ACT Duration Cost Cost Days Cost/Da Y Days Shorten Normal Crash Normal Crash
ACT Duration Cost Cost Days Cost/Da Y Days Shorten Normal Crash Normal Crash
∆ ∆
ACT COST/DA
P1 NORMAL CRASH NORMAL CRASH COST DAYS Y
DAYS SHORTEN
A 6 3 300 360 60 3 20
B 6 4 450 500 50 2 25 1 1
C 4 2 360 420 60 2 30 1 1
D 6 3 600 675 75 3 25 1
E 3 2 325 350 25 1 25 1
F 2 1 250 285 35 1 35 1
G 2 1 310 350 40 1 40 1
DAYS CUT NIL 1 1 1 1 1
PROJECT
11 10 9 8 7 6
DURATION
INCREASED
NIL 25 35 40 55 80
COST/DAY
DIRECT COST 2595 2620 2655 2695 2750 2820
OVERHEAD
660 600 540 480 420 360
COST
TOTAL COST 3255 3220 3195 3175 3170 3190
OVERHEAD
$ 60/DAY
COST
Optimum cost
= $7415
DURATION COST ∆ ∆ ∆
ACT
NORMAL CRASH NORMAL CRASH COST DAYS COST/DAY DAYS SHORTEN
P5 A 3 2 400 430 30 1 30
B 4 2 1020 1100 80 2 40 1 1
C 2 2 350 350 0 0 0
D 7 5 1250 1300 50 2 25 2
E 5 3 825 895 70 2 35 2
F 6 3 610 700 90 3 30
G 4 2 430 490 60 2 30 2
H 5 2 525 660 135 3 45 2 1
I 3 2 390 410 20 1 20
J 6 3 615 765 150 3 50 1
DAYS CUT NIL 2 2 2 1 1
PROJECT
20 18 16 14 13 20
DURATION
INCREASED
NIL 25 35 75 85 90
COST/DAY
DIRECT
6415 6465 6535 6685 6770 6860
COST
OVERHEAD
1800 1620 1440 1260 1170 1080
COST
TOTAL COST 8215 8085 7975 7945 7940 7440
OVERHEAD
$90/DAY
COST
Duration of project = 20 days
Optimum duration = 13 days
S1
DURATION COST ∆
∆ ∆
ACT COST/DA
NORMAL CRASH NORMAL CRASH COST DAYS Y
DAYS SHORTEN
S4
Duration of project =22 days
Optimum duration = 17 days
A 3 2 400 425 25 1 25
S5
B 8 4 1020 1140 120 4 30 1 2
C 2 2 350 350 0 0 0
D 3 2 1250 1315 65 1 65
E 3 2 825 850 25 1 25 1
F 6 3 610 700 90 3 30
G 4 2 430 550 120 2 60 2
H 5 3 525 625 100 2 50 2
I 4 2 390 480 90 2 45 1 1
J 8 5 615 675 60 2 20 1 2
DAYS CUT NIL 1 1 2 1 1 2
PROJECT
20 19 18 16 15 14 12
DURATION
INCREASED
NIL 20 30 80 45 70 80
COST/DAY
DIRECT COST 6415 6435 6465 6625 6670 6740 6900
OVERHEAD
1600 1520 1440 1280 1200 1120 960
COST
TOTAL COST 8015 7955 7905 7905 7870 7860 7860
OVERHEAD
$ 80/DAY
COST