Bar Chart Project Schedule Rainy Days
Bar Chart Project Schedule Rainy Days
11 18 20 17 24
11 29 49 66 90
DESCRIPTION UNIT QTY WT% W1 W2 W1 W2 W3 W4 W1 W2 W4 W5 W3 W4 W5 W1 W2 W3 W4
GENERAL REQUIREMENTS
Material Sampling and Testing lot 1.00 0.58% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% ###
As-built Shop Drawings (CAD Generated) lot 1.00 0.78% 0.16% 0.16% 0.16% 0.16% 0.16%
Bonds and Insurances lot 1.00 0.97% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
Temporary Facilities lot 1.00 2.62% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
Permits and Licenses lot 1.00 1.46% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% ###
Overhead and Contingency lot 1.00 1.46% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%
Cleanliness and Waste Disposal lot 1.00 0.49% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
Construction Board and Board-Up Barricade lot 1.00 0.58% 0.58% ###
Provision of Temporary Fence lot 1.00 0.97% 0.97% ###
Provision of Bluesack lot 1.00 0.49% 0.49% ###
EARTHWORKS
Clearing and Grubbing m3 15,716.00 4.58% 1.53% 1.53% 1.53% ###
Area Drains set 160.00 0.45% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% ###
Cross Drains lm 630.00 0.66% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
a. 200mm Ø PVC (thru pipe) set 783.00 5.38% 0.90% 0.90% 0.90% 0.90% 0.90% 0.90% ###
Clearing and Grubbing of Storm Drainage m2 9,822.00 2.86% 0.72% 0.72% 0.72% 0.72% ###
Excavation of Storm Drainage m2 9,822.00 2.86% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% ###
ROADWORKS
Subgrade Preparation m2 13,097.00 13.15% 2.19% 2.19% 2.19% 2.19% 2.19% 2.19% ###
Aggregate Sub-base Course (200mm thick) m2 13,097.00 5.26% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% ###
Aggregate Base Course (150mm thick) m2 13,097.00 3.97% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% ###
ELECTRICAL WORKS
Street Light Connection
Rough-ins lot 1.00 3.88% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% ###
b. 14 sqmm TTHN lm 2,350.00 0.46% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
c. PVC Pipe 25mm Ø lm 2,350.00 0.46% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
LEGEND:
Prepared by: CRITICAL PATH
PARALLEL ACTIVITIES
EDGARDO C. CEREDON JR. WORKING DAYS EXCLUDE ALL SUNDAYS
Project Engineer
JLSR Hauling and General Contractor
jlsr Hauling and General Contractor
PROJECT : DESIGN AND CONSTRUCTION OF PROPOSED SARIAYA RELOCATION SITE DEVELOPMENT
LOCATION : Brgy. Castañas, Sariaya, Quezon
OWNER : Arthocem Concrete Industries Inc.
BAR CHART
MAY 20 - 31, 2019 JUNE 1 - 23, 2019 JULY 1 - 31, 2019 AUGUST 1 - 31, 2019 SEPTEMBER 1-28, 2019
11 18 20 17 24
11 29 49 66 90
DESCRIPTION UNIT QTY WT% W1 W2 W1 W2 W3 W4 W1 W2 W4 W5 W3 W4 W5 W1 W2 W3 W4
GENERAL REQUIREMENTS
Mobilization/Demobilization lot 1.00 13.58% 6.79% 6.79%
Construction Survey, Site Survey and Stake-out lot 1.00 0.97% 0.49% 0.49% ###
Material Sampling and Testing lot 1.00 0.58% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% ###
As-built Shop Drawings (CAD Generated) lot 1.00 0.78% 0.16% 0.16% 0.16% 0.16% 0.16%
Bonds and Insurances lot 1.00 0.97% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
Temporary Facilities lot 1.00 2.62% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
Permits and Licenses lot 1.00 1.46% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% ###
Overhead and Contingency lot 1.00 1.46% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%
Cleanliness and Waste Disposal lot 1.00 0.49% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
Construction Board and Board-Up Barricade lot 1.00 0.58% 0.58% ###
Provision of Temporary Fence lot 1.00 0.97% 0.97% ###
Provision of Bluesack lot 1.00 0.49% 0.49% ###
EARTHWORKS
Clearing and Grubbing m3 15,716.00 4.58% 1.53% 1.53% 1.53% ###
Area Drains set 160.00 0.45% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% ###
Cross Drains lm 630.00 0.66% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
a. 200mm Ø PVC (thru pipe) set 783.00 5.38% 0.90% 0.90% 0.90% 0.90% 0.90% 0.90% ###
Clearing and Grubbing of Storm Drainage m2 9,822.00 2.86% 0.72% 0.72% 0.72% 0.72% ###
Excavation of Storm Drainage m2 9,822.00 2.86% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% ###
ROADWORKS
Subgrade Preparation m2 13,097.00 13.15% 2.19% 2.19% 2.19% 2.19% 2.19% 2.19% ###
Aggregate Sub-base Course (200mm thick) m2 13,097.00 5.26% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% ###
Aggregate Base Course (150mm thick) m2 13,097.00 3.97% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% ###
ELECTRICAL WORKS
Street Light Connection
Rough-ins lot 1.00 3.88% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% ###
b. 14 sqmm TTHN lm 2,350.00 0.46% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
c. PVC Pipe 25mm Ø lm 2,350.00 0.46% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
11 18 20 27 14
11 29 49 76 90
DESCRIPTION UNIT QTY WT% W1 W2 W1 W2 W3 W4 W1 W2 W4 W5 W1 W2 W3 W4 W5 W1 W2
GENERAL REQUIREMENTS
Mobilization/Demobilization lot 1.00 13.58% 6.79% 6.79%
Construction Survey, Site Survey and Stake-out lot 1.00 0.97% 0.49% 0.49% ###
Material Sampling and Testing lot 1.00 0.58% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% ###
As-built Shop Drawings (CAD Generated) lot 1.00 0.78% 0.16% 0.16% 0.16% 0.16% 0.16%
Bonds and Insurances lot 1.00 0.97% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
Temporary Facilities lot 1.00 2.62% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
Permits and Licenses lot 1.00 1.46% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% ###
Overhead and Contingency lot 1.00 1.46% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%
Cleanliness and Waste Disposal lot 1.00 0.49% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
Construction Board and Board-Up Barricade lot 1.00 0.58% 0.58% ###
Provision of Temporary Fence lot 1.00 0.97% 0.97% ###
Provision of Bluesack lot 1.00 0.49% 0.49% ###
EARTHWORKS
Clearing and Grubbing m3 15,716.00 4.58% 1.53% 1.53% 1.53% ###
Area Drains set 160.00 0.45% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% ###
Cross Drains lm 630.00 0.66% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
a. 200mm Ø PVC (thru pipe) set 783.00 5.38% 0.90% 0.90% 0.90% 0.90% 0.90% 0.90% ###
Clearing and Grubbing of Storm Drainage m2 9,822.00 2.86% 0.72% 0.72% 0.72% 0.72% ###
Excavation of Storm Drainage m2 9,822.00 2.86% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% ###
ROADWORKS
Subgrade Preparation m2 13,097.00 13.15% 2.19% 2.19% 2.19% 2.19% 2.19% 2.19% ###
Aggregate Sub-base Course (200mm thick) m2 13,097.00 5.26% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% ###
Aggregate Base Course (150mm thick) m2 13,097.00 3.97% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% ###
ELECTRICAL WORKS
Street Light Connection
Rough-ins lot 1.00 3.88% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% ###
b. 14 sqmm TTHN lm 2,350.00 0.46% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
c. PVC Pipe 25mm Ø lm 2,350.00 0.46% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
LEGEND:
Prepared by: ACTUALACCOMPLISHMENT
TARGET ACCOMPLISHMENT
EDGARDO C. CEREDON JR. WORKING DAYS EXCLUDE ALL SUNDAYS
Project Engineer
JLSR Hauling and General Contractor
jlsr Hauling and General Contractor
PROJECT : DESIGN AND CONSTRUCTION OF PROPOSED SARIAYA RELOCATION SITE DEVELOPMENT
LOCATION : Brgy. Castañas, Sariaya, Quezon
OWNER : Arthocem Concrete Industries Inc.
SUBJECT : REVISED SCHEDULE
BAR CHART
MAY 20 - 31, 2019 JUNE 1 - 23, 2019 JULY 1 - 31, 2019 AUGUST 1 - 31, 2019 SEPTEMBER 1-28, 2019 OCTOBER 1-31, 2019 NOVEMBER 1-30, 2019 DECEMBER 1-4, 2019
11 18 20 17 24 27 24 4
Construction Survey, Site Survey and Stake-out lot 1.00 0.97% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
Material Sampling and Testing lot 1.00 0.58% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
As-built Shop Drawings (CAD Generated) lot 1.00 0.78% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
Bonds and Insurances lot 1.00 0.97% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
Temporary Facilities lot 1.00 2.62% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
SUBTOTAL 7.63%
STORM DRAINAGE SYSTEM
Drainage System, Pipelines, 600mm RCP lm 2,585.00 13.26% 1.66% 1.66% 1.66% 1.66% 1.66% 1.66% 1.66% 1.66%
Area Drains set 160.00 0.45% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07%
Cross Drains lm 630.00 0.66% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
Clearing and Grubbing of Storm Drainage m2 9,822.00 2.86% 0.72% 0.72% 0.72% 0.72%
Excavation of Storm Drainage m2 9,822.00 2.86% 0.48% 0.48% 0.48% 0.48% 0.48% 0.48%
SUBTOTAL 26.11%
SEWER DRAINAGE SYSTEM
Drainage System Pipelines, 200mm Ø PVC lm 2,100.00 x x x x x x x
SUBTOTAL
ROADWORKS
Subgrade Preparation m2 13,097.00 13.15% 1.88% 1.88% 1.88% 1.88% 1.88% 1.88% 1.88%
Aggregate Sub-base Course (200mm thick) m2 13,097.00 5.26% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75%
Aggregate Base Course (150mm thick) m2 13,097.00 3.97% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57%
SUBTOTAL 22.38%
WATER SUPPLY SYSTEM
Construction of Over-head Water Tank lot 1.00 13.67% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59%
SUBTOTAL 13.67%
ELECTRICAL WORKS
Street Light Connection
Rough-ins lot 1.00 3.88% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49%
b. 14 sqmm TTHN lm 2,350.00 0.46% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
c. PVC Pipe 25mm Ø lm 2,350.00 0.46% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66%
SUBTOTAL 5.25% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66%
TOTAL 100.00%
WEEKLY ACCOMPLISHMENT 9.40% 2.69% 3.74% 3.74% 2.21% 1.67% 4.04% 5.02% 5.02% 5.02% 4.31% 3.83% 3.83% 2.64% 0.98% 0.98% 4.78% 5.88% 5.88% 5.88% 5.88% 5.88% 5.88% 4.00% 0.06% 6.79%
ACCUMULATED ACCOMPLISHMENT (TARGET) 0 9.40% 12.10% 15.83% 19.57% 21.78% 23.45% 23.45% 27.49% 32.51% 32.51% 37.54% 42.56% 42.56% 46.87% 50.70% 54.53% 57.17% 58.15% 59.14% 63.91% 69.79% 75.67% 81.55% 87.43% 93.31% 99.19% 103.19% 103.26% 110.05%
ACCUMULATED ACCOMPLISHMENT (ACTUAL) 0 20.26% 21.30% 22.57% 25.00% 27.97% 30.44% 30.44% 32.77% 35.76% 36.92% 37.24% 41.20% 42.07% 45.21% 46.78% 48.70% 51.60% 53.23%
LEGEND:
Prepared by: ADDITIONAL WORK
PARALLEL ACTIVITIES
EDGARDO C. CEREDON JR. WORKING DAYS EXCLUDE ALL SUNDAYS
Project Engineer
JLSR Hauling and General Contractor
jlsr Hauling and General Contractor
PROJECT : DESIGN AND CONSTRUCTION OF PROPOSED SARIAYA RELOCATION SITE DEVELOPMENT
LOCATION : Brgy. Castañas, Sariaya, Quezon
OWNER : Arthocem Concrete Industries Inc.
BAR CHART
MAY 20 - 31, 2019 JUNE 1 - 23, 2019 JULY 1 - 31, 2019 AUGUST 1 - 31, 2019 SEPTEMBER 1-28, 2019 OCTOBER 1-31, 2019 NOVEMBER 1-30, 2019 DECEMBER 1-4, 2019
11 18 20 17 24 27 24 4
Temporary Facilities lot 1.00 2.62% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
Permits and Licenses lot 1.00 1.46% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21%
Overhead and Contingency lot 1.00 1.46% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%
Cleanliness and Waste Disposal lot 1.00 0.49% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
Construction Board and Board-Up Barricade lot 1.00 0.58% 0.58%
Area Drains set 160.00 0.45% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07%
Cross Drains lm 630.00 0.66% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
a. 200mm Ø PVC (thru pipe) set 783.00 5.38% 0.90% 0.90% 0.90% 0.90% 0.90% 0.90%
Clearing and Grubbing of Storm Drainage m2 9,822.00 2.86% 0.72% 0.72% 0.72% 0.72%
Excavation of Storm Drainage m2 9,822.00 2.86% 0.48% 0.48% 0.48% 0.48% 0.48% 0.48%
ROADWORKS
Subgrade Preparation m2 13,097.00 13.15% 1.88% 1.88% 1.88% 1.88% 1.88% 1.88% 1.88%
Aggregate Sub-base Course (200mm thick) m2 13,097.00 5.26% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75%
Aggregate Base Course (150mm thick) m2 13,097.00 3.97% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57%
ELECTRICAL WORKS
Street Light Connection
Rough-ins lot 1.00 3.88% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49%
b. 14 sqmm TTHN lm 2,350.00 0.46% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
c. PVC Pipe 25mm Ø lm 2,350.00 0.46% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
TOTAL 100.00%
WEEKLY ACCOMPLISHMENT 9.40% 2.69% 3.74% 3.74% 2.21% 1.67% 4.04% 5.02% 5.02% 5.02% 4.31% 3.83% 3.83% 2.64% 0.98% 0.98% 3.52% 4.62% 4.62% 4.62% 4.62% 4.62% 4.62% 2.75% 0.06% 6.79%
ACCUMULATED ACCOMPLISHMENT (TARGET) 0 9.40% 12.10% 15.83% 19.57% 21.78% 23.45% 23.45% 27.49% 32.51% 32.51% 37.54% 42.56% 42.56% 46.87% 50.70% 54.53% 57.17% 58.15% 59.14% 62.66% 67.28% 71.90% 76.53% 81.15% 85.78% 90.40% 93.14% 93.21% 100.00%
ACCUMULATED ACCOMPLISHMENT (ACTUAL) 0 20.26% 21.30% 22.57% 25.00% 27.97% 30.44% 30.44% 32.77% 35.76% 36.92% 37.24% 41.20% 42.07% 45.21% 46.78%
LEGEND:
Prepared by: CRITICAL PATH
PARALLEL ACTIVITIES
EDGARDO C. CEREDON JR. WORKING DAYS EXCLUDE ALL SUNDAYS
Project Engineer
JLSR Hauling and General Contractor
jlsr Hauling and General Contractor
PROJECT : DESIGN AND CONSTRUCTION OF PROPOSED SARIAYA RELOCATION SITE DEVELOPMENT
LOCATION : Brgy. Castañas, Sariaya, Quezon
OWNER : Arthocem Concrete Industries Inc.
SUBJECT : REVISED SCHEDULE
BAR CHART
MAY 20 - 31, 2019 JUNE 1 - 23, 2019 JULY 1 - 31, 2019 SEPTEMBER 1-28, 2019 OCTOBER 1-31, 2019 NOVEMBER 1-30, 2019 DECEMBER 1-4, 2019
11 18 20 24 27 24 4
Construction Survey, Site Survey and Stake-out lot 1.00 0.97% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.62% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
Material Sampling and Testing lot 1.00 0.58% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.35% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
As-built Shop Drawings (CAD Generated) lot 1.00 0.78% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
Bonds and Insurances lot 1.00 0.97% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.91% 0.06%
Temporary Facilities lot 1.00 2.62% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 2.47% 0.15%
Permits and Licenses lot 1.00 1.46% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 1.46%
Overhead and Contingency lot 1.00 1.46% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 1.37% 0.09%
Cleanliness and Waste Disposal lot 1.00 0.49% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.46% 0.03%
Construction Board and Board-Up Barricade lot 1.00 0.58% 0.58% 0.58%
Area Drains set 100.00% 160.00 0.45% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.45%
Cross Drains lm 630.00 0.66% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.66%
Clearing and Grubbing of Storm Drainage m2 100.00% 9,822.00 2.86% 0.72% 0.72% 0.72% 0.72% 2.86%
Excavation of Storm Drainage m2 100.00% 9,822.00 2.86% 0.48% 0.48% 0.48% 0.48% 0.48% 0.48% 2.86%
SUBTOTAL
ROADWORKS
Subgrade Preparation m2 13,097.00 13.15% 1.88% 1.88% 1.88% 1.88% 1.88% 1.88% 1.88%
Aggregate Sub-base Course (200mm thick) m2 13,097.00 5.26% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75%
Aggregate Base Course (150mm thick) m2 13,097.00 3.97% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57%
SUBTOTAL 22.38%
WATER SUPPLY SYSTEM
Construction of Over-head Water Tank lot 1.00 13.67% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 8.92% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59%
SUBTOTAL 65.22% 13.67% 8.92%
ELECTRICAL WORKS
Street Light Connection
Rough-ins lot 1.00 3.88% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49%
b. 14 sqmm TTHN lm 2,350.00 0.46% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
c. PVC Pipe 25mm Ø lm 2,350.00 0.46% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66%
SUBTOTAL 5.25% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66%
TOTAL 100.00%
WEEKLY ACCOMPLISHMENT 9.40% 2.69% 3.74% 3.74% 2.21% 1.67% 4.04% 5.02% 5.02% 5.02% 4.31% 3.83% 3.83% 2.64% 0.98% 0.98% 4.78% 5.88% 5.88% 5.88% 5.88% 5.88% 5.88% 4.00% 0.06% 6.79%
ACCUMULATED ACCOMPLISHMENT (TARGET) 0 9.40% 12.10% 15.83% 19.57% 21.78% 23.45% 27.49% 32.51% #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
ACCUMULATED ACCOMPLISHMENT (ACTUAL) 0 20.26% 21.30% 22.57% 25.00% 27.97% 30.44% 32.77% 35.76% 37.24% 41.20% 45.21% 46.78% 48.70% 51.60% 53.23%
LEGEND:
Prepared by: ADDITIONAL WORK
PARALLEL ACTIVITIES
EDGARDO C. CEREDON JR. WORKING DAYS EXCLUDE ALL SUNDAYS
Project Engineer
JLSR Hauling and General Contractor