NO JENIS BAHAN,MATERIAL , HARGA SATUAN SUBTOTAL / GLOBAL

PERALATAN & JASA

1 PIPA 8’ ( 23 LONJOR ) RP 600.000 RP 13.800.000

2 TALANG SENG 20M RP 1.500.000 RP 1.500.000

3 ELBOW 8’ PVC ( 4 PCS ) RP 200.000 RP 800.000

4 UNP BESI / SIKU KUDA2 RP 250.000 RP 2.500.000

5 BAUT DRYLL ( 4 DOS ) RP 150.000 RP 600.000

6 PAKU REPEAT ( 4 DOS ) RP 50.000 RP 200.000

7 LEM PVC ( 15 KALENG ) RP 50.000 RP 750.000

8 KAWAT LAS ( 4 DOS ) RP 75.000 RP 300.000

9 PISAU GERINDA (4 DOS ) RP 50.000 RP 200.000

10 AQUAPROF + KASA RP 600.000 RP 600.000

11 SEALANT SIKA ( 10 PCS ) RP 100.000 RP 1.000.000

12 PRLTAN FULLSEAT RP 4.000.000 RP4.000.000

13 BIAYA JASA ( 4 RP 15.000.000 RP 15.000.000


MANPOWER)

GRAND SUBTOTAL RP 41.250.000