Definition:-

Planned order is the proposal to make product or to procure items.


Planned orders for in house manufactured product indicates the
tentative production plan.

Scheduling, component availability check can be done on planned


order. Once planned order is firmed, it will not be deleted by the
system automatically.

Objective :-

Production plan is available and one has to schedule the plan across
different production version and resources using the planning Table.
Planned orders are already available, but it might be required to create
planned order manually through while using MF50 transaction. At the
end of this document one will be able to create Planned order through
MF50 transaction code.

Prerequisites:-

Production Plan
Production versions and Resources

Menu path :-

Logistics  Production  Repetitive Manufacturing  Planning Table


 MF50 - Change Mode
1. Press Twice MF50 – Change Mode.

Planning Table Initial Screen: Change Mode


2. Press radio button WkCtr hierarchy .

3. Maintain the following data

Field Name Values


Work Center Enter value in Work
hierarchy center hierarchy.
Start Enter value in Start.
End Enter value in End.

4. Select Month in dropdown .

5. Press tab Scheduling .

Planning Table Initial Screen: Change Mode

6. Select Forward scheduling in dropdown


.
7. Press Planning table Button .

Planning Table for Repetitive Manufacturing: Change Mode

Note: The top part of the table shows the work centers.
The bottom part of the screen shows the products that can be
manufactured at the work centers and the present production
schedule.

8. Press in the required row and column where you want to create
your planned order, for example, row PE-1 RX-1 and column 05.11.02

9. Enter a quantity, for example, 99

10. Press to create a Planned Order.

Detailed Data for Production Quantity


11. Enter the quantity 99 in the Quantity field.

12. Press Check button .

Detailed Data for Production Quantity


13. Press Pegged requirements button .

14. Press Copy button .

Planning Table for Repetitive Manufacturing: Change Mode


15. Press Save .

16. The message bar displays “Changes were made to the master
plan”