Formwork Inspection Sheet

Date: Sheet No.:


Project: KEFITA APARTMENTS Location: ADDIS ABEBA, YEKA SUBCITY, ETHIOPIA
Employer: ROCKSTONE ETHIOPIA REAL ESTATE PLC
Contractor: HUA HONG CONSTRUCTION PLC
Consultant: BIGAR BUILDERS AND DEVELOPERS PLC
Formwork structure:
Formwork level: Setting-out by:
Type of formwork: Approved by:
Parameters Yes/Good No/Poor Notes
Quality of formwork
Safety precautions
Formwork design
Method statement
Accessibility
Formwork quality (planks)
Formwork quality (props)
Prop bearing plates
Positioning tolerances
Formwork rigidity
Permeability of formwork
Hanging forms & loose material
Setting-out
Support systems in place
Squareness and dimensions

NB: The contractor must issue internal approval


documents if and when such a document is requested
by the consultant
Additional Items/Comments:

Following the request for inspection, the works as per the above listed items and supportive documents have
been evaluated and permission to proceed is hereby Granted / Refused 

Contractor Consultant Project Manager


Name

Signature

After performing the works the contractor is to report on a daily bases the progress and performance of works.