Professional Documents
Culture Documents
014 - Pressure Checking and Setting - 8 - 06-3746300en
014 - Pressure Checking and Setting - 8 - 06-3746300en
8.6.1.3 General
Before recommissioning, all pro-
tective devices must be refitted. The reference numbers used in the text and illus-
trations correspond to those used in the hydraulic
Catwalks on the boom are only to
circuit diagram.
be walked on when the excavator's
working attachment has been
Since the machine is equipped with the BCS-Board
brought into the position required
Control System, most pressures are available on
for checking/settings pressures.
the BCS display.
Hydraulic cylinders must be If pressure must be reset, in any case calibrated
brought into their end positions gauges have to be used, they have to be con-
before pressures are checked or nected to the relevant test points.
set to ensure that working attach-
ment does not move when pres-
sure is applied. Numbering of main pumps
The excavator operator must oper-
The 4 main pumps are numbered in travel direction
ate the relevant function gently
from left to right P1, P2, P3, and P4 (Fig.1),
(gradual application of pressure)
thus P1 and P2 are driven by the LH engine, and
and then shift the joystick/pedals
P3 and P4 are driven by the RH engine.
fully to their end position.
All pressure test points on the ex-
cavator have Minimess connec- Numbering of swing pumps
tions. Pressure gauges used for
checking must therefore have cor- Each drive unit is equipped with 2 swing pumps
responding fittings. (double pump). The swing pumps on the LH pump
gearbox are named SP1 / SP2, the pumps on the
Always connect the Minimess-hose
RH pump gearbox are named SP3 / SP4 (Fig. 1).
first to the gauge and then to the
test point on the machine to avoid
Auxiliary pumps (Fig. 1)
spillage of pressurized oil!
The springs in pressure relief - Double gear pump for the pilot pressure and
valves must never be tightened PTO cooling system. (6)
fully to "block". The windings of - Double pump for the fan drives of the hydraulic
the spring are then jammed so that oil cooler and the engine radiator. (7)
the valve cannot open. - Hydraulic oil cooling pump (12)
- Charge pump (13)
Before setting/resetting a relief
valve (primary or secondary) loo-
sen the valve insert by approx. 2
turns:
Turning anti-clockwise (loosening)
= lower pressure setting
Turning clockwise (tightening)
= increase pressure setting
To set/reset a pressure relief valve
loosen the counter nut on the valve
insert, set the opening pressure
using the setting crew, and then
tighten the counter nut again.
When checking/setting pressures
Fig. 1 642066
the hydraulic oil temperature must
be above 50°C.
8.6.3 Tools
For pressure checking and setting the tools listed in table 2 are required.
Fig. 2 630640
Fig. 3 642712
Fig. 7 642709
Note:
- Servicelift
- Pressure increase of the main pumps for trav-
eling
- Travel motor speed control (2. travel speed)
- Releasing the swing parking brake.
- Supply of the swing balance valve.
Fig. 9 642711
3. Check pressure.
The gauge must indicate approx. 8 bar
Fig. 8 642710 (225mA).
2. Run LH engine with maximum speed. The RH In case the required pressures are not achieved
engine has to be shut off. the proportional valve must be checked.
For this checking an adapter (A, Fig. 10) is re-
3. Check pressure. quired, to measure the current (mA) supplied by
The gauge must indicate approx. 8 bar the load limit system.
(225 mA).
Fig. 10 630782
Note:
It is also possible to check and read the current
values via the BCS
Note:
Fig. 13 642077
Setting of PRV 1:
2. Start the LH engine. The attachment must be Activate function "RH travel" forward or re-
placed on the ground and the parking brake verse.
"swing" must be activated to avoid turning of
the superstructure. Check pressure (rated; 380 bar).
3. Set primary relief valve (PRV2, Fig. 13) of If necessary reset valve.
main pump P2:
Turn pressure cut-off valve again down to 300
When a new primary relief valve is installed bar.
screw the adjuster 1 turn out, to avoid pressure
peaks.
Setting of PRV 4:
Screw the adjuster of the pressure cut-off
valve (A, Fig. 15) of pump (P2) completely in. 1. Connect a gauge (range: 400 bar) to test point
This is to raise the set value of this valve M4. The test points are installed on the high
above 380 bar. pressure filter blocks (Fig. 14).
Start LH engine and bring it to maximum 2. Start the RH engine. The attachment must be
speed. placed on the ground and the parking brake
"swing" must be activated to avoid turning of
Activate function "LH travel" forward or re- the superstructure.
verse.
3. Set primary relief valve (PRV4, Fig. 13) of
Check pressure (rated; 380 bar). main pump P4:
2. Start the RH engine. The attachment must be Activate function "LH travel" forward or re-
placed on the ground and the parking brake verse.
"swing" must be activated to avoid turning of
the superstructure. Check pressure (rated; 380 bar).
3. Set primary relief valve (PRV3, Fig. 13) of If necessary reset valve.
main pump P3:
Turn pressure cut-off valve again down to 300
When a new primary relief valve is installed bar.
screw the adjuster 1 turn out, to avoid pressure
peaks.
The secondary relief valves are located on the control blocks on the boom (Fig. 16).
Fig. 16 642078
Note:
Fig. 18 642076
8.6.4.6 Secondary relief system for travel 5. Engage the function 'LH travel forward' by
depressing the foot-pedal slowly into the end
Note:
position.
The check of the travel secondary relief valves
6. Check pressure.
should only be carried out in case of travel per-
At the check point M2 (Fig. 18) the pressure
formance- or temperature problems.
must read 390 bar.
If required adjust valve A (Fig. 21) accordingly.
Layout and function of the travel system is de-
scribed in chapter 8.5.5.
Because each crawler has installed two travel
motors, the gauge on the check point always
For securing the travel system each travel motor is
indicates the lowest pressure setting of the 2
equipped with 2 relief valves (Fig. 21).
valves. Therefore it is possible that, even with
an indicated pressure of 390 bar, one valve is
The valves (A + B) are screwed into the travel re-
still set too high.
tarder valves of the travel motors.
Therefore reduce pressure setting on 1st valve
A1, Fig.21) of the pair to less than 360 bar.
Gauge reading must drop noticeably. Increase
pressure setting back up to 390 bar.
Set pressure on 2nd valve (A2, Fig. 21) in the
same way: Lower it firstly, and than increase
back up to 390 bar.
Note:
Fig. 22 642715
9. Activate 'swing right'. Move joy stick slowly into Fig. 24 642716
the end position.
Note:
8.6.4.8 Track tensioning system 2. Start both engines and let them run with max-
imum speed.
Layout and function of the track tensioning system
is described in chapter 8.5.7.
3. Check auxiliary pressure 2.
Rated: 60 bar;
The pressure for the hydraulic track tensioning
If necessary adjust auxiliary pressure 2 (see
system is taken from the 60-bar auxiliary circuit 2.
chapter 8.6.4.1).
The pressure to discharge the hydraulic track ten-
sioning system is taken from the 80-bar auxiliary
4. Activate service switch S31 (Fig. 27) and
circuit 1.
check the pressure at test point M1 (Fig. 26).
Rated: 80 bar;
The pilot controlled check valves and the change
If necessary adjust auxiliary pressure 1 (see
over valve, factory set to 70 bar, are located on the
chapter 8.6.4.1).
track tensioning valve block (133, Fig. 29).
Discharge function
3. Check pressures.
Rated:
At test point M-A2 = 60 bar
At test point M-B1 = 0 bar
Overview:
S31 M-A2 M-B1
OFF 60 bar 0 bar
ON 80 bar 80 bar
Table 5
Fig. 27 642714
Inlet pressure:
Fig. 28 642062
1. Connect gauge (range: 100 bar) to test point
M1 (Fig. 26).
If the pressures will not appear as shown in table The track tensioning system is protected by two
5, the function and setting of the change over valve secondary relief valves, which are preset to 330
(SV, Fig. 28) has to be checked. bar.
To make the switch point of the change over valve
visible, the auxiliary pressure 2 has to be tempo- These valves are installed in the carbody (134, Fig.
rary increased to 70 bar (see chapter 8.6.4.1). 29).
4. Check pressures.
There are two possible situations:
a) At test point M-A2 = 70 bar
At test point M-B1 = 0 bar Fig. 29 630776a
or
b) At test point M-A2 = 70 bar
At test point M-B1 = 70 bar
5. If the pressure at test point M-B1 is not 0 bar, Tensioning the tracks
the set screw of the change over valve (SV,
Fig. 28) has to be turned out (ccw) until the Tensioning and slackening the tracks is described
valve switches over to 0 bar. in the operator's manual.
The hydraulic oil is cooled by two independent The coolant of the engines is cooled by two inde-
cooling circuits. pendent cooling circuits.
Each circuit is related to one engine. Each circuit is related to one engine.
The fan pump on the LH engine drives the front
fan. The cooling pump on the RH engine drives the Fig. 31 is showing fan pump (7a) with flanged on
rear fan. proportional valve and its coil (C).
The flow of the fan pumps is in relation to the hy-
draulic oil temperature electronically controlled.
Fig. 31 642084
Fig. 32 642708
Charging and testing unit for Charging and testing unit for
diaphragm accumulators bladder accumulators with
adaptor A3
Fig. 37 642065
OPERATINGINSTRUCTIONS
INCREASING PRE-CHARGE PRESSURE
PREPARATION Only use nitrogen for charging accumulators.
Prior to each testing, topping-up or re-charging of
Never use oxygen! Danger of ex-
nitrogen, the accumulator must be isolated from the
pressurized system and the fluid released. plosion! If the gas pressure in the
nitrogen bottle is higher than the
a) Releasing the pilot pressure system by max. operating pressure of the
shifting both control levers repeatedly into accumulator, a gas pressure re-
all directions with both engines at stand- ducer must be fitted.
still, emergency switch S211 (attachment
down) activated and the electric system Connect the flexible charging hose to the
switched on. pressure reducer on the nitrogen bottle by
b) Releasing the auxiliary pressure system means of the connector (Pos. 6, Fig. 37). For
by shifting both control levers repeatedly nitrogen bottles from other countries the ap-
into all directions with the motor at stand- propriate adaptor is required see chapter
still, emergency switch S211 (attachment 3.2.8 ,THB). Connect connector (Pos. 4, Fig.
down) activated and the electric system 37) of the charging hose to the check valve C
switched on. of the charging and testing unit. Open the
c) Releasing the track tensioning system shut-off valve on the nitrogen bottle, and slow-
by opening the pressure relief valves (134, ly release nitrogen into the accumulator. Wait
Fig 33) with both engines at standstill. until approximately 1 bar has been reached
d) Releasing the hydraulic system of the before opening the shutoff valve of the nitro-
ladder by shifting the control lever (151, gen bottle further to enable faster charging.
Fig. 34) repeatedly with both engines at
standstill. Interrupt the charging process from time to
time and check the pre-charge pressure
Unscrew the protective caps S and H (only on reached. Repeat this process until the re-
bladder accumulators). Remove the O-ring O on quired gas pre-charge pressure is achieved.
bladder accumulators. Slightly loosen the internal After temperature equalization has taken
hexagon screw P on piston and diaphragm accu- place, re-check the pre-charge pressure and
mulators by means of an Allen key SW 6, DIN 911 adjust if necessary. If the pressure is too high,
(approx. ½ turn). Place the charging and testing it can be lowered via the pressure release B
unit onto the accumulator and screw connector D of the charging and testing unit.
by hand onto accumulator gas valve. At the same
time, ensure that the release B of the charging and If the required gas pre-charge pressure has
testing unit is closed. Turn charging and testing been reached, turn the spindle anticlockwise
unit to a position where the gauge can be easily to close the gas valve on bladder accumula-
read. tors. On piston or diaphragm accumulators
close the internal hexagon screw P by turning
TESTING the spindle clockwise. Discharge the charging
On bladder accumulators (Charging and testing and testing unit via the pressure release and
unit with adaptor A3) open valve by turning spindle remove it by loosening the connector. On
A clockwise. bladder accumulators, unscrew the adaptor
On piston and diaphragm accumulators (Charg- and replace the O-ring O. On piston and dia-
ing and testing unit) open valve V by turning the phragm accumulators, tighten the internal
internal hexagon screw anticlockwise with spindle hexagon screw P with Allen key [20 Nm].
A. When the needle of the gauge begins to move, Check for leakages on the accumulator gas
give the spindle another complete turn. The gauge valve using a leak detector spray.
now shows the charging pressure in the accumula-
tor. The check valve C prevents any escape of Screw on cap nut H (only on bladder accumu-
nitrogen. lators) and valve protection cap S onto the
gas valve of the accumulator and tighten.
REDUCING THE PRE-CHARGE PRESSURE
Carefully open release B. The nitrogen escapes into
the atmosphere.
WARNING
Nitrogen and operating fluid can
escape when filling or testing
the accumulator due to a faulty,
i.e. leaking, bladder, diaphragm
or piston seals.
Caution!
Risk to health in the case of
aggressive fluids!
The check valve C must not be
removed. The valve has a safety
function for the whole charging
and testing unit.