Inlet pressure:
3. Check pressure.
Rated: 60 bar;
If necessary adjust auxiliary pressure 2 (see
chapter 8.6.4.1).
11. Start both engines and let them run with ma-
ximum speed.
13. If the pressure at test point M-B1 is not 0 bar, Tensioning the tracks
the set screw of the change over valve (SV,
Fig. 34) has to be turned out (ccw) until the Tensioning and slackening the tracks is described
valve switches over to 0 bar. in the operator's manual.
The hydraulic oil is cooled by two independent The coolant of the engines is cooled by two inde-
cooling circuits. pendent cooling circuits.
Each circuit is related to one engine. Each circuit is related to one engine.
The two cooling pumps on the LH engine drive the
two front fan motors. The two cooling pumps on Fig. 37 is showing fan pump (11) with flanged on
the RH engine drive the two rear fan motors. proportional valve and its coil (C).
The fan speed is electronically controlled and var-
ies in relation to the hydraulic oil temperature.
Fig. 37 642106
Pressure relief The fan pumps are equipped with a pressure cut-
off valve A (Fig. 37), which is set at the factory to
Pressure relief valves (85) are works set to approx. 280 bar.
65 bar. To check, proceed as follows: The adjustment of minimum flow is done at valve B
(Fig. 37). This valve is also set at the factory.
Set valves to circuiting pressure. To do this,
reduce valve cracking pressure until the circuit-
ing pressure starts to drop.
Fig. 38 642135
Charging and testing unit for Charging and testing unit for
diaphragm accumulators bladder accumulators with
adaptor A3
Fig. 43 642065
Fig. 41 642063
Legend, Fig. 43
Legend, Fig. 41 1 = Hydr. accumulator 5 = charging hose
A = Spindle 2 = Adaptor A 6 = Connector
B = Pressure release 3 = Charging and test- 7 = pressure reducer l
C = Check valve ing unit 8 = adaptor
A3 = Adaptor 4 = Connector 9 = nitrogen bottle
Gas valve for diaphragm Gas valve for bladder accu- DESCRIPTION (Charging and testing unit)
accumulators mulators
FUNCTION
The charging and testing unit is used to charge ac-
cumulators with nitrogen or to check or to change the
existing pre-charge pressure in accumulators. For this
purpose the charging and testing unit is screwed onto
the gas valve of the hydraulic accumulator and con-
nected to a commercial nitrogen bottle via a flexible
charging hose. If the nitrogen pressure is only to be
checked or reduced, the charging hose does not
need to be connected. The unit has a screw-type
fitting with a built-in gauge, check valve and a spindle
for opening the accumulator gas valve to control the
pressure. Piston and diaphragm accumulators can be
charged and checked without the need for adaptors.
Bladder accumulators, however, require an adaptor
Fig. 42 642064
A3.
Legend, Fig. 42
S= Protective cap
O= O-Ring
SW6 = Allen key
H= Hexagon cap nut
P= internal hexagon screw
V= Valve
OPERATINGINSTRUCTIONS
INCREASING PRE-CHARGE PRESSURE
PREPARATION Only use nitrogen for charging accumulators.
Prior to each testing, topping-up or re-charging of
Never use oxygen! Danger of ex-
nitrogen, the accumulator must be isolated from the
pressurized system and the fluid released. plosion! If the gas pressure in the
nitrogen bottle is higher than the
a) Releasing the pilot pressure system by max. operating pressure of the
shifting both control levers repeatedly into accumulator, a gas pressure re-
all directions with both engines at stand- ducer must be fitted.
still, emergency switch S211 (attachment
down) activated and the electric system
switched on. Connect the flexible charging hose to the
b) Releasing the auxiliary pressure system pressure reducer on the nitrogen bottle by
2 by shifting both control levers repeatedly means of the connector (Pos. 6, Fig. 43). For
into all directions with both engines at nitrogen bottles from other countries the ap-
standstill, emergency switch S211 (at- propriate adaptor is required (see chapter 3.2,
tachment down) activated and the electric THB). Connect connector (Pos. 4, Fig. 43) of
system switched on. the charging hose to the check valve C of the
c) Releasing the track tensioning system charging and testing unit. Open the shut-off
by opening the pressure relief valves (134, valve on the nitrogen bottle, and slowly re-
Fig 39) with both engines at standstill. lease nitrogen into the accumulator. Wait until
d) Releasing the hydraulic system of the approximately 1 bar has been reached before
ladder by shifting the control lever (151, opening the shutoff valve of the nitrogen bottle
Fig. 40) repeatedly with both engines at further to enable faster charging.
standstill.
Interrupt the charging process from time to
Unscrew the protective caps S and H (only on time and check the pre-charge pressure rea-
bladder accumulators). Remove the O-ring O on ched. Repeat this process until the required
bladder accumulators. Slightly loosen the internal gas pre-charge pressure is achieved. After
hexagon screw P on piston and diaphragm accu- temperature equalization has taken place, re-
mulators by means of an Allen key SW 6, DIN 911 check the pre-charge pressure and adjust if
(approx. ½ turn). Place the charging and testing necessary. If the pressure is too high, it can
unit onto the accumulator and screw connector D be lowered via the pressure release B of the
by hand onto accumulator gas valve. At the same charging and testing unit
time, ensure that the release B of the charging and
testing unit is closed. Turn charging and testing If the required gas pre-charge pressure has
unit to a position where the gauge can be easily been reached, turn the spindle anticlockwise
read. to close the gas valve on bladder accumula-
tors. On piston or diaphragm accumulators
TESTING close the internal hexagon screw P by turning
On bladder accumulators (Charging and testing the spindle clockwise. Discharge the charging
unit with adaptor A3) open valve by turning spindle and testing unit via the pressure release and
A clockwise. remove it by loosening the connector. On
On piston and diaphragm accumulators (Charg- bladder accumulators, unscrew the adaptor
ing and testing unit) open valve V by turning the and replace the O-ring O. On piston and dia-
internal hexagon screw anticlockwise with spindle phragm accumulators, tighten the internal
A. When the needle of the gauge begins to move, hexagon screw P with Allen key [20 Nm].
give the spindle another complete turn. The gauge
now shows the charging pressure in the accumula- Check for leakages on the accumulator gas
tor. The check valve C prevents any escape of valve using a leak detector spray.
nitrogen.
Screw on cap nut H (only on bladder accumu-
REDUCING THE PRE-CHARGE PRESSURE lators) and valve protection cap S onto the
Carefully open release B. The nitrogen escapes into gas valve of the accumulator and tighten.
the atmosphere.
WARNING
Nitrogen and operating fluid can
escape when filling or testing
the accumulator due to a faulty,
i.e. leaking, bladder, diaphragm
or piston seals.
Caution!
Risk to health in the case of
aggressive fluids!
The check valve C must not be
removed. The valve has a safety
function for the whole charging
and testing unit.
Fig. 46 642089
Fig. 44 642087
Fig. 47 642090