Document No.

KEC/IMS/EHS/07/F/53

CHECKLIST FOR DB Issue. No. 02 Rev. No. 00


ELECTRICAL INSTALLATION Issue. Date 08-12-2018 Rev. Date 00-00-00

Page No. 1

Name of Site / Location : Date :

Name of Contract Agency : DB No :

Inspected by : Work Area :

SR NO POINTS OF INSPECTION YES NO NS REMARKS


1 Metal Clad Distribution Board Provided

2 DB is Earthed Properly

3 Canopy/Shed to DB Provided

4 DB is Properly Anchored

5 30 mA ELCB/RCCB Provided

6 I/C & O/G Cables Properly Terminated

7 Cable gland is provided


Cable Joints Properly Insulated with insulation
8
tape
9 Plug tops (3 Pin) for O/G cables Provided
Cables put under ground in vehicular
10
Movement Area
Flammable items are not kept close to electrical
11
Installation
Danger board with Skull & cross bone sticker
12
displayed
13 Locking provision in DB

14 Electrician contact no. is displayed.

IF any Other Points

REMARKS:-

Signature:

Designation:

N – No, Y – Yes, NS – Not satisfactory