DURATION COST ∆

∆ ∆
ACT COST/DA
P1 NORMAL CRASH NORMAL CRASH COST DAYS Y
DAYS SHORTEN

A 6 3 300 360 60 3 20
B 6 4 450 500 50 2 25 1 1
C 4 2 360 420 60 2 30 1 1
D 6 3 600 675 75 3 25 1
E 3 2 325 350 25 1 25 1
F 2 1 250 285 35 1 35 1
G 2 1 310 350 40 1 40 1
DAYS CUT NIL 1 1 1 1 1
PROJECT
11 10 9 8 7 6
DURATION
INCREASED
NIL 25 35 40 55 80
COST/DAY
DIRECT COST 2595 2620 2655 2695 2750 2820
OVERHEAD
660 600 540 480 420 360
COST
TOTAL COST 3255 3220 3195 3175 3170 3190
OVERHEAD
$ 60/DAY
COST

Duration of project = 11 days

Optimum duration = 7 days

Optimum cost = $3170


P2 DURATION COST ∆ ∆

ACT COST/DA
NORMAL CRASH NORMAL CRASH COST DAYS DAYS SHORTEN
Y
A 6 4 600 780 180 2 90 2
B 10 7 500 875 375 3 125 2
C 12 8 600 900 300 4 75 2 2
D 8 4 800 940 140 4 35 2 2
E 6 3 600 795 195 3 65 2
F 4 2 800 850 50 2 25 2
DAYS CUT NIL 2 2 2 2 2 2
PROJECT
30 28 26 24 22 20 18
DURATION
INCREASED
NIL 25 35 75 90 100 200
COST/DAY
DIRECT COST 3900 3950 4020 4170 4350 4550 4950
OVERHEAD
3000 2800 2600 2400 2200 2000 1800
COST
TOTAL COST 6900 6750 6620 6570 6550 6550 6750
OVERHEAD
$ 100/DAY
COST
Duration of project = 30 days

Optimum duration = 22days

Optimum cost = $6550


DURATION COST ∆
∆ ∆
ACT COST/DA
P3 NORMAL CRASH NORMAL CRASH COST DAYS Y
DAYS SHORTEN

A 10 8 1000 1100 100 2 50 1 1


B 4 3 500 575 75 1 75
C 10 6 400 800 400 4 100 1
D 19 14 1000 1100 100 5 20 1 1
E 13 9 300 400 100 4 25
F 6 4 120 200 80 2 40 2
DAYS CUT NIL 2 1 1 1
PROJECT
26 24 23 22 21
DURATION
INCREASED
NIL 40 50 70 120
COST/DAY
DIRECT COST 3320 3400 3450 3520 3640
OVERHEAD
1950 1800 1725 1650 1575
COST
TOTAL COST 5270 5200 5175 5170 5215
OVERHEAD
$ 75 /DAY
COST
Duration of project = 26days

Optimum duration = 22days

Optimum cost = $5170


DURATION COST ∆
∆ ∆
ACT COST/DA
P4 NORMAL CRASH NORMAL CRASH COST DAYS DAYS SHORTEN
Y
A 5 3 400 530 130 2 65 2
B 3 2 350 410 60 1 60
C 7 4 1020 1095 75 3 25
D 4 3 525 560 35 1 35 1
E 6 3 825 975 150 3 50 2
F 4 2 610 750 140 2 70
G 6 3 430 565 135 3 45 2 1
H 7 4 1250 1415 165 3 55 3
I 4 2 390 450 60 2 30
DAYS CUT NIL 2 3 1 2
PROJECT
22 20 17 16 14
DURATION
INCREASED
NIL 45 55 80 115
COST/DAY
DIRECT COST 5800 5890 6055 6135 6365
OVERHEAD
1760 1600 1360 1280 1120
COST
TOTAL COST 7560 7490 7415 7415 7485
OVERHEAD
$ 80/DAY
COST
Duration of project = 22 days

Optimum duration = 16 days

Optimum cost
= $7415
DURATION COST ∆ ∆ ∆
ACT
NORMAL CRASH NORMAL CRASH COST DAYS COST/DAY DAYS SHORTEN

P5 A 3 2 400 430 30 1 30
B 4 2 1020 1100 80 2 40 1 1
C 2 2 350 350 0 0 0
D 7 5 1250 1300 50 2 25 2
E 5 3 825 895 70 2 35 2
F 6 3 610 700 90 3 30
G 4 2 430 490 60 2 30 2
H 5 2 525 660 135 3 45 2 1
I 3 2 390 410 20 1 20
J 6 3 615 765 150 3 50 1
DAYS CUT NIL 2 2 2 1 1
PROJECT
20 18 16 14 13 20
DURATION
INCREASED
NIL 25 35 75 85 90
COST/DAY
DIRECT
6415 6465 6535 6685 6770 6860
COST
OVERHEAD
1800 1620 1440 1260 1170 1080
COST
TOTAL COST 8215 8085 7975 7945 7940 7440
OVERHEAD
$90/DAY
COST
Duration of project = 20 days
Optimum duration = 13 days

Optimum cost = $7940

S1
DURATION COST ∆
∆ ∆
ACT COST/DA
NORMAL CRASH NORMAL CRASH COST DAYS Y
DAYS SHORTEN

A 8 4 300 420 120 4 60 1


B 6 4 450 520 70 2 35 1
C 2 1 360 430 70 1 70
D 6 3 600 690 90 3 30
E 3 2 325 365 40 1 40
F 2 1 250 330 80 1 80 1
G 3 1 310 360 50 2 25 1 1
DAYS CUT NIL 1 1 1 1
PROJECT
11 10 9 8 7
DURATION
INCREASED
NIL 25 25 35 40
COST/DAY
DIRECT COST 2595 2620 2645 2680 2820
OVERHEAD
825 750 675 600 525
COST
TOTAL COST 3420 3370 3320 3280 3345
OVERHEAD
$ 75/DAY
COST

Duration of project = 11 days


Optimum duration = 8 days
Optimum cost = $3280
DURATION COST ∆
∆ ∆
ACT COST/DA
NORMAL CRASH NORMAL CRASH COST DAYS DAYS SHORTEN
S2 Y
A 6 4 600 670 70 2 35 1
B 12 8 500 660 160 4 40
C 10 6 600 760 160 4 40
D 8 5 800 890 90 3 30
E 6 4 600 690 90 2 45 3
F 4 2 800 900 100 2 50
DAYS CUT NIL 3 1
PROJECT
30 27 26
DURATION
INCREASED
NIL 30 35
COST/DAY
DIRECT COST 3900 3990 4025
OVERHEAD
900 810 780
COST
TOTAL COST 4800 4800 4805
OVERHEAD
$ 30/DAY
COST
Duration of project =301 days
Optimum duration = 30 days

Optimum cost = $4800


S3
DURATION COST ∆
∆ ∆
ACT COST/DA
NORMAL CRASH NORMAL CRASH COST DAYS Y
DAYS SHORTEN

A 10 8 1000 1120 120 2 60


B 5 3 500 630 130 2 65
C 6 3 400 505 105 3 35
D 19 12 1000 1210 210 7 30 2 1
E 12 8 300 480 180 4 45 1
F 6 4 120 200 80 2 40 2
DAYS CUT NIL 2 2 1
PROJECT
25 23 21 20
DURATION
INCREASED
NIL 30 40 75
COST/DAY
DIRECT COST 3320 3380 3460 3535
OVERHEAD
1250 1150 1050 1000
COST
TOTAL COST 4570 4530 4510 4535
OVERHEAD
$ 50/DAY
COST

Duration of project = 25 days


Optimum duration = 21 days
DURATION COST ∆
∆ ∆
ACT COST/DA
NORMAL CRASH NORMAL CRASH COST DAYS Y
DAYS SHORTEN

A 4 2 400 570 170 2 85


B 5 2 350 455 105 3 35 3
C 11 6 1020 1145 135 5 27
D 4 2 525 575 50 2 25
E 6 4 825 935 110 2 55 1
F 6 5 610 650 40 1 20 1
G 6 4 430 570 140 2 70
H 3 2 1250 1325 75 1 75
I 5 3 390 450 60 2 30 2
DAYS CUT NIL 2 3 1
PROJECT
22 20 17 16
DURATION
INCREASED
NIL 30 35 75
COST/DAY
DIRECT COST 5800 5860 5965 6040
OVERHEAD
1100 1000 850 800
COST
TOTAL COST 6900 6860 6815 6840
OVERHEAD
$ 50/DAY
COST
Optimum cost = $4510

S4
Duration of project =22 days
Optimum duration = 17 days

Optimum cost = $6815


DURATION COST ∆
∆ ∆
ACT COST/DA
NORMAL CRASH NORMAL CRASH COST DAYS Y
DAYS SHORTEN

A 3 2 400 425 25 1 25
S5
B 8 4 1020 1140 120 4 30 1 2
C 2 2 350 350 0 0 0
D 3 2 1250 1315 65 1 65
E 3 2 825 850 25 1 25 1
F 6 3 610 700 90 3 30
G 4 2 430 550 120 2 60 2
H 5 3 525 625 100 2 50 2
I 4 2 390 480 90 2 45 1 1
J 8 5 615 675 60 2 20 1 2
DAYS CUT NIL 1 1 2 1 1 2
PROJECT
20 19 18 16 15 14 12
DURATION
INCREASED
NIL 20 30 80 45 70 80
COST/DAY
DIRECT COST 6415 6435 6465 6625 6670 6740 6900
OVERHEAD
1600 1520 1440 1280 1200 1120 960
COST
TOTAL COST 8015 7955 7905 7905 7870 7860 7860
OVERHEAD
$ 80/DAY
COST

Duration of project = 20 days


Optimum duration = 14 days

Optimum cost = $7860