Programme Management

Infrastructure and Public Realm

Riyadh City Development

Ramadan Management Plan


RS-02-00001-05-11-HS-SBD-PL-000005[02]
[RS-02-00001-05-11-HS-SBD-PL-000005] Rev. 02
[Ramadan Management Plan] Page 2 of 4

Prepared by:
KBR Services International, Inc.
PO Box 127741,
Abu Dhabi United Arab Emirates
www.kbr.com

Prepared for:
Aldar Projects, LLC
Abu Dhabi, United Arab Emirates

This document is the property of KBR and Aldar.

All Paper copies of this document are UNCONTROLLED.


Please refer to Aconex for the current version.

Template Ref. No.: RS-02-00001-00-19-OA-KBR-FO-000002 | Rev. 06


[RS-02-00001-05-11-HS-SBD-PL-000005] Rev. 02
[Ramadan Management Plan] Page 3 of 4

All rights reserved. No section or element of this document


may be removed from this document, reproduced,
electronically stored or transmitted in any form without
the written permission of KBR and Aldar.

This document contains confidential or proprietary


information which may be subject to export control and
should not be copied, reproduced, republished, uploaded,
transmitted, printed or distributed in any way without
prior written authorization as required

All Paper copies of this document are UNCONTROLLED.


Please refer to Aconex for the current version.

Template Ref. No.: RS-02-00001-00-19-OA-KBR-FO-000002 | Rev. 06


[RS-02-00001-05-11-HS-SBD-PL-000005] Rev. 02
[Ramadan Management Plan] Page 5 of 13

Ramadan Management Plan

All Paper copies of this document are UNCONTROLLED.


Please refer to Aconex for the current version.

Template Ref. No.: RS-02-00001-00-19-OA-KBR-FO-000002 | Rev. 06


[RS-02-00001-05-11-HS-SBD-PL-000005] Rev. 02
[Ramadan Management Plan] Page 6 of 13

TABLE OF CONTENTS
S. No Description Page Number
01 Introduction 06
02 Iftaar 06

03 The Working Hours 06


04 The Working Culture 07
05 The Daily Work Routine 07
06 Some Dos and Don’ts for Fasting Employees 07

07 Workforce development 08

08 Labour law 08

09 Emergecny procedure 08

11
On the Concluding Note and Reference
10

Appendix 01

Program of works
Approved drawing of rest areas.

All Paper copies of this document are UNCONTROLLED.


Please refer to Aconex for the current version.

Template Ref. No.: RS-02-00001-00-19-OA-KBR-FO-000002 | Rev. 06


[RS-02-00001-05-11-HS-SBD-PL-000005] Rev. 02
[Ramadan Management Plan] Page 7 of 13

1.0 Introduction

Ramadan – The Holy Month

Ramadan is the ninth month of the Islamic calendar. The month is considered to be extremely
auspicious and Muslims worldwide observe fasting from dawn till sunset. The month of
Ramadan is an annual observance that is considered as one of the five pillars of Islam.

This year, the month of Ramadan commenced (expectation) on the 13-04.2021 and will
probably end around 12.05.2021. The UAE is the hottest and has the longest days during this
month. Hence, Muslims fasting would have to do so for around 14-15 hours daily. Other than
fasting, the Muslims also pray for 5 times a day and worship believing that it will bring them
closer to God.

2.0 Iftaar

In the month of Ramadan, Iftaar is when friends and family gather together to break the fast.
The meaning of the word Iftaar is breaking fast. Iftaar is one of the many religious observances
of Ramadan and often takes place as a community with people who gather at one place to
break the fast.

Iftaar is taken just after Maghrib, which is around the sunset. The Muslims have a tradition of
breaking their fast with three dates though it is not compulsory. It is also a Muslim belief that it
is charity to feed someone Iftaar.

Now that you know the importance of the month and fasting, the UAE and other neighboring
Emirates observe some changes. As a professional working there, it is necessary that you are
acquainted with these changes.

3.0 The Working Hours

Under the UAE Labor Law, Muslims as well as non-Muslims have reduced working hours. This is
covered under Article 65 of the UAE Labor Law and is applicable to every employee. The
compensation though remains the same. During the month of Ramadan, the normal working
hours are reduced by 2 hours.

This law is not applicable for companies that are located in areas designated as Free Zones.
The workers working outside (construction sites) are eligible for a day break of 12pm to 3pm.

During the Ramadan site working hours is daily 06 hours remains under the overtime consider
as per labor law.

Daily 06:00 am to 12:00 and office time is 07:00 am to 13:00.

If any changes in site and office working timing, SBD management will be informed to Engineer
for approval.

All Paper copies of this document are UNCONTROLLED.


Please refer to Aconex for the current version.

Template Ref. No.: RS-02-00001-00-19-OA-KBR-FO-000002 | Rev. 06


[RS-02-00001-05-11-HS-SBD-PL-000005] Rev. 02
[Ramadan Management Plan] Page 8 of 13

4.0 The Working Culture

If you are working in the UAE, you might observe some changes in the working culture in the
companies. You are not allowed to eat and drink publicly. If you are a non-Muslim, you might
observe that your Muslim co-workers who are fasting could experience changes in their daily
routine leaving them exhausted. As a co-worker, it is expected that you remain calm and
respectful towards them.

SBD project management will be provided a separate rest rooms for non-Muslims and who
don’t have fasting for having food and drinking. Please find attached approved rest area
drawing in Appendix 02.

5.0 The Daily Work Routine

During the time of Ramadan, it is possible that Muslims who are fasting do not get proper rest.
At this point it is advised for the non-Muslims to avoid coming up with a discussion that you
think can offend them. SBD project management will be provided rest rooms for workers at
work place, if you are not fasting, make sure you do not compare yourself with the ones fasting
during the month of Ramadan.

6.0 Some Dos and Don’ts for Fasting Employees

If you are fasting, here are some quick tips that will help you to manage your work efficiently:

– Plan your work a month before. You know you are going to be fasting for the entire month,
so make sure that you have a plan for the month well in advance
– Use your breaks efficiently – if you feel exhausted, you might use your breaks for power
naps
– If you are planning to take some days off from work, be professional and inform your
employer about the same well in advance
– If you are involved in some tasks that requires physical strength, reschedule to a month
before or after. Keep the lightest work for yourself in this month

Some Dos and Don’ts for Non-Fasting Employees

Even if you are not fasting, there are some ways you can help your Muslim co-workers go
through the month of Ramadan efficiently. Some quick tips on how you should be behaving in
this month:

– Be understanding: Your Muslim co-worker might be low on energy, so be understanding and


avoid indulging them into activities that might drain their energy
– Avoid assigning strenuous tasks to those who are fasting. They do not even consume water
for the time they are fasting, so be considerate

All Paper copies of this document are UNCONTROLLED.


Please refer to Aconex for the current version.

Template Ref. No.: RS-02-00001-00-19-OA-KBR-FO-000002 | Rev. 06


[RS-02-00001-05-11-HS-SBD-PL-000005] Rev. 02
[Ramadan Management Plan] Page 9 of 13

– Avoid asking why someone is not fasting. There can be a number of reasons that your co-
worker is not fasting. Avoid asking them why as they might not be comfortable disclosing the
reason and can feel offended
– Offer help wherever possible. Be generous and ask your co-worker if you could be of any
help to them.
– Show that you respect them by avoiding talking about food in front of them.
– Be modestly dressed

7.0 Workforce development


Educating and training of the workforce is an ongoing process, the challenge that many SBD
project management face is the allocation of the right time for these types of activities. Since
Ramadan is falling during a very hot time of the year, SBD Project management will be
provided shaded and air-conditioned areas for their staff. In addition, Laborers should work in
the shade as much as possible or at night, drink plenty of water after Iftar, wear lightweight,
light colored and loose-fitting clothes and use fans to improve air flow.

Site RAMADAN Management plan and site Emergency response procedures will be
communicated with all employees, sub-contractors and visitors through induction, tool box
talks, posted information and formal trainings.

8.0 Labour law


The Labour Law (Federal Law 8 of 1980) entitles UAE employees to work reduced hours during
Ramadan without any corresponding reduction in their salary. Under the law, the working day
is reduced by two hours. For the majority of employees, this will mean a six-hour working day
(exclusive of breaks). The Labour Law does not differentiate between Muslims and non-
Muslims.

9.0 Emergency Procedure


SBD site management will follow the same emergency procedure of Client and Engineer during
RAMADA working time Emergency incidents. As below Flowchart – Accident/Incident Reporting.
Emergency contact numbers will be displayed at office and site different locations. SBD will
provide site Emergency response team; roles responsibilities and procedures shall be
communicated to them.

Fire marshals, first aiders, emergency coordinators/ managers, security personnel, CoSHH
coordinators (etc.) will be trained, formally appointed and where required available at every
shift and within every work team. Site Emergency response procedures will be communicated
with all employees, sub-contractors and visitors through induction, tool box talks, posted
information and formal trainings.

All Paper copies of this document are UNCONTROLLED.


Please refer to Aconex for the current version.

Template Ref. No.: RS-02-00001-00-19-OA-KBR-FO-000002 | Rev. 06


[RS-02-00001-05-11-HS-SBD-PL-000005] Rev. 02
[Ramadan Management Plan] Page 10 of 13

DIRECTORY OF CONTACT NUMBERS

Site Emergency Telephone Number: 056 369 5546


In addition, the following personnel may be able to offer advice or assistance in an emergency

PROJECT HSE DIVISION SITE NURSE GOVERNMENT


Phone: 02 582
056 882 8484 Abu Dhabi
HSE Office 2277 Ph: 993
Municipality
Fax: Fax:
Venkadesh PR. FIRST AIDERS Mafraq Hospital
HSE Manager Phone: 050 106 Rajesh Pillai 056 123 8604 Ph: 02 501
Hospital
1849 (Please refer to poster at site) 1111
(Nearest)
Project HSE Zahid Jan
Lead 0566879260
HSE Officer Babar Hanif Fire 997
056 7131021 Water 991
Civil
Defence 997
OSHAD 800 555

DIVISION/DEPARTMENT EMERGENCY COORDINATOR DISTRIBUTION


MANAGERS AGENCIES
Phone: 02 Imran Sohail– 054 309 1528
Electricity
SBD H.O. 8184444 02-4464677
FIRE MARSHAL
Fax: Etisalat 02-8005500
Vimal kumar ADNOC 02-6023177
Sr. Project Mohammad Ali- 056 773 6151
Coast
Manager
050 6168203 (Please refer to poster at site) Guard 02-6731900
Srinivasan
Construction Transco
Kannan 02-6414000
Manager
050 4411539 ADDC 02-6423000
ADSSC 02-6943333
ADWEA 02-6943334

10.0 On the Concluding Note and Reference


Ramadan is the holy month that the Muslims world-wide wait for. The month of patience
rewards happiness. Moreover, Islam has a great value for work. Hence, these little tips would
keep you energetic all through the month.

Reference

1. Federal Law 8 of 1980

2. UAE Labor Law Article 65

All Paper copies of this document are UNCONTROLLED.


Please refer to Aconex for the current version.

Template Ref. No.: RS-02-00001-00-19-OA-KBR-FO-000002 | Rev. 06


[RS-02-00001-05-11-HS-SBD-PL-000005] Rev. 02
[Ramadan Management Plan] Page 11 of 13

All Paper copies of this document are UNCONTROLLED.


Please refer to Aconex for the current version.

Template Ref. No.: RS-02-00001-00-19-OA-KBR-FO-000002 | Rev. 06


[RS-02-00001-05-11-HS-SBD-PL-000005] Rev. 02
[Ramadan Management Plan] Page 12 of 13

Appendix 01

Program of works

All Paper copies of this document are UNCONTROLLED.


Please refer to Aconex for the current version.

Template Ref. No.: RS-02-00001-00-19-OA-KBR-FO-000002 | Rev. 06


RIYADH CITY SOUTH - PHASE 05 ROADS INFRASTRUCTURE - 100 DAYS SCHEDULE Page No - 1 of 7
Activity ID Activity Name Orig Dur Start Finish 2020
Mar Apr May Jun
RIYADH CITY SOUTH - PHASE 05 ROADS & INFRASTRUCTURE - 100 DAYS SCHEDULE 682 25-Feb-20 A 07-Jul-22
RIYAD CITY SOUTH - PHASE 5 96 25-Feb-20 A 01-Jul-20
RIYAD CITY SOUTH - PHASE 5 96 25-Feb-20 A 01-Jul-20
RIYAD CITY SOUTH - PHASE 5 96 25-Feb-20 A 01-Jul-20
CONTRACT AWARD 69 25-Feb-20 A 01-Jun-20
CON-000 Receipt of leer - LOA 0 25-Feb-20 A
CON-100 Kickoff Mee$ng 0 26-Feb-20 A
CON-120 Handing over of Site and Site Access Date (Part 1) 0 18-Mar-20 A
CON-130 Mobilisa$on Start (Subject to finaliza$on of office loca$on by Employer) 0 25-Mar-20 A
CON-110 Receipt of Contract Documents / IFC Drawings 0 26-Mar-20 A
CON-125 Handing over of Site and Site Access Date (Part 2) 0 30-Mar-20 A
CON-150 Receipt of Storm Water Pond Details / IFC Drawings 0 02-Apr-20*
CON-135 Handing over of Site and Site Access Date (Part 3) 0 30-Apr-20*
CON-140 Contract Commencement 0 01-Jun-20*
CONTRACTUAL REQUIREMENTS 80 15-Mar-20 A 01-Jul-20
CD-150 Contractor to nominate Contractor Representa$ve / Key Personnel 4 15-Mar-20 A 18-Mar-20 A
CD-170 Contractor to submit the proposed organiza$on chart 5 15-Mar-20 A 19-Mar-20 A
CD-190 Contractor to submit the CVs of the Key Personel 7 15-Mar-20 A 22-Mar-20 A
CD-200 Submission of the Performance Bond 10 21-Mar-20 A 31-Mar-20 A
CD-240 Submit the Payment cer$ficate for Advance Payment 6 26-Mar-20 A 15-Apr-20
CD-220 Submission of Advance Payment Guarantee 10 21-Mar-20 A 15-Apr-20
CD-250 Receipt of Advance Payment by Contractor 6 16-Apr-20 22-Apr-20
CD-270 Submission of Reten$on Bond 19 09-Jun-20 01-Jul-20
INSURANCES 44 21-Mar-20 A 09-Apr-20
CD-210 Submission Insurance of the works 18 21-Mar-20 A 09-Apr-20
CD-290 Submission of Construc$on All Risk Insurance (CAR) 18 21-Mar-20 A 09-Apr-20
CD-300 Submission of Third Party Liablity Insurance 18 21-Mar-20 A 09-Apr-20
CD-310 Submission of Workmen's Compensa$on Employer's Liability Insurance 18 21-Mar-20 A 09-Apr-20
CD-320 Submission of Motor Vehicle Third Party & Passenger Liability Insurance 18 21-Mar-20 A 09-Apr-20
CD-330 Submission of Proffessional Indemnity Insurance 18 21-Mar-20 A 09-Apr-20
CD-340 Submission of Transit Insurance of all Ocean Marine Cargo Shipments 18 21-Mar-20 A 09-Apr-20

Actual Work Page No - 1 PREPARED BY. C DEVENDRAN


Date Revision Checked Approved
Remaining Work Total Page - 7
05-Apr-20 REV 0 T S RAJENDRAN
Critical Remaining Work Print Out Date - 05-Apr-20 RIYADH CITY SOUTH - PHASE 05 ROADS
Milestone INFRASTRUCTURE - 100 DAYS SCHEDULE

100 DAYS SCHEDULE UPDATED AS OF02-Apr-20


© Oracle Corporation
RIYADH CITY SOUTH - PHASE 05 ROADS INFRASTRUCTURE - 100 DAYS SCHEDULE Page No - 2 of 7
Activity ID Activity Name Orig Dur Start Finish 2020
Mar Apr May Jun
CD-360 Contractor's Plant and Equipment Insurance 18 21-Mar-20 A 09-Apr-20
SPECIFIED REQUIREMENTS 18 04-May-20 06-Jun-20
SR-100 Vehicle for Employer - 4WD / PICKUP - Submit Specifica$ons 3 04-May-20 10-May-20
SR-110 Vehicle for Employer - 4WD / PICKUP -Approval of Specifica$ons 3 10-May-20 16-May-20
SR-120 Vehicle for Employer - 4WD / PICKUP - Delivery 12 16-May-20 06-Jun-20
CONTRACT DELIVERABLES 85 26-Feb-20 A 20-Jun-20
CONTRACT DELIVERABLES 85 26-Feb-20 A 20-Jun-20
CONTRACT DELIVERABLES 85 26-Feb-20 A 20-Jun-20
SUBMITTAL OF CONTRACT DELIVERABLES 79 26-Feb-20 A 13-Jun-20
CD1-100 Submission of 100 days Look ahead program 6 26-Feb-20 A 03-Mar-20 A
CD1-130 Submit Project Quality Control Plan 18 03-Mar-20 A 23-Mar-20 A
CD1-140 Submit Construc$on Health & Safety Plan 18 04-Mar-20 A 24-Mar-20 A
CD1-110 Submission of the Logis$cs plan 18 14-Mar-20 A 01-Apr-20 A
CD1-120 Submission of the Traffic management plan 18 30-Apr-20 03-Jun-20
CD1-160 Submit Baseline Programme of works 26 30-Apr-20 13-Jun-20
APPROVAL OF CONTRACT DELIVERABLES 61 25-Mar-20 A 20-Jun-20
CD2-130 Approve Project Quality Control Plan 6 25-Mar-20 A 04-Apr-20
CD2-140 Approve Construc$on Health & Safety Plan 6 25-Mar-20 A 04-Apr-20
CD2-110 Approval of the Logis$cs plan 6 02-Apr-20 08-Apr-20
CD2-120 Approval of the Traffic Management Program 6 03-Jun-20 10-Jun-20
CD2-160 Approve Baseline Programme of works 6 13-Jun-20 20-Jun-20
STAKEHOLDER'S NOC 93 26-Feb-20 A 29-Jun-20
STAKEHOLDER'S NOC 93 26-Feb-20 A 29-Jun-20
ISSUE / OBTAIN OF NOI TO THE AUTHORITIES 93 26-Feb-20 A 29-Jun-20
ISSUE OF NOI TO THE AUTHORITIES (ABU DHABI REGION) 92 26-Feb-20 A 15-Jun-20
NOC1-190 Receipt of Support Leer from Employer for NOC Submission 6 26-Feb-20 A 03-Mar-20 A
NOC1-200 Issue of NOI to the Authority - Earthwork NOC - Submission through ADM 14 04-Mar-20 A 19-Mar-20 A
NOC1-205 Receipt of all design Route Approvals from Employer 68 26-Feb-20 A 31-May-20
NOC1-210 Issue of NOI to the Authority - Infra NOC - Submission through ADM 12 01-Jun-20 15-Jun-20
OBTAIN NOC FROM AUTHORITIES (ABU DHABI REGION) 69 21-Mar-20 A 29-Jun-20
NOC2-200 Obtain NOC from the Authority - Earthwork NOC from Authori$es 12 21-Mar-20 A 04-Apr-20
NOC2-210 Obtain NOC from the Authority - Infra NOC from Authori$es 12 15-Jun-20 29-Jun-20
ESTABLISHMENT OF SITE OFFICE AND LABORATORY 82 16-Mar-20 A 05-Jul-20
ESTABLISHMENT OF SITE OFFICE AND LABORATORY 82 16-Mar-20 A 05-Jul-20
SITE OFFICE AND LABORATORY 82 16-Mar-20 A 05-Jul-20
MOBILIZATION TO SITE 48 25-Mar-20 A 31-May-20
040 Mobilisa$on - key Person 48 25-Mar-20 A 31-May-20
RIYADH CITY SOUTH - PHASE 05 ROADS INFRASTRUCTURE - 100 DAYS SCHEDULE Page No - 3 of 7
Activity ID Activity Name Orig Dur Start Finish 2020
Mar Apr May Jun
SURVEY WORKS 57 25-Mar-20 A 15-Jun-20
SVY-050 Establish the GPS Base Sta$on 12 25-Mar-20 A 04-Apr-20
SVY-030 Demarca$on of Boundaries and Benchmarks 12 25-Mar-20 A 08-Apr-20
SVY-020 Establishment of Control Points 18 25-Mar-20 A 11-Apr-20
SVY-040 Take OGL of the Site - Part 1 25 02-Apr-20 05-May-20
SVY-045 Take OGL of the Site - Part 2 25 06-May-20 15-Jun-20
SUBMIT SHOP DRAWINGS 34 19-Mar-20 A 29-Apr-20
SH1-GN-120 Submit Shop drg: Project Office Loca$on Plan 12 19-Mar-20 A 25-Mar-20 A
SH1-GN-160 Submit Shop drg: Project sign Board 12 23-Mar-20 A 01-Apr-20 A
SH1-GN-110 Submit Shop drg: Facili$es, Laydown Area, Laboratory etc. 22 23-Mar-20 A 01-Apr-20 A
SH1-GN-200 Submit Shop drg: Trial Pit Loca$ons 22 02-Apr-20 29-Apr-20
APPROVE SHOP DRAWINGS 34 02-Apr-20 A 11-May-20
SH2-GN-120 Approve Shop drg: Site Office Loca$on Plan 6 02-Apr-20 A 08-Apr-20
SH2-GN-160 Approve Shop drg: Project sign Board 6 02-Apr-20 A 08-Apr-20
SH2-GN-110 Approve Shop drg: Facili$es, Laydown Area, Laboratory etc. 6 02-Apr-20 A 08-Apr-20
SH2-GN-200 Approve Shop drg: Trial Pit Loca$ons 6 30-Apr-20 11-May-20
SUBMITTAL OF METHOD STATEMENT 43 16-Mar-20 A 11-May-20
MS1-GN-110 Submit Method Statement: Site Office Mobiliza$on & Erec$on 12 16-Mar-20 A 29-Mar-20 A
MS1-GN-120 Submit Method Statement: Site Clearance 6 24-Mar-20 A 30-Mar-20 A
MS1-GN-130 Submit Method Statement: Project Sign Board 12 21-Apr-20 11-May-20
APPROVAL OF METHOD STATEMENT 37 30-Mar-20 A 27-May-20
MS2-GN-110 Approve Method Statement: Site Office Mobiliza$on & Erecrion 6 30-Mar-20 A 08-Apr-20
MS2-GN-120 Approve Method Statement: Site Clearance 6 31-Mar-20 A 08-Apr-20
MS2-GN-130 Approve Method Statement: Project Sign Board 6 12-May-20 27-May-20
ORDER, MANUFACTURE AND SUPPLY OF MATERIALS 38 02-Apr-20 01-Jun-20
MT3-GN-110 Submit Material - Project Sign Board 12 02-Apr-20 15-Apr-20
MT3-GN-120 Approve Material - Project Sign Board 6 16-Apr-20 22-Apr-20
MT3-GN-130 Material Supply - Project Sign Board 20 23-Apr-20 01-Jun-20
ESTABLISHMENT OF SITE OFFICE AND LABORATORY 61 09-Apr-20 05-Jul-20
PR-SO-100 Construc$on of Site office / Store Facili$es - Founda$on works 18 09-Apr-20 04-May-20
PR-SO-110 Erec$on of Site office / Store Facili$es 18 16-Apr-20 16-May-20
PR-SO-160 Establishment of Precast Yard 18 20-Apr-20 21-May-20
PR-SO-120 Furnishing of Site / Store office 18 16-May-20 13-Jun-20
PR-SO-130 Power Connec$on / Generator / MEP works 18 30-May-20 20-Jun-20
PR-SO-140 Telephone / Data Connec$on 18 14-Jun-20 05-Jul-20
SIGN BOARD 12 01-Jun-20 15-Jun-20
PR-SB-100 Installa$on of Project Sign Boards 2 nos 12 01-Jun-20 15-Jun-20
RIYADH CITY SOUTH - PHASE 05 ROADS INFRASTRUCTURE - 100 DAYS SCHEDULE Page No - 4 of 7
Activity ID Activity Name Orig Dur Start Finish 2020
Mar Apr May Jun
SUBCONTRACTOR 32 08-Apr-20 31-May-20
SUBMITTAL OF SUBCONTRACTOR PROPOSAL 26 08-Apr-20 17-May-20
SC1-BH-100 Submit Subcontractor Proposal - Boreholes (Substa$on) 12 08-Apr-20 21-Apr-20
SC1-ST-100 Submit Subcontractor Proposal - Precast Structure works 12 22-Apr-20 13-May-20
SC1-BH-110 Submit Subcontractor Proposal - NDM 12 25-Apr-20 17-May-20
APPROVAL OF S UBCONTRACTOR PROPOSAL 20 22-Apr-20 31-May-20
SC2-BH-100 Approval of Subcontractor - Boreholes (Substa$on) 6 22-Apr-20 02-May-20
SC2-ST-110 Approval of Subcontractor - Precast Structure works 6 13-May-20 28-May-20
SC2-BH-110 Approval of Subcontractor - NDM 6 18-May-20 31-May-20
ENGINEERING (SHOP DWGS / METHOD STATEMENT / MATERIAL) 92 23-Mar-20 A 23-Jul-20
REMOVAL OF OBSTRUCTIONS 30 08-Apr-20 28-May-20
SUBMITTAL OF METHOD STATEMENT 12 08-Apr-20 21-Apr-20
MS1-OB-100 Submit Method Statement: Protec$on / Reloca$on of Exis$ng U$lity 12 08-Apr-20 21-Apr-20
APPROVAL OF METHOD STATEMENT 12 22-Apr-20 13-May-20
MS2-OB-110 Approve Method Statement: Protec$on / Reloca$on of Exis$ng U$lity 12 22-Apr-20 13-May-20
SUBMIT SHOP DRAWINGS 12 15-Apr-20 02-May-20
SH1-OB-100 Submit Shop drg: Protec$on / Reloca$on of Exis$ng U$lity 12 15-Apr-20 02-May-20
APPROVE SHOP DRAWINGS (CONSULTANT) 12 02-May-20 28-May-20
SH2-OB-110 Approve Shop drg: Protec$on / Reloca$on of Exis$ng U$lity 12 02-May-20 28-May-20
SEWER WORKS 69 15-Apr-20 20-Jul-20
SUBMITTAL OF METHOD STATEMENT 12 15-Apr-20 02-May-20
MS1-SW-100 Submit Method Statement: Sewer Pipe Laying 12 15-Apr-20 02-May-20
APPROVAL OF METHOD STATEMENT 6 02-May-20 13-May-20
MS2-SW-100 Approve Method Statement: Sewer Pipe Laying 6 02-May-20 13-May-20
SUBMITTAL OF MATERIAL (SEWER) 56 04-May-20 20-Jul-20
MT1-SW-110 Material Submial: Reinforcement Steel (Sewer) 12 04-May-20 30-May-20
MT1-SW-120 Material Submial: uPVC Pipes & FiMngs 12 16-May-20 06-Jun-20
MT1-SW-100 Material Submial: Concrete Mix Design (Sewer) 12 19-May-20 08-Jun-20
MT1-SW-130 Material Submial: GRP Pipes & FiMngs 12 27-May-20 10-Jun-20
MT1-SW-140 Material Submial: Geo-Tex$le 12 01-Jun-20 15-Jun-20
MT1-SW-150 Material Submial: GRP Liners for Manholes 12 08-Jun-20 22-Jun-20
MT1-SW-160 Material Submial: Granular bed (Surround) 12 15-Jun-20 29-Jun-20
MT1-SW-170 Material Submial: Waterproofing & Bitu-Paints 12 22-Jun-20 06-Jul-20
MT1-SW-180 Material Submial: Manhole ladder 12 06-Jul-20 20-Jul-20
APPROVAL OF MATERIAL (SEWER) 38 30-May-20 13-Jul-20
MT2-SW-110 Material Approval: Reinforcement Steel (Sewer) 6 30-May-20 06-Jun-20
MT2-SW-120 Material Approval: uPVC Pipes & FiMngs 6 06-Jun-20 13-Jun-20
RIYADH CITY SOUTH - PHASE 05 ROADS INFRASTRUCTURE - 100 DAYS SCHEDULE Page No - 5 of 7
Activity ID Activity Name Orig Dur Start Finish 2020
Mar Apr May Jun
MT2-SW-100 Material Approval: Concrete Mix Design (Sewer) 6 08-Jun-20 15-Jun-20
MT2-SW-130 Material Approval: GRP Pipes & FiMngs 6 10-Jun-20 17-Jun-20
MT2-SW-140 Material Approval: Geo-Tex$le 6 15-Jun-20 22-Jun-20
MT2-SW-150 Material Approval: GRP Liners for Manholes 6 22-Jun-20 29-Jun-20
MT2-SW-160 Material Approval: Granular bed (Surround) 6 29-Jun-20 06-Jul-20
MT2-SW-170 Material Approval: Waterproofing & Bitu-Paints 6 06-Jul-20 13-Jul-20
SUBMITTAL OF SHOP DRAWINGS (PARTIAL AREA - FIRST ZONE) 12 26-Apr-20 19-May-20
SH1-SW-100 Submit Shop drg: Sewerage Layout Plan 12 26-Apr-20 19-May-20
SH1-SW-110 Submit Shop drg: Sewerage Line Profile 12 26-Apr-20 19-May-20
APPROVAL OF S HOP DRAWINGS (PARTIAL AREA - FIRST ZONE) 6 19-May-20 01-Jun-20
SH2-SW-100 Approval of Shop drg: Sewerage Layout Plan 6 19-May-20 01-Jun-20
SH2-SW-110 Approval of Shop drg: Sewerage Line Profile 6 19-May-20 01-Jun-20
STORMWATER WORKS 86 23-Mar-20 A 16-Jul-20
SUBMITTAL OF METHOD STATEMENT 62 23-Mar-20 A 18-Jun-20
MS1-ST-120 Submit Method Statement: Storm Water Pond 12 23-Mar-20 A 02-Apr-20 A
MS1-ST-100 Submit Method Statement: Storm Water - Pipe Laying 12 13-May-20 04-Jun-20
MS1-ST-110 Submit Method Statement: Storm Water - Manhole/Chamber 12 04-Jun-20 18-Jun-20
APPROVAL OF METHOD STATEMENT 59 02-Apr-20 25-Jun-20
MS2-ST-120 Approve Method Statement: Storm Water Pond 12 02-Apr-20 15-Apr-20
MS2-ST-100 Approve Method Statement: Storm Water - Pipe Laying 6 04-Jun-20 11-Jun-20
MS2-ST-110 Approve Method Statement: Storm Water - Manhole/Chamber 6 18-Jun-20 25-Jun-20
SUBMITTAL OF MATERIAL (STORM WATER) 27 08-Jun-20 09-Jul-20
MT1-ST-100 Material Submial: Concrete Mix Design (Stormwater) 12 08-Jun-20 22-Jun-20
MT1-ST-130 Material Submial: uPVC Pipes (Perforated) 12 11-Jun-20 25-Jun-20
MT1-ST-110 Material Submial: Reinforcement Steel (Stormwater) 12 15-Jun-20 29-Jun-20
MT1-ST-120 Material Submial: GRP Pipes 12 22-Jun-20 06-Jul-20
MT1-ST-140 Material Submial: Waterproofing & Bitu-Paints 12 25-Jun-20 09-Jul-20
APPROVAL OF MATERIAL (STORM WATER) 21 22-Jun-20 16-Jul-20
MT2-ST-100 Material Approval: Concrete Mix Design (Stormwater) 6 22-Jun-20 29-Jun-20
MT2-ST-130 Material Approval: uPVC Pipes (Perforated) 6 25-Jun-20 02-Jul-20
MT2-ST-110 Material Approval: Reinforcement Steel (Stormwater) 6 29-Jun-20 06-Jul-20
MT2-ST-120 Material Approval: GRP Pipes 6 06-Jul-20 13-Jul-20
MT2-ST-140 Material Approval: Waterproofing & Bitu-Paints 6 09-Jul-20 16-Jul-20
SUBMIT SHOP DRAWINGS (PARTIAL AREA - FIRST ZONE) 62 09-Apr-20 06-Jul-20
SH1-ST-60 Submit Shop drg: Storm Water Pond Excava$on Details 12 09-Apr-20 22-Apr-20
SH1-ST-40 Submit Shop drg: Storm Water Catch Basin and Inlet Reinforcement Details 12 19-May-20 08-Jun-20
SH1-ST-10 Submit Shop drg: Storm Water - Pipe Details 12 01-Jun-20 15-Jun-20
RIYADH CITY SOUTH - PHASE 05 ROADS INFRASTRUCTURE - 100 DAYS SCHEDULE Page No - 6 of 7
Activity ID Activity Name Orig Dur Start Finish 2020
Mar Apr May Jun
SH1-ST-20 Submit Shop drg: Storm Water - Layout Plan 12 08-Jun-20 22-Jun-20
SH1-ST-30 Submit Shop drg: Storm Water Trench, Bed & Surround - Typical 12 15-Jun-20 29-Jun-20
SH1-ST-50 Submit Shop drg: Storm Water Frame and Cover Details 12 22-Jun-20 06-Jul-20
APPROVE SHOP DRAWINGS (PARTIAL AREA - FIRST ZONE) 56 23-Apr-20 13-Jul-20
SH2-ST-60 Approve Shop drg: Storm Water Pond Excava$on Details 12 23-Apr-20 16-May-20
SH2-ST-40 Approve Shop drg: Storm Water Catch Basin and Inlet Reinforcement Details 6 08-Jun-20 15-Jun-20
SH2-ST-10 Approve Shop drg: Storm Water - Pipe Details 6 15-Jun-20 22-Jun-20
SH2-ST-20 Approve Shop drg: Storm Water - Layout Plan 6 22-Jun-20 29-Jun-20
SH2-ST-30 Approve Shop drg: Storm Water Trench, Bed & Surround - Typical 6 29-Jun-20 06-Jul-20
SH2-ST-50 Approve Shop drg: Storm Water Frame and Cover Details 6 06-Jul-20 13-Jul-20
POTABLE WATE R WORKS 39 08-Jun-20 23-Jul-20
SUBMITTAL OF METHOD STATEMENT 24 22-Jun-20 20-Jul-20
MS1-PW-100 Submit Method Statement: Potable Water - Pipe Laying 12 22-Jun-20 06-Jul-20
MS1-PW-110 Submit Method Statement: Potable Water - Manhole/Chamber 12 06-Jul-20 20-Jul-20
APPROVAL OF METHOD STATEMENT 6 06-Jul-20 13-Jul-20
MS2-PW-100 Approve Method Statement: Storm Water - Pipe Laying 6 06-Jul-20 13-Jul-20
SUBMITTAL OF MATERIAL (POTABLE WATER) 27 15-Jun-20 16-Jul-20
MT1-PW-110 Material Submial: Reinforcement Steel (Potable Water) 12 15-Jun-20 29-Jun-20
MT1-PW-100 Material Submial: Concrete Mix Design (Potable Water) 12 25-Jun-20 09-Jul-20
MT1-PW-120 Material Submial: HDPE Pipes & FiMngs (Potable Water) 12 02-Jul-20 16-Jul-20
APPROVAL OF MATERIAL (POTABLE WATER) 21 29-Jun-20 23-Jul-20
MT2-PW-110 Material Approval: Reinforcement Steel (Potable Water) 12 29-Jun-20 13-Jul-20
MT2-PW-100 Material Approval: Concrete Mix Design (Potable Water) 12 09-Jul-20 23-Jul-20
SUBMIT SHOP DRAWINGS 21 08-Jun-20 02-Jul-20
SH1-PW-20 Submit Shop drg - Potable Water line Profile 12 08-Jun-20 22-Jun-20
SH1-PW-10 Submit Shop drg - Potable Water Layout Plan 12 11-Jun-20 25-Jun-20
SH1-PW-30 Submit Shop drg - Potable Water Trench, Bed & Surround 12 15-Jun-20 29-Jun-20
SH1-PW-50 Submit Shop drg - Potable Water Frame and Cover Details 12 18-Jun-20 02-Jul-20
APPROVE SHOP DRAWINGS (CONSULTANT) 18 22-Jun-20 13-Jul-20
SH2-PW-20 Approve Shop drg - Potable Water line Profile 12 22-Jun-20 06-Jul-20
SH2-PW-10 Approve Shop drg - Potable Water Layout Plan 12 25-Jun-20 09-Jul-20
SH2-PW-30 Approve Shop drg - Potable Water Trench, Bed & Surround 12 29-Jun-20 13-Jul-20
CONSTRUCTION WORKS 130 12-May-20 24-Oct-20
SECTOR 130 12-May-20 24-Oct-20
CONSTRUCTION OF SECTOR 130 12-May-20 24-Oct-20
EXCAVATE TO LOCATE / TRIAL PITS OR TRENCHES 24 12-May-20 17-Jun-20
TR-100 Trial Pits / Excavate to Locate (If Required) 24 12-May-20 17-Jun-20
RIYADH CITY SOUTH - PHASE 05 ROADS INFRASTRUCTURE - 100 DAYS SCHEDULE Page No - 7 of 7
Activity ID Activity Name Orig Dur Start Finish 2020
Mar Apr May Jun
DEMOLITION AND SITE CLEARANCE 24 27-May-20 24-Jun-20
CL-100 Site Clearance 24 27-May-20 24-Jun-20
SEWER WORKS 114 31-May-20 15-Oct-20
SEWER - MAIN LINE (EXCAVATION & PIPE LAYING) 102 10-Jun-20 12-Oct-20
SW-ML-100 Sewer Line - Excava$on 90 10-Jun-20 28-Sep-20
SW-ML-110 Sewer Line - Bedding & GeoTex$le 90 14-Jun-20 01-Oct-20
SW-ML-120 Sewer Line - Pipelaying 90 24-Jun-20 12-Oct-20
SEWER - MANHOLE 99 17-Jun-20 15-Oct-20
SW-MH-100 Sewer Manhole - Blinding & Waterproofing 90 17-Jun-20 05-Oct-20
SW-MH-110 Sewer Manhole - Base (Cast-in-situ) MH & Backdrop 90 21-Jun-20 08-Oct-20
SW-MH-120 Sewer Manhole - Cut-off Wall 90 28-Jun-20 15-Oct-20
SEWER - NDM WORKS 40 31-May-20 16-Jul-20
SW-ND-100 Sewer - NDM works 40 31-May-20 16-Jul-20
STORM WATER WORKS 128 16-May-20 24-Oct-20
STORM WATER - MAIN LINE (GRP) - EXCAVATION & PIPE LAYING 90 06-Jul-20 24-Oct-20
ST-ML-100 Stormwater Mainline GRP - Excava$on 90 06-Jul-20 24-Oct-20
STORM WATER POND 96 16-May-20 16-Sep-20
ST-ML-110 Stormwater Pond - Excava$on 90 16-May-20 09-Sep-20
ST-ML-130 Stormwater Pond - Forma$on 90 30-May-20 16-Sep-20
PRECAST YARD 600 15-Jun-20 07-Jul-22
PRECAST YARD 600 15-Jun-20 07-Jul-22
PRECAST YARD 600 15-Jun-20 07-Jul-22
PRE-SW-100 Precast Yard - Installa$on and produc$on 600 15-Jun-20 07-Jul-22
[RS-02-00001-05-11-HS-SBD-PL-000005] Rev. 02
[Ramadan Management Plan] Page 13 of 13

Appendix 02

Approved drawing of rest area.

All Paper copies of this document are UNCONTROLLED.


Please refer to Aconex for the current version.

Template Ref. No.: RS-02-00001-00-19-OA-KBR-FO-000002 | Rev. 06


NOTES:
1. ALL DIMENSIONS ARE IN METRES UNLESS
OTHERWISE STATED.

LEGEND
PLASTIC BARRIER
PATH WAY TO ASSEMBLY POINT
LOGISTIC ROAD

ASSEMBLY
POINT

SMOKING
AREA

REST ROOM REST ROOM RE


REST ROOM REST ROOM RE
REST ROOM REST ROOM RE
REST ROOM REST ROOM RE
GENERAL WASTE

TOILET
TOILET
TOILET
ABLUTION AREA

WATER TANK

ST ROOM REST ROOM REST


ST ROOM REST ROOM REST
ST ROOM REST ROOM REST

GENERATOR
ST ROOM REST ROOM REST

REV. DESCRIPTION BY CHKD APPD DATE

SKETCH
CLIENT

PROGRAMME MANAGER
ROOM REST ROOM REST RO
ROOM REST ROOM REST RO

CONTAINER
ROOM REST ROOM REST RO
ROOM REST ROOM REST RO

LEAD CONSULTANT

REVERSE PARKING AREA


GENERATOR

Design & Consultancy


for natural and
built assets
P.O. Box: 93863
Abu Dhabi, U.A.E
Tel: +971 2 566 4000
www.arcadis.com

CONTRACTOR

P.O. Box 47 Abu Dhabi, UAE


Tel: 02-8184444
Email: sbdco@dbasons.com
PROJECT

RIYADH CITY SOUTH - PHASE 05


ROAD & INFRASTRUCTURE

DRAWING TITLE
OM
OM
OM
OM

EVACUATION LAYOUT
SMOKING REST ROOM REST ROOM FOR REST ROOM AREA

AREA
DRAWN: CHECKED: APPROVED: DATE:
. . . .
DATUM Sheet: A1 A3
NEW ABU DHABI DATUM Scale: 1:100 1:200
Drawing No. REV.